PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
PDD Preparation Process and PDD Preparation Process and FormatFormat
Amr Abdel-Aziz, Ph.D.Consultant
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
CDM Project CycleCDM Project Cycle First step in
the CDM project cycle
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
Who Prepares a PDD ?Who Prepares a PDD ?Responsibility of project participant
Usually, project participant hires a consultant to prepare the PDD
Project participant should avail funds for PDD preparation
Can be funded through special arrangements (CD Projects, seller and buyer agreement, etc.)
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
Why Prepare a PDD ?Why Prepare a PDD ?
Validation is done based on a PDD
One of the requirements to be registered as a CDM project
Registration is a step done prior to verification and certification
i.e. can not have a CDM project and consequently certified emission reductions (CERs) without a PDD
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
PDD Cost ?PDD Cost ?
Approximately $ 40,000 to $ 50,000
– Baseline $ 20,000 to $ 30,000– Monitoring Plan $ 10,000 to 20,000
Cost can be reduced by:
– Development of Standardized baseline– National Experts– Previous experience of existing PDDs
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
PDD Preparation ProcessPDD Preparation Process
Prepare Project Identification Note (PIN) prior to Proceeding with PDD
Preliminary approval of Designated National Authority (DNA)
Prepare PDD
Assign DOE for validation
Submission of PDD to DNA to obtain official approval for project (voluntarily participation + assists in achieving SD)
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
Registration ProcessRegistration Process
Prior to registration, DOE shall make the PDD available for public comments for 30 days (parties, stakeholders, UN-FCCC accredited NGO)
Registration requires the following:– PDD– DNA written approval– Explanation of how DOE has taken into account public comments
Registration of project should be completed in 8 weeks, unless there is a request for review
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
PDD FormatPDD FormatPDD format available on UNFCCC CDM website
Must prepare PDD according to format
PDD Format available in 6 official languages of UN
Working language of the board is English Must submit in english
7 Sections and 5 Annexes
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
PDD FormatPDD FormatA. General Description of Project Activity
B. Baseline Methodology
C. Duration of Project Activity / Crediting Period
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
PDD FormatPDD Format
D. Monitoring Methodology and Plan
E. Calculation of GHG Emissions by Sources
F. Environmental Impacts
G. Stakeholder Comments
Objections
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
PDD FormatPDD FormatAnnex 1 : Contact Info on Project Participants
Annex 2 : Info Regarding Public Funding
Annex 3 : New Baseline Methodology
Annex 4: New Monitoring Methodology
Annex 5: Table of Baseline Data
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
Proposing a new MethodologyProposing a new Methodology
Have to submit draft PDD + Annex 3 for new baseline methodology + Annex 4 for new monitoring methodology
Takes approximately 4 months to get approved by Meth panel and EB
Public comments are invited for 15 days
Better use existing approved methodology to reduce time
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
Small Scale Projects - CriteriaSmall Scale Projects - CriteriaRenewable energy project activities with a maximum
output capacity equivalent of up to: 15 MW Energy efficiency improvement project activities which
reduce energy consumption, on the supply and/or demand side, by up to the equivalent of:
15 GWh per year Other project activities that both reduce anthropogenic
emissions by sources and directly emit less than: 15 ktCO2eq annually
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
Small Scale Projects - RequirementsSmall Scale Projects - Requirements
Reduced requirements for PDD preparation
Simplified baseline methodologies by project category
Simplified Monitoring methodologies by project category
Less cost in preparation
Same DOE may undertake validation and verification
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
Small Scale Projects - FormatSmall Scale Projects - FormatA. General description of project activity
B. Baseline methodology
C. Duration of the project activity/crediting period
D. Monitoring methodology and plan
E. Calculation of GHG emission by sources
F. Environmental impacts
G. Stakeholder comments
Annex 1. Contact information on project participants
Annex 2. Information regarding public funding
Annex 3. New baseline methodology
Annex 4. New monitoring methodology
Annex 5. Table of baseline data
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
Bundling and DebundlingBundling and Debundling
Bundling
– Combining a number of small scale projects in one PDD to reduce transaction costs
– Projects may be bundled as long as the total size is below limits for single project
Debundling a large project to benefit from small scale simplified procedures is not allowed
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
Useful Resources and ToolsUseful Resources and Tools
Approved methodologies on UNFCCC CDM website
PDDs under review on UNFCCC CDM website
IPCC guidelines for emission estimation
PDD guidelines
CDM guidebook
PDD Preparation Cairo, June 14th -15th , 2004
TIMS/EEAA CD4CDM- Third National Workshop (Phase II) UNEP RISO / APEX
RecommendationsRecommendationsDo not underestimate the difficulty of preparing a
PDD
Use conservative assumptions
Be transparent and “truthful”
A good PDD increases the chances of accepting a project
Process entails several check points (Stakeholder comments, validation, Public comments, may be a request for review)