Partnering to Rebuild after the Oso...

19
4/12/2016 1 Partnering to Rebuild after the Oso Landslide By Janice Fahning, Megan Slater, Jason Smith, and Becki Kniveton

Transcript of Partnering to Rebuild after the Oso...

4/12/2016

1

Partnering to Rebuild after the Oso Landslide

By Janice Fahning, Megan Slater, Jason Smith, and Becki Kniveton

4/12/2016

2

SR 530 Slide

Emergency Response Phase 2: Reconstruction/RestorationApril 29, 2014 to Present

Six projects totaling $43 million

• Emergency Temporary Berm Constructionand Dewatering

• North Fork Stillaguamish River Pilot Channel

• SR 530 Access Road Maintenance and Traffic Control

• SR 530 Roadway Clearing

• SR 530 Emergency Roadway Reconstruction– Streams/drainage restoration

– Flood protection

– Mitigation for environmental impacts

• SR 530 Incident Debris Removal

4/12/2016

3

Emergency Temporary Berm Construction and Dewatering | $300,000 U.S. Army Corps of Engineers and Snohomish County

North Fork Stillaguamish River Pilot Channel | $480,000BCI Contracting Inc. – Amphibious Excavation

4/12/2016

4

SR 530 Access Road Maintenance and Traffic Control | $3.4 million WSDOT and Granite Construction

SR 530 Roadway Clearing Project $5.0 million

4/12/2016

5

SR 530 Emergency Roadway Reconstruction Project $21.0 million WSDOT – Atkinson - Jacobs

SR 530 Incident Debris Removal Project $13.0 million

4/12/2016

6

Procurement

• Traffic Impacts

• Schedule

• Earthwork Movement

• Community Impacts

• Environmental Impacts

SR 530 Project Limits

4/12/2016

7

Staging

Staging

4/12/2016

8

Staging

Earthwork Movement

4/12/2016

9

Earthwork Movement

Earthwork Movement

4/12/2016

10

Reducing Environmental Impacts• Fish Passage Design with Tribal Agencies

• Wetland Delineation

• Stream Delineation

• Marbled Murrelet & Spotted Owl Assessment

• Coordination between WSDOT, County, and different contractors (IMCO, Granite, Atkinson)

• Reducing Impacts to Wetlands with design refinement (2:1 Slopes, Roadway Alignment, Roadway Elevation)

Key Partners• FEMA• Snohomish County

• Public Works• Parks• Community Development

• Stillaguamish Tribe of Indians• Washington Dept. of Fish and

Wildlife• US Army Corps of Engineers• Washington State Ecology• Atkinson Construction• Jacobs

Reducing Community Impacts

• Local contractors and people hired from the surrounding community to work on the reconstruction and debris removal.

• Creation of on-site mitigation (instead of using proposed mitigation bank) reduced project costs, created open space for the County, and preserved high-quality wetlands.

• One-on-one coordination with adjacent property owners.

4/12/2016

11

SR 530 Landslide Recovery Timeline

Reconstructed SR 530 Open To TrafficSeptember 22nd

Two-Lane Detour OpenedJune 20th

Design & Reconstruct SR 530 - June 13th to September 22nd

DB Team Controls SR 530June 16th

Contract AwardedMay 30th

WSDOT Releases RFP April 29th

FEMA Rescue and Recovery – March 22nd to June 22nd

Landslide March 22nd

3 months6 months

Comparison of Project Delivery Models

Typical Design-Bid-Build Project Delivery

2.5-3 years

• Endangered Species Act (ESA)

• Section 106• NEPA• SEPA

• Section 404/401 Permitting• Mitigation Plan/Design• State and Local Permitting

• Environmental Construction and Commitment Monitoring

SR 530 Design-Build Project Delivery

18 months

• Agency Coordination• Culvert design/sizing• Mitigation Coordination• Emergency Permits• Construction Monitoring

• ATF Section 404/401 Permitting• Mitigation Plan/Design• ATF Endangered Species Act

Consultation

• NHPA Section 106 Consultation• Snohomish County Local Permitting• Environmental Construction and

Commitment Monitoring

RoadConstruction3-4 months

MitigationConstruction

2 months

MitigationConstruction

2 months

Preliminary Design/NEPA12 months

Final Design/Permitting12 to 18 months

After-the-fact Permitting/Mitigation

12 months

Design and Construction

4 months

4/12/2016

12

Emergency Permitting & Restoration

SR 530 Restoration & Permitting Timeline

Sept. 2014 Roadway open to public

Sept. 2014 - March 2015 Restore roadside/staging areas

July 2014 - March 2015 Design mitigation site

July 2014 – Sept. 2015 Complete regulatory permitting

Sept. – Oct 2015 Construct Linda Lee McPhersonMitigation Site

4/12/2016

13

Emergency Permitting & Restoration

Proposed Mitigation

4/12/2016

14

Wetland, Stream, & Buffer Mitigation

soil stockpile

area

existing wetland

Endangered Species Act ReviewPotential Marbled Murrelet/Northern Spotted Owl Habitat

Drains to Stillaguamish River(salmon-bearing stream)

WDFW In-Water Work Window:August 1-15Marbled Murrelet

Nesting Season:April 1 – Sept. 23

Northern Spotted Owl Early Nesting Season:March 1- July 15

4/12/2016

15

SR 530 Landslide Recovery Timeline

construction planting

Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec

X X X X X

X X X X X

X X X X X X X X X X X X

Allowed

Allowed with restrictions/Not likely to adversely affect

X Likely to adversely affect

Construction – Grading and Soil Amendment

4/12/2016

16

Stream Restoration

McPherson Mitigation Site

4/12/2016

17

Environmental Successes/Design Build Innovations

• Collaboration focused on the community and environment allowed flexibility by the contractor, designer, and agencies as the project progressed

• Right-sizing culverts and the onsite wetland and stream mitigation site saved money, restored streams and wetlands, is a memorial to Linda McPherson, and was transferred to Snohomish County Parks as a protected natural area

• Extraordinary construction water quality management by Atkinson

• Reuse of excavated soil on Snohomish County’s White Horse Trail reconstruction

• Contractors shared security costs

Successful Project Outcomes• Completed reconstruction of SR 530 in just 6

months after the landslide — construction lasted only 13 weeks.

• Opened two-way temporary road within days of contract award.

• Coordinated, designed, and constructed six fish passage culverts.

• Designed and restored wetlands at two staging areas.

• Designed, permitted, and constructed the Linda Lee McPherson wetland and stream mitigation site on 36.3 acres.

• Saved WSDOT $5.4 million over the engineer’s estimate.

4/12/2016

18

McPherson Mitigation Site“The goal of putting a high price tag on the use of the existing mitigation site was to incentivize the DB to minimize impacts to aquatic resources but it had an unexpected—but extraordinary—result. The DB decided that it was a better value to purchase and develop their own mitigation site, McPherson. This is unprecedented in my experience with the agency and it resulted in the acquisition and protection of a really high quality property in the immediate impact area, the McPherson site.”

-Linda Cooley, WSDOT Environmental

Tips to share

• Start planning now• Bringing your A Team• Assign areas of responsibility • Have extra people on hand• Start tracking – daily logs, dollars expended, labor

hours.• Communicate, Communicate, Communicate• Use internal and external resources• Recognize and tend to emotions • Give grace to people

4/12/2016

19

Questions?

Contact Info:

Janice Fahning Megan SlaterSnohomish Co. Atkinson [email protected] [email protected]

Jason Smith Becki KnivetonJacobs [email protected] [email protected]