OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter...

21
Jim Leidel Oakland University April 2008 Wind Power

Transcript of OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter...

Page 1: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Jim LeidelOakland University

April 2008

Wind Power

Page 2: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

• Wind Speed Study Results (Meteorological Tower Data Compilation and Analysis)

• Feasibility Study Results

Oakland Wind Data Results

Page 3: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Height Wind Speed Method 30 m 3.0 m/s measured40 m 3.6 m/s measured50 m 4.1 m/s measured

75 m 5.2 m/s calculated 80 m 5.4 m/s calculated100 m 6.2 m/s calculated

Oakland Wind Data Results

Page 4: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Meters per second

Wind Speed Frequency Distribution at 50 Meters (percent time for each wind speed)

Page 5: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Annual Average Wind Power DensityWind Rose at 50 Meter Height

(shows magnitude and direction of annual wind power potential)

50 W/m2

100 W/m2

150 W/m2

Page 6: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

1

2 3

4

Page 7: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

( artist’s rendering: courtesy of Khales Dahr & Jim Leidel. This is not the actual, proposed location. )

Page 8: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

AAER Wind Turbine 1,500 kW each

77 meter bladediameter

100 meter tower

Page 9: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Illustration of turbine components

Page 10: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

One 1.5MW Wind Turbine Installed at Site #1

$ 2,473 Cost per MW Installed

$ 3,710,000Total Installed Cost

6%$ 210,000Owner Contingency

$ 3,500,000Subtotal

$ 3,500,000AAER 100m Tower at Location 1

Page 11: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Two 1.5MW Turbines Installed at Sites #1 and #2

$ 2,438 Cost per MW Installed

$ 7,314,000Total Installed Cost

6%$ 414,000Owner Contingency

$ 6,900,000Subtotal

$ (100,000)Two Turbine Crane Economy$ 3,500,000 AAER 100m Tower at Location 2$ 3,500,000 AAER 100m Tower at Location 1

Page 12: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

$(500,000)

$-

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

2,010

2,012

2,014

2,016

2,018

2,020

2,022

2,024

2,026

2,028

2,030

2,032

2,034

Net Annual Cash Flow

Cumulative Cash Flow

15 year CREB @ 0% 20 year financing on remainder @ 4.5% 3% utility cost escalation 3% O&M cost escalation 1.5 cent / kWhr REC's

Net Annual and Cumulative Cash Flow Over 25 Year Project(construction in 2009, beginning operation in 2010)

Page 13: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Projected Unit Cost of Electricity Over 25 Year Project

Page 14: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Overview of an Integrated, Renewable Energy Supply Infrastructure

Page 15: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Overview of an Integrated, Renewable Energy Supply Infrastructure

Page 16: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Overview of an Integrated, Renewable Energy Supply Infrastructure

Page 17: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Overview of an Integrated, Renewable Energy Supply Infrastructure

Page 18: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

100%100%100%100%Totals

20%Wind Power

50%80%Biomass Boiler Plant

10%5%Diesel Generators

20%95%Detroit Edison

20%100%Central Heating Plant (natural gas)

ElectricalThermal(Heating)

ElectricalThermal(Heating)

Proposed Renewable Energy

Existing Fossil Fuel Mix

Overview of an Integrated Renewable Energy Supply Infrastructure

Page 19: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Proposed Funding Sources

1. Sale of Renewable Energy Credits2. $1.5M Clean Renewable Energy Bond3. Investigate grant opportunities4. Leveraged lease5. Issue 15 to 20 year bonds6. Enter into one or more bank qualified

debt arrangements7. Public / private partnership arrangement

Page 20: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

Recommendations1. Select the project financing method

a. Issue 15 to 20 year bondsb. Enter into bank qualified debt arrangementsc. Combine with biomass project – 3rd party “owned & operated”

2. Hire a design/build firma. Create high resolution wind map of campusb. Detailed engineering and construction documentsc. Environmental study & any needed approvals

3. Establish a utility interconnect agreement with DTE4. Offering of REC’s should be made to interested parties

to solicit pricing and potential customers interested ina bilateral contract.

5. Enter into Call Contracts Against the Euro or Canadian Dollar

Page 21: OU Wind Project Presentation April 2008 - Oakland University€¦ · Turbine 1,500 kW each 77 meter blade diameter 100 meter tower. Illustration of turbine components . One 1.5MW

WindPower

A Sustainable Energy Option for the Future of Oakland University