Pelton Turbine Design scope

download Pelton Turbine Design scope

of 19

Transcript of Pelton Turbine Design scope

  • 7/30/2019 Pelton Turbine Design scope

    1/19

    Background

    Pelton wheels are a high head, low flow, high velocity turbine. Currently, they are

    used in renewable energy by integrating them with existing renewable power systems (wind

    turbines, large streams, etc.). For this reason, the Civil Engineering Department at University

    of Idaho has a Pelton Wheel Laboratory as part of their Hydraulics curriculum.

    Unfortunately, the quality of the two existing Pelton Wheels leaves much to be

    desired. First, the current operational assembly is a smaller, integrated package. It is in

    working order, but has fewer measurable quantities. This reduces the overall learning value

    for students as they are unable to directly measure Energy transfer through the system. In

    addition, the systems small size makes it inefficient.

    The second Pelton wheel assembly is an older, more robust, system. However, it is

    currently inoperable and suffers from several design flaws. The tank is old, top heavy, and

    deteriorating. For these reasons, our team designed a new tank, frame, and mounting

    assembly to be used with the older three phase motor/pump assembly and turbine.

    In this new assembly, students will be able to measure quantities necessary to

    analyze power transfer and energy flow through the system. Concerns for the students

    safety and learning experience made it necessary to take this ambitious approach to

    improving the laboratory setup.

  • 7/30/2019 Pelton Turbine Design scope

    2/19

    Problem Definition

    At a fundamental level, the goal of the Pelton Wheel Development Project is to

    improve the existing implementation of a Pelton wheel inside the Civil Engineering

    hydraulics laboratory. To this end, our team has several specific tasks in order to achieve

    this overarching goal of improving the laboratory and the learning value that students gain

    from it.

    First and foremost is the design of a new mobile tank frame. It is to be constructed

    with angle iron and metal sheeting that support the tank and additional loading components

    on the top of the assembly. The parts for this task have been ordered, designed for, and are

    ready for fabrication and welding.

    Going forward, the first task that must be tackled in the new semester is fabrication

    and the welding of the new assembly. In parallel with this, design and further specification

    of the electrical load must be completed. The depth and automation level of this solution is

    directly tied in to our budget limitations, as well as time constraints.

    The rough budget for the Pelton Wheel Development Project is altogether about

    $4,000. The University of Idaho Civil Engineering Department has committed $2,000 to our

    project, while the Shell Grant has given an estimate of up to $2,000. We have already

    bought some mechanical components for the system. The new tank with shipping cost $380

    and framing parts so far have cost $260. Additional framing components will cost another

    $100. The most expensive part of the design is the torque transducer, which will cost about

    $1,700. The generator will be about $300 and the microcontroller and electrical load

    components will be around $100.

  • 7/30/2019 Pelton Turbine Design scope

    3/19

    Total spending so far has been $640 taken from the CE Department money. The

    torque transducer will be purchased with the Shell Grant money, using $1,700 of their

    offered budget. The rest of the materials (generator, frame components, microcontroller,

    and electrical load) will cost about $500. This will leave about $860 leftover from the CE

    Department budget.

  • 7/30/2019 Pelton Turbine Design scope

    4/19

    Project Plan

    A list of design parameters for both the tank and torque transducer has been

    compiled and verified. Mechanical components have been purchased and the new tank will

    be fabricated, primarily due to efforts by Ken and Phil, by February. Meanwhile, Ken, Ian,

    and Jenny, will be designing loading logic that allows for fast and precise variations in

    induced torque. Simulations of the generators performance will be developed by Ian and

    Phil prior to implementation to rate the resistive elements in the array, the wires

    transferring the power to the load architecture, and the relays that will be used to

    implement the control logic. Once this has been accomplished the loading system can be

    purchased and tested. Ken, Ian, and Jenny, will monitor the interactions of the control

    system and load architecture and compare the results to expectations. The design will then

    be revised as needed to maximize system performance. Once the design has been finalized

    the system can be mounted on the assembly and used in demonstrations.

    Concepts Considered

    Mechanical:

  • 7/30/2019 Pelton Turbine Design scope

    5/19

    The two primary options for the pelton wheel lab station were to modify one of the

    existing solutions or to create a new solution that would suit our needs. There were two

    existing lab stations which were available to be modified: an older and larger model, or a

    newer, smaller model.

    The older model was a long, shallow, two-part tank mounted on a tubular metal

    chassis. The pump was mounted under the upper part of the tank, and the turbine was

    solidly mounted on top of the upper tank above the pump. Output power and torque were

    obtained by measuring the force from a lever arm on a brake clamped and tightened on the

    output shaft. Flow rate was measured by a v-notch gauge. Trundle bearings on the pump

    allow the mechanical power produced by the pump motor to be measured. A wattmeter is

    available for measuring the electrical power into the motor.

    While testing was not possible on this lab station due to a missing force gauge, our

    client informed us that in prior tests the overall efficiency of this station was low, mainly due

    to poor tank and pump design and placement. This lab station would not have been difficult

    to modify as there was a lip on the inside of the top of the tank, allowing for easy mounting

    of additional components. The long, narrow shape of this lab station would require that a

    generator be mounted axially along the tank, with the electrical load further down the

    length of the tank.

    The newer lab station is shorter, with a larger cross section. The tank, frame, and

    pump compartment form an integrated structure, while the turbine is mounted to a plate

    which can be repositioned over the trough the water falls in. As with the older model,

    torque is measured with a brake, however this one is a band tightened around the pulley

    from both ends rather than clamped to the pulley. Flow measurement is very imprecise as

  • 7/30/2019 Pelton Turbine Design scope

    6/19

    it is done by timing how long it takes for a smaller reservoir to fill to a specified level. Power

    into and out of the pump cannot be directly measured.

    The pump motor on this lab station is 580W, according to the nameplate, however

    the pelton wheel produces approximately 38W of power at most, for an overall system

    efficiency of less than 10%. Modification of this assembly would be more difficult due to the

    integrated nature of the tank and frame. The generator and electrical load could be placed

    in a number of configurations as there is more free space on the top of the assembly.

    In addition to modifying the two existing solutions, we considered building a new

    tank/chassis assembly that existing components, as well as future components, could be

    integrated into.

    The tank for the new assembly had multiple options, each with their own advantages

    and disadvantages. A short, wide tank would provide more stability to the final design, as it

    would have a wider footprint and a lower center of gravity. However, a taller tank would

    provide better net positive suction head to the pump, as well as reduce the chance of a

    vortex forming which could allow introduction of air into the pump inlet. A custom tank

    design was briefly considered as it could allow for inclusion of the advantages of both,

    however it was quickly ruled out due to cost.

    The main options for the material for the frame were flat metal strips, metal tubing,

    and angle iron. The metal strips were the cheapest option but provided the least support.

    The metal tubing was more expensive than the flat metal, however provided more support.

    The round sides would present challenges in mounting the tank. The angle iron provided

  • 7/30/2019 Pelton Turbine Design scope

    7/19

    the greatest deal of support and ease of mounting the tank; however it was the most

    expensive.

    There were two main geometric arrangements considered for the chassis. The first

    had the pump mounted sideways next to the tank at the bottom of the assembly, with a

    metal frame holding the tank and the turbine/generator assembly in place. This option

    reduces the height to improve stability while maintaining the pump near the bottom of the

    assembly. Alternately, a two-level frame was considered which would allow the pump to be

    underneath the tank. This option provides more space for the motor controller, as well as

    allowing for pump to be positioned so a longer run of straight piping could be provided to

    the pump inlet.

    Electrical:

    One of the primary concerns of our client is coupling an electrical torque transducer

    between the turbine and load. Knowing that this would a necessary component, we had to

    constrain our design decisions (as well as budget) to match these needs. Since the electrical

    rotary torque transducer will have an output, we knew having some control logic, to handle

    inputs like torque and possibly a venture flow-meter, would be desirable.

    Moreover, this torque transducer must be coupled to an electrical generator. The

    purpose of this generator is to act as the loading device on the turbine. This is in place of the

    manual braking arm which was discussed earlier. The generator will be acting as an

    electrical load on the turbine; a way to manually adjust load in real-time is a necessary

    solution.

  • 7/30/2019 Pelton Turbine Design scope

    8/19

    Since our project had a wide operating range of speeds, it was desirable to select a

    machine with a large speed bandwidth, as well as a linear torque-versus speed output

    characteristic. This is desirable since the lab requires students to vary load, and the

    relationship between torque and speed of the pelton turbine is also linear. With these

    considerations in mind, the two main machine types considered were a synchronous

    induction machine, as well as a direct current permanent magnet machine. The

    consideration for each machine is further discussed in the following section.

  • 7/30/2019 Pelton Turbine Design scope

    9/19

    Concept Selection

    Mechanical:

    The main decision made for the project was that a new tank and chassis assembly

    was wanted. Both of the existing solutions had significant disadvantages, and they would

    have given a final product that both our team and our client would likely be unsatisfied with.

    The older lab station had more learning potential. More quantities could be measured, but

    the tank was deteriorating and required repairs and extensive cleaning. The new lab station

    was in good condition but was very limited in the measureable quantities. Thus it was

    decided to design a new assembly despite the additional work that would be required.

    The tank selected for the final design was the taller one. Although it was not ideal for

    stability, the increased pump efficiency was deemed to be more important. As stated

    earlier, the custom tank design was not considered due to the significant increase in price.

    A rectangular tank was chosen as it would be much easier to mount than a cylindrical tank.

    In addition to the shape, a thicker tank was chosen to meet client specifications.

    A two-level frame was chosen for the final design. While this was counterproductive

    to our goal of increased stability, it was necessary as our client strongly desired increased

    pump efficiency, including a longer run of straight pipe leading into the inlet, necessitating

    that the pump be mounted below the tank. Angle iron was chosen for the portion of the

    frame holding the tank as it could be arranged in such a way as to easily hold the tank with

    minimal amounts of material. It was decided that the lower frame would be made out of

    the metal tubing as it is cheaper than the angle iron and did not need to interface with a flat

    surface.

  • 7/30/2019 Pelton Turbine Design scope

    10/19

    Electrical:

    As discussed previously, it was necessary for students to operate in a wide speed

    range (from 0 rpm non-moving turbine to no load conditions). For this reason, an optimal

    solution would have a linear torque speed characteristic. This is desirable since the lab

    requires students to vary load, and the relationship between torque and speed of the pelton

    turbine is also linear. For these reasons, a direct current permanent magnet brush machine

    was selected. They are very robust machines with all the characteristics desired. A

    synchronous induction machine would have been a better simulation of the large pelton

    wheels used in industry. However, this solution was not practical for cost and size

    considerations (small scale) of our project.

    In order to control the load level of our project, as well as the output current, a

    microcontroller will be used in conjunction with relays. Do to availability, low cost, and

    familiarity with the PIC32MX7 Cerebot, our team plans to do initial load testing and design

    with this board using the MPLab Integrated Development Environment.

    System Architecture

    Mechanical systems:

  • 7/30/2019 Pelton Turbine Design scope

    11/19

    Once the tank shape and frame components had been selected, the main

    mechanical considerations were providing adequate suction head, improving stability,

    ensuring the frame can support the assembly, providing adequate area to mount

    components, and preventing vortex formation and air introduction.

    No data was available for the required net positive suction head for the pump, so a

    direct calculation was not possible. Therefore, the tank height was selected based on the

    height of the existing tanks. Our client informed us that the older tank, which was

    approximately 1ft tall, was not sufficient for this purpose. The newer lab station,

    approximately 30 inches tall, had no evidence of cavitation when in use. Due to the lack of

    data on the pump, the minimum tank height was unknown; however a tank height of 30

    inches was selected, as although this may have not been the minimum, it was sufficient to

    prevent cavitation.

    In order to improve the stability, two things were done. First, the base of the

    assembly was made wider. The goal was to make it larger than the existing solution while

    still being narrow enough to be maneuverable through doors. An upper limit of 2 feet

    was established for the entire assembly, and the width of the main frame was decided to be

    24 inches. Second, the center of gravity was lowered by making the tank as close to the

    ground as possible. The lower bound for this was determined by providing sufficient space

    for the piping to run under the tank for improved pump efficiency. The wheels and lower

    frame are approximately 14 inches high, which is a significant improvement over the

    existing solution, which had the tank more than 2 feet above the ground.

    A statics analysis was conducted to determine the stresses on the main frame

    beams. While there were smaller sizes that could support the weight, 1.5 inch angle iron

  • 7/30/2019 Pelton Turbine Design scope

    12/19

    was selected as smaller sizes would have caused difficulties in providing enough space for

    the tank to rest on. The corner posts on the tank will extend 2 inches above the tank to

    attach the upper assembly consisting of the turbine, generator, and electrical load. The

    lower frame is made of 1.5 inch steel tubing (sized to match the angle iron), and extends 1

    foot to the rear of the tank to provide a place to support the motor controller and pump.

    The lower frame is 8 inches high to provide room for the pipe to pass under the tank.

    The final mechanical concern was preventing air introduction into the pump inlet.

    There are two main mechanisms that would cause air introduction are entrained air from

    the water plunging into the tank, and formation of an air core vortex in the tank. In order to

    counter this, a flow spreader and a vortex breaker were included. The flow spreader is a

    slanted plate mounted below the turbine, extending into the water into the tank. Water

    falls onto the plate and runs down into the water in the tank rather than plunging directly

    into the tank from the turbine. The vortex breaker is a pair of crossed thin metal plates

    positioned on top of the pipe inlet which prevents the circular water motion that would lead

    to a vortex.

    Electrical systems:

    At a rudimentary level, adding an electrical generator will have increased value to

    students by allowing them to see energy transfer and power flow through the entire system

    (electricalmechanical hydraulicmechanical electrical). On top of this, being able

    to manually adjust mechanical loading by varying the electrical load on the generator should

    give a better applications understanding from a students view.

  • 7/30/2019 Pelton Turbine Design scope

    13/19

    The specific torque transducer selected for the project was justified based on the

    worst case possible scenario. This was used assuming maximum efficiency in all

    components, as well as maximum torque. This worst case scenario is shown in graphical

    format in Figure 4 of appendices. Adding this torque transducer, as well as the electrical

    generator, satisfies to basic requirements of the project directly from our client. The

    quantitative analysis of the torque requirements is shown in the calculations on Figure 3a &

    b.

  • 7/30/2019 Pelton Turbine Design scope

    14/19

    Future Work

    Next Semester

    Going forward, the team is prepared to begin fabricating the new tank frame and

    chassis. In addition to construction the frame, the new tank will need to be slightly modified

    from its manufactured dimensions. This will incorporate how we are going to remount and

    reassemble the three phase induction motor and pump assembly.

    Ideally, mechanical construction and mounting will not extend far into the semester.

    With that in mind, the team plans for the mechanical aspect of the new assembly to be

    completed by early February of the New Year. This leaves the remainder of the semester to

    begin debugging and testing the electrical load on the physical assembly.

    At a minimum, we would like to have a working assembly with an adjustable load. A

    baseline assembly would be a manually adjustable rheostat configuration to electrically load

    the machine. If team ideals are realized, well have implemented a microcontroller to sense

    and measure voltage and current (with the load being adjustable using pushbuttons). This

    setup would incorporate the use of relays and an LED display.

    Future Phases of Work

    There will still be plenty of work for future teams to improve upon after our team is

    finished next semester. Namely, this includes further automation and implementation in

    regards to real time data acquisition.

    More specifically, our client had requested a change-order at preliminary design

    review. This involved integrating real-time data acquisition into a program called LabView.

  • 7/30/2019 Pelton Turbine Design scope

    15/19

    Due to the lateness of this request and the number of team members qualified to

    incorporate this solution; it is a tertiary item. For this reason, this would be a great project

    for future Computer Engineers or Computer Scientists who could improve upon the data

    acquisition and interfacing with a PC lab station.

    Appendices

    Figure 1: Moment and Force calculations

  • 7/30/2019 Pelton Turbine Design scope

    16/19

    Figure 2: Moment and Force diagrams

    Figure 3a: Torque and Power calculations

  • 7/30/2019 Pelton Turbine Design scope

    17/19

    Figure 3b: Torque and Power calculations

  • 7/30/2019 Pelton Turbine Design scope

    18/19

    Figure 4: Power and Torque as a function of Speed

    Figure 5: New Tank Design

  • 7/30/2019 Pelton Turbine Design scope

    19/19

    Figure 6: Team Schedule