Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

10
Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014

Transcript of Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

Page 1: Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

Objective FCM04

ESSIP Plan 2014

Octavian CIOARADPS/PEPR

19.09.2014

Page 2: Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

ESSIP Plan 2014 / Objective FCM04 2

Objective FCM04

• Comprehensive Explanation• What is new or has changed since LSSIP 2013• Link to European ATM Master Plan• Finalisation Criteria and Closed Questions• ESSIP Report 2013• Objective Coordinator’s Analysis, recommendations, tips & tricks• Links and contacts

Page 3: Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

Comprehensive Explanation

ESSIP Plan 2014 / Overview LSSIP 2013 3

Area of applicability: France, Germany, Italy, Poland, Spain, Switzerland Applicable to: Paris, Bordeaux, Marseille, Brest, Karlsruhe, Roma, Warsaw,

Madrid, Barcelona, Geneva and Zurich FMP

Initial Operational Capability (IOC): 09/2013Full Operational Capability (FOC): 12/2015

The objective will ensure the deployment of Short Term ATFCM Measures – Phase 1 (as defined by the Interim Deployment Programme – IDP)

As deployed in London, Raims and Maastricht FMP

A more automated version of STAM (labeled STAM phase 2) will be released in the next years by SESAR – Not within the scope of FCM04!

Page 4: Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

What is new or has changed since LSSIP 2013

ESSIP Plan 2014 / Overview LSSIP 2013 4

Nothing.

Page 5: Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

Link to European ATM Master Plan

ESSIP Plan 2014 / Overview LSSIP 2013 5

Objective FCM04 covers the following SESAR OI steps:

OI step - [DCB-0205] – Short Term ATFCM Measures

Page 6: Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

Most important SLoA(s)

FCM04-ASP01 – Availability of demand-capacity balancing tools via CHMI (finalisation date 12/2015)

FCM04-ASP02 – Provision of ANSPs sector and traffic occupancy parameters data to NM (finalisation date 12/2015)

FCM04-ASP03 – Implement FCM procedures to enable application of flow management techniques on traffic streams closer to real-time and including more accurate assessment of forecast sector loads and cooperative management of groups of sectors and ATCO resources (finalisation date 12/2015)

ESSIP Plan 2014 / Overview LSSIP 2013 6

Page 7: Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

Finalisation Criteria and Closed Questions

ESSIP Plan 2014 / Overview LSSIP 2013 7

Finalisation criteria: Contact your subject matter expert to determine the deployment Status for

each SloA

Closed questions: Closed Questions have been introduced for this Objective Statements on Deployment Status should provide answers

to Closed Questions

Page 8: Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

ESSIP Report 2013

ESSIP Plan 2014 / Overview LSSIP 2013 8

The submitted reports indicate that the objective will be implemented in time by the States within its area of applicability. However there is still a need for the clarification of implementation intention of States which have reported -No Plan- despite being in the applicability area of the objective.

It is also desirable to capture the plans for the States which are not formally with the applicability area but which have expressed interest for the implementation of STAM Phase 1 through other channels, in order to have a better view of the progress.

Page 9: Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

Objective Coordinator’s Analysis, recommendations, tips & tricks

ESSIP Plan 2014 / Overview LSSIP 2013 9

Ensure that your subject matter expert is involvement once you make your statement.

Information provided per SLoA can be easily verified by checking the provisions laid down in the supporting material.

Attention to the applicability to the Military stakeholders as airspace users.

Page 10: Objective FCM04 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014.

Links and contacts

ESSIP Plan 2014 / Overview LSSIP 2013 10

Objective Coordinator: Octavian CIOARA +32 2 729 3282

[email protected]

NMD Objective Expert: Marcel RICHARD +32 2 729 9857

[email protected]