Level of development - BIM

4

Click here to load reader

Transcript of Level of development - BIM

Page 1: Level of development - BIM

Practical BIM-

LOD was developed by a construction costing software company (Vicosoftware) and was used to make

the process of estimating possible in BIM. Estimating involves human factor, but LOD makes BIM models

do estimation without the involvement of human.

- They developed the concept of Level of Detail

o LOD 100 – not very definitive, but area/volume rate are accurate enough

o LOD 200 – number of items in the model are correct, but they have to estimated

individually

o LOD 300 – items defined, actual cost can be used

o LOD 400 – has supply data also, so can be used to assess payments for purchases

- AIA redefined the term LOD to mean Level of Development to be used in reference to BIM

- Renamed it so that it is not confused with amount of information, rather than the decisiveness

of information

Level of Development

- It is a measure of how seriously you take the information represented by a BIM element

- Different people perceive the information differently - to be able to work they require a certain

level of details

o To order something, contractor requires only the model number and manufacturer. But

to install it, the carpenter requires the dimensions, material etc. So, for the same

product - different details are required by different players

- Level of Development “LOD” - LOD 100 – describing what it is; LOD 200 – its dimension; LOD 300

– its functions and options; LOD 400 – manufacturer and model; LOD – 500 LOD 400 + delivery

details

- Tells information what a particular person can use

- Also a measure of the completeness of work- LOD 100= 20%; LOD 200= 40%... LOD 500= 100%

Level of Detail

- It is a measure of the amount of information provided – measure of quantity

- Level of Detail “LOD”

o Differently used by various agencies

CIC (Penn State) called as Information Level of Details aka “Info”– A: size,

location, material, object parameters; B: general size and location, object

parameters; C: schematic size and location

USACE M3 (Min. Model Matrix) called as Grade – A: 3D + facility data; B: 2D +

facility data; C: 2D + text description

AEC (UK) BIM Protocol called as Graded Component Creation- G0: Schematic;

G1: Concept; G2: Defined 3D; G3: Rendered 3D

o LOD Tables – tabular representation of LOD data; describes how information in BIM

model will progress; how much information is usable at each stage of project etc

Link between Development and Detail

- Both are quite different but closely related and interdependent

Page 2: Level of development - BIM

- One cannot have a certain Level of Development if Level of Details does not exist

- Without Details you cannot successfully visualize a product, and without Development you

cannot order the right product.

- Level of Detail – required more in the starting phase and decreases as project proceeds

- Level of Development – required less in the starting phase, but increases as project proceeds

- So, for clarity – LOD: Level of Development; Grade: Level of Details

An LOD table is an attempt to record agreed responsibilities around a BIM Model. It sets the Division of

Responsibility inside the BIM model. There are various LOD concepts which can be used. The author

finds the US AIA E203 document which uses LOD and MEA (Model Element Author) in its Model Element

Table as most appropriate. It allows to use the broad structure and concept, and gives flexibility change

the structure, add new levels etc. and cater it to needs required by the project. It treats LOD not a set

rules, but as a process.

To make the best use of LOD we have to think about how we can make it meaningful to our project and

the project team.

- US AIA E203 gives freedom to create LOD table the way you like

- Keep it simple enough to understand and complex enough to accommodate all the needs

- Create multiple levels

o Create levels even for sub tasks like inspection, QA/QC check etc.

- Make multiple tables for different players containing the details they require

- Treat LOD as a concept, not a rule. Tweak it to your own needs

BIM: Measurement of design progress on large capital projects-

In this chapter, the author delves into techniques that can be used to make implementation of BIM

more effectively by focusing his attention on LOD. One of the key challenge that BIM practitioners face

is the measurement of design progress in a BIM model.

- BIM model tends to evolve unlike 2D drawings that follow linear fashion. So, different method

has to be used for progress measurement in BIM

- Analytical Analysis ability of BIM is useful in this case and author puts forward some analytical

analysis techniques that can be used

Setting up data collection now to enable progress tracking later:-

- It begins with the definition of LOD. Different LOD levels should be defined. LOD 100, LOD 200,

LOD 300, LOD350, LOD 400 and LOD 500

- As we move from LOD 100 to LOD 350 more and more details should be added to make the

object more defined and certain

- LOD should definitions can be customized

- Intermediate LOD levels like LOD 350 should be created to enable better understanding and

coordination between various disciplines.

- Higher level of LOD like LOD 400 and LOD 500 have more details and can be used for

prefabrication and field verification rather than design coordination.

o LOD 400 and LOD 500 can be added later on, they are not necessarily required during

design process

Page 3: Level of development - BIM

o This will save time during design phase

Model Progression Table (MPT)

- Accompanies customized LOD definitions

- Unit Measurement per element per LOD should be added

o Helps in keeping track of progress at different LOD levels

o As it uses Measurement Units – it becomes easier – it is like integrating old and new i.e.

2D measurement for quantity to BIM

- Grouping and layering of model elements

o Layers and objects should be named to help designing and coordination

o In addition, elements should be separated with their respective LOD layers

LOD 100 level details in one layer, and then LOD 200, LOD 300 etc. level details

are added in separate layer. All these combine to for the complete element

- Schedule, categorize and link activities to model elements

o Various phases like design/engineering, modelling, coordination, revision, re-

coordination etc. should be categorized in the BIM model

o Attach each of these phases with a WBS code

o This helps track how much time and resources are spent in each phase

Lack of sufficient effort during design/engineering phase causes revisions in the

design, and then it has to be re-coordinated – loss of time and resources

If revision and re-coordination for a particular activity is more, it means there

was faults in its design, and thus, more time can be allocated to these activities

in future to avoid it

- Track inputs of productivity

o People involved in BIM modelling should keep a time-log for keeping track of time they

spent on different activities, WBS, LOD level etc.

o This will help in knowing how much time was spent on a particular element – area of

time wastages can be avoided to increase productivity

Using data collected to analyze and measure progress by leveraging data analytics

- Input hours tracked in time sheets

- Model output tracked in LOD layers connected via WBS

- Combining both (input hours and model output) creates a living dataset

- Applying Data Analytics – different analysis can be done to track and measure BIM progress

o Hours spent per LOD %age completion

Gives visibility to effort spent in LOD per progress %age points gained

o Hours spent per category per LOD %age completion

Know if efforts spent were proportional or disproportionate to %age completion

by LOD

If disproportionality is there, then time spent can either be increased or

decreased to enhance productivity

If downstream activities (revision) takes more time, then time spent on

upstream activities (design/engineering) can be increased which will

result in less revisions downstream

Page 4: Level of development - BIM

o Vertical Analysis – the BIM “efficiency ratio”

Hours spent redesigning, remodeling and re-coordinating are waste in system

Lesser or no time should be spent here

Greater time spent in initial design, modelling and coordination lead to less

waste in system

BIM efficiency ratio: Ratio of (time spent in initial design, modelling and

coordination) to (time spent in redesigning, remodeling and re-coordination)

o Horizontal analysis – the BIM “weighted average efficiency ratio

Different phases were created in MPT by blending model elements with

schedule activities through WBS

By using this we are able to find time spent in each phase of the LOD

o Initial design – more time spent on LOD 100s

o Later phase – more time spent on LOD 350s

Calculate BIM efficiency ratio per LOD

This can be further used to create weighted average efficiency ratio

This provides information regarding efficiency over particular time period of

design as well as a trending measure over various phases of project

o Using RACI (Responsible, Accountable, Consulted and Informed) matrix to allocate tasks

to individuals

RACI analysis of each individual across each activity done to spot overlaps and

gaps

Enhances clarity of individual responsibilities

o Regression analysis and bench marking

The data obtained from one project can be used to make improvements in

future projects

Data can also be used for selection of individuals like architect, engineer etc.

o Linking element/activity to schedule of values

Making progress payments like monthly payments to contractors

Will require more effort in initial stages but very useful in later stages of project