Lecture 4 PMIS

download Lecture 4 PMIS

of 19

Transcript of Lecture 4 PMIS

  • 7/27/2019 Lecture 4 PMIS

    1/19

    L e c t u r e r : E m m a L o n g e iE m a i l : e m m a . l o n g e i @ g m a i l . c o m

    1

    HEP 3104: PROJECTMANAGEMENT INFORMATION

    SYSTEMS

    Lecture 4: Using a PMIS to createand plan a project

    21 June 2012

  • 7/27/2019 Lecture 4 PMIS

    2/19

    Topics Covered last week / this week

    1. Review of Project life Cycle and Project planning stages2. Tasks, Sub-tasks, Components and Work Packages3. Work Breakdown Structure4. Network planning diagrams

    3.1 Critical Path3.2 Program Evaluation and Review Technique

    5. Milestone Charts/ Gantt Charts6. Creating a project in PMIS7. Using WBS in PMIS

    8. Using CPA in PMIS9. Creating a Baseline in PMIS10. Creating reports in PMIS

  • 7/27/2019 Lecture 4 PMIS

    3/19

    Basic Requirements of a PMIS (rev)3

    1. List phases, tasks and sub-tasks

    2. Create a Work Breakdown Structure (WBS)

    3. Create network diagrams Critical Path Analysis

    (CPA), Project Evaluation and Review Technique(PERT)

    4. Produce varied reports for different stakeholders

  • 7/27/2019 Lecture 4 PMIS

    4/19

    Other requirements of a PMIS4

    5. Allow different team members to create and updateitems collaboration

    6. Budget, plans, schedules, calendars, email/chat,

    7. Dependent on organisation, budget, complexity ofproject, experience and capacity of the projectmanager and project team

  • 7/27/2019 Lecture 4 PMIS

    5/19

    Todays Topics: Building a house

    Listing of tasks

    Work in groups to create Parent tasks, sub-tasks, work-packages (3 levels)

    Work Breakdown structure Critical Path diagram

    View the creation of the project tasks, scheduleactivities and indicate predecessor and successor

    tasks in MS Project 2007

  • 7/27/2019 Lecture 4 PMIS

    6/19

    Step 1: Identify the work to be done

    Surveying

    Excavation

    Request Permits

    Buy Material Lay foundation

    Build Outside Wall

    Install Exterior Plumbing Install Exterior Electrical

    Install Interior Plumbing

    Install Interior Electrical

    Plaster walls

    Paint Interior

    Install Interior Doors Tile Floor

    Install Roof

    Install Exterior Doors Paint Exterior

    Move In

  • 7/27/2019 Lecture 4 PMIS

    7/19

    Step 1 -4

    1. List tasks and sub-tasks

    2. Create a WBS

    3. Create a network diagram (CPM)

    4. Create the project in MS Project 2007 Gantt Chart

    WBS

    CPM

    MAJOR TASKS (Building a house)

    1. Preparation 2. Build Exterior 3. Finishing

  • 7/27/2019 Lecture 4 PMIS

    8/19

    Activity break: 10 minutes

    In groups of two, create a task list with each of theactivities in the previous slide

  • 7/27/2019 Lecture 4 PMIS

    9/19

  • 7/27/2019 Lecture 4 PMIS

    10/19

    1. Tasks and sub-tasks

    3. Finishing

    3.1. Install Interior Plumbing

    3.2. Install Interior Electrical

    3.3. Plaster walls

    3.4. Paint Interior

    3.5. Install Interior Doors

    3.6. Tile Floor

    3.7. Move In

  • 7/27/2019 Lecture 4 PMIS

    11/19

    Activity 2: Create a WBS

    With pen & paper, or using a software application,create a work breakdown structure of tasks createdin activity 1

  • 7/27/2019 Lecture 4 PMIS

    12/19

    Build

    house

    1. Preparation

    1.1. Surveying

    1.2. Excavation

    1.4. Materials

    1.5. Foundation

    1.3. Permits

    2. BuildExterior

    2.1. Outside Walls

    2.2. Exterior Plumbing

    2.3. Roof

    2.4.Exterior Doors

    2.5. Paint Exterior

    3. Finishing

    3.1. Interior Plumbing

    3.2. Interior Electrical

    3.3. Plaster walls

    3.4. Paint Interior

    3.5. Interior Doors

    3.6. Tile Floors

    3.7. Move In

    2. WBS

  • 7/27/2019 Lecture 4 PMIS

    13/19

    2. WBS

    What important tasks are missing from WBS

    PowerPoint allows you to modify shapes and colours

    The sum of the sub-tasks contributes to 100%

    completion of the parent task Microsoft PowerPoint is suitable for drawing a small

    WBS and a large WBS is better constructed inMicrosoft Visio or similar program

    (http://www.project-blog.com/?page_id=64).

  • 7/27/2019 Lecture 4 PMIS

    14/19

    3. CPM

    Update task list to indicate predecessors and taskdurations in weeks (or suitable time period)

    Each task should have a predecessor (task before it)

    and a successor (task or event after it) except theSTART and END tasks

    The network will be updated during the course of theproject in order to remain current

    May be done in Excel

  • 7/27/2019 Lecture 4 PMIS

    15/19

    Activity 3: Create a network diagram

    With pen & paper, or using a software application,create a critical path diagram of tasks created inactivity 1

  • 7/27/2019 Lecture 4 PMIS

    16/19

    Using PMIS to create a project

    Create a new project

    File > New

    File > Properties

    File > Save (do this every 15 minutes)

    Modify the calendar

    Copy tasks from the Task and Sub-task list intoGantt View

    Put in the task durations Create the linkages (dependencies) by indicating pre-

    decessors

  • 7/27/2019 Lecture 4 PMIS

    17/19

    Create a Baseline

    This is the original project plan, including the timeschedule and resource and cost allocation.

    The baseline is used for comparing projected values

    to actuals, and facilitates the tracking and analyzingof a projects progress.

    Because the baseline provides the reference pointsagainst which you compare actual project progress,

    the baseline should include your best estimates fortask duration, start and finish dates, costs, and otherproject variables that you want to monitor.

    http://office.microsoft.com/en-us/project-help/create-or-update-a-baseline-or-an-interim-plan-HA010156784.aspx

  • 7/27/2019 Lecture 4 PMIS

    18/19

    Create a Baseline

    Project > Tools > Tracking > Set Baseline

    TO view a Baseline

    Project Information > Statistics

    Your baseline creates a snapshot of your project at a

    specific place in the timeline. You can have multiplebaselines.

    It enables you to assess performance vs your plan

    http://www.brighthub.com/office/project-management/articles/14643.aspx

  • 7/27/2019 Lecture 4 PMIS

    19/19

    References

    Westland, Jason. 2003. Project ManagementGuidebook

    Work breakdown structure.http://en.wikipedia.org/wiki/Work_breakdown_structure

    Course Q7503: Principles of Software ProjectManagement, lectures by, Instructor: John Musser

    [email protected]. Seehttp://www.projectreference.com/

    Microsoft Project: 1 Introductionby Mike Glen,MVP.http://pubs.logicalexpressions.com/Pub0009/LPMArticle.asp?ID=141

    http://en.wikipedia.org/wiki/Work_breakdown_structurehttp://en.wikipedia.org/wiki/Work_breakdown_structuremailto:[email protected]:[email protected]://en.wikipedia.org/wiki/Work_breakdown_structurehttp://en.wikipedia.org/wiki/Work_breakdown_structure