MP - asm mẫu (1).docx
-
Upload
phuonganh712 -
Category
Documents
-
view
260 -
download
0
Transcript of MP - asm mẫu (1).docx
-
8/11/2019 MP - asm mu (1).docx
1/27
Managing ProjectsProject management for VobienLtd. and IBEK Ltd.
Individual Assignment Report - I!""#
By Nguyen Hai Khanh MyStudent ID: 119163906
International School of Management andEconomics
National Economics University
Hanoi !cto"er #01#
-
8/11/2019 MP - asm mu (1).docx
2/27
Table of Contents
TASK 1: the case of Vobien Ltd....................................................................................................2
1. The network diagram using activity on the node..................................................................2
2. The timing of activities and total float..................................................................................5
a. The forward pass...............................................................................................................5
b. The backward pass............................................................................................................5
c. The float............................................................................................................................6
3. The project duration and critical path...................................................................................6
. The project earliest completion date.....................................................................................6
5. !hange in activities" duration and its effect on project.........................................................6
6. The limitations of network diagram.....................................................................................#
APPENDICES................................................................................................................................$
%ppendi& 1.1................................................................................................................................$
%ppendi& 1.2................................................................................................................................'
TASK 2: the case of IBEK Ltd....................................................................................................11
(&ecutive )ummary...................................................................................................................11
*ajor +indings...........................................................................................................................11
1. ,roject objectives............................................................................................................112. +easibility study..............................................................................................................11
3. The ,roject -ife !ycle ,-!/.........................................................................................12
. ,roject manager skills and competencies.......................................................................1#
!onclusion.................................................................................................................................1$
APPENDICIES............................................................................................................................1'
%ppendi& 2.1..............................................................................................................................1'
%ppendi& 2.2..............................................................................................................................20
%ppendi& 2.3..............................................................................................................................21
%ppendi& 2...............................................................................................................................22
%ppendi& 2.5..............................................................................................................................23
E!EENCE...............................................................................................................................25
ooks........................................................................................................................................25
1
-
8/11/2019 MP - asm mu (1).docx
3/27
nternet......................................................................................................................................25
TASK 1
The case of Vobien Ltd.
This part will present one of different tools used in project planning and control 4 the network
diagram and its details of activities timing floats duration as well as the critical path. There will
also be some e&les of analying the effect on the whole project duration. n the other hand
limitations of this tool are also given.
1. The net"o#$ dia%#a& 'sin% acti(it) on the node
7Notes:
EST (arliest start time
E!T (arliest finish time
LST -atest start time
L!T -atest finish time
8on9critical path
!ritical path
2
L!T!loatLST
Acti(it) Identifie#
ES D'#ation E!T
-
8/11/2019 MP - asm mu (1).docx
4/27
Figure: Vobien Ltd. Project Network diagra
3
-
8/11/2019 MP - asm mu (1).docx
5/27
2. The ti&in% of acti(ities and total float
a. The fo#"a#d *ass
+orward pass must be the first to accomplish. The start time is ero. The formula for forward pass
calculations is
EST = EFT of preceding activity
EFT = EST + activity duration
+or e&le the ()T of activity ! is e:ual to (+T of its preceding activity / which is #.
%ctivity !"s earliest finish time will be # plus # its duration/ are 1. ;hen there is more than one
task start at the same time means that have the same ()T/ the following activity"s ()T e:ual to
the highest of preceding (+T. n the diagram < has four preceding activities = > ?/ and =
has the highest value of (+T is 26. Therefore the ()T of < is 26.
b. The bac$"a#d *ass
t starts the calculations at the last activity in the network and working backward subtracting
the succeeding duration of an activity from the calculated ()T of the activity.
LST = LFT activity duration
LFT= LSTof next activity
;hen multiple activities converge previous activity"s -+T e:uals to the lowest of succeeding
-)T times. (&le %ctivity 8 has two successors @ and ,/. The -)T of @ is lower than ,
0A2/ hence the -+T of 8 is 0.
-
8/11/2019 MP - asm mu (1).docx
6/27
c. The float
t is the amount of time that an activity can delay without affecting the whole project.
Float= LFT EST activity duration = LFT EFT
(&le The float of activity , B 5 4 0 4 2 B 5 4 2 B 3 days/
The project float is presented in a tabular please see %ppendi& 1.1/.
+. The *#o,ect d'#ation and c#itical *ath
CProject duration is te elapsed ti!e fro! project start date troug to project finis dateD
"ide!an 2002/. n this case the project starts from activity % and ends at activity E. The
duration of this project is actually the latest finish time of E which is 50 days.
#Te critical pat is defined as te series of activities tat ave $ero float% Te critical pat
al&ays runs troug te project fro! te first activity to te last activity% 'ctivities &it $ero float
are on critical pat( urke 2003/. >ence the critical path in this network is A-B-C-!--K-L-
/-N-0--.
. The *#o,ect ea#liest co&*letion date
The project needs 50 days to complete therefore with 5 days work a week no holidays/ it will
take 10 weeks in total. f the project starts on *onday +ebruary 2013 the earliest date they can
finish it is +riday 12 %pril 2013 please see %ppendi& 1.2 for =antt chart and the calendar/.
3. Chan%e in acti(ities4 d'#ation and its effect on *#o,ect
a. %ctivity ( is delayed 1 day
5
-
8/11/2019 MP - asm mu (1).docx
7/27
t will not affectto the whole project because activity ( has 2 days of float more than 1 day
delayed/ and it is not on the critical path.
b. %ctivity , is delayed 1 day
, also has 3 days float and not be in the critical path hence this delaying will not affectto the
project"s duration.
c. %ctivity F is completed 1 day early
%ctivity F is on the critical path of this project with no float then if F completes 1 day earlier the
entire project also will finish 1 day earlier.
5. The li&itations of net"o#$ dia%#a&
,eople may attach special important to the critical path hence controlling the balance of project"s
time may not fle&ible and effective.
n fact the network diagram only can state the time without covering other resources such as
skills human finance etc. which are important as well to have a good project planning.
f the project is huge with a lot of comple& tasks it will be a big difficulty for the project manager
to plan and control it well. esides other people also may not fully understand the diagram.
,roject manager may make mistake by calculating wrongly the precedence and durations or
prone to underestimate time for activities which leads to behind schedule and costs are much
higher.
)"ord count: ** &ords,
6
-
8/11/2019 MP - asm mu (1).docx
8/27
APP!N"#$!S
A**endi6 1.1
Total float and project float for each activity are calculated as below
Acti%it& Tota' f'oat
% 0
0
! 0
G 5
( 2
+ 0
= 0
> 6
#
? 6
< 0
- 0
* 0
8 0
@ 0
, 3
F 0
E 0
Project f'oat 27
#
-
8/11/2019 MP - asm mu (1).docx
9/27
A**endi6 1.2
n 2013 +ebruary has only 2$ days. +ollowing is the timing of the process
8ee$ /onda) T'esda) 8ednesda) Th'#sda) !#ida)
Fe-ruary ./0
1 start/ 5 6 # $
2 11 12 13 1 15
3 1$ 1' 20 21 22
25 26 2# 2$
1arc ./0
5 5 6 # $
6 11 12 16 1 15
# 1$ 1' 20 21 22
$ 25 26 2# 2$ 2'
'pril ./0
' 1 2 3 5
10 $ ' 10 11 12 finish/
,roject ()T B 50 days B 10 H 59day9work weeks B !#ida)9 12 A*#il 21+
Iobien project"s =antt chart
$
-
8/11/2019 MP - asm mu (1).docx
10/27
!ritical path8on9critical path
'
-
8/11/2019 MP - asm mu (1).docx
11/27
TASK (
The case of #)!K Ltd.
E6ec'ti(e S'&&a#)
(< -td. is a company specialiing in supplying of specialist auto parts to motor industry. Their
area served includes regional national and international. !urrently the company trades from a
single main warehouse 4 also includes office accommodation with the area of 25000 mJ. %s a
part of e&pansion strategy they make a decision to open a new building with the same structure as
the current one. n order to be successful the company needs a precise project with good
management. This report will present a detail plan and management for this project covers and
applies
The four phases of the project life cycle.
,rocesses leadership administration and control problems associated with managing the
lifecycle.
/a,o# !indin%s
1. P#o,ect ob,ecti(es
n this case the company wants to concentrate serve their large global organiation with a larger
area of 35000 mJ. The project needs to be ensured to open on time and within budget as well.
2. !easibilit) st'd)
C' feasi-ility study is designed to provide an overvie& of te pri!ary issues related to a -usiness
idea% Te purpose is to identify any #!a2e or -rea2( issues tat &ould prevent your -usiness
fro! -eing successful in te !ar2etplace% 3n oter &ords4 a feasi-ility study deter!ines &eter
10
-
8/11/2019 MP - asm mu (1).docx
12/27
te -usiness idea !a2es senseD K;!! chapter 5/. %s in the scenario the company has been
successful since 200# means that they already have the good foundation e&perience and skills.
*oreover they already ac:uired the building and had the plan to apply the old structure so they
did have the technical e&pertise to accomplish the project. ecause the company has a new target
consumer of the global organiations therefore assume that this new building is place in another
country. They want to be also successful in international environment. Thus the project is :uite
realistic and possible to implement.
+. The P#o,ect Life C)cle ;PLCowever this report will use the four phase from urke 2003/ C a four pase
life cycle tat passes troug four pase eadings: concept and initiation pase4 design pase
and develop!ent pase4 i!ple!entation and co!!ission and andover paseD.
a. Conce*t o# Initiation Phase
!ost 4 benefits analysis
C5ost and -enefits analysis !eans tat identifying4 specifying and evaluating te costs and te
-enefits of te proposal over its projected lifeti!eD 9 +ield and
-
8/11/2019 MP - asm mu (1).docx
13/27
%ppointing project team
The project in order to success needs a good team with high spirit of responsibility and
corporation. ;orking as a team will support each person in technical issues and improve the
ability of solving a problem. ,eople share works and skills would get the task done faster and
more efficient. n this case the project team of (< initially has a clearly understanding of the
project objectives and goals. (ach member also has to have right knowledge skill technic and
e&perience in organiing. +urthermore the good communication and negotiation are very
important as well. )pecially each person must have trust from other members.
b. Desi%n o# De(elo*&ent Phase
uilding design
%lthough (< has decided to apply their old structure the new building is :uite much larger. )o
the company can think of which function they should e&pand is that the office the warehouse or
bothM %ssuming that (< choose to increase the area used for storage to increase the supply
volume for their large global organiations and keep the office area the same. >ence the
company may need more warehouse staffs. To have a general idea and manage the whole project
processes the team needs to provide a ;ork reakdown )tructure ;)/. t is Cte &or2 of a
project is divided and su- divided for !anage!ent and control purposesD Eodney Turner 1''3/.
The ;) for (< has five stages which is the structure application development evaluation
and review finaliing the building and organiing people please see %ppendi& 2.3/
)chedule
12
-
8/11/2019 MP - asm mu (1).docx
14/27
Se6uencing tas2s ased on the major steps in ;) the project team will determine the
estimated duration and the resources need. %fter that the timing of start and end is calculated. The
=antt chart is the clearest way to state the project"s duration please see %ppendi& 2./.
Ti!e !anage!ent To control and monitor the time spent for each task the manager has to record
the actual used time of the activities from that if there is any changes he can clarify and update
all timing of activities hence responding :uickly and make right decisions. *oreover some
strategies will be given out to avoid the delay as well.
udgets
Total project budget is the aggregation of costs e&penditures and overheads allocated to the
project. ecause (< is a motor industry supplier company they have cash in hand therefore
the fund to do this project is available in the business. %ccording to ?oseph ,hillips 2010/ there
are three ways to estimate the project budget ballpark estimate budget estimate top9down/ and
definitive estimate bottom9up/. %t first team should consider the b'd%et esti&atemethod which
using e&perience from a similar project and then apply to their current case. %fter that they can
use the definiti(e esti&ateway this method is more accurate because its calculation based on the
;) of the project.
Eisk management
Eisks always lengthen times increase costs and reduce the outcome of delivery. The risk
planning is important because it helps us to avoid or reduce those bad affects. %ccording to +ield
and
-
8/11/2019 MP - asm mu (1).docx
15/27
The risks that (< project could face up with can be
*isk T&+e of risk *es+onse
!onflict between teammembers
!ontrollable
Eeducing by develop and
maintain a good relationshipwith team members create
motivation
The client company suddenly
changes their objectivesLgoalsKncontrollable
%ccept the risk change the
plan and schedule if possible/
The key member sub9
manager/ :uit off the project
because of health problem
!ontrollable @utsource recruitment
(lectrical leakageLfire KncontrollableTransferring the risk to other
by taking fire insurance
@ver the budget !ontrollableEeducing the scope of project
ask for more funds
8atural disasters +orce majeure%ccept the risk and get over
the damages
c. I&*le&entation Phase
@rganiing team
This is a large project (< can allocates 1 project manager 1 assistant manager 1 human
resource manager 1 financial manager 1 office administration 1 warehouse administration 2
staffs from the company itself and other contracted labors. The first important is to organie the
information. The detail of planning schedule etc. has to impart to everyone in the team. t must
be clear and the project manager must ensure all members understand it. This is to avoid
misunderstanding leads to faults and delaying. +urthermore the team can create ownership and
1
-
8/11/2019 MP - asm mu (1).docx
16/27
responsibility through good working condition and motivation both monetary and non9
monetary/ it increase the working perform and efficiency outcome of the project team.
%ssigning works
n this period the project manager will give out specific tasks and assignments to all members.
The given tasks are based on the ability and position of each person. (veryone has to receive all
related documents like schedules procedures checklist and budgets. The member will be
responsible for the duties and will be supervised by the project manager. y that during the
process if the project manager sees any person tend to follow a wrong direction he can :uickly
give advice and get the problem fi&ed.
,lanning changes
%ny project has une&pected problem big or less hence he team also needs plan to react. t could
be changes in time people resources or even changes in the client"s decision (< !ompany/.
;hen there is a sudden change in project the project manager has to gather all plan and consider
if it make big influence or not and if he needs to change anything in the current plan and
schedule.
d. Co&&issionin% Phases
The project needs evaluation and review to provide feedback to help every member focusing and
achieve the project objectives. To evaluate project the manager will use review method through
organie daily meeting in the team. n the meeting the manager will collect data and report from
team members.
efore the project can close it must be re9checked and accepted by the client 4 (< !ompany.
%ll the documents is completed and signed offN relieving labors and resourcesN informing and
15
-
8/11/2019 MP - asm mu (1).docx
17/27
disclosing warehouse to stakeholders "eiss and "ysoc2i4 0778./ %ccording to Spirer 1'$3/
project closure should be concern as a small plan which also has problems itself in aspects of
emotion for project staffs clients and intellection for internal e&ternal organiations. This will
help to maintain the outcome of the new building and develop trust for every stakeholder of
business in the future.
. P#o,ect &ana%e# s$ills and co&*etencies
The project manager involves the project from the beginning steps. %ccording to Field and 9eller
2005/ he with the supporting of an assistant firstly starts with the identification of objectives
planning the flow of activities step9by9step and estimating how much time resources what skills
needed to complete the project. The project manager must comprehensively understand all duties
along with every phases of the ,-! in his specialiation. n order to get the project successful
this manager also must have necessary personality to leads the whole team. The project manager
is
The one create vision transparent objectives communicating persuading influencing
integrating and leading people having trust from other members.
% person with outstanding energy levels enthusiastic and challenging the problems.
The manager also knows how to assess the human resources. >e must choose the team member
with right knowledge right skills and right attitude. %n intelligent manager will look for the most
suitable members not the best one. To get success in this project select a good leader with
suitable style is very importance. The manager"s leadership style will have a big impact to the
others. -eadership has some different styles such as autocratic bureaucratic charismatic
democratic laisse9faire and etc. n general the democratic leadership style is the most suitable
for the current project team. The democratic leader always encourages members to share the
16
-
8/11/2019 MP - asm mu (1).docx
18/27
ideas opinions and involve as a part of the decision marking. >owever in team process has some
situation in which the leader should not use democratic style. +or e&le in the case when the
time is limit and not allow discussing with members the manager must use autocratic style
isolated decision/ to make his own decision. esides in any situation if he feels threatened by
this type of leadership for the team work he can refuse to use democratic style. %part from that
the project manager usually also has responsible to Creport and liaiseD with different level of
management from general director clients sponsors to stakeholders and this is when skills of
using reporting9line is applied.
Concl'sion
This report has been written as a detailed planning for the (< !ompany"s project in order to
support the project manager and his team. t includes the detailed phases in the project life9cycle
concurrent with contemporary skills and competencies needed for project manager in controlling
project.
)"ord count: .4/7 &ords,
1#
-
8/11/2019 MP - asm mu (1).docx
19/27
Define
O Ee:uirements
analysisO +easibility
study
O +unctionalspecification
O )cenariodevelopment
O !ost9benefit
analysisO )et objectives
O !omparealternatives
Plan
O 3dentify tasks
O 3dentifycriticalactivities
O (stimate timeand cost
O Geterminestaffing
O Eisk analysis
O Ialueplanning
0#%ani=e
O @rgani6e
team
O %ssign work
E6ec'te
O 3ssue change
ordersO Eeview
project status
O Eeport onproject
O Eeview
schedule andbudget
O Fualifying
Close
O @btain client
acceptanceO !omplete
documentation
O )ign offO !onduct post
implementatio
n auditO *aintenance
O Ialueassessment
APP!N"#$#!S
A**endi6 2.1
%ccording to "eiss and "ysoc2i1''/ the basic project life9cycle has five stages define
plan organie e&ecute and close. ecause of large project this 59stage ,-! is
appropriate precise and easy to manage activities.
%ccording to ?. ;estlend 2006/ a standard project typically has the following four major
phases each with its own agenda of tasks and issues/ initiation planning e&ecution
and closure. Taken together these phases represent the path a project takes from the
beginning to its end and are generally referred to as the project life cycle.
1$
(stablish control
tools
nstall deliverables
Eecruit staff
)e:uence tasks
-
8/11/2019 MP - asm mu (1).docx
20/27
A**endi6 2.2
(&le for EE 8,I and E@ calculation
nitial nvestment P0000/
,rojected cash flow
Qear 1 P20000
Qear 2 P25000
Qear 3 P15000
Qear P10000
Qear 5 P5000
Total project cashflow P#5000
EE 33R
8,I at 5R/ P66$26
,ayback ,eriod Qears/ 2.33
E@ 8,I 4 nvestment/ P26$26
Source: te igeredico%co!
1'
-
8/11/2019 MP - asm mu (1).docx
21/27
0*en a ne" officeand "a#eho'se
b'ildin%
)tructure application
*ake the companyname sign
Eedesigning buildinginferior to suite
company culture
Gevelopment
1uyingL>iringfurniture5 device5
e:uipment
Gelivering products towarehouse
)ecurity and safety(valuation and review
+inali6ing thebuilding
@rgani6ing the people
Eecruitment
Training
A**endi6 2.+
The ;) for (< case
20
-
8/11/2019 MP - asm mu (1).docx
22/27
A**endi6 2.
(< project scheduling
Acti%it&
#dentifier
Acti%it& "escri+tion "uration ,da&s-uan
resource needs
Predecessor
%*ake the company
name sign# 2 9
Eedesigning
building inferior to
suite company
culture
20 10 %
!
uyingL>iring
furniture device
e:uipment
30 10
GGelivering products
to warehouse0 15
( )ecurity and safety 6 5 !G
++inaliing the
building15 10 (
= Eecruitment 20 $ +
> Training 60 10 =
=antt chart
21
-
8/11/2019 MP - asm mu (1).docx
23/27
A**endi6 2.3
22
Source: Sa!ser ;aider P1
-
8/11/2019 MP - asm mu (1).docx
24/27
Source: proteusadvisors%co!
23
-
8/11/2019 MP - asm mu (1).docx
25/27
*!F!*!N$!
Boo$s:
1. urke E. 2003/Project 1anage!ent4 Planning and 5ontrol Tecni6ues% ?ohn ;iley and
)ons.
2. +ield *. and arold ?. 1'$5/ uilding Aour usiness Plan. 8ew Qork ?ohn ;iley S
)ons.
Inte#net:
1. )hamsher >aider 200$/Bis2 Besponse Planning Strategies. %vailable at
httpLLerppm.blogspot.comL200$L0#Lrisk9response9planning9strategies.html %ccessed 23
)ep 2012/.
2.5onducting a Feasi-ility Study4 capter . Kniversity of ;isconsin !enter for
!ooperatives. %vailable athttpLLwww.uwcc.wisc.eduLmanualLchap5.html%ccessed 1$
)ep 2012/.
2
http://erppm.blogspot.com/2008/07/risk-response-planning-strategies.htmlhttp://erppm.blogspot.com/2008/07/risk-response-planning-strategies.htmlhttp://www.uwcc.wisc.edu/manual/chap_5.htmlhttp://erppm.blogspot.com/2008/07/risk-response-planning-strategies.htmlhttp://www.uwcc.wisc.edu/manual/chap_5.html -
8/11/2019 MP - asm mu (1).docx
26/27
3. Bis2 Besponse 5onsulting. %vailable at
httpLLwww.proteusadvisors.comL200$0501archive.htm%ccessed 2' )ep 2012/.
. B@3 5alculator Te!plate for 3T 3nvest!ents Csing NPD4 3BB and Pay-ac2 Period.
%vailable at httpLLthehigheredcio.comLproductsLroi9calculator9templateL %ccessed 21
)ep 2012/.
5. ?e!ocratic leadersip style% %vailable fromhttpLLwww.essortment.comLallLleadershipstylerrn:.htm%ccessed 2# )ep 2012/
6. -ee Q. 8. Eoland T. )ee Q. -. )eet >. -. 200'/ Trend and callenge of &areouse
and distri-ution center: uestions > 'ns&ers%%vailable at
httpLLwelovedcm.blogspot.comL200'L01L:uestion9answer.html%ccessed 15 )ep 2012/.
25
http://www.proteusadvisors.com/2008_05_01_archive.htmhttp://thehigheredcio.com/products/roi-calculator-template/http://www.essortment.com/all/leadershipstyle_rrnq.htmhttp://welovedcm.blogspot.com/2009/01/question-answer.htmlhttp://www.proteusadvisors.com/2008_05_01_archive.htmhttp://thehigheredcio.com/products/roi-calculator-template/http://www.essortment.com/all/leadershipstyle_rrnq.htmhttp://welovedcm.blogspot.com/2009/01/question-answer.html -
8/11/2019 MP - asm mu (1).docx
27/27