Pre-Feasibility Report Working

download Pre-Feasibility Report Working

of 27

Transcript of Pre-Feasibility Report Working

  • 8/8/2019 Pre-Feasibility Report Working

    1/30

    ITEM COST (RS.)

    Construction Office / Store 675,000

    Construction Service Stations 850,000

    Masonry Work 120,000

    Mechanical Repairs Equipment 90,000

    Denting Equipment 100,000

    Painting Equipment 30,000Wheel Alignment Machine 1,000,000

    Wheel Balancing Machine 650,000

    High Pressure Cleaning Equipment 550,000

    Piston Pump 250,000

    Spare Parts Purchases 125,000

    Lubricant Purchases 25,000

    Advance Rent & Deposit 900,000

    Working Capital 552,000

    Pre Operating Costs 50,000

    Office Furniture & Equipment 80,000

    Total Cost 6,047,000

  • 8/8/2019 Pre-Feasibility Report Working

    2/30

    Capacity Human Resource Equipmen

    867 Cars / Month 5 (Management) Local / Eurpoean /

    20 (Technical Staff) Chinese

    Financial Summary

    Project Cost IRR NPV Payback Period

    6,047,000 33% Rs. 4,099,801 3 Years & 5 months

  • 8/8/2019 Pre-Feasibility Report Working

    3/30

    Location

    High Income

    Locality

    Cost of Capital

    (WACC)

    17.50%

  • 8/8/2019 Pre-Feasibility Report Working

    4/30

    MECHANICAL REPAIRS & MAINTENANCE

    Equipment Number Estimated Cost (Rs.)

    Complete Mechanical Toolbox 2 26,000

    Work Bench 2 5,000

    Vice 2 9,000

    Tool Box Cupboard 1 5,000

    Voltmeter / Ammeter 2 5,000Timing Light 2 12,000

    Battery Charger 1 7,000

    Compression Gauge 1 6,000

    Others - 15,000

    Total 90,000

    DENTING

    Equipment Number Estimated Cost (Rs.)

    Denting Toolbox 2 20,000

    Mechanical Toolbox 1 13,000

    Pressure Jack (Large) 1 30,000

    Gas Cylinder 1 6,000

    Carbide Tank 1 3,000

    Welding Kits 2 6,000

    Drill Machine (Hand) 2 3,000

    Puller Jack 1 4,000

    Others - 15,000

    Total 100,000

    PAINTING

    Equipment Number

    Painting Compressor (2 hp; 1k lbs) 1

    Spray Gun (Small) 1

    Spray Gun (Large) 1

    Pipe 1

    Others -

    Total

    HIGH PRESSURE CLEANINGEquipment Number

    High Pressure Cleaner (incl.Piston Pump)

    Piston Pump

    Total

    WHEEL ALIGNMENT & BALANCING

    Equipment Number Estimated Cost (Rs.)

  • 8/8/2019 Pre-Feasibility Report Working

    5/30

  • 8/8/2019 Pre-Feasibility Report Working

    6/30

    Estimated Cost (Rs.

    15,000

    3,000

    4,000

    1,000

    7,000

    30,000

    Estimated Cost (Rs.

    1 550,000

    1 250,000

    800,000

  • 8/8/2019 Pre-Feasibility Report Working

    7/30

  • 8/8/2019 Pre-Feasibility Report Working

    8/30

    OFFICE FURNITURE

    Item Number Estimated Cost (Rs.)

    Table & Chair Set (Owner) 1 10,000

    Table & Chair Set (Customer Service) 1 5,000

    Air Conditioner (Split Unit) 1 30,000

    Waiting Chairs 10 10,000

    Sofa Set for Customers 1 15,000Curtains / Interior Dcor - 10,000

    Total 80,000

  • 8/8/2019 Pre-Feasibility Report Working

    9/30

    GENERAL MANAGEMENT

    Designation / Type Number Monthly Salary (Rs.)

    Owner 1 -

    Accountant 1 2500 (10- 12 Hrs.)

    Purchaser 1 5,000

    Office Assistant / Store Keeper 1 2,500

    Guard 1 2000 (Night Only)

    JOB / DUTY ALLOCATION

    Designation / Type Number Monthly Salary (Rs.)

    Foreman 1 8,500

    MECHANICAL REPAIRS & MAINTENANCE

    Mechanics (Ustad) 2 12,000

    Assistant Mechanics 2 8,000

    Helpers 2 3,000

    DENTING

    Head Denter (Ustad) 1 8,000

    Denters 2 12,000

    Assistant Denter 1 4,000

    Helper 1 2,000

    PAINTING

    Painter Ustad 1 8,000

    Assistant Painters 2 10,000

    Helper 1 2,000

    Total 122,500

    WHEEL ALIGNMENT & BALANCING

    Designation / Type Number Monthly Salary (Rs.)

    Operator (Incharge) 1 8,000

    Assistant Operator 1 4,000

    HIGH PRESSURE CLEANING

    Cleaner (Incharge) 1 8,000

    Assistant Cleaner 1 4,000

    Total 4 24,000

    16

  • 8/8/2019 Pre-Feasibility Report Working

    10/30

    SERVICE GROSS MARGIN

    Denting & Painting 29%

    > Cosmetic Touchups 28%

    > Accidental Repairs 29%

    > Full Body Restoration 30%

    Mechanical Repairs & Maintenance 25%

    > Maintenance Services 33%

    > Major Repairs 14%

    Wheel Alignment & Balancing 90%

    > Alignment 91%

    > Balancing 89%

    High Pressure Cleaning 79%

    Overall 56%

  • 8/8/2019 Pre-Feasibility Report Working

    11/30

    SERVICE MARGIN

    Spare Parts 10.00%

    Lubricants 12.50%

    Subletting 25.00%

  • 8/8/2019 Pre-Feasibility Report Working

    12/30

    MASONRY WORK FOR BAY AR

    Item

    Mechanical Work (Duct & Ramp)

    Denting

    Painting

    Total

    CONSTRUCTION COST FOR WHEEL ALIGNMENT / BALANCING & PR

    Item

    Wheel Alignment & Balancing

    Ramp for Alignment

    High Pressure Cleaning

    Total

  • 8/8/2019 Pre-Feasibility Report Working

    13/30

    AS

    Bay Areas Estimated Cost (Rs.)

    6 60,000

    4 30,000

    4 30,000

    14 120,000

    SSURE CLEANING

    Estimated Cost (Rs.)

    400,000

    50,000

    400,000

    850,000

  • 8/8/2019 Pre-Feasibility Report Working

    14/30

    UTILITY MONTHLY CHARGES (RS.)

    Electricity 12,000

    Water 10,000

    Telephone 2,500

    Entertainment 1,000

    Total 25,500

  • 8/8/2019 Pre-Feasibility Report Working

    15/30

  • 8/8/2019 Pre-Feasibility Report Working

    16/30

  • 8/8/2019 Pre-Feasibility Report Working

    17/30

  • 8/8/2019 Pre-Feasibility Report Working

    18/30

    Particulars Rate

    Required return on equity 20.00%

    Cost of finance 15.00%

    Weighted average cost of capital 17.50%

  • 8/8/2019 Pre-Feasibility Report Working

    19/30

  • 8/8/2019 Pre-Feasibility Report Working

    20/30

    Period

    Per Year

    Per Year

    Per Year

    Per Year

    Per Year

    Per Year

    Per annum (Diminishing Balance)

    Per annum (Diminishing Balance)

    Per annum (Diminishing Balance)

    Per annum (Diminishing Balance)

    Per annum (Diminishing Balance)

    Straight Line Per Year

    Per annum

    Income Tax on Salaried Individuals

  • 8/8/2019 Pre-Feasibility Report Working

    21/30

    Item Revenue / Fee Charged (Rs.)

    R

    evenue

    Denting & Painting 181,000

    Cosmetic Touchup

    (3 Piece Patching & 5,000 6 30,000

    Paint)

    Accidental Repairs 13,000 7 91,000

    Full Body Restoration 30,000 2 60,000

    Mechnical Repairs 190,000

    General Repairs 1,500 100 150,000

    Major Repairs 20,000 2 40,000

    TOTAL 371,000

    ASSUMPTIONS ASSU

    Full Body Restoration % age of Revenue General Repairs

    Spare Parts 10% Spare Parts

    Subletting 10% Subletting

    Lubricants 2.50% Lubricants

    ASSUMPTIONS ASSU

    Accidental Repairs % age of Revenue Major Repairs

    Spare Parts 5% Spare Parts

    Subletting 5% Subletting

    Lubricants 1% Lubricants

    F

    ee

    Charge

    d

    (

    Rs.)

    E

    stima

    ted

    C

    ars

  • 8/8/2019 Pre-Feasibility Report Working

    22/30

    Cost of Sales (Rs.) Margin

    (%)

    M

    ateria

    l

    L

    abor

    S

    pare

    Parts

    L

    ubrican

    ts

    S

    ubletting

    T

    otalCos

    t

    132,271 27%

    1,000 3283 - - - 25,698 14%

    3,000 4,957 591 116 520 64,285 29%

    6,000 9,350 2,727 667 2,400 42,288 30%

    135,556 29%

    - 247 614 67 84 101,130 33%

    - 12,350 3,636 427 800 34,426 14%

    267,827 28%

    PTIONS

    % age of Revenue

    45%

    7%

    5%

    PTIONS

    % age of Revenue

    20%

    5%

    2.50%

  • 8/8/2019 Pre-Feasibility Report Working

    23/30

    MONTHLY REVENUE / COST SCHEDULE

    Item Revenue / Fee Charged (Rs.)

    Es

    tima

    tedCars

    Revenue

    Ma

    teria

    l

    La

    bor

    Spare

    Parts

    Wheel Alignment / Balancing 125,000

    Wheel Alignment 350 250 87,500 - 32 -

    Wheel Balancing 150 250 37,500 - 16 -

    High Pressure Cleaning 62,500

    High Pressure Cleaning 250 250 62,500 20 48 -

    TOTAL 187,500

    Fee

    Charged

    (Rs.)

  • 8/8/2019 Pre-Feasibility Report Working

    24/30

    Gross

    Margin

    (%)

    Lu

    brican

    ts

    Su

    bletting

    To

    talCos

    t

    12,000 90%

    - - 8,000 91%

    - - 4,000 89%

    17,000 73%

    - - 17,000 73%

    29,000 85%

    (Rs.)

  • 8/8/2019 Pre-Feasibility Report Working

    25/30

    Projected Income Statement (Rs.) Year1 Year2 Year3

    Revenue 6,702,000 7,506,240 8,406,989

    Denting & Painting 2,172,000 2,432,640 2,724,557

    Genera l Repairs / Maintenance 2,280,000 2,553,600 2,860,032

    Wheel Alignment & Balancing 1,500,000 1,680,000 1,881,600

    High Pressure Cleaning 750,000 840,000 940,800

    Net Sales ### ### ###

    Cost of Sales ### ### ###

    Gross Profit ### ### ###

    Gross Profit Margin 46% 47% 48%

    General Administrative & Selling Expenses

    Salaries 144,000 158,400 174,240

    Utilities Expense 306,000 336,600 370,260

    Rent Expense 900,000 990,000 1,089,000

    Office Misc. & Traveling Exp. 60,000 66,000 72,600

    Amort. of Preliminary Expenses 10,000 10,000 10,000

    Maintenance Expense 91,667 45,833 -

    Depreciation Expense 567,833 529,383 494,778

    Subtotal ### ### ###

    Operating Income ### ### ###

    Financial Charges(15%PerAnnum) 424,156 353,587 271,673

    Earnings Before Taxes 636,414 ### ###

    Tax 101,603 256,910 437,576Net Profit 534,810 841,404 ###

    Monthly Profit After Tax 44,568 70,117 98,077

  • 8/8/2019 Pre-Feasibility Report Working

    26/30

    Year4 Year5 Year6 Year7 Year8 Year9 Year10

    9,415,827 10,545,727 11,811,214 13,228,560 14,815,987 16,593,905 18,585,174

    3,051,504 3,417,684 3,827,806 4,287,143 4,801,600 5,377,792 6,023,127

    3,203,236 3,587,624 4,018,139 4,500,316 5,040,354 5,645,196 6,322,620

    2,107,392 2,360,279 2,643,513 2,960,734 3,316,022 3,713,945 4,159,618

    1,053,696 1,180,140 1,321,756 1,480,367 1,658,011 1,856,972 2,079,809

    ### ### ### ### ### ### ###

    ### 5,215,022 5,736,524 6,310,176 6,941,194 7,635,313 8,398,844

    ### 5,330,705 6,074,690 6,918,383 7,874,793 8,958,592 ###

    49% 50% 51% 52% 53% 53% 54%

    191,664 210,830 231,913 255,105 280,615 308,677 339,544

    407,286 448,015 492,816 542,098 596,307 655,938 721,532

    1,197,900 1,317,690 1,449,459 1,594,405 1,753,845 1,929,230 2,122,153

    79,860 87,846 96,631 106,294 116,923 128,615 141,477

    10,000 10,000 - - - - -

    100,833 50,417 - 110,917 55,458 - 122,008

    481,967 453,937 428,710 426,172 405,738 387,348 392,980

    ### 2,578,735 2,699,529 3,034,990 3,208,888 3,409,808 3,839,694

    ### 2,751,970 3,375,161 3,883,393 4,665,905 5,548,784 6,346,635

    176,591 66,224 - - - - -

    ### 2,685,746 3,375,161 3,883,393 4,665,905 5,548,784 6,346,635

    582,579 812,511 1,053,806 1,231,688 1,505,567 1,814,574 2,093,822### 1,873,235 2,321,355 2,651,706 3,160,338 3,734,210 4,252,813

    120,518 156,103 193,446 220,975 263,362 311,184 354,401

  • 8/8/2019 Pre-Feasibility Report Working

    27/30

    Projected Balance Sheet (Rs.) Year 0 Year 1 Year 2 Year 3

    Assets

    Current Assets

    Cash & Bank Balance 552,000 826,879 1,371,554 2,032,376

    Accounts Receivable (Net) 0 83,775 93,828 105,087

    Lubricants & S.Parts Inventory 150,000 165,000 181,500 199,650

    Prepaid Rent 900,000 900,000 900,000 900,000Total Current Assets ### ### ### ###

    Fixed Assets

    Building & Workshop 1,645,000 1,480,500 1,332,450 1,199,205

    Technical Equipment 220,000 198,000 178,200 160,380

    Office Furniture 80,000 72,000 64,800 58,320

    Machinery 2,200,000 1,851,667 1,519,833 1,202,850

    Total Fixed Assets ### ### ### ###

    Intangible Assets

    Pre Operating Costs 50,000 40,000 30,000 20,000

    Total Assets ### ### ### ###

    Owner's Equity 3,023,500 3,258,310 3,799,714 4,576,640

    Long Term Liability 3,023,500 2,584,510 2,074,951 1,483,478

    Total Equity & Liabilities ### ### ### ###

  • 8/8/2019 Pre-Feasibility Report Working

    28/30

    Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10

    2,146,430 3,100,595 4,960,684 6,328,771 8,595,775 11,162,954 13,266,437

    117,698 131,822 147,640 165,357 185,200 207,424 232,315

    219,615 241,577 265,734 292,308 321,538 353,692 389,061

    900,000 900,000 900,000 900,000 900,000 900,000 900,000### ### ### ### ### ### ###

    1,079,285 971,356 874,220 786,798 708,119 637,307 573,576

    144,342 129,908 116,917 105,225 94,703 85,233 76,709

    52,488 47,239 42,515 38,264 34,437 30,994 27,894

    1,485,898 1,175,975 876,878 1,232,857 932,104 639,244 1,063,353

    ### ### ### ### 1,769,363 1,392,777 1,741,532

    10,000 0 0 0 0 0 0

    ### ### ### ### ### ### ###

    5,522,859 6,846,094 8,317,448 9,969,154 11,879,492 14,113,702 16,616,515

    796,922 0 0 0 0 0 0

    ### ### ### ### ### ### ###

  • 8/8/2019 Pre-Feasibility Report Working

    29/30

    Projected Statement of Cash Flows (Rs.) Year 0 Year 1 Year 2 Year 3

    Cash Flow From Operating Activities

    Net Profit 0 534,810 841,404 1,176,927

    Add: Depreciation Expense 0 567,833 529,383 494,778

    Amortization Expense 0 10,000 10,000 10,000

    (Increase) / decrease in A/c Rec. -83,775 -10,053 -11,259

    (Increase) / decrease in inventory -15,000 -16,500 -18,150

    Net Cash Flow From Operations 0 1,013,869 1,354,234 1,652,295

    Cash Flow From Financing Activities

    Receipt of Long Term Debt 3,023,500

    Repayment of Long Term Debt -438,990 -509,559 -591,473

    Owner's Equity 3,023,500 -300,000 -300,000 -400,000

    Net Cash Flow From Fin. Activities 6,047,000 -738,990 -809,559 -991,473

    Cash Flow From Investing Activities

    Capital Expenditure -1,645,000

    Office Furniture -80,000

    Technical Equipment -2,670,000

    Lubricant & Parts Inventory -150,000

    Preliminary Operating Expenses -50,000

    Advance Rent -900,000

    Net Cash Flow From Investing Activities -5,495,000 0 0 0

    NET CASH FLOW 552,000 274,879 544,675 660,822

    Cash at the Beginning of the Period 0 552,000 826,879 1,371,554

    Cash at the End of the Period 552,000 826,879 1,371,554 2,032,376

  • 8/8/2019 Pre-Feasibility Report Working

    30/30

    Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10

    1,446,218 1,873,235 2,321,355 2,651,706 3,160,338 3,734,210 4,252,813

    481,967 453,937 428,710 426,172 405,738 387,348 392,980

    10,000 10,000 0 0 0 0 0

    -12,610 -14,124 -15,819 -17,717 -19,843 -22,224 -24,891

    -19,965 -21,962 -24,158 -26,573 -29,231 -32,154 -35,369

    1,905,610 2,301,087 2,710,088 3,033,588 3,517,003 4,067,180 4,585,532

    -686,555 -796,922

    -500,000 -550,000 -850,000 -1,000,000 -1,250,000 -1,500,000 -1,750,000

    -1,186,555 -1,346,922 -850,000 -1,000,000 -1,250,000 -1,500,000 -1,750,000

    -605,000 -665,500 -732,050

    -605,000 0 0 -665,500 0 0 -732,050

    114,055 954,165 1,860,088 1,368,088 2,267,003 2,567,180 2,103,482

    2,032,376 2,146,430 3,100,595 4,960,684 6,328,771 8,595,775 11,162,954

    2,146,430 3,100,595 4,960,684 6,328,771 8,595,775 11,162,954 13,266,437