Project Risk Management. What is Risk? Risk and uncertainty are equivalent.

104
Project Risk Management
  • date post

    19-Dec-2015
  • Category

    Documents

  • view

    221
  • download

    0

Transcript of Project Risk Management. What is Risk? Risk and uncertainty are equivalent.

Project Risk Management

What is Risk?

Risk and uncertainty are equivalent

Three Definitions• Risk

– A possible future event which if it occurs will lead to an undesirable outcome.

• Project Risk– The cumulative effect of the chances of an

uncertain occurrence that will adversely affect project objectives.

• Risk Management– A systematic and explicit approach for

identifying, quantifying, and controlling project risk.

DEFINITIONPROJECT RISK MANAGEMENT IS THE ART AND SCIENCE OF

IDENTIFYING, ASSESSING, AND RESPONDING TO PROJECTRISK THROUGHOUT THE LIFE OF A PROJECT AND IN THE BEST INTERESTS OF ITS OBJECTIVES

PROJECT RISK IS THE CUMULATIVE EFFECT OF THE CHANCES OF UNCERTAIN OCCURRENCES ADVERSELY AFFECTING PROJECT OBJECTIVES

RISK MANAGEMENT PURPOSE

IDENTIFY FACTORS THAT ARE LIKELY TO IMPACT THE PROJECT OBJECTIVES OF SCOPE, QUALITY, COST AND TIME

QUANTIFY THE LIKELY IMPACT OF EACH FACTOR

GIVE A BASELINE FOR PROJECT NON-CONTROLLABLES

MITIGATE IMPACTS BY EXERCISING INFLUENCE OVER PROJECT CONTROLLABLES

THE PMBOK ALSO POINTS OUT THAT RISK MANAGEMENT INCLUDES MAXIMIZING THE RESULTS OF POSITIVE EVENTS AND MINIMIZING THE CONSEQUENCES OF ADVERSE EVENTS.

ISSUES

A RISK SHOULD ONLY BE TAKEN WHEN THE POTENTIAL BENEFIT AND CHANCES OF WINNING EXCEED THE REMEDIAL COST OF AN UNSUCCESSFUL DECISION AND CHANCES OF LOSING BY A SATISFACTORY MARGIN

WHAT WILL BE GAINED?WHAT COULD BE LOST?WHAT ARE THE CHANCES OF SUCCESS (AND FAILURE)?WHAT CAN BE DONE IF THE DESIRED RESULT IS NOT ACHIEVED?IS THE POTENTIAL REWARD WORTH THE RISK?

POTENTIAL FREQUENCY OF LOSSAMOUNT AND RELIABILITY OF INFORMATION AVAILABLEPOTENTIAL SEVERITY OF LOSSMANAGEABILITY OF THE RISKVIVIDNESS OF THE CONSEQUENCESPOTENTIAL FOR (ADVERSE) PUBLICITYWHOSE MONEY IS IT?

NATURE OF RISK MANAGEMENT

WHEN SPEAKING OF RISK, THINK OF ONLY HAZARDOUS ONES

EVERYDAY COMMON DAY ONES ARE IGNORED

RARELY DO WE SYSTEMATICALLY IDENTIFY ALL RISKS INVOLVED

HOWEVER, INCLINED TO CONSIDER RISK DIFFERENTLY RELATIVE TO FAMILY - VERY PRECIOUS AND LOTS OF POTENTIAL

EXAMPLES:SMALL CHILDREN - STAY AWAY FROM ROAD - RISK ID & AVOIDANCEHOW DID DAY GO? - DO MORE TO HELP THEM - INFO FEEDBACK

THESE ACTIONS ARE ESTABLISHING THE BASIC ELEMENTS OF MANAGING PROJECT RISK INTO OUR CHILDREN

PROJECT RISK MGMT IS PRO-ACTIVE

CLASSIC SYSTEMS METHODOLOGY:

INPUT PROCESS OUTPUT

FEEDBACK LOOP

THIS PROCESS VITAL TO EFFECTIVE PROJECT CONTROL, HOWEVER

RISK IS DIFFERENT - - HAS TO DO WITH:

UNCERTAINTY, PROBABILITY OR UNPREDICTABILITY, AND CONTINGENT PLANNING

REACTIVE vs. PRO-ACTIVE

CRISIS MANAGEMENT -- REACTIVE MODE -- SELECT RESPONSE

PRO-ACTIVE -- ANTICIPATE AND PLAN TO AVOID

RISK & DECISION MAKING:

TAKE RISK IF POTENTIAL BENEFIT AND CHANCE OF WINNING EXCEEDS COST OF UNSUCCESSFUL DECISION AND CHANCES OF LOSING BY A SATISFACTORY MARGIN (CLASSIC COST / BENEFIT ANALYSIS)

Project Risk Management

R iskIdentifica tion

11.1

R iskQ uantifica tion

11.2

R isk ResponseD evelopm ent

11.3

R isk ResponseC ontro l

11.4

P ro jec t R iskM anagem ent

11.0

PMBOK Risk

• Opportunities - Positive outcome

• Threats - Negative outcome

Benefits of Risk Management

• More and better information is available during planning and decision making

• Project objectives are verified

• Improved communications

• Higher probability of project success

• Proactive approach

• Project might be canceled

Why Organizations don’t doRisk Management

• Unwillingness to admit risks exist

• Postpone the hard parts of the project until later

• Risk management costs money– Up front investment of time– Can’t prove it’s necessary

• Think health insurance

Why Organizations don’t doRisk Management

• “Can Do” management style severely inhibits risk management

• Risk identification can make you look like a whiner

Ways to AvoidRisk Management

• “Managing risk is everybody’s business”

• “There is only one risk: The project might fail. And we’re managing that by working real hard to assure that doesn’t happen.”

The Uncertainty Spectrum

TOTALCERTAINTY

TOTALUNCERTAINTY

GENERALUNCERTAINTY

SPECIFICUNCERTAINTY

(Unknownunknowns) (Knowns)

NOInformation

CompleteInformation

PartialInformation

(Knownunknowns)

SCOPE OF PROJECT RISK MANAGEMENT*

*Note: in this range the information to be sought is known

Project Risk

Project Risk

Scope

IntegrationCommunication

Human Resources

Procurement

Cost

Quality

Time

INTEGRATING RISKPROJECT

MANAGEMENT INTEGRATION

SCOPE

QUALITY

TIME

COST

HUMAN RESOURCES

CONTRACT / PROCUREMENT

INFORMATION / COMMUNICATIONS

PROJECT RISK

Life Cycle and Environment Variables

Services, Plant, Materials: Performance

Cost Objectives, Restraints

Time Objectives, Restraints

Expectations Feasibility

Ideas, Directives, Data Exchange Accuracy

Requirements Standards

AvailabilityProductivity

Project Risk Management

A subset of project management that includes the processes concerned with

identifying, analyzing, and responding to project risk.

Risk Management Objectives

• Reduce the number of surprise events

• Minimize consequences of adverse events

• Maximize the results of positive events

Risk Classification

• Business risks vs. pure (insurable) risks

• Classified by uncertainty (business risks)

• Classified by impact on project elements

• Classified by their nature

• Classified by their source

• Classified by their probability to occur and amount at stake

Consequences of Risk Analysis

Positives• greater information is made available during

the course of planning and decision making• project objectives are verified• better communications• better probability that project realization will be

optimal• increased chance of project success

Consequences of Risk Analysis

Negatives• belief that all risks have been accounted for• project could be shut down

Some Considerations

• Real information is the key.• The relationship between uncertainty and

information is inverse.• For the project manager, conditions of relative

uncertainty (partial information) are the rule.• There is a natural resistance to formal risk

analysis.• Risks should only be taken to achieve a project

objective.

PMBOK FIGURE 11-1

PROJECT RISK MANAGEMENT OVERVIEW

Risk Identification

Inputs

Product Description

Other Planning Outputs

Historical Information

Tools & Techniques

Checklists

Flowcharting

Interviewing

Outputs

Sources of Risk

Potential Risk Events

Risk Symptoms

Inputs to other Processes

Risk Identification

Inputs

Product Description

Other Planning Outputs

Historical Information

Tools & Techniques

Checklists

Flowcharting

Interviewing

Outputs

Sources of Risk

Potential Risk Events

Risk Symptoms

Inputs to other Processes

Risk Quantification

Inputs

Stakeholder risk tolerances

Sources of Risk

Potential Risk Events

Cost Estimates

Activity Duration Estimates

Tools & Techniques

Expected Monetary Value

Statistical Sums

Simulation

Decision Trees

Expert Judgment

Outputs

Opportunities to pursue, threats to respond to

Opportunities to ignore, threats to accept

Risk Quantification

Inputs

Stakeholder risk tolerances

Sources of Risk

Potential Risk Events

Cost Estimates

Activity Duration Estimates

Tools & Techniques

Expected Monetary Value

Statistical Sums

Simulation

Decision Trees

Expert Judgment

Outputs

Opportunities to pursue, threats to respond to

Opportunities to ignore, threats to accept

Response Development

Inputs

Opportunities to pursue, threats to respond to

Opportunities to ignore, threats to accept

Tools & Techniques

Procurement

Contingency Planning

Alternative Strategies

Insurance

Outputs

Risk Management Plan

Inputs to other Processes

Contingency Plans

Reserves

Contractual Agreements

Response Development

Inputs

Opportunities to pursue, threats to respond to

Opportunities to ignore, threats to accept

Tools & Techniques

Procurement

Contingency Planning

Alternative Strategies

Insurance

Outputs

Risk Management Plan

Inputs to other Processes

Contingency Plans

Reserves

Contractual Agreements

Response Control

Inputs

Risk Management Plan

Actual Risk Events

Additional Risk Identification

Tools & Techniques

Workarounds

Additional Risk Response Development

Outputs

Corrective Action

Updates to Risk Management Plan

Response Control

Inputs

Risk Management Plan

Actual Risk Events

Additional Risk Identification

Tools & Techniques

Workarounds

Additional Risk Response Development

Outputs

Corrective Action

Updates to Risk Management Plan

Risk Identification

R iskIdentification

11.1

R iskQ uantifica tion

11.2

R isk ResponseD evelopm ent

11.3

R isk ResponseC ontro l

11.4

P ro jec t R iskM anagem ent

11.0

Risk identification is determining which risks are likely to affect the project and documenting the characteristics of each.

Typical Life Cycle ProfilesRisk versus Amount at Stake

Total project life cycleINCREASING

RISK

$

VALUE

TIME

Plan Accomplish

Phase 1Conceive

Phase 2Develop

Phase 3Execute

Phase 4Finish

Opportunity & Risk

Amount at Stake

(period when highestrisks are incurred)

(period of highestrisk impact)

Inputs to Risk Identification

• Product description– Specification– SOW– Contract

• Other planning outputs– WBS– OBS– Cost and Schedule estimates

Inputs to Risk Identification

• Historical information– Commercial databases– Corporate memory– Corporate database (lessons learned)– Websites

Inputs to Risk Identification

• Assumptions– Explicit– Implicit

• Critical success factors

PHASE 1: RISK IDENTIFICATIONIDENTIFY ALL POSSIBLE RISKS WHICH MAY SIGNIFICANTLY IMPACT

THE SUCCESS OF THE PROJECT -- CAN DO THIS BY:

CAUSE-AND-EFFECT ANALYSIS (WHAT COULD HAPPEN WHAT ENSUES)

EFFECT-AND-CAUSE ANALYSIS (WHAT OUTCOMES TO AVOID HOW THEY MIGHT OCCUR)

BRING IN THE EXPERTS ON THE PROGRAM AND QUESTION THEM

BRAINSTORM

WBS - INDIVIDUAL WORK PACKAGES PLUS COMBINATIONS THEREOF

WILLOUGHBY TEMPLATES, SEI TAXONOMY AND CHARELLET CHECKLIST

Risk typically examines possibility of suffering harm or loss; however, Risk Identification is also concerned with opportunities (positive outcomes) and threats (negative outcomes).

Risk typically examines possibility of suffering harm or loss; however, Risk Identification is also concerned with opportunities (positive outcomes) and threats (negative outcomes).

TYPES OF RISK

• Business vs. Insurable Risk

• Risk Sources– External Unpredictable– External Predictable– Internal Non-Technical– Technical– Legal

TYPES OF RISK (2)• Knowns

– An item or situation containing no uncertainty

• Known Unknowns

– Things which we know exist but do not know how they will affect us. These can be identified and evaluated.

• Unknown Unknowns

– Those risks that cannot be identified and evaluated (unexpected needs). These can be handled via contingency allowances.

TYPES OF RISK (3)• Risks can also be classified as:

– External Unpredictable

– External Predictable

– Internal Non-Technical

– Technical

– Legal

EXTERNAL UNPREDICTABLE • Regulatory

• Natural Hazards

• Postulated Events

• Unexpected Side Effects of the Project

• Failure to Complete Project Due to Uncontrollable External Events

EXTERNAL PREDICTABLE• Market Risks

• Operational

• Environmental Impacts

• Social Impacts

• Currency Risk

• Inflation

• Taxes

INTERNAL, NON-TECHNICAL

• Management

• Schedule

• Cost

• Cash Flow

• Loss of Potential Benefit or Profit

TECHNICAL

• Changes in Technology

• Performance Uncertainty

• Risks Associated with Project’s Technology

• Design

• Sheer Size or Complexity

LEGAL• Licensing

• Patent Rights

• Contractual Difficulties

• Outsider Suits

• Insider Suits

• Force Majeure (PMI’s Word)

OTHER RISK ID SOURCES• Overly Aggressive Cost Estimates

• Overly Aggressive Duration Estimates

• Staffing Plan - Personnel With Special Skills

• Procurement Management Plan

• Historical Project Files & Project Team Knowledge

• Commercial Databases

KEEP IN MIND

• How can you assess risks?– Break things down into individual elements and

determine their relationships

• What risks should you assess?– All of them– Concentrate on those with greatest impact and

most likely probability of occurrence

RISK FACTORSALL PROJECT RISKS ARE CHARACTERIZED BY THE FOLLOWING

THREE RISK FACTORS

RISK EVENT: PRECISELY WHAT MIGHT HAPPEN TO THE DETRIMENT OF THE PROJECT

Write it as an “If - Then” Statement

RISK PROBABILITY: HOW LIKELY THE EVENT IS TO OCCUR

AMOUNT AT STAKE: THE SEVERITY OF THE CONSEQUENCES

WITH THIS DATA, THE RISK EVENT STATUS ("CRITERION VALUE" ORRANKING) OF A GIVEN RISK EVENT CAN BE DETERMINED BY:

RISK EVENT STATUS = RISK PROBABILITY X AMOUNT AT STAKE

RISK EVENT vs. RISK SYMPTOM

RISK EVENT ARE DISCRETE OCCURRENCES

RISK SYMPTOM TRIGGERS

THESE ARE INDIRECT MANIFESTATIONS OF ACTUAL RISK EVENTS

EXAMPLES OF RISK SYMPTOMS:

POOR MORALE = EARLY WARNING SIGN OF SCHEDULE DELAY

EARLY PROJECT COST OVERRUN = POTENTIAL POOR PROJECT OVERALL ESTIMATING

Risk IdentificationTools and Techniques

• Checklists– Project Healthcheck

• Flowcharting– Cause & Effect (fishbone or Ishikawa charts

• What could happen What ensues

– Effect & Cause• Outcomes to avoid How they occur

– System or Process flowcharts

Risk IdentificationTools and Techniques

• Interviewing

• Brainstorming

Outputs• Sources of risk (i.e., categories)

– Stakeholder actions– Estimates– Staffing plans– Common sources of risk:

• Changes in requirements

• Design errors, omissions, and misunderstandings

• Poorly defined R & R

• Insufficiently skilled staff

Outputs

• Potential Risk events– Specific discrete events that might effect the

project– Generally include:

• Probability

• Alternative outcomes

• Timing

• Frequency (more than once?)

Outputs

• Risk Symptoms– Triggers, or trip wires, or indicators– Indirect manifestations of risk events

• Poor morale

• Lack of reported progress

• Inputs to other processes– Improved estimating– More training

Risk Quantification

R iskIdentification

11.1

R iskQ uantifica tion

11.2

R isk ResponseD evelopm ent

11.3

R isk ResponseC ontro l

11.4

P ro jec t R iskM anagem ent

11.0

Risk quantification consists of evaluating the risks and risk interactions to assess the range of possible project outcomes.

PHASE 2: RISK QUANTIFICATION

INCREASE THE UNDERSTANDING OF THE PROJECT

IDENTIFY THE ALTERNATIVES AVAILABLE

ENSURE THAT UNCERTAINTIES AND RISKS ARE ADEQUATELY CONSIDERED IN A STRUCTURED AND SYSTEMATIC WAY AND INCORPORATED INTO THE PLANNING AND DEVELOPMENT PROCESS

ESTABLISH THE IMPLICATIONS OF THESE UNCERTAINTIES ON ALL OTHER ASPECTS OF THE PROJECT

GOALS OF QUANTIFICATION (OR ASSESSMENT)

Risk Quantification - Inputs

• Stakeholder risk tolerances

• Sources of risk

• Potential risk events

• Cost estimates

• Activity duration estimates

Risk QuantificationTools and Techniques• Expected monetary value

• Statistical sums

• Simulation

• Decision trees

• Expert judgment

RISK ANALYSIS TECHNIQUESBRAINSTORMING - SPONTANEOUS CONTRIBUTION OF IDEAS FROM TEAM

DELPHI METHOD - METHOD TO DERIVE CONSENSUS USING EXPERT OPINION

MONTE CARLO - ITERATIVE SIMULATION USING RANDOM NUMBERS TO INCORPORATE PROBABILISTIC DATA AND DERIVE A PROBABILITY DISTRIBUTION OF THE FINAL RESULT

SENSITIVITY ANALYSIS - EVALUATE EFFECT OF A CHANGE IN A SINGLE VARIABLE ON THE ENTIRE PROJECT

DECISION TREE ANALYSIS - GRAPHICAL "EITHER / OR" CHOICES

UTILITY THEORY - TAKES ATTITUDE OF DECISION MAKER INTO ACCOUNT

DECISION THEORY - TECHNIQUE TO REACH DECISION UNDER UNCERTAINTYAND RISK. POINTS TO BEST POSSIBLE COURSE NO MATTERTHE FORECAST ACCURACY

PROBABILITY ANALYSIS - NEXT PAGE

SIMPLE PROBABILITYSIMPLE PROBABILITY EQUATION:

Pr (Event #1) x Pr (Event #2) = Pr (Both Events)

0.70 X 0.80 = 0.56 OR 56%

NOTE: THIS APPLIES TO INDEPENDENT EVENTS ONLY

OR

P(t) = P(A) * P(B)

PROBABILITY EXAMPLEDATA:

Probability of Scope = 0.70Probability of No Scope = 0.30

Probability of Approval = 0.80Probability of No Approval = 0.20

EXAMPLE:

Pr(Scope) x Pr(Approval) = 0.70 x 0.80 = 0.56Pr(Scope) x Pr(No Approval) = 0.70 x 0.20 = 0.14Pr(No Scope) x Pr(Approval) = 0.30 x 0.80 = 0.24Pr(No Scope) x Pr(No Approval) = 0.30 x 0.20 = 0.06 Total= 1.00

PRACTICAL APPLICATION -- DECISION TREE ANALYSIS

Expected Monetary Value (EMV)

• Product of two values– Risk event probability– Risk event value

• Valuation of the risk event is key– Must include tangible as well as intangible

value– 1 week slippage with minor client impact– 6 week slippage with major client impact

Expected Monitary Value Example Given the following:

Cost Probability

Optimistic $100,000 0.20

Most likely $130,000 0.60

Pessimistic $180,000 0.20

Expected Value Calculation:

Optimistic $100,000 x 0.20 = 20,000

Most likely $130,000 x 0.60 = 78,000

Pessimistic $180,000 x 0.20 = 36,000

Expected Monitary Value $134,000

(*EMV = Opt imistic + 4(most likely) + Pessimistic)6

* formula if probability is not known

EMV Example

• If no probabilities are given, useEMV=(Opt + 4*ML + Pes)/6

• EMV= ($100 +4*$130+$180)*1000/6

= $133,333

Descriptive Statistics

• Mean

• Mode

• Median

• Variance

• Standard Deviation

• Range

Descriptive Statistics Example

Test scores are 10, 20, 25, 40, 45, 45, 50, 55, 55, 60, 60, 60, 65, 65, 65, 70, 70, 70, 70, 70, 75, 80, 80, 85, 90, 90, 90, 95, 100

Mean: number obtained by dividing the sum of a set of quantities by the number of quantities in the set. (answer is 1855 / 29=64)

Mode: value or item occurring most frequently in a series of observations. (answer is 70 -it occurs 5 times)

Median: middle value in a distribution, above and below which lie an equal number of values (answer is 65)

Variance: average of the squares of the variations from the mean of a frequency distribution. (answer is 486.4)

Standard deviation: square root of the variance. (answer is 22)

Range: measure of the dispersion equal to the difference or interval between the smallest and the largest of the set of quantities. (answer is 90 or 100-10)

Approximations

• Mean = (Opt + 4*ML + Pes)/6

• SD = (Max - Min)/6

Exercise

Opt ML Pess EMV SDev Vari

Proj. A 100,000 125,000 180,000 130,000 13,000 169,000,000

Proj.B 80,000 100,000 125,000 100,833 7,500 5,625,000

Proj.C 75,000 130,000 180,000 129,167 17,500 306,250,000

So What?• Normal Distribution

– Mean is expected value– Mean = Mode = Median– Standard deviation is a measure of dispersion

about the mean• 68.27% of cases occur between Mean + SD and

Mean - SD

• 95.45% of cases occur between Mean+2SD and Mean-2SD

• 99.73% of cases occur between Mean+3sd and Mean-3SD

Mean

+ SD + 2SD + 3SD- SD- 2SD- 3SD

Blue = 68%

Blue + Green = 95%

Blue + Green + Red = 99.7%

Normal Distribution

34.1% 34.1%

13.6% 13.6% 1.1%1.1%

Mode

Mean

Median

Skewed Normal Distribution

BETA vs. TRIANGULAR DISTRIBUTIONS

EXPECTED VALUE

COST ESTIMATE

PROBABILITY

EXPECTED VALUE

COST ESTIMATE

PROBABILITY

BETA DISTRIBUTION

TRIANGULAR DISTRIBUTION

Variance = [(b - a) / 6]

Mean = (a + 4m + b) / 6 2

Mean = (a + m + b) / 3 Variance = [(b - a) 2 + (m - a) (m - b)] / 18

Simulation

Simulation uses a representation or model of a

system to analyze the behavior or

performance of the system.• Monte Carlo analysis is best known• results used to quantify risk of various schedule

choices

Monte Carlo

• Requires Optimistic, Most Likely, and Pessimistic estimates.

• Uses random number generator to select which value to use

• Calculates the database multiple times to develop a probability distribution of the data

Decision Trees

Aggressive schedule EMV = $110,000

Conservative schedule EMV = $7,000

Given the following decision tree: Outcome250 k

100 k

45 k

20 k

EMV150 k

40 k

9 k

16 k

60%

40%

20%

80%

aggressive

conservative

Choiceevent

Choiceevent

Choiceevent

UTILITY THEORY• Definition

– Endeavors to formalize management’s attitude toward risk of the decision maker.

• Types

– Risk Seeking

– Risk Neutral

– Risk Averse

Expert Judgment

Expert judgment can often be applied in lieu of or in addition to the mathematical techniques described above.

Derived from:• team members• others in or outside of organization• published findings• industry averages / statistics

QUALITY RISK

GOALS OF RISK MANAGEMENT

- INCREASE UNDERSTANDING OF PROJECT

- IMPROVE PLANS, DELIVERY, AND ID GREATEST RISKS

- WHERE TO FOCUS ATTENTION

REMAINING MAJOR PROJECT RISK AREA ...

WHAT IF PROJECT FAILS TO PERFORM AS EXPECTED DURING OPERATIONAL LIFE / PRODUCT LIFE CYCLE?

CONFORMANCE TO QUALITY REQUIREMENT REMEMBERED LONG AFTER COST AND SCHEDULE PERFORMANCE.

QUALITY MANAGEMENT HAS MOST IMPACT ON LONG-TERM PERCEIVED & ACTUAL SUCCESS OF PROJECT

SCHEDULE RISK

CAN MANAGE “CRITICAL PATH” BUT NOT MANAGE DURATION

REASON --> SCHEDULE RISK

HIGHEST RISK PATH = PATH WITH MOST PROJECT COMPLETION RISK

RISK IN ALL ACTIVITY DURATION BECAUSE FUTURE IS UNCERTAIN

LONGEST DURATION ACTIVITY RISKIEST

THEREFORE, NEED TO ID & MANAGE WHAT COULD CONTRIBUTE TO PROJECT DELAY -- COULD OVERRIDE MANAGEMENT OF CRITICAL PATH

C

START

FINISH

A D

B

E

MOST MEAN

ACTIVITY LOW LIKELY HIGH EXPECTED

A-B 8 9 10 9

B-C 4 5 6 5

C-E 0 0 0 0

B-E 1 6 7 4.7

A-D 4 9 14 9

D-E 1 2 7 3.3

SCHEDULE RISK (CONT'D)

SCHEDULE RISK (CONT'D)

START

FINISH

A D

B

E

SUM OF SUM OF SUM OF

PATH MOST LIKELY MEANS HIGHS

A-B-C-E 14 14 16

A-B-E 15 13.7 17

A-D-E 11 12.3 21

MOST RISKY A-B-E A-B-C-E A-D-E

Risk Quantification- Outputs

Opportunities to pursue, threats to respond to

Opportunities to ignore, threats to accept

Risk Response Development

R iskIdentification

11.1

R iskQ uantifica tion

11.2

R isk ResponseD evelopm ent

11.3

R isk ResponseC ontro l

11.4

P ro jec t R iskM anagem ent

11.0

Risk response development defines the enhancement steps for opportunities and responses to threats.

Risk Response Development

• Defines steps for– enhancing opportunities– responding to threats

Types of Responses

• Avoidance - eliminate

• Mitigation– Reduce EMV by reducing probability– Reduce Impact - buy insurance

• Acceptance– Active: develop plan to deal with risk if it

occurs – Passive: Accept risk (e.g., lower profit)

PLANNING ALTERNATIVES

• Project Managers have Several Response Options– Avoidance– Absorption– Adjustment– Deflection– Contingent Planning– A Combination of the Above

AVOIDANCE

• Defined

– Characterized by project manager statements such as: “This alternative is totally unacceptable to me

– You would take the appropriate steps to avoid this situation.

ABSORPTION

• Risk is Recognized-But Not Acted Upon

• Accept the Risk AS IS

• It’s a Matter of Policy• Retained & Absorbed (by prudential

allowances)

• Unrecognized, Unmanaged, or Ignored (by default)

ADJUSTMENT• Modification of the Project

– Scope

– Budget

– Schedule

– Quality Specification

– Combination of the Above

DEFLECTION

• Involves transfer of risk by such means as:

– Contracting Out to Another Party

– Insurance or Bonding

– By Recognizing it in the Contract

CONTINGENT PLANNING

CONTINGENT PLANNING IS A MEANS TO ADDRESS RISKS TO THE PROJECT THROUGH A FORMAL PROCESS AND PROVIDE RESOURCESTO MEET THE RISK EVENTS.

IT IS THE ESTABLISHMENT OF MANAGEMENT PLANS TO BE INVOKEDIN THE EVENT OF SPECIFIED RISK EVENTS

EXAMPLES:

THE PROVISION AND PRUDENT MANAGEMENT OF A CONTINGENCY ALLOWANCE IN THE BUDGET

THE PREPARATION OF SCHEDULE ALTERNATIVES AND WORK-AROUNDS

EMERGENCY RESPONSES TO DEAL WITH MAJOR SPECIFIC AREAS OF RISK

AN ASSESSMENT OF LIABILITIES IN THE EVENT OF A COMPLETE PROJECT SHUT-DOWN

Types of Responses

• Prevent risk from occurring– Reduce the probability that the event will occur– Eliminate means P=0

• Reduce the impact (think “containment”)– Buy insurance (monetary)– Alternative strategies (additional supplier to

PDQ)

CONTRACT STRATEGY

• To Select the Right Form of Contract Requires:– Identification of Specific Risks– Determination of how they should be shared

between the parties, and – The insertion of clear, legal language in the

contract documents to put it into effect.

CONTRACT TYPE vs. RISK

SCOPE OF WORK INFORMATION

UNCERTAINTY

DEGREE OF RISK

SUGGESTED RISKALLOCATION

CONTRACTTYPES

CPPF CPIF CPFF FPPI FFP

VERY LITTLE PARTIAL COMPLETE

HIGH MODERATE LOW

HIGH MEDIUM LOW

100%

0%

0%

100%

AGENCY (BUYER)

SELLER (CONTRACTOR)

CONTRACT TYPE vs. RISK (CONT'D)

COST ESTIMATE VALUE

PROBABILITY

80% 90% 95% 100% 110% 120% 140%

+/- 15%: FFP

+/- 50%: CPIF

+/- 25%: CPFF

> 50%: CPPF

Project A Well defined scope and work content. High probability of achieving realistic cost estimate at 100%

Project c Poorly defined scope and content. Low probability of 100% cost estimate

Project B Fairly well defined scope and work content. Fair probability of achieving 100% cost estimate

Suggested types of contract for various spreads

FAST-TRACKING

• Awarding contracts before all the information is complete to reduce the overall time for the project

• Much higher risk category!!

• Appropriate contingency allowances must be increased accordingly.

Risk Response Development - Inputs

Opportunities to pursue, threats to respond to

Opportunities to ignore, threats to accept

Risk Response DevelopmentTools and Techniques• Procurement

– Buy outside skills

• Contingency planning– what to do if the event occurs

– containment

• Alternative strategies– Prevention

• Insurance

Risk Response Development - Outputs• Risk management plan

• Inputs to other processes

• Contingency plans

• Reserves

• Contractual agreements

Risk Response Control

R iskIdentification

11.1

R iskQ uantifica tion

11.2

R isk ResponseD evelopm ent

11.3

R isk ResponseC ontro l

11.4

P ro jec t R iskM anagem ent

11.0

Risk response control involves responding to changes in risk over the life of the project.

PHASE 4: RISK RESPONSE

CONTROL• EXECUTE THE RISK MANAGEMENT PLAN FROM PHASE #3

-ID, QUANTIFY AND RESPOND TO ANY CHANGES EXECUTE WORKAROUNDS -- UNPLANNED RESPONSES TO NEGATIVE EVENTS -ADDITIONAL RISK RESPONSE DEVELOPMENT

•CURRENT PROJECT DATABASE

-DOCUMENTING ON-GOING RISKS

•BUILD HISTORICAL DATABASES

RELIABLE DATA IS HARD TO FIND! SHOULD CONSIST OF:

-RECORDED RISK EVENTS -EXPERIENCE ON PAST PROJECTS (SIMILAR IS PREFERRED)

•POST-PROJECT ASSESSMENT AND ARCHIVE UPDATE

Risk Response Control

• Respond to the changes in project risk over the life of the project

Risk Response Control - Inputs

• Risk management plan

• Actual risk events

• Additional risk identification

Risk Response ControlTools and Techniques

• Workarounds– Unplanned responses to unforeseen risks that

actually occur

• Additional risk response development– Revisions to the response, if it proves

inadequate

Risk Response Control - Outputs

• Corrective action– Implementing the risk management plan when

the risk occurs

• Updates to risk management plan– Revisions to the risk management plan as

circumstances require• Risk never materializes

• Probability of occurrence is reduced

Risk DocumentationHistorical database

Current project database

Post project assessment and archive update• Lessons learned• Plan variances• Actuals• Methods, tools and techniques• Case studies

SUMMARY

PROJECTS ARE LAUNCHED TO TAKE ADVANTAGE OF OPPORTUNITIES,BUT OPPORTUNITIES ARE ASSOCIATED WITH UNCERTAINTIES WHICHHAVE RISKS ATTACHED

RISK CAN NEVER BE 100% ELIMINATED

FOR THE PROJECT TO BE VIABLE, THE EXPECTED VALUE RESULTINGFROM A FAVORABLE PROBABILITY OF GAIN MUST BE HIGHER THANTHE CONSEQUENCES AND PROBABILITY OF LOSS

THEREFORE, THE RISKS ASSOCIATED WITH A PROJECT MUST RECEIVECAREFUL EXAMINATION IN THE CONTEXT OF THE ORGANIZATION'SWILLINGNESS OR AVERSION TO TAKING RISKS

THIS IS THE DOMAIN OF PROJECT RISK MANAGEMENT, WHICH FORMSA VITAL AND INTEGRAL PART OF PROJECT MANAGEMENT

When Should Risk Assessments be Carried Out?

Risk assessments should be carried out

as early as possible and then continuously.

Don’t take the risk if...

• the organization cannot afford to lose.• the exposure to the outcome is too great.• the situation (or project) is not worth it.• the odds are not in the project’s favor.• the benefits are not clearly identified.• there appear to be a large number of acceptable

alternatives.

Don’t take the risk if...

• the risk does not achieve the project objective.• the expected value from baseline assumptions is

negative.• the data is unorganized, without structure or

pattern.• there is not enough data to understand the results.• a contingency plan for recovery is not in place

should the results prove unsatisfactory.