Planning Habitat Restoration for Dredging Projects WEDA Midwest Chapter Conference Green Bay, Wisconsin April 27, 2012 Jack Brunner

description

Planning Habitat Restoration for Dredging Projects. WEDA Midwest Chapter Conference Green Bay, Wisconsin April 27, 2012 Jack Brunner. Outline. Advantages of Habitat Restoration Planning Considerations Grand Calumet River: Case Study Lessons Learned Summary. - PowerPoint PPT Presentation

Transcript of Planning Habitat Restoration for Dredging Projects

Page 1: Planning Habitat Restoration for Dredging Projects

Planning Habitat Restoration forDredging Projects

WEDA Midwest Chapter ConferenceGreen Bay, Wisconsin

April 27, 2012Jack Brunner

Page 2: Planning Habitat Restoration for Dredging Projects

Outline• Advantages of Habitat Restoration

• Planning Considerations

• Grand Calumet River: Case Study

• Lessons Learned

• Summary

Page 3: Planning Habitat Restoration for Dredging Projects

Advantages of Habitat Restoration

• Wildlife and Ecosystem Benefits

• Community Relations

• Program Priority - EPA, USACE, and State

• Permitting Requirements

• Cost Savings

Page 4: Planning Habitat Restoration for Dredging Projects

Planning Considerations:Assessment Factors

Page 5: Planning Habitat Restoration for Dredging Projects

Planning Considerations: Project Components

• Stakeholders• Funding/Authority• Site Access• Substrate• Hydrology• Vegetative

Communities

Page 6: Planning Habitat Restoration for Dredging Projects

Planning Considerations:Project Components

• Planting Strategy• Performance

Standards• T&E Species• Invasive Species• Predator Control

• Maintenance

Page 7: Planning Habitat Restoration for Dredging Projects

Planning Considerations

Page 8: Planning Habitat Restoration for Dredging Projects

Grand Calumet River• Great Lakes Legacy Act project

• EPA GLNPO, USFWS and State of Indiana

• Grand Calumet River AOC, Lake County, IN

Page 9: Planning Habitat Restoration for Dredging Projects

WBGCR Reaches 1 & 2 and Roxana Marsh

• Restoration goals– Excavate ~109,000 CY of contaminated sediment

from 19-acre marsh

– Dredge river and wetland shelves

– Remove invasive species

– Restore native habitat

– Stabilize banks

• Construction substantially complete: June 2012

Page 10: Planning Habitat Restoration for Dredging Projects

West Branch Reaches 1 & 2 and Roxana Marsh

Page 11: Planning Habitat Restoration for Dredging Projects

Roxana Marsh – Restoration Plan

Page 12: Planning Habitat Restoration for Dredging Projects

Invasive Species Control• Sprayed Phragmites in non-dredge areas

• Utility and other access limitations

Page 13: Planning Habitat Restoration for Dredging Projects

Marsh Excavation• Removed Phragmites root mass with

contamination

• Used road mats for access

Page 14: Planning Habitat Restoration for Dredging Projects

Marsh Excavation

Page 15: Planning Habitat Restoration for Dredging Projects

Marsh Excavation

Page 16: Planning Habitat Restoration for Dredging Projects

River Dredging• Undercut Phragmites along banks

• Removed from the site

Page 17: Planning Habitat Restoration for Dredging Projects

Sand Capping• Placed hydraulically in river

• Placed mechanically in marsh and wetland shelves

Page 18: Planning Habitat Restoration for Dredging Projects

Mowing• Prescribed burn restrictions

• Mowed after herbicide application

Page 19: Planning Habitat Restoration for Dredging Projects

Raking or Tilling• Tilled to improve seed to soil contact

• Depth limitations in pipeline buffer areas

• Raked as needed

Page 20: Planning Habitat Restoration for Dredging Projects

Seeding and Planting• Adjust planting zones

based on as-built conditions

• Blanket seeded areas

Page 21: Planning Habitat Restoration for Dredging Projects

Providing Habitat Structure• Removed trees for site access

• Placed within pond and along shoreline as habitat structure

Page 22: Planning Habitat Restoration for Dredging Projects

Bank Stabilization• Used bioengineering techniques

• Modified design based on field conditions

Page 23: Planning Habitat Restoration for Dredging Projects

EBGCR Reaches 4A and 4B

Page 24: Planning Habitat Restoration for Dredging Projects

EBGCR Reaches 4A and 4B

Page 25: Planning Habitat Restoration for Dredging Projects

Lessons Learned• Involve stakeholders early in planning

• Spray invasives before sediment removal

• Use prescribed burning where possible

• Adjust planting zones as needed

• Blanket seeded areas

• Install and maintain predator control fencing

Page 26: Planning Habitat Restoration for Dredging Projects

Summary• Consider assessment factors and project

components during planning and design

• Employ adaptive management during project implementation

• Restoration takes time

Page 27: Planning Habitat Restoration for Dredging Projects

Questions?