Ottawa fall construction season 2016

34
Fall Technical Briefing 2016 1

Transcript of Ottawa fall construction season 2016

Page 1: Ottawa fall construction season 2016

Fall Technical Briefing 2016

1

Page 2: Ottawa fall construction season 2016

Overview

1. Infrastructure Investments

2. O-Train Confederation Line LRT construction update

3. OC Transpo fall service

4. Traffic update

5. Wrap-up

2

Page 3: Ottawa fall construction season 2016

Infrastructure Investments

3

Page 4: Ottawa fall construction season 2016

Construction Completed in 2016

•ByWard Market Parking Garage

•9th Line Road

•Albert Street

•Coventry Road

•Hearst Way

•Moodie Drive

•Ramsayville Road

•Snake Island Road

•Wellington Street, O’Connor to Plaza Bridge

•Edison, Princeton, Tillbury, Kenwood, Avondale

•St. Francis and Edgar Street

•Prince of Wales Culvert

•Deer Park and Higwood

•Irving, Laurentian, Carling, Lynwood and Oakvale

•Gregory Casey Storm Water Management Facility

4

Page 5: Ottawa fall construction season 2016

Investing in Renewal, Growth and Expansion

$210 million invested at over 225 sites to renew existing infrastructure:

• 63 resurfacing

• 114 bridge and culverts

• 18 road renewal projects

Includes $32 million in buildings, parks and accessibility barrier removal.

$132 million invested in 50 new and improvement projects:

• 13 cycling and multi-use pathways projects

• 11 sidewalk projects

• 9 roads projects

5

Page 6: Ottawa fall construction season 2016

Major Projects Continuing Combined Sewage Storage Tunnel (CSST)

Gilmour Street integrated renewal

Industrial Road watermain renewal

Innovation Park and Ride

Kanata West Pumping Station and Forcemains

Mackenzie Avenue Cycling Track

McIllraith Bridge

Minto Bridges Phase 2

O’Connor Street Bikeway

O-Train Confederation Line light rail transit (LRT)

St. Laurent Boulevard transit priority lanes and intersection improvements

Tenth Line

St. Joseph Boulevard water main renewal

OAG Expansion and Arts Court

Mooney’s Bay Play structure

Works Yards at Bloomfield and Trim Road

New fire stations at Cyrville and Orleans

Transit control centre

Transit LRT training facility

ByWard Market – George Street Plaza Redevelopment

O-Train Trillium Line fare gate enclosures

Reid Park Redevelopment

Crestview Pool and Change Facility

Greely Village Park

Nepean Minto Field

King’s Grant Park

6

Page 7: Ottawa fall construction season 2016

Road renewal and resurfacing underway

Resurfacing:

•Airport Parkway ramps

•Bridge Street

•Carp Road

•Crofters Grove

•Fallowfield Road

•Farm Lane

•Kent Street

•Kitoman Crescent

•Majestic Drive

•Ottawa Street

•River Road

•Royal York Street

•Uplands Drive

•Wagon Drive

•Highway 174, Jeanne d’Arc Boulevard to Trim Road

7

Major roads:

•Alta Vista Hospital Link

•Greenbank Road widening

•Iris Street

•Lyon and McLeod integrated renewal project

•MacFarlane, Orrin, Reid

•Main Street “Complete Street”

•Queen Street streetscaping

•Rideau Street renewal

•Rideau Valley Drive South

•Spencer Street

•West Transitway Extension (Bayshore to Moodie)

•Maplehurst watermain renewal

•Brian Coburn Extension

Page 8: Ottawa fall construction season 2016

O-Train Confederation Line Update

8

Page 9: Ottawa fall construction season 2016

Blair Station Cyrville Station

Station Construction

9

Page 10: Ottawa fall construction season 2016

Guideway and Trackwork

Belfast Hurdman Station elevated guideway

10

Page 11: Ottawa fall construction season 2016

Tunnel and Station Cavern Progress

11

Page 12: Ottawa fall construction season 2016

Tunnel activities

Tunnel near Lyon Station Near Rideau Station

Lyon Station West Entrance 12

Page 13: Ottawa fall construction season 2016

Belfast Yard Maintenance and Storage Facility

Light Rail Vehicle for testing Overhead catenary system

13

Page 14: Ottawa fall construction season 2016

Re-opening Booth Street Bridge

Booth St bridge

14

Page 15: Ottawa fall construction season 2016

Reminder: Nicholas Street Transitway Detour

15

Page 16: Ottawa fall construction season 2016

uOttawa Pedestrian Tunnel

16

Page 17: Ottawa fall construction season 2016

OC Transpo Fall Service

17

Page 18: Ottawa fall construction season 2016

On Track 2018

18

• The Transitway between Tunney’s Pasture and Blair Stations is fully closed to allow for the construction of the Confederation Line;

• Service adjustments for Confederation Line construction will remain in effect until the opening of the Confederation Line in 2018; and,

• Starting September 4, LeBreton Station will move one block east to Albert at Booth Street due to the closure of Preston Street north of Albert.

Page 19: Ottawa fall construction season 2016

LeBreton Station is Moving

19

• Booth Street bridge over the future O-Train Confederation Line will open and Preston Street extension will close;

• LeBreton Station relocated from Albert/Preston to Albert/Booth; and,

• Bus stop arrangement will be similar to the current service, with buses to Gatineau at a new stop on Booth Street just north of Albert.

Page 20: Ottawa fall construction season 2016

LeBreton Station is Moving

20

Page 21: Ottawa fall construction season 2016

Fall Service Changes

21

• New Route 167 will serve the Blackstone community in Stittsville;

• Place d’Orléans Park and Ride overflow lot is moving to a new area conveniently located in the covered parking section just north of the current area, courtesy of the Place d’Orléans Shopping Centre;

• Improved service to Carling Campus on Moodie Drive to accommodate Phase 1 of the relocation of federal employees to this location; and,

• Seasonal schedule adjustments on many bus routes.

Page 22: Ottawa fall construction season 2016

Service for Students

22

• School service is back for the school year: service started August 30 for French schools, and will start September 6 for English schools;

• Eligible university and college students can get their new 2016-17 U-Pass on campus at Carleton University, Saint Paul University, the University of Ottawa, and Algonquin College; and,

• Beginning in October, all students paper passes will be converted to the Presto card, and photo ID will no longer be required.

Page 23: Ottawa fall construction season 2016

Construction Affecting OC Transpo Service

23

Construction Area Routes Detoured Comments

Main Street Clegg to Riverdale Routes 5 and 16x Ongoing

Queen Street Bronson to Elgin Routes 4, 9 and 12 Ongoing

Carling Campus Carling Campus Routes 101, 103, 152 and 182 Ongoing

Crystal Beach Carling to Ullswater Route 152 Spring 2016 – Date TBD

O’Connor First to Pretoria Route 6 Summer 2016 – September 27, 2016

Navaho Iris to Agincourt Route 150 August 29 – November 18, 2016

Page 24: Ottawa fall construction season 2016

Information For Customers

24

• Route, schedule, and travel planning information is available at octranspo.com

• It’s easy to use self-serve travel-planning resources before September 4

Page 25: Ottawa fall construction season 2016

Impacts to Mobility

During the Fall Construction Season

25

Page 26: Ottawa fall construction season 2016

Schedules are subject to change

Traffic Impacts – Core Area – 2016

Rideau St Development Project & LRT Station Construction

IMPACT: High Medium

Low

Main St Reconstruction McIlraith Bridge Rehab

Hwy 417 WB to OR 174 EB Ramp Closure (LRT)

Lyon LRT Station /Parliament LRT Station and Queen St.

Streetscaping (LRT)

Arts Court

26

Lees to Hwy 417 EB Ramp Closure (LRT)

Kent Resurfacing

O’Connor St. Bikeway

Lyon St. Reconstruction

NAC Renovations

St. Laurent Transit Priority

Mackenzie Cycle Track

Mackenzie King Bridge

Wellington Bridge

Nicholas Bus Lane (LRT)

Industrial Watermain

Metcalfe Gas Main

St. Joseph Watermain

Bank St. Utility Work

Page 27: Ottawa fall construction season 2016

SEE ‘CORE’ SLIDES

Schedules are subject to change

Traffic Impacts – Outer Area – 2016

IMPACT: High Medium

Low

27

Hwy 417 Bridge Repair: Richmond, Pinecrest, Woodroffe, Maitland

Tenth Line Widening

Greenbank Widening

Terry Fox, Maple Grove to

Palladium water main

Page 28: Ottawa fall construction season 2016

• Ongoing monitoring from Traffic Control Centre

• Continued prioritization of critical road network and adjustment of signal timings

• Coordination of operations with road and traffic agencies/partners through the Traffic Incident Management Group

Construction Traffic Management

28

Page 29: Ottawa fall construction season 2016

Manage Congestion Impacts / Adjust Commuting Habits

• Avoid traveling during peak periods

• Use alternative modes of transportation such as transit, cycling, walking

• Carpool

• Embrace technology in the workplace (e.g. Teleconference)

• Consider alternative work arrangements (e.g. Work from home)

• Allow extra travel time especially during morning commute

• Plan your trip ahead of time and be informed (travel apps (OttawaNav), Twitter, web links, media messaging, etc.)

29

Page 30: Ottawa fall construction season 2016

Back to School – Road Safety

• Watch for pedestrians and reduce your speed in school zones.

• Always stop for school buses when signals are flashing.

• Wear reflective gear to be visible at night to other road users. Ensure all bikes are fitted with a bell, light and reflective tape.

• Wear a helmet and protect yourself from head injuries. ‘Just Wear It!’

• Share the Road and ensure the safety of all road users.

• Reminder to all road users to slow down and move over for emergency vehicles. New legislation also requires the same for tow trucks.

30

Page 31: Ottawa fall construction season 2016

New for 2016 - Pedestrian Crossovers

• Introduced by MTO in January 2016.

• Crossovers are pedestrian crossings marked with specific signs and roadway markings.

• May also include flashing beacons.

• When pedestrians are present at a Crossover, all drivers, including cyclists, must stop and yield the right of way until pedestrians have completely crossed the road.

• Drivers and cyclists will be fined $150 - $500 with 3 demerit points for non compliance.

31

Page 32: Ottawa fall construction season 2016

Wrap-up

32

Page 33: Ottawa fall construction season 2016

Tips for Residents

• Plan around construction

• Give priority to emergency vehicles

• Avoid traveling during peak periods

• Consider carpooling

• Walk, bike, take transit. Combine them if your commute is longer. • Embrace technology in the workplace (e.g. Teleconference)

• Consider alternative work arrangements

33

Page 34: Ottawa fall construction season 2016

Stay in the Know - City information:

• ottawa.ca

• octranspo.com

- Sign-up for construction

project newsletters

- Ottawa Nav mobile app

- OC Transpo MyTransit app

- Local media

- Twitter:

• @ottawacity

• @ottawa_traffic

• @OC_Transpo, @STOGatineau

34