Operational Research Project Menagement Method by CPM/ PERT

Transcript of Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09......

Page 1: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Operational Research Project Menagement Method by CPM/

PERT

Page 2: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Project definition

“A project is a series of activities directed to accomplishment of a desired

objective.”

Plan your work first…..then work your plan

Page 3: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Network analysis is the general name given to certain

specific techniques which can be used for the planning,

management and control of projects.

One definition of a project:

“A project is a temporary endeavour undertaken to

create a "unique" product or service”

Network analysis introduction

Page 4: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

History

PERT was developed by the US Navy for the planning and control of

the Polaris missile program and the emphasis was on completing the

program in the shortest possible time. In addition PERT had the

ability to cope with uncertain activity completion times (e.g. for a

particular activity the most likely completion time is 4 weeks but it

could be anywhere between 3 weeks and 8 weeks).

CPM was developed by Du Pont and the emphasis was on the

trade-off between the cost of the project and its overall

completion time (e.g. for certain activities it may be possible to

decrease their completion times by spending more money - how

does this affect the overall completion time of the project?)

Page 5: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

CPM - Critical Path Method

Definition: In CPM activities are shown as a network of precedence relationships using activity-on-node network construction

– Single estimate of activity time

– Deterministic activity times

USED IN : Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience.

Page 6: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

PERT as a Project Evaluation & Review Techniques

Definition: In PERT activities are shown as a network of precedence relationships using activity-on-arrow network construction

– Multiple time estimates

– Probabilistic activity times

USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.

Page 7: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Originated by H.L.Gantt in 1918

Gantt chart

Advantages

• Gantt charts are quite commonly used.

• They provide an easy graphical

representation of when activities (might)

take place.

Limitations

• Do not clearly indicate details regarding

the progress of activities.

• Do not give a clear indication of

interrelation ship between the separate

activities

Page 8: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

CPM/PERT

• These deficiencies can be eliminated to a large extent by showing the interdependence of various activities by means of connecting arrows called network technique.

• Overtime CPM and PERT became one technique

• ADVANTAGES:

– Precedence relationships

– large projects

– more efficient

Page 9: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

The Project Network

Use of nodes and arrows

Arrows An arrow leads from tail to

head directionally

– Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work.

Nodes A node is represented by a circle

- Indicate EVENT, a point in time where one or more activities start and/or finish.

Page 10: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Activity Slack

Each event has two important times associated with it:

- Earliest time , Te , which is a calendar time when a event

can occur when all the predecessor events completed at the earliest possible times

- Latest time , TL , which is the latest time the event can occur

with out delaying the subsequent events and completion of project.

• Difference between the latest time and the earliest time of an event is the slack time for that event

Positive slack: Slack is the amount of time an event can be

delayed without delaying the project completion

Page 11: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Critical Path

• Is that the sequence of activities and events where there is no “slack” i.e.. Zero slack

• Longest path through a network

• Minimum project completion time

Page 12: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Benefits of CPM/PERT

• Useful at many stages of project management

• Mathematically simple

• Give critical path and slack time

• Provide project documentation

• Useful in monitoring costs

Page 13: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Questions Answered by CPM & PERT

• Completion date?

• On Schedule?

• Within Budget?

• Critical Activities?

• How can the project be finished early at the least cost?

Page 14: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

CPM calculation

• Path

– A connected sequence of activities leading from the starting event to the ending event

• Critical Path

– The longest path (time); determines the project duration

• Critical Activities

– All of the activities that make up the critical path

Page 15: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Forward Pass

• Earliest Start Time (ES)

– earliest time an activity can start

– ES = maximum EF of immediate predecessors

• Earliest finish time (EF)

– earliest time an activity can finish

– earliest start time plus activity time EF= ES + t

Page 16: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Backward Pass

• Latest Start Time (LS)

Latest time an activity can start without delaying critical path time

LS= LF - t

• Latest finish time (LF)

latest time an activity can be completed without delaying critical path time

LS = minimum LS of immediate predecessors

Page 17: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

CPM analysis

• Draw the CPM network

• Analyze the paths through the network

• Determine the float for each activity

– Compute the activity’s float

float = LS - ES = LF - EF

– Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project

• Find the critical path is that the sequence of activities and events where there is no “slack” i.e.. Zero slack

– Longest path through a network

• Find the project duration is minimum project completion time

Page 18: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

CPM Example

CPM Network

a, 6

f, 15

b, 8

c, 5

e, 9

d, 13

g, 17 h, 9

i, 6

j, 12

Page 19: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

CPM Example

ES and EF Times

a, 6

f, 15

b, 8

c, 5

e, 9

d, 13

g, 17 h, 9

i, 6

j, 12

0 6

0 8

0 5

Page 20: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

CPM Example

a, 6

f, 15

b, 8

c, 5

e, 9

d, 13

g, 17 h, 9

i, 6

j, 12

0 6

0 8

0 5

5 14

8 21

6 23

6 21

ES and EF Times

Page 21: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

CPM Example

a, 6

f, 15

b, 8

c, 5

e, 9

d, 13

g, 17 h, 9

i, 6

j, 12

0 6

0 8

0 5

5 14

8 21 21 33

6 23 21 30

23 29

6 21

Project’s EF = 33

ES and EF Time

Page 22: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

LS and LF Times

a, 6

f, 15

b, 8

c, 5

e, 9

d, 13

g, 17

h, 9

i, 6

j, 12

0 6

0 8

0 5

5 14

8 21 21 33

6 23

21 30

23 29

6 21

21 33

27 33

24 33

CPM Example

Page 23: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

a, 6

f, 15

b, 8

c, 5

e, 9

d, 13

g, 17

h, 9

i, 6

j, 12

0 6

0 8

0 5

5 14

8 21 21 33

6 23

21 30

23 29

6 21

4 10

0 8

7 12

12 21

21 33

27 33

8 21

10 27

24 33

18 24

LS and LF Times

CPM Example

Page 24: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Float

a, 6

f, 15

b, 8

c, 5

e, 9

d, 13

g, 17

h, 9

i, 6

j, 12

0 6

0 8

0 5

5 14

8 21 21 33

6 23

21 30

23 29

6 21

3 9

0 8

7 12

12 21

21 33

27 33

8 21

10 27

24 33

9 24

3 4

3

3

4

0

0

7

7

0

CPM Example

Page 25: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Critical Path

a, 6

f, 15

b, 8

c, 5

e, 9

d, 13

g, 17 h, 9

i, 6

j, 12

CPM Example

Page 26: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

PERT

• PERT is based on the assumption that an activity’s duration follows a probability distribution instead of being a single value

• Three time estimates are required to compute the parameters of an activity’s duration distribution:

– pessimistic time (tp ) - the time the activity would take if things did not go well

– most likely time (tm ) - the consensus best estimate of the activity’s duration

– optimistic time (to ) - the time the activity would take if things did go well

Mean (expected time): te =

tp + 4 tm + to

6

Variance: Vt =2 =

tp - to 6

2

Page 27: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

PERT analysis

• Draw the network.

• Analyze the paths through the network and find the critical path.

• The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal

• The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum

• Probability computations can now be made using the normal distribution table.

Page 28: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Limitations to CPM/PERT

• Clearly defined, independent and stable activities

• Specified precedence relationships

• Over emphasis on critical paths

Page 29: Operational Researchhome.agh.edu.pl/~hyla/Downloads/Operation_Research/… ·  · 2013-01-09... (research and development work ... Gantt chart Advantages • Gantt charts are quite

Thank you for your attention