Module 5: Wind Project Contracts - USAID SARI/Energy ... · – “ENERCON guarantees its customers...
Transcript of Module 5: Wind Project Contracts - USAID SARI/Energy ... · – “ENERCON guarantees its customers...
Module 5: Wind ProjectContracts
1.800.580.3765 ▪ WWW.TTECI.COM
Module 5: Wind ProjectContracts
Presented to:
DFCC Bank and RERED Consortia MembersJanuary 25– 27, 2011 | Colombo, Sri Lanka
Pramod Jain, Ph.D.
Agenda
Structure of wind project and relationships Power Purchase Agreement Turbine Procurement contract EPC contract O&M Contract
Module Objectives
Learning Objectives• Understand the entities involved in a wind project• Understand the nature of contracts• Understand how to protect and minimize risk with contracts• Understand contract with turbine suppliers• Understand contract with EPC contractors• Understand Power Purchase Agreements
Wind Project Structure & Associated Contracts, Similar to Any Other IPP
Lender
Project LLC
Equity Partners
LocalInvestors
OutsideInvestors
TurbineSupplier
O&M
Government
Utility
EPCContractor
LandOwners
Power Purchasing Agreement
O&MAgreement
Project Equity
Payments forWind Rights
ProjectEquity
ProjectProfits
Contract Types and Purpose
Type of Contract Areas of Focus
Turbine Supplier
Interconnection Agreement
Others
Type of legal entity: Partnership, corporation, special purpose entity. Management rightsCash flow: Tax Incentives vs others
Securitized, Recourse
Buying, leasing, royalty payments
Long‐term PPA with credit‐worthy utility.Tariffs for supply of electrical energy, and rates for environmental attributesPenalties for delay, non‐performance, poor quality power. Take‐or‐pay contract
Construction contract requiring completion dates and penalties. Turnkey contract. Liquidated damages.
Turbine Supply contract. Power curve warranty. OEM warranty. Commissioning and project handover.
Access to grid, quality of power, protection systems, responsibility and payment of upgrades and new transmission
O&M, Insurance, employment
Ownership
Lender
Land
EPC Contractor
PPA with Utility
Ownership Contracts
Two types of ownership:• Corporate
– Project is in the balance sheet of a corporation– Lower cost of capital, depends on quality of balance sheet of sponsor– Example: Utility company, industrial conglomerate, etc.
• Special purpose entity– Established for the sole purpose of funding, owning and operating wind project. – Equity from shareholders that are commercial entities, investors, tax investors– Off the balance sheet of shareholders– No recourse or limited recourse to shareholders. Higher cost of capital.– Credit appraisal and lending decision is based on the inherent economics of the
project – not the credit standing or balance sheet of any sponsor• Contract will specify the allocation of cash flow and tax incentives as a
function of time• Example: Leveraged Flip structure.
Leveraged Flip Structure
• Initial Capital: 40% Equity, 60% Debt
• 95% Equity from tax investor, 5% from developer/sponsor
• Pre-flip: • Tax credit & losses: Tax
investor=95%. Sponsor=5%• Cash distribution: tax
investor=95%. Sponsor=5%• Post-flip
• Tax credits: None, fully utilized• Cash distribution: Tax
Investor=30%. Sponsor=70%• Tax losses: Tax investor=5%.
Sponsor=95%• Debt is paid from revenue
QUESTIONS?Questions?
Turbine Supplier
Types of contract:• Turnkey with turbine supplier (Common in SE Asia)• Equipment supply and commissioning (Common in USA, EU)
Scope of Supply and Services:• Equipment Supply:
– Blades, hub, nacelle, tower. – Spare parts, Special tools, Consumables– Others: Corrosion package, transformers, reactive power capability
• Services: – Site suitability– Instructions for transportation, handling, foundation, etc.– Supervision of installation– Start-up and commissioning– Operations training
Timeline for Turbine Supplier
Down payment: 25 to 60%. Delivery of turbines: 30% to 90%. 9 to 24 months Installation, assembly and erection: 2.5% to 10%. 1 to 2 months Commissioning, start of production: 5 to 10%
• Turbine operates as a single unit• Interconnection with utility and synchronization with grid• SCADA installed and commissioned. SCADA tested with live turbine data• Punch list of items remaining
Final project completion and handoff: 2.5 to 5%• Punch list items completed• All documents, manuals, designs, compliance certificates, training delivered• All equipment and debris removed from site• Ownership transfers from contractor to owner
Liquidated Damages with Turbine Supplier
Guidelines• Purpose is not to punish, but to compensate the affected party• Amount of damage is ascertained in advance or to be agreed/determined by court• Damages must be sufficiently uncertain at the time the contract is signed
Delay related• Related to delay of delivery or commissioning of wind plant• $ per turbine per day of delay, with an overall cap
Power curve related• 95 to 98% of warranted power curve is not achieved. Supplier has right to test• $ for deficient production until end of warranty period
Availability related• Hours turbine is ready to produce – hours allocated for scheduled maintenance• After ramp-up period, payments start. May have incentives for exceeding availability
Cap on liquidated damages, options:• Sub-caps apply to each items• Overall cap of 100%
Other Warranty, Defects Liability & Serial Defects
Noise level, similar to power curve warranty Defect causes part to fail
• Failure is: Break, failure to perform for which it was designed, intended or installed; or does not comply with specifications
• Serial defect: Defects that require replacement or repair of component in all turbines
• Supplier is obligated to fix Items excluded:
• Alterations by third party• Failure to service or maintain• Damage from force majeure• Improper foundation or installation
Warranty with Turbine Supplier
Alternatives:• Base warranty is 2 to 5 years• Performance warranty: 12 to 15 years
– “ENERCON guarantees its customers a technical availability of up to 97 % per year incl. a clearly defined maintenance factor. We offer this high availability for a service life of 15 years – this is unique on the wind market.
– From servicing to safety inspections, maintenance and repairs, all eventualities are covered by one single contract.
– Damage caused by unforeseeable events such as acts of nature and vandalism can be covered by a specially developed additional EPK insurance policy.
– The fees under the ENERCON PartnerKonzept contract are based on the annual wind turbine output. The customer pays a minimum fee depending on the respective wind turbine type plus a yield-oriented surcharge. The fee is calculated separately for each individual wind turbine / wind farm per year and according to the annual kWh produced during the elapsed operating year”
Source: http://www.enercon.de/en-en/673.htm
EPC Contractor
Engineering, Procurement and Construction contract• Turnkey• Delivers completed project• At pre-specified cost• Within pre-specified timeframe• With pre-specified production level and quality
Ideal EPC contract is:• Fixed price with fixed delivery date• Security deposit or performance bond to guarantee performance• Liquidated damages for delay in completion and substandard performance
Advantages of EPC: • Single point of responsibility
Disadvantages:• More expensive because of build in contingencies• In tight market contractors may not be willing to bid on fixed price contracts
QUESTIONS?Refer to Chapter 2 of Riso’s Burgos Project Review
Power Purchase Agreement (PPA) with Utility
PPA: Agreement between wind project owner (Independent Power Producer, IPP) and Utility• Simple exercise if PPA rates are mandated by legislation for wind projects• Complex if PPA is signed with Utility that will pass on rates to consumers
Components:• Price of energy and duration of purchase• Pricing or sharing of renewable energy credits and other incentives• Capacity contract versus energy delivery contract• Penalties/incentives related to planned vs actual date of commissioning• Allocation of risk related to permitting, siting and interconnection
PPA must have enough protection for IPP:• Utility should bear risks due to changes in law, and uncontrollable events
because it can pass on cost to consumers• IPP cannot pass on cost
PPA, Distribution of Risk (contd.)
Risk Borne by Developer Project risk related to:
Equipment, development, engineering, installation, commissioning, financing, and others that it can control
Equipment failure due to poor maintenance
Availability guarantee
Risk that Developer cannot Bear
Weather: Strength of wind• Cannot write long term climate
insurance
Change of laws• Cannot write change-in-law
insurance
Uncontrollable events Production guarantee without
force majeure
If IPP is assuming risks above and beyond the cost of producing power, make sure it is paid for it!In other words, ensure IPP is not in the insurance business, without collecting premium.
QUESTIONS?Review SDGE PPA Contract
Land Lease or Easement Contract
Scope of agreements with land owners:• Development period (met-tower, studies and survey):
– Fixed amount per acre per year– Tower fee per tower per year
• Construction period– Installation fee per MW or per turbine
• Operating period– Production payment: Based on amount of energy production– Royalty payment: Percentage of gross revenue (exclude tax credits)
• May be a minimum royalty payment: Per MW per year
Other Contracts
O&M: Based on availability of wind energy plant Interconnection agreement:
• Specifies the interconnection specifications• Quality of power in terms of:
– Low Voltage Ride Through (LVRT): Ability of plant to stay operational during a short duration fault
– Amount of reactive power consumed– Amount of reactive power that can be supplied– Limit high frequency harmonics– Limit amount of flicker– Voltage and frequency tolerances
Conclusions
There are numerous contracts in a wind project, akin to any other power project
In addition to good contracts, risks can be minimized by:• Experienced & proven engineer and contractor• Experienced & credit worthy operators for O&M• Experienced, credit worthy wind turbine supplier with long history quality
product