16
PARADIP PORT TRUST INVITATION OF BUDGETARY OFFER FOR ELECTRICAL INSTALLATION TO MILENNIUM GUEST HOUSE AT MADHUBAN. SUBMISSION OF BUDGETARY OFFER ON OR BEFORE Dt.02/07/2018 EXECUTIVE ENGINER (ELECT.) PORT ELECTRICLA DIVISION III PARADIP PORT TRUST, PARADIP, JAGATSINGHPUR, ODISHA 754142 Contact No.9861244414 Email Id: [email protected]

Transcript of PARADIP PORT TRUST INVITATION OF BUDGETARY OFFER FOR · 2018-06-22 · paradip port trust...

PARADIP PORT TRUST

INVITATION OF BUDGETARY OFFER

FOR

ELECTRICAL INSTALLATION TO MILENNIUM GUEST HOUSE AT

MADHUBAN.

SUBMISSION OF BUDGETARY OFFER

ON OR BEFORE Dt.02/07/2018

EXECUTIVE ENGINER (ELECT.)

PORT ELECTRICLA DIVISION – III

PARADIP PORT TRUST,

PARADIP, JAGATSINGHPUR,

ODISHA – 754142

Contact No.9861244414

Email Id: [email protected]

REQUEST FOR BUDGETARY OFFER

(A) GENERAL INFORMATIONS:

Sl. No. Item Details

1. Name of Work Electrical installation to Millennium Guest House at

Madhuban.

2. Department / Organization ELECTRICAL & MECHANICAL DEPARTMENT /

PARADIP PORT TRUST

3. Executive Division Port Electrical Division.

4 Officer Inviting the Offer Executive Engineer.

5. Immediate Next Authority Superintending Engineer

6. Sanctioning Authority Dy. Chairman, PPT

7. Executing Authority Executive Engineer

(B) OTHER INFORMATIONS:

Sl. No. Item Date Time

1 Publication date 22/06/2018 13:30 Hrs.

2.a) Document download start date 22/06/2018 13:30 Hrs.

b) Document download end date 02/07/2018 15:00 Hrs.

3.a) Start date for seeking Clarification on-line 22/06/2018 13:30 Hrs.

b) Last date for seeking Clarification on-line 29/06/2018 15:00 Hrs.

4. Date of uploading response to Clarifications sought 30/06/2018 17:00 Hrs.

5. Offer Submission end date 02/07/2018 15:00 Hrs.

6. Offer Validity period 120 days

7. Currency of Offer Indian Rupee

8. Language of Offer English

Budgetary offer for the work “Electrical installation to Millennium Guest House at

Madhuban”.

Scope of Work

Paradip Port intends to take up the work “Electrical installation to Millennium Guest House at

Madhuban”. The Contractor has to carry out the total works including supply, installation and

commissioning of different types of LED Light fittings, Feeder pillar/ panel board, supply & laying of

XLPE insulated Aluminium armoured cable, fixing and wiring of different installations as specified in

the Bill of Quantity (BOQ). The scope of work is as follows:

1) The Contractor shall supply and fix different LED fittings including study lamps/night lamps as

specified in the Bill of Quantity and as per the indicative drawings attached as Annexure(s). The

LED lights shall be of reputed make such as Philips / Bajaj / Havells / Crompton / Syska / Wipro

etc.

2) The Contractor shall supply and fix 1400mm sweep decorative ceiling fan with modular type

electronic regulator and exhaust fan. The Ceiling Fan / Exhaust Fan shall be of reputed make

such as Havells / Bajaj / Crompton / Polar/ Usha/ Khaitan etc.

3) The Contractor shall supply & install 04 nos. 60 watt LED post top decorative light for gates.

4) The Contractor has to supply and install 630 Amp. LT main panel board, 250 Amp. Feeder pilar,

125 Amp. Distribution panel, 63 Amp. 16 way double door MCB panel board, digital room

indication panel as specified in the Bill of Quantity (BOQ). The Contractor shall arrange

required materials such as bricks, cement, sand, bolt & nut for making foundation and fixing of

panel boards. The panel board shall be made with 2mm thickness CRCA Sheet with powder

coated painting. The MCB & MCCB shall be from reputed manufacture such as C & S / Siemens

/ L & T / Indoasian / Schneider etc.

5) The Contractor shall supply 1.1 KV grade , 3 ½ X 300 Sq.mm, 3 ½ X 185 Sq.mm , 3 ½ X 50

Sq.mm , 3 ½ X 35 Sq.mm, 4 X 16 Sq.mm Aluminium XLPE cable (GI armoured ) and 3 X 1.5

Sq.mm copper flexible cable confirming to relevant Indian standard and carry out laying and

clamping of cable . The cable shall be from reputed manufacturer.

6) The Contractor shall supply and install 40 mm dia, 3 meter long medium gauge perforated GI

Pipe and execute the earthing by excavation of soil and refill the same with a uniform mixture of

charcoal, salt and sweet earth and provide necessary earthing connection by using no.8 SWG

Copper wire as per Indian Standard including earth pit at his own cost and arrangement.

7) The Contractor shall execute concealed wiring to light points, fan points, call bell points etc.

with Bureau of Indian Standards (BIS) certified PVC insulated 1.5 sq.mm. size copper wire and

No. 16 SWG copper Earth Continuity Conductor (ECC) drawn in BIS certified polythene / PVC

conduit pipe by embedding it into the wall.. The copper wire shall be of reputed make such as

Finolex / KDK /KEI /Havells etc.

8) Wiring to each of the above points shall be completed with supply of 6 Amp. & 16 Amp. 250

Volt, 50 Hz rated glossy finish IP-20 modular type switch, socket and fixing them on a suitable

GI board having designed modular plate cover. Wiring to fan point shall have provision of fixing

modular type fan regulator / dimmer. The modular switch, socket, regulator, dimmer shall be of

reputed make such as Crabtree (Verona) / Schneider (Opale) / Legrand (Myrius).

9) The Contractor shall execute wiring to sub-main, A.C Points, 6 way BDB Points from 125 Amp.

Distribution box with BIS certified, PVC insulated 06 sq.mm. size, copper wire along with No.

16 SWG copper conductor ECC drawn in BIS certified polythene pipe / PVC by embedding it

into the wall. The Contractor shall also supply & install switch board having 25 / 32 Amp.

modular starter and 16 Amp. Switch, plug socket & pin for each air conditioner. The Contractor

shall execute wiring to AC points / Power plug points 4 Sq. mm Copper wire and 01 sq. mm

copper wire for running earth.

10) Wiring to telephone point shall be carried out with modular telephone socket board.

11) The Contractor shall make Kuchha Cable trench of size 300mm x 900mm by excavating the

materials aside by and lay the cable inside the trench and refilling the same. In addition to above

the contractor has to carry out clamping/saddling of cable.

12) The Contractor shall lay out the heavy gauge GI Pipes as per the location identified by Engineer

in Charge (EIC) after opening of cable trench and lay the cable inside the GI Pipe and refilling

the trench with excavated material.

13) The Contractor shall execute road cutting and put heavy gauge 4” GI Pipe in that road for taking

cable across the road. The Contractor shall supply GI Pipes in his own cost and arrangement and

refill the cutting area and finishing it as per original condition.

Other Commercial Conditions:

1. Payment Terms:

The payment will be made as follows:

i) 90% payment will be released after successful completion of the work and acceptance

thereof by the Engineer In-charge (EIC).

ii) Balance 10% of the total contract value shall be retained by PPT towards Performance

Security Deposit. The Performance Security Deposit shall be released after successful

completion of the warranty period only. The Contractor may furnish a Bank Guarantee of

equal value valid till 60 days after expiry of the warranty period in which case the balance

10% money will be released for payment.

2. Security Deposit:

A sum of 10% of accepted value of the tender shall be deposited by the successful bidder

(Contractor) as Security Deposit (SD). This will be deposited initially 1% value of the contract

as initial security deposit (ISD) in shape of a Bank Guarantee or Demand Draft (DD) / Banker‟s

Cheque drawn in favour of FA&CAO, Paradip Port Trust (DD/ Banker’s cheque shall be payable

at Paradip) within 15 days of issue of Letter of Intent (LOI). After deducting the EMD and ISD

from the stipulated security deposit, the balance amount will be recovered in instalment through

deduction at the rate of 10% of the value of each running account bill subject to attaining the

required amount by the last running bill. In case of exemption of EMD, the successful bidder has

to deposit initially 3% of the contract value as ISD instead of 1% of contract value.

The Contractor may submit Bank Guarantee for the balance amount after deducting the EMD

and ISD from the stipulated security deposit in which case there will be no deduction from the

running bills towards security deposit.

EMD of the successful bidder may be refunded to the bidder after receiving an equivalent

amount of Bank Guarantee only after issue of work order and signing of agreement.

The Contractor may also submit Bank Guarantee for a sum of 10% of accepted value of tender as

Security Deposit (SD) within 15 days of issue of Letter of Intent (LOI) in which case (i) deposit

of 1% ISD will not be required; (ii) there will be no deduction from the running bills towards

security deposit; and (iii) EMD of the successful bidder will be refunded to the bidder after issue

of work order and signing of agreement.

The security deposits shall be returned to the Contractor within 45 days of successful execution

and acceptance of the work. The BG shall be valid till 45 days after the scheduled date of

completion of the work.

3. Completion Period :

The Contractor shall complete the entire work “Electrical installation to newly constructed

multipurpose hall at Paradip” in all respect within 60 (Sixty) Calendar days from the date of

issue of work order.

4. Warranty:

The warranty period shall be valid up to 01 (one) year on the entire work inclusive of supply

items with effective from the date of acceptance of work. However warranty period on the LED

light fittings shall be 02 years and 05% of the cost of LED lights has to be furnished by the

contractor as Bank Guarantee towards warranty performance obligation.

5. Liquidated Damage:

In case of delay in completing the work, liquidated damage shall be charged to the Contractor at

the rate 0.1% of the contract price for a delay of one week or part thereof subject to a maximum

of 5% of the contract price. Where the Liquidated Damage amount exceeds the maximum limit,

Paradip Port Trust reserves the right to :- i) Terminate the contract and / or ii) Forfeit the Initial

Security Deposit (ISD).

NOTE:

1. GST percentage to be mentioned extra against each item.

2. Any query in this regard may be raised to the following email id prior to dt.29/06/2018 (up to

15:00 hrs.) which will be clarified by dt.30/06/2018 by uploading in the website for facilitating

submission of a competitive budgetary offer.

3. Budgetary offers shall be submitted to the following address (through email or by Registered

Post):

Executive Engineer (Elect),

Port Electrical Division – III,

Paradip Port Trust.

PO:- Paradip,

Dist:- Jagatsighpur

Odisha – 754142

Contact No. 9861244414

Email Id: [email protected]

BILL OF QUANTITY

Sub.: Electrical installation to Millennium Guest House at Madhuban.

Sl.

No.

Description of Work Qty. Unit Rate

(in Rs.)

Amount

(in Rs.)

Remarks

(A) SUPPLY PART:

1 Supply of LT panel board having (a) one 630 amp.,

4 P MCCB as incomer and one 400 amp. Change

over with Bus bar arrangement and (b) (i) 3 nos. 250

Amp. 4 P MCCB (ii) 3 Nos. 125 Amp. 4P MCCB

(iii) 2 Nos. 63 amp. 4P MCCB (iv) 06 Nos. 32 Amp.

DP MCB as outgoing along with provision of

Ammeter, Voltmeter, Indicator and Danger Board in

the Panel as per scope of work.

1 No.

2 Supply of wall mounted double door panel board

having 4P, 125 Amp. MCCB as incomer with bus

bar arrangement and 2 nos. 63 Amp. 4P MCB & 6

nos. 32 amp. DP MCB as outgoing.

5 No.

3 Supply of outdoor type feeder pillar having (a) 01

no. 250 amp., 4P MCCB as incomer & (b) 2 nos.

125 amp., 4P MCCB (c) 2 nos. 63 Amp. 4P MCCB

and 02 nos. 32 amp. DP MCB as outgoing with bus

bar arrangement.

3 No.

4 Supply of 16 way double door MCB Panel board

having one no.63 amp. , 4P MCB and 06 nos. 32

amp. DP MCB.

12 No.

5 Supply of 15 watt recess mounted square/round LED

light as per indicative drawing at Annexure-A & B.

171 No.

6 Supply of 15 watt recess mounted square LED

light(1’ X1’) as per indicative drawing at Annexure-

A.

70 No.

7 Supply of recess mounted 42 watt LED light fittings

complete with inbuilt LED lamp, size: 2 ft. X 2ft.

approx. as per indicative drawing at Annexure-C.

12 No.

8 Supply of 90 watt LED Street light fitting complete

with inbuilt LED lamps.

10 No.

9 Supply of 40 watt LED post top decorative light

with Aluminium body for Gates.

4 No.

10 Supply of 09 watt decorative LED study lamp /

Light as per the indicative drawing at Annexure-D.

17 No.

Sl.

No.

Description of Work Qty. Unit Rate

(in Rs.)

Amount

(in Rs.)

Remarks

11 Supply of 4/6/7 watt wall mounted LED night lamp

as per indicative drawing at Annexure-E.

28 No.

12 Supply of 18 watt batten type LED light fitting with

inbuilt LED lamp.

30 No.

13 Supply of 15 watt surface mounted LED light fitting

with inbuilt LED lamp, size 1 ft. X 1 ft.

4 No.

14 Supply of 9 watt LED batten light with inbuilt LED

lamp.

60 No.

15 Supply of 9 Watt decorative LED Mirror Light with

inbuilt LED lamp.

48 No.

16 Supply of 1400 mm sweep decorative ceiling fan. 71 No.

17 Supply of 400mm sweep exhaust fan. 32 No.

18 Supply of Geyser (20 Ltr.), ABS polymer outer

body.

24 No.

19 Supply of 1.1 KV, 3½ X 300 Sq. mm XLPE

insulated Aluminium cable with GI armoured.

350 Mtr.

20 Supply of 1.1 KV, 3½ X 185 Sq. mm XLPE

insulated Aluminium cable with GI armoured.

400 Mtr.

21 Supply of 1.1 KV, 3 ½ X 50 Sq. mm XLPE

insulated Aluminium cable with GI armoured.

650 Mtr.

22 Supply of 1.1 KV, 3 ½ X 35 Sq. mm XLPE

insulated Aluminium cable with GI armoured.

450 Mtr.

23 Supply of 1.1 KV, 4 X 16 Sq. mm XLPE insulated

Aluminium cable with GI armoured.

400 Mtr.

24 Supply of 3 core x 1.5 Sq. mm copper flexible

cable.

200 Mtr.

25 Supply of heavy gauge GI Pipe (4"). 60 Mtr.

26 Supply of 6 way having 20 Amp. MCBs. 20 No.

27 Supply of Call Bell. 28 No.

28 Supply of digital room indicator Panel having 30

points.

1 No.

TOTAL (A):

Sl.

No.

Description of Work Qty. Unit Rate

(in Rs.)

Amount

(in Rs.)

Remarks

(B) EXECUTION PART:

29 Wiring to LED Light point with 6 Amp. Modular

switch and copper wire as per scope of work.

355 No.

30 Wiring to 6 Amp. Plug & socket as per scope of

work.

452 No.

31 Wiring to Ceiling fan points with 6 Amp. modular

switch and regulator as per scope of work.

71 No.

32 Wiring to Exhaust Fan points with 6 Amp. modular

switch as per scope of work.

32 No.

33 Wiring to 16A modular type plug point with

provision of switch & socket as per scope of work.

30 No.

34 Wiring to call bell point with modular bell push

switch as per scope of work.

30 No.

35 Wiring to digital room indication panel from each

room with modular bell push and 1 sq.mm copper

wire.

30 No.

36 Wiring to TV Point with 6 Amp. Modular switch &

socket with TV round pin board.

24 No.

37 Wiring to telephone point with modular socket

board.

25 No.

38 Wiring to A.C Point with 25 Amp./32 Amp.

Modular starter board as per scope of work.

50 No.

39 Wiring to Sub-main as per scope of work. 2000 Mtr.

40 Wiring to 6 way BDB Point. 20 No.

41 Wiring to 90 Watt LED Street light with 3 core x 1.5

sq.mm copper flexible cable.

10 No.

42 Execution of Earthing as per scope of work. 10 No.

43 Making of Kuchha cable trench as per scope of

work.

500 Mtr.

44 Road Cutting & laying of GI pipe as per scope of

work.

60 Mtr.

45 Clamping / saddling of Cable. 300 Mtr.

46 Laying of 1.1 KV, 3½ X 300 Sq. mm XLPE

insulated Aluminium cable with GI armoured.

350 Mtr.

Sl.

No.

Description of Work Qty. Unit Rate

(in Rs.)

Amount

(in Rs.)

Remarks

47 Laying of 1.1 KV, 3½ X 185 Sq. mm XLPE

insulated Aluminium cable with GI armoured.

400 Mtr.

48 Laying of 1.1 KV, 3½ X 50 Sq. mm XLPE insulated

Aluminium cable with GI armoured.

650 Mtr.

49 Laying of 1.1 KV, 3½ X 35 Sq. mm XLPE insulated

Aluminium cable with GI armoured.

450 Mtr.

50 Laying of 1.1 KV, 4 X 16 Sq. mm XLPE insulated

Aluminium cable with GI armoured.

400 Mtr.

51 Fixing of light fittings. 384 No.

52 Fixing of Ceiling Fan. 71 No.

53 Fixing of Exhaust Fan. 32 No.

54 Installation of 125 Amp. Distribution Panel after

making of brick foundation.

3 No.

55 Making of brick foundation & Installation of 250

Amp. Outdoor feeder pillar

3 No.

56 Making of brick foundation & Installation of 630

Amp. LT Panel board.

1 No.

57 Fixing of 63 Amp. MCB Panel Board. 12 No.

58 Fixing of Call Bell. 28 No.

59 Fixing of Street light fitting with supply of G.I. bend

pipe.

10 No.

60 Installation of digital room indication panel having

30 points.

1 No.

61 Fixing of 40 watt LED post top decorative light for

Gate(s).

4 No.

62 Fixing of 9 Watt LED Mirror Light. 48 No.

TOTAL (B):

GRAND TOTAL (A + B):

NOTE: GST shall be paid as extra.