Lecture 8 Reporting Using PMIS
Transcript of Lecture 8 Reporting Using PMIS
-
7/27/2019 Lecture 8 Reporting Using PMIS
1/27
HEP 3104: PROJECT
MANAGEMENT INFORMATIONSYSTEMS
2nd August 2012
Lecturer: Emma Longei
Email: [email protected]
1
Lecture 8: Reporting using PMIS
Monitoring, correction, evaluation
-
7/27/2019 Lecture 8 Reporting Using PMIS
2/27
Topics covered
Project monitoring with PMIS
Correcting Project Deviation
Budget management using a PMIS Creating and disseminating project reports
Producing reports using other software tools
2
-
7/27/2019 Lecture 8 Reporting Using PMIS
3/27
3
Project Life Cycle
http://en.wikipedia.org/wiki/Project_management
-
7/27/2019 Lecture 8 Reporting Using PMIS
4/27
Project Deviation
Scope of a project in project management is the
sum total of all of its products and their
requirements or features.
Scope creep (or drift) refers to uncontrolled
changes in a project's scope. This phenomenon
can occur when the scope of a project is not
properly defined, documented, or controlled. It isgenerally considered a negative occurrence that
is to be avoided.
4http://en.wikipedia.org/wiki/Glossary_of_project_management.htm
-
7/27/2019 Lecture 8 Reporting Using PMIS
5/27
Project Deviation
Requirements creep: time and cost estimation
techniques used when planning did not
include contingency time or budget
Common problem with software projects
If not managed, project deviation will lead to
failure to meet project objectives, failure to
complete project on time or on budget, and
perhaps project failure
5
-
7/27/2019 Lecture 8 Reporting Using PMIS
6/27
Managing Project Deviation
Build a flexible approach that can accommodatechanges as they arise.
Aim for a balance - if the plan is too flexible the
project will meander like a horse without a riderand if it is too rigid the project will break like glassthe first time a stakeholder tosses you a newrequirement.
The best way to handle this is to have a plan, toupdate it regularly and make sure everyone isfollowing it and pointing in the same direction.
6
Jenkins (2005)
-
7/27/2019 Lecture 8 Reporting Using PMIS
7/27
1. Add time delay the project to give you more
time to add the functionality
2. Add cost recruit, hire or acquire more
people to do the extra work
3. Cut quality trade off some non-essential
requirements for the new requirements
7
Managing Project Deviation
-
7/27/2019 Lecture 8 Reporting Using PMIS
8/27
8
Duration * Units = Work Duration = Work / Units (D = W/U)
Work = Duration * Units (W = D*U)
Units = Work / Duration (U = W/D)
Adding more resources to a task shortens duration
Can be changed on a per-task basis In the advanced tab of Task Information dialog box
Task Type setting
Beware the Mythical Man-month: adding resourcesto a task does not always mean the task can be donefaster
Managing Project Deviation: MSProject elements
-
7/27/2019 Lecture 8 Reporting Using PMIS
9/27
Assignment: Modify your project
Add 3 or so tasks without changing the
schedule
Increase schedule by without changing the
budget
Reduce budget by without changing scope
Is this possible?
9
-
7/27/2019 Lecture 8 Reporting Using PMIS
10/27
10
THE PROJECT MANAGER
Risk Quality or other
-
7/27/2019 Lecture 8 Reporting Using PMIS
11/27
Project Deviation: Maintain and
Analyze the Project Schedule Updating the Project Schedule on a regular
basis while keeping a close watch on thetimeline and budget is the primary
mechanism to measure quality of theschedule.
If the project timeline or budget are not ontrack, the Project Manager can determine whyand take immediate action to remedy theproblem.
11
-
7/27/2019 Lecture 8 Reporting Using PMIS
12/27
Managing Project Deviation: Reports
Reports are a good way of reviewing
allocations of resources at the beginning of
the project, and as it progresses, progress to
date
Reports > Reports > Current Activities >
Slipping Tasks
Project summary (Status) report
12
-
7/27/2019 Lecture 8 Reporting Using PMIS
13/27
Some good reports may be produced from the
PMIS, but others from other software
including specialized (project) accounting
software, Excel, and others.
MS Project 2007 can produce reports in Excel
and Vision
13
Managing Project Deviation: Reports
-
7/27/2019 Lecture 8 Reporting Using PMIS
14/27
14
Managing Project Deviation: Excel
Reports
0
500000
1000000
1500000
2000000
2500000
3000000
3500000
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
Q4 Q1 Q2 Q3 Q4
2011 2012
CumulativeCost
Cost
Cash Flow ReportCost Cumulative Cost
-
7/27/2019 Lecture 8 Reporting Using PMIS
15/27
Click Report on the Menu bar, and then click
Copy Picture to display the Copy Picture dialog
box. Keep the default settings. Click OK.
15
Using the Copy Picture Feature
-
7/27/2019 Lecture 8 Reporting Using PMIS
16/27
16
Managing Project Deviation: Reports
-
7/27/2019 Lecture 8 Reporting Using PMIS
17/27
17
Managing Project Deviation: Reports
-
7/27/2019 Lecture 8 Reporting Using PMIS
18/27
Outside PMIS
Outside the PMIS, how can project deviation
be managed?
There are various tools and documents such
as:
Change Management
Quality Assurance and Quality Control
processes
Risk Management Plan
18
-
7/27/2019 Lecture 8 Reporting Using PMIS
19/27
Activity
Generate one or two reports in Excel, and save
them. Hyperlink them to the last line of your
project (Finish)
Create a word document (Project Plan), and
paste the Gantt chart in it.
19
-
7/27/2019 Lecture 8 Reporting Using PMIS
20/27
Budget Management
The Project Manager must know the extent of
his/her authority to make budget decisions.
For example, is the Project Manager allowed
to authorize work that requires additional
hours of salaried personnel time, or must
employee time extensions go through the
same approval process as contract personnelor equipment purchases?
20
-
7/27/2019 Lecture 8 Reporting Using PMIS
21/27
Part of the Project Managers job is to ensure that
the project is completed within the allocated and
approved budget.
MS Project creates budgets based on assignmentwork and resource rates - people, equipment and
materials
Budget management includes all the project costsi.e. human resources, equipment, travel, materials
and supplies.
21
Budget Management
-
7/27/2019 Lecture 8 Reporting Using PMIS
22/27
Changes to the scope of the project will have
an impact on the budget. Just as scope
changes need to be controlled and managed,
so do changes to the Project Budget.
22
Budget Management in PMIS
-
7/27/2019 Lecture 8 Reporting Using PMIS
23/27
Budget in MS Project: work
Resources are the people and equipment
needed to accomplish your project tasks. In
order to be able to assign tasks to them, you
need to create the resources in your projectplan file.
By default, resources are work resources,
meaning that they consume time toaccomplish the task.
23
-
7/27/2019 Lecture 8 Reporting Using PMIS
24/27
Material resources are goods that your project
will consume, such as sand for a construction
project. They have a cost associated with
them, but have no calendar and are notassigned overtime rates.
24
Budget in MS Project: materials
-
7/27/2019 Lecture 8 Reporting Using PMIS
25/27
Cost resources are miscellaneous expenses
that do not vary from task to task and do not
change by the amount of work performed on
the task, such as airfare.
Budget resources are the work, material and
cost resource types applied at the project level
by applying them to the project summarytask.
25
Budget in MS Project: cost
-
7/27/2019 Lecture 8 Reporting Using PMIS
26/27
CAT 2 Performance
Summary task
Numbering of project activities should be
done, whether manually or using the software
Break down the resources and materials to
units to ease allocation
Learn to use Copy Picture tool to enable
embedding of MS Project Screen in a Word
document such as the project plan
26
-
7/27/2019 Lecture 8 Reporting Using PMIS
27/27
References
Jenkins, Nick (2005). A Project Management
Primer or a guide on how to make projects
work
Software Project Management: Development
Management. http://www.columbia.edu
Q7503_8post Development Mgt.ppt
Project ExecutionAndControl NY State.pdf
27
http://www.columbia.edu/~jm2217http://www.columbia.edu/~jm2217