Project Management.ppt

22
1 PROJECT MANAGEMENT For this portion of the session, the learning objectives are: Understand the variety of applications of Project Management. Understand the history of Project Management. Learn the quantitative techniques for Project Management. Learn the qualitative concepts of Project Management. Learn the “basics” of Microsoft Project.

description

 

Transcript of Project Management.ppt

Page 1: Project Management.ppt

1

PROJECT MANAGEMENT

For this portion of the session, the learning objectives are:

Understand the variety of applications of Project Management.

Understand the history of Project Management.

Learn the quantitative techniques for Project Management.

Learn the qualitative concepts of Project Management.

Learn the “basics” of Microsoft Project.

Page 2: Project Management.ppt

2

Project Management

Program Evaluation and Review Technique (PERT)

Critical Path Method (CPM)

Successful project management asks and answers the following questions:

1. What is an estimate of the project’s duration?

2. Among the project’s activities, which are likely to be “critical” activities in the sense that they will directly affect the project’s duration? (While the project is still in its planning phase, the project manager may take actions that will speed up one or more critical activities, thereby shortening the project’s planned duration. Furthermore, once the project begins, the project manager should closely monitor critical activities in order to prevent delays that would otherwise increase the project’s planned duration.)

3. For each of the project’s activities, what should be the scheduled Start Time and Finish Time?

4. What are the resource implications of the schedule for the activities?

5. Because a project never proceeds exactly as planned, how can the project manager quickly recognize and react to a “surprise” that might otherwise unfavorably affect the project’s duration?

Page 3: Project Management.ppt

3

Some Applications of Project Management

Construction or renovation of a plant, an office complex, a residential housing plan, a sports stadium, or a freeway.

Research and development associated with a new product.

Relocation of a major facility (e.g., a plant or a hospital).

Manufacture, maintenance, or repair, of a large item (e.g., an airplane or a nuclear reactor).

Installation of a new information technology (e.g., a new accounting system or a new supply chain management system).

Countdown for a launch of a rocket.

Making financial arrangements (e.g., an IPO or a revenue bond).

A fund raising campaign for a charity.

An advertising campaign.

A political campaign.

Performing a complex surgery.

Filming a major motion picture.

Page 4: Project Management.ppt

4

The History of PERT and CPM

In the late 1950s, two methodologies for managing projects emerged concurrently but independently:

the Program Evaluation and Review Technique (PERT)

the Critical Path Method (CPM).

PERT was developed jointly by representatives of the United States Navy and the management consulting firm of Booze, Allen, and Hamilton. Their motivation was the research and development associated with one of the Navy’s “new products”, the Polaris nuclear missile, designed to launch from a submarine beneath the ocean’s surface.

CPM was developed jointly by representatives of Du Pont and Remington-Rand. Their motivation was Du Pont’s desire to improve the planning and execution of both the construction of new production facilities and the maintenance shutdowns of existing facilities.

Although developed independently, PERT and CPM have much in common. Although traditionalists continue to distinguish between PERT and CPM, most practitioners today use the acronyms interchangeably or, as we will, combine them into the single acronym of PERT/CPM. In this session, we will learn the elements of PERT and CPM that are common to both.

Page 5: Project Management.ppt

5

PROJECT MANAGEMENT:

THE 3 PHASES AND 10 STEPS

Step 1: Project Decomposition Step 2: Specification of the Precedence Relationships Step 3: Estimation of the Activity Durations

Phase I: Project Formulation

Step 4: Construction of the Project Network

Step 5: Computation of Each Activity’s Earliest Start Time and Earliest Finish Time

Step 6: Computation of Each Activity’s Latest Start Time and Latest Finish Time

Step 7: Computation of Each Activity’s Total Slack and Identification of the Critical Path

Phase II: Planning & Scheduling

Step 8: Scheduling the Activities

Step 9: Monitoring of the Project’s Activities Phase III: Monitoring & Replanning Step 10: Replanning of the Remaining Portion of the

Project

Page 6: Project Management.ppt

6

THE DESIGNER GENES PROJECT

Designer Genes, a rapidly expanding genetic engineering firm, is relocating to a new office building. Jean Ettic, the project manager, has already leased a vacant office building and approved architectural plans for renovating it. To save money and to gain more control over the project, Jean herself will act as the general contractor for the renovation. Jean has already selected the subcontractors that she will employ. The move to the new building is complicated by the fact that Designer Genes' current outsourcing of its computer needs is no longer viable. Therefore, in moving to the new building, Designer Genes will use this opportunity to purchase a new main-frame computer and establish an in-house Computer Services Department.

Page 7: Project Management.ppt

7

Phase I: Project Formulation

Step 1: Project Decomposition

Step 2: Specification of the Precedence Relationships

Step 3: Estimation of the Activity Durations

EstimatedDuration Special

Code Description of Activity (days) Predecessors Responsibility RequirementsA Hiring of Manager of Computer Services Department 10 NoneB Structural Modifications 19 NoneC Enlarging and Resurfacing of Parking Lot 13 NoneD Hiring of Staff of Computer Services Department 8 AE Purchasing and Receipt of Computer 14 AF Electrical Modifications 4 BG Heating and Cooling Modifications 1 BH Plumbing Modifications 3 BI Exterior Painting and Installation of Exterior Fixtures 5 BJ Installation of Computer 4 E, F, GK Sheetrocking of Walls and Ceiling 6 F, G, HL Training of Staff of Computer Services Department 8 D, JM Interior Painting and Interior Decorating 9 KN Landscaping 7 C, I

“Coarse” versus “Fine” Decomposition

“Hard” versus “Soft” Activities

Redundant Predecessor Relationship

Cyclic Predecessor Relationships

Page 8: Project Management.ppt

8

Phase I: Project Formulation

Step 4: Construction of the Project Network

D (8)

A (10)

E (14) L (8)

F (4) J (4)

G (1) K (6)

START B (19) M (9) FINISH

H (3)

I (5)

N (7)

C (13)

Page 9: Project Management.ppt

9

Phase II: Planning & Scheduling

Step 5: Computation of Each Activity's EST & EFT

An activity's Earliest Start Time (EST) is the earliest possible time at which the activity can start.

An activity's Earliest Finish Time (EFT) is the earliest possible time at which the activity can finish.

Step 6: Computation of Each Activity's LST & LFT

An activity's Latest Start Time (LST) is the earliest possible time at which the activity can start without causing the project to finish after its earliest finish time.

An activity's Latest Finish Time (LFT) is the earliest possible time at which the activity can finish without causing the project to finish after its earliest finish time.

Step 7: Computation of Each Activity’s TS and Identification of the Critical Path

An activity's Total Slack (TS) is the maximum possible increase in the activity's duration that will not increase the project's earliest finish time (assuming that all other durations remain the same).

A critical activity has a Total Slack of 0. The critical path consists of the critical activities. (It is possible to have more than one critical path.)

Page 10: Project Management.ppt

10

Suppose it is desired to shorten the project's duration by one day. Then, the project manager should proceed as follows:

SHORTENING THE PROJECT’S DURATION

NOTE: If you need to shorten the project duration by more than one day, then repeat the above procedure one day at a time.

Page 11: Project Management.ppt

11

Phase II: Planning & Scheduling Step 8: Scheduling the Activities

The Gantt Chart (“Stripped Down” Version)NOTE: Temporarily ignore the [bracketed numbers] after the activity codes.

G [4]

1 2 30 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 36 37 3832 33 34 35

L [1]

M [3]

TIME

EARLIEST START TIME (EST) GANTT CHART

A [4]

B [1]

C [4]

D [4]

E [2]

F [3]

N [3]

I [3]

J [2]

K [2]

H [1]

Page 12: Project Management.ppt

12

GANTT CHARTS: EST versus LST

G [4]

1 2 30 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 36 37 3832 33 34 35

L [1]

M [3]

TIME

EARLIEST START TIME (EST) GANTT CHART

A [4]

B [1]

C [4]

D [4]

E [2]

F [3]

N [3]

I [3]

J [2]

K [2]

H [1]

G [4]

H [1]

I [3]

N [3]

C [4]

J [2]

B [1] F [3] K [2] M [3]

D [4]

L [1]

A [4]

E [2]

TIME

LATEST START TIME (LST) GANTT CHART

36 37 3832 33 34 3528 29 30 3124 25 26 2720 21 22 2316 17 18 1912 13 14 158 9 10 114 5 6 71 2 30

Page 13: Project Management.ppt

13

G [4]

= EST = LST = In Between EST & LST

C [4]

H [1]

I [3]

N [3]

J [2]

B [1] F [3] K [2] M [3]

D [4]

L [1]

A [4]

E [2]

TIME

HYBRID GANTT CHART

36 37 3832 33 34 3528 29 30 3124 25 26 2720 21 22 2316 17 18 1912 13 14 158 9 10 114 5 6 71 2 30

Page 14: Project Management.ppt

14

GANTT CHARTS: EST versus LST versus Hybrid

G [4]

1 2 30 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 36 37 3832 33 34 35

L [1]

M [3]

TIME

EARLIEST START TIME (EST) GANTT CHART

A [4]

B [1]

C [4]

D [4]

E [2]

F [3]

N [3]

I [3]

J [2]

K [2]

H [1]

G [4]

H [1]

I [3]

N [3]

C [4]

J [2]

B [1] F [3] K [2] M [3]

D [4]

L [1]

A [4]

E [2]

TIME

LATEST START TIME (LST) GANTT CHART

36 37 3832 33 34 3528 29 30 3124 25 26 2720 21 22 2316 17 18 1912 13 14 158 9 10 114 5 6 71 2 30

G [4]

= EST = LST = In Between EST & LST

C [4]

H [1]

I [3]

N [3]

J [2]

B [1] F [3] K [2] M [3]

D [4]

L [1]

A [4]

E [2]

TIME

HYBRID GANTT CHART

36 37 3832 33 34 3528 29 30 3124 25 26 2720 21 22 2316 17 18 1912 13 14 158 9 10 114 5 6 71 2 30

Page 15: Project Management.ppt

15

ADDING A RESOURCE TO THE DESIGNER GENES PROJECT

In the Designer Genes project, assume (unrealistically) that the same type of laborers perform all activities.

More specifically, assume that the table below displays the size of the daily workforce of these laborers required to perform each activity, where an activity’s daily requirement remains constant during the activity’s duration.

For example, for each day of activity C’s duration, 4 laborers are required.

ACTIVITY A B C D E F G H I J K L M N

REQUIRED SIZE OF DAILY WORKFORCE

(laborers)4 1 4 4 2 3 4 1 3 2 2 1 3 3

Note: In the preceding Gantt Charts, the above numbers were the [bracketed numbers] that appeared after the activity codes.

Page 16: Project Management.ppt

16

FROM EST GANTT CHART TO EST RESOURCE LOADING DIAGRAM

G [4]

1 2 30 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 36 37 3832 33 34 35

L [1]

M [3]

TIME

EARLIEST START TIME (EST) GANTT CHART

A [4]

B [1]

C [4]

D [4]

E [2]

F [3]

N [3]

I [3]

J [2]

K [2]

H [1]

4

3

8

7

6

77

3

13

99

11

1 2 30 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 36 37 3832 33 34 35TIME

EARLIEST START TIME (EST) RESOURCE LOADING DIAGRAM

13

12

11

10

9

8

7

6

17

16

15

14

5

4

3

LA

BO

RE

RS

0

1

2

20

19

18

Page 17: Project Management.ppt

17

FROM LST GANTT CHART TO LST RESOURCE LOADING DIAGRAM

G [4]

H [1]

I [3]

N [3]

C [4]

J [2]

B [1] F [3] K [2] M [3]

D [4]

L [1]

A [4]

E [2]

TIME

LATEST START TIME (LST) GANTT CHART

36 37 3832 33 34 3528 29 30 3124 25 26 2720 21 22 2316 17 18 1912 13 14 158 9 10 114 5 6 71 2 30

16

11

7

10

9

18

12

15

1

5

3

7

5

4

3

LA

BO

RE

RS

0

1

2

20

19

18

17

16

15

14

TIME

LATEST START TIME (LST) RESOURCE LOADING DIAGRAM

13

12

11

10

9

8

7

6

36 37 3832 33 34 3528 29 30 3124 25 26 2720 21 22 2316 17 18 1912 13 14 158 9 10 114 5 6 71 2 30

Page 18: Project Management.ppt

18

FROM HYBRID GANTT CHART TO HYBRID RESOURCE LOADING DIAGRAM

G [4]

= EST = LST = In Between EST & LST

C [4]

H [1]

I [3]

N [3]

J [2]

B [1] F [3] K [2] M [3]

D [4]

L [1]

A [4]

E [2]

TIME

HYBRID GANTT CHART

36 37 3832 33 34 3528 29 30 3124 25 26 2720 21 22 2316 17 18 1912 13 14 158 9 10 114 5 6 71 2 30

7

4

7

9

7

8

5

9

11

1 2 30 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 36 37 3832 33 34 35TIME

HYBRID RESOURCE LOADING DIAGRAM

13

12

11

10

9

8

7

6

17

16

15

14

5

4

3

LA

BO

RE

RS

0

1

2

20

19

18

Page 19: Project Management.ppt

19

RESOURE LOADING DIAGRAMS: EST versus LST versus HYBRID

4

3

LA

BO

RE

RS

8

7

6

77

3

13

99

11

1 2 30 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 36 37 3832 33 34 35TIME

EARLIEST START TIME (EST) RESOURCE LOADING DIAGRAM

13

12

11

10

9

8

7

6

14

5

4

3

0

1

2

LA

BO

RE

RS

16

11

7

10

9

18

12

15

1

5

3

7

5

4

3

0

1

2

19

18

17

16

15

14

TIME

LATEST START TIME (LST) RESOURCE LOADING DIAGRAM

13

12

11

10

9

8

7

6

36 37 3832 33 34 3528 29 30 3124 25 26 2720 21 22 2316 17 18 1912 13 14 158 9 10 114 5 6 71 2 30

7

4LA

BO

RE

RS

7

9

7

8

5

9

11

1 2 30 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 36 37 3832 33 34 35TIME

HYBRID RESOURCE LOADING DIAGRAM12

11

10

9

8

7

6

5

4

3

0

1

2

Page 20: Project Management.ppt

20

In fact, from among all possible Hybrid Schedules, there is one that has a peak resource usage of 10 laborers.

Desirable Characteristics of a Resource Loading Diagram

1.

2.

What happens when there is more than one resource?

Page 21: Project Management.ppt

21

Phase III: Monitoring & Replanning Step 9: Monitoring of the Project’s Activities Step 10: Replanning of the Remaining Portion of the Project

Thus far, Phases I & II have provided a plan for how the project should go. However, once the project begins, this plan must undergo periodic revision. A revision should occur in one of the following two ways:

On a periodic basis at the end of every week, 2 weeks, or month – whichever is most appropriate.

Whenever there is a “big surprise”.

Step 9: Monitoring of the Project’s Activities

As the project progresses, the project manager must closely monitor the project’s activities, comparing the planned progress to the actual progress. Such monitoring will enable the project manager to quickly recognize and react to an unforeseen event that significantly affects one or more activity durations.

Step 10: Replanning of the Remaining Portion of the Project

When it’s time for a periodic review (e.g., an end-of-the-week review), or when an unforeseen event occurs that significantly affects one or more activity durations, the project manager should proceed as follows:

1. Considering the most up-to-date information, the project manager should revise the estimate of all activity durations. (At the time of revision, there is no uncertainty about the durations of the activities that have already finished.

However, for those activities either in-progress or not-yet-started, the most up-to-date information should lead to more accurate estimates of the durations.)

2. Using these revised estimates of the activity durations, the project manager should determine a revised plan by repeating Phase II’s planning and scheduling.

Page 22: Project Management.ppt

22

PROJECT MANAGEMENT: QUALITATIVE CONCEPTS

1. Post the project network, schedule, and other data prominently (e.g., on a wall or on a website).

2. Form a “Planning & Monitoring Committee” consisting of the Project Manager and the persons responsible for the major activities. Have this Planning & Monitoring Committee meet regularly to review any new information and to anticipate potential problems. For each potential problem, formulate a plan that will either resolve or mitigate the problem.

3. Create a culture that fosters timely and honest communication. There should be no “punishment” for conveying bad news. The “punishment” should be for delaying or concealing bad news.

4. Learn from prior similar projects (e.g., Boeing with its 707, 727, 737, 747).5. Create a “Change Order Board” to review each change order, assess the change

order’s impact on both schedule and budget, and decide for each change order which is more important – schedule or budget.

6. Leave as little as possible to chance. Before the project begins, anticipate what might go wrong and prepare a contingency plan (e.g., Boeing’s approach to the transportation of the 767’s body sections from Japan to Seattle).

7. Create a policy that a project is never done until it has been reviewed in a timely manner by asking and answering the following three questions:

What did we do well that must been sustained in the future when performing similar projects? What did we do poorly that must be improved in the future when performing similar projects? Have we “transferred” the knowledge gained to the corporate level, so that the entire organization can benefit?