Large Chilled Water System

download Large Chilled Water System

of 314

Transcript of Large Chilled Water System

  • 8/10/2019 Large Chilled Water System

    1/314

    Large Chilled Water SystemDesign Seminar

    Presented by:

    Larry Konopacz, Manager of Training & Education

    Bell & Gossett Little Red Schoolhouse

    This presentation is being brought to you

    by:ASHRAE India Chapter and Xylem, Inc.

    Saturday, September 21, 2013

  • 8/10/2019 Large Chilled Water System

    2/314

    Large Chilled Water System Design Seminar

    The Production Loop

  • 8/10/2019 Large Chilled Water System

    3/314

    Chillers

    Cooling towers

    Free-Cooling &Waterside Economizer

    Thermal Storage

    Water Source Heat Pumps

    Chilled Water Sources

  • 8/10/2019 Large Chilled Water System

    4/314

    I Ton Ice =

    2000 LB;1LB Ice =144 Btu;

    1 Ton ice =288,000 Btu

    Whats a Ton?

  • 8/10/2019 Large Chilled Water System

    5/314

    12,000 Btu/h = 500 x gpm x tF = 1 ton

    gpm/ton = 12,000/(500 x tF)

    = 24/tF

    Rule of 24

  • 8/10/2019 Large Chilled Water System

    6/314

    What Types of Chillersare Available?

    Centrifugal

    Rotary screw

    Reciprocating Absorption

    Evaporator

    Condenser

    Compressor

  • 8/10/2019 Large Chilled Water System

    7/314

    Refrigeration Cycle

    Cooling

    Tower

    Condenser

    CondenserWater Pump

    Compressor

    Motor

    Expansion Device

    Chilled

    WaterPump

    High

    PressureZo

    ne

    LowP

    ressureZone

    L

    oad

    Hot Water Liquid Flow

    Return

    WaterVapor Flow

    Cool Water

    Supply

    WaterEva

    porator

  • 8/10/2019 Large Chilled Water System

    8/314

    Where is What Used?

    Large chilled water plants - centrifugal Mid-range size - rotary screw

    Smaller chilled water applications -reciprocating

    Inexpensive source of steam or other

    energy source - absorption Combinations of the above

  • 8/10/2019 Large Chilled Water System

    9/314

    CHILLERChiller 2

    Chiller 1

    SupplyReturn Common Pipe

    Chiller Piping - Evaporator Side

  • 8/10/2019 Large Chilled Water System

    10/314

    Supply

    Return

    CommonPipe

    TripleDuty

    Chiller 3

    Chiller 2

    Chiller 1TripleDuty

    Typical Piping Method

  • 8/10/2019 Large Chilled Water System

    11/314

    Supply

    Return

    Common

    Pipe

    Triple

    Duty

    Chiller 2

    Triple

    DutyChiller 1

    Adding Pump Redundancy

  • 8/10/2019 Large Chilled Water System

    12/314

    Piped forStandbyPumps

    Supply

    Return

    CommonPipe

    TripleDuty

    Chiller 3

    Chiller 2

    Chiller 1

    TripleDuty

    Actuated Control Valve

    Headered Primary Pumps

  • 8/10/2019 Large Chilled Water System

    13/314

    Chiller Piping - Condenser Side

    CondenserCondenser

    Condenser

    Pumps

    Cooling Towers

    Triple Duty

    SRS SRS SRS

  • 8/10/2019 Large Chilled Water System

    14/314

    TripleDuty

    Standby Pump

    Condenser

    Condenser

    Condenser

    Multi-cell Cooling Tower

    SRS

    Multi-celled Cooling Tower

  • 8/10/2019 Large Chilled Water System

    15/314

    Cooling Towers

    Triple Duty

    Condenser

    Condenser

    Condenser

    Equalization

    Line

    SRS

    Tower Equalization

  • 8/10/2019 Large Chilled Water System

    16/314

    Cooling Tower Piping Practices

    Fill all sections of pipe to purge air. Size piping at a minimum of 2 fps to

    move free air bubbles to tower.

    All piping installed below system purge

    level.

  • 8/10/2019 Large Chilled Water System

    17/314

    System Purge Level

    SRS

    Condenser Water Piping Above Grade

  • 8/10/2019 Large Chilled Water System

    18/314

    Overhead Piping Concerns

    Piping manifolds can result in low velocities. Low velocity will allow air to be released.

    Air trapped in piping increases head required.

    Piping installed above purge level compounds

    problem.

    Unpurged areas are potential sources ofproblems when pumps are turned on.

  • 8/10/2019 Large Chilled Water System

    19/314

    Elevated Suction Piping Concerns

    Condenser water pump difficult to purge. At start-up a manual air vent may be required.

    During operation air will again accumulate.

    Automatic air vent may not work.

    If above the basin fill level, the result is

    cavitation.

  • 8/10/2019 Large Chilled Water System

    20/314

    Improper Piping Above Basin Level

    System Purge Level

    Basin Fill Level

  • 8/10/2019 Large Chilled Water System

    21/314

    System Purge Level

    SRS

    Multi-tower System, Properly Piped

  • 8/10/2019 Large Chilled Water System

    22/314

    Tower Piping Observations

    At part load reduced velocities in headers may

    allow air to be released.

    Idle pumps will accumulate air that should be

    released prior to starting the pump. Tower basins should be elevated to ensure

    positive pressure under all flow conditions.

    Pump casings should be fitted with automatic

    air vents.

  • 8/10/2019 Large Chilled Water System

    23/314

    Condenser Head Pressure Control

    With centrifugal chillers a minimum supplywater temperature is needed to:

    Maintain optimum efficiency

    Maintain a minimum pressure differential

    between condenser and evaporator

    Prevent pressure imbalance

  • 8/10/2019 Large Chilled Water System

    24/314

    Hermetic Compressor Guidelines

    Condenser water temperature > 75 F. Establish 75 F within 15 minutes.

    N/O condenser water throttling valve.

    Three-way bypass valve can be used.

    Constant condenser water flow.

    Water temperature control through fan

    modulation, or other methods.

  • 8/10/2019 Large Chilled Water System

    25/314

    Open Compressor Guidelines

    Condenser water temperature > 55 F. Three-way bypass valve can be used.

    Constant condenser water flow.

    Water temperature control through fan

    modulation, or other methods.

  • 8/10/2019 Large Chilled Water System

    26/314

    Water In Water out

    Air in Air out

    Cooling Towers

  • 8/10/2019 Large Chilled Water System

    27/314

    Water out

    Air in Air in

    Water in

    Air Out

    Induced Draft, Counter-flow Tower

  • 8/10/2019 Large Chilled Water System

    28/314

    Air Out

    Air inAir in

    Water out

    Water in

    Forced Draft, Cross-flow Tower

  • 8/10/2019 Large Chilled Water System

    29/314

    Temperature Water Flow

    Hot water F

    Cold water F

    Wet bulb F

    L lb/min of water

    L lb/min of water

    Load

    Range

    (RF)

    A

    pproach

    (

    F)

    Heat Load = L x R

    Dynamic Relationship of Load,Approach, and Range

  • 8/10/2019 Large Chilled Water System

    30/314

    Tower Size Relationships

    Variables: Heat Load (Varies Directly)

    Range (Varies Inversely)

    Approach (Varies Inversely)

    Wet-bulb Temperature (Varies Inversely)

    Varying any of these variables will affect

    the size of the tower.

  • 8/10/2019 Large Chilled Water System

    31/314

    Types of Free-Cooling(Waterside Economizer)

    Water out

    Air in Air in

    Water in

    Air Out

    Earth ContactEvaporative

  • 8/10/2019 Large Chilled Water System

    32/314

    Earth Contact Characteristics

    Usually indirect. Cooling medium and load separated by heat

    exchanger.

    Stable temperatures. Water temperature limitations.

    Water treatment and pumping costs.

    Environmental concerns.

  • 8/10/2019 Large Chilled Water System

    33/314

    Heat Exchangers

  • 8/10/2019 Large Chilled Water System

    34/314

    How do they work?

    Thin plates are stamped with

    a unique chevron pattern andassembled in a frame

    Four holes punched in the

    plate corners form a

    continuous tunnel which actsas a distribution manifold for

    the inlet and outlet of each

    fluid

  • 8/10/2019 Large Chilled Water System

    35/314

    How do they work?

    Each plate has a gasket that

    confines the fluid to the portor to the heat transfer area of

    the plate

    Units are built to order with a

    standard 150 psi ASME Codestamped design or to custom

    designs

  • 8/10/2019 Large Chilled Water System

    36/314

    LOAD

    C

    O

    N

    D

    E

    V

    A

    P

    Triple Duty

    Sediment RemovalSeparator

    Triple Duty

    TOWER

    H

    E

    A

    T

    E

    X

    C

    H

    GPX

    Earth Contact - Summer Cycle

  • 8/10/2019 Large Chilled Water System

    37/314

    LOAD

    C

    O

    N

    D

    E

    V

    A

    P

    Triple Duty

    Sediment RemovalSeparator

    Triple Duty

    TOWER

    H

    E

    A

    T

    E

    X

    C

    H

    GPX

    Earth Contact - Winter Cycle

  • 8/10/2019 Large Chilled Water System

    38/314

    Evaporative Characteristics

    Heat rejection device (tower) exists. As temperature declines, opportunity

    arises.

    Higher sensible vs. latent loads

    Leaving water temperature approaches

    42 F. Freeze protection may be required.

  • 8/10/2019 Large Chilled Water System

    39/314

    Freeze Protection

    Sump heaters. Close temperature control.

    Accurate water level control.

    Prevention of moist air recirculation.

    External piping freeze protection.

  • 8/10/2019 Large Chilled Water System

    40/314

    Evaporative Cooling - Direct

    LOAD

    C

    ON

    D

    E

    VA

    P

    Triple Duty

    Triple DutySediment Removal

    Separator

    TOWER

    Single Tower, Summer Cycle

  • 8/10/2019 Large Chilled Water System

    41/314

    LOAD

    C

    O

    N

    D

    E

    V

    A

    P

    Triple Duty Triple Duty

    Sediment Removal

    Separator

    TOWER

    * Alternate location of SRS, depending on

    system conditions

    NOT RECOMMENDED

    Single Tower, Winter Cycle

    Evaporative Cooling - Direct

  • 8/10/2019 Large Chilled Water System

    42/314

    Evaporative Cooling - Indirect

    LOAD

    C

    O

    ND

    E

    V

    AP

    Triple Duty

    Sediment Removal

    Separator

    Triple Duty

    TOWER

    H

    E

    A

    T

    E

    X

    C

    H

    GPX

    Single Tower/GPX, Summer Cycle

  • 8/10/2019 Large Chilled Water System

    43/314

    Evaporative Cooling - Indirect

    LOAD

    C

    O

    ND

    E

    V

    AP

    Triple Duty

    Sediment Removal

    Separator

    Triple Duty

    TOWER

    H

    E

    A

    T

    E

    X

    C

    H

    GPX

    Single Tower/GPX, Winter Cycle

  • 8/10/2019 Large Chilled Water System

    44/314

    COND. WATER

    CH. WATER

    TEMP.

    DEG. F

    EXCHANGER

    LENGTH

    57=

    42=

    45=

    52=

    7F TEMPERATURE

    CROSS

    3F COOLING

    APPROACH

    T1

    t2

    t1

    T2

    Temperature Cross and Approach

  • 8/10/2019 Large Chilled Water System

    45/314

    Temperatures are in F Flow is in USGPM

    Heat exchanger selection based on max pressure drop of 7 psi

    10/3.92=2.55 Approach = 3F10/4.93=2.03 Approach = 4F

    10/5.94=1.69 Approach = 5F

    COND. WATER CH. WATER LMTD AREA EXCH. COST

    EWT LWT FLOW EWT LWT FLOW DEG F SQ.FT. MODEL INDEX

    42 52 1000 57 45 834 3.92 1390 GPX807 1.00

    42 52 1000 58 46 834 4.93 1135 GPX807 0.85

    42 52 1000 59 47 834 5.94 975 GPX807 0.76

    Heat Transfer Area vs Approach

  • 8/10/2019 Large Chilled Water System

    46/314

    Production Source - Thermal Storage

    Application Criteria Economics

    Storage Media

    Storage Technologies

    System Configurations

  • 8/10/2019 Large Chilled Water System

    47/314

    Application Criteria

    High maximum load. Significant premium for peak demand.

    Incentives.

    Limited space available.

    Limited electrical capacity.

    Back-up or redundancy required.

  • 8/10/2019 Large Chilled Water System

    48/314

    Storage Media

    Chilled Water Ice Harvesting

    External/Internal Ice Melt

    S f C S

  • 8/10/2019 Large Chilled Water System

    49/314

    T

    Vent

    Load

    Pressure sustainingand check valve

    StorageWarm

    Cool

    Variable volumedistributionpump

    Constant volumeprimary pump

    Chiller

    Stratified Chilled Water System

    T t St tifi ti

  • 8/10/2019 Large Chilled Water System

    50/314

    30 40 50 60 70

    -5

    -10

    -15

    Bottom -20

    Top 0

    Deptho

    ftank,ft

    Temperature, F

    Thermocline

    Temperature Stratification

    U f P S t i i V l

  • 8/10/2019 Large Chilled Water System

    51/314

    Vent

    Pressure sustaining

    and check valve

    StorageWarm

    Cool

    Constant volume

    primary pump

    Chiller

    Distributionpump

    Primarypump

    Load

    Transfer PumpDirectioncontrolvalves

    Use of Pressure Sustaining Valves

    I ti H t E h

  • 8/10/2019 Large Chilled Water System

    52/314

    Load

    T

    Vent

    Pressure sustainingand check valve

    StorageWarm

    Cool

    Variable volumeprimarypump

    Constant volumeprimary pump

    Chiller

    T

    Heat

    Exchanger

    Variable volumesecondarypump

    Incorporating Heat Exchangers

  • 8/10/2019 Large Chilled Water System

    53/314

    Section1

    Section2

    Section3

    Section4

    Ice harvester

    chiller

    Load

    Chilled water

    pump

    Ice waterrecirculation

    pump

    Ice Harvesting System

  • 8/10/2019 Large Chilled Water System

    54/314

    Charging ModeDischarging Mode

    External Melt Ice Storage

  • 8/10/2019 Large Chilled Water System

    55/314

    Ice

    WaterIceCold glycol

    Warm glycol

    Charging Mode Discharging Mode

    Encapsulated Ice StorageCharge and Discharge Modes

  • 8/10/2019 Large Chilled Water System

    56/314

    Tons

    Time of Day

    Cooling load

    (met by storage)

    Charging

    Storage

    Charging

    Storage

    Chiller meets load directly

    Chiller on

    Chiller off

    Full Storage Strategy

  • 8/10/2019 Large Chilled Water System

    57/314

    T

    ons

    Time of Day

    Cooling load(met by storage)

    ChargingStorage

    ChargingStorage

    Cooling load

    (met by chiller)

    Chiller runs continuously

    Partial Storage - Load Leveling

  • 8/10/2019 Large Chilled Water System

    58/314

    Tons

    Time of Day

    (met by storage)Charging

    StorageCharging

    Storage

    (met by chiller)

    Cooling load

    Reduced on-peak demandPartial Storage - Demand Limiting

  • 8/10/2019 Large Chilled Water System

    59/314

    Production Source - Water Source Heatpumps

    Growing market segment System temperature range 40 - 90 F

    Energy added below 40 F (heat)

    Heat removed above 90 F (cooling

    tower)

    Heat Pump Cycles Water Source

  • 8/10/2019 Large Chilled Water System

    60/314

    Air Coil(Evaporator)

    CoolAir Compressor

    Reversing Valve

    Capillary

    Air Conditioner Cooling

    Air Coil(Condenser)

    WarmAir

    Reversing Valve

    Capillary

    Air Conditioner Heating

    Water Coil(Evaporator)

    Water Coil(Condenser)

    System WaterSupply

    Return

    Compressor

    Refrigerant

    Loop

    Heat Pump Cycles - Water Source

  • 8/10/2019 Large Chilled Water System

    61/314

    Design Considerations

    Use slow closing two-way valves foreach zone

    Good system balance required

    Use staged c/s or v/s pumps

    Use with cooling towers and GPX

    Use with closed circuit cooling towers

    Heat Pump-Water Source Schematic

  • 8/10/2019 Large Chilled Water System

    62/314

    Water Source

    Heat Pump

    Water Source

    Heat Pump

    Water Source

    Heat Pump

    Water Source

    Heat Pump

    Water Source

    Heat Pump

    Water Source

    Heat Pump

    Water Source

    Heat Pump

    Water Source

    Heat Pump

    Water Source

    Heat Pump

    Buffer

    Tank

    ( Optional )

    Compression

    Tank

    Gasketed

    Plate Heat

    Exchanger

    Cooling

    Tower

    Heat Pump-Water Source Schematic

    Heat Pump-Water Source Schematic

  • 8/10/2019 Large Chilled Water System

    63/314

    Closed Circuit Cooler

    Heat Rejecter

    Water SourceHeat Pump

    Water SourceHeat Pump

    Water SourceHeat Pump

    Water SourceHeat Pump

    Water SourceHeat Pump

    Water Source

    Heat Pump

    Water Source

    Heat Pump

    Water Source

    Heat Pump

    Water Source

    Heat Pump

    Buffer

    Tank

    ( Optional )

    Compression

    Tank

    Heat Pump-Water Source Schematic

  • 8/10/2019 Large Chilled Water System

    64/314

    Comments?

    Questions?Observations?

  • 8/10/2019 Large Chilled Water System

    65/314

    Large Chilled Water System Design Seminar

    Variable Volume Distribution

  • 8/10/2019 Large Chilled Water System

    66/314

    Variable flow through coilConstant flow through system

    Three Way Valve

    Variable flow through coilVariable flow through system

    Two Way Valve

  • 8/10/2019 Large Chilled Water System

    67/314

    Three-Way Valve Systems

    Low return temperatures Balance problems

    Increased flow at part load

    Extra chillers to provide flow at low t

    Chillers operate at high kW/ton

    Two Way Valve System with

  • 8/10/2019 Large Chilled Water System

    68/314

    C

    H

    I

    L

    L

    E

    R

    C

    H

    I

    L

    L

    E

    R

    Two-Way Valve System with

    Chiller BypassA

  • 8/10/2019 Large Chilled Water System

    69/314

    We want:

    a. variable volume, to save pumping

    costs at part load,

    b. constant flow through the chiller to

    protect it.

    A Solutiona. constant flow primary system for the chillers

    b. variable flow secondary system for the load

    A Problem

  • 8/10/2019 Large Chilled Water System

    70/314

    C

    HI

    L

    L

    E

    R

    C

    HI

    L

    L

    E

    R

    C

    HI

    L

    L

    E

    R

    Return

    Primary-SecondaryCommon Pipe

    SupplyPrimary Loop

    Production

    Secondary Loop

    Distribution

    Primary-Secondary Terms

  • 8/10/2019 Large Chilled Water System

    71/314

    Fundamental Idea

    Secondary

    Pump

    Tee

    APrimary

    Pump

    Tee

    B

    Low pressure drop in the common pipe

  • 8/10/2019 Large Chilled Water System

    72/314

    Primary-Secondary Pumping

    The idea is based on:

    Conservation of Mass

    Conservation of Energy

  • 8/10/2019 Large Chilled Water System

    73/314

    50 GPM100 GPM

    50 GPM

    Law of the Tee: Diversion

  • 8/10/2019 Large Chilled Water System

    74/314

    40 GPM60 GPM

    100 GPM

    Law of the Tee: Mixing

  • 8/10/2019 Large Chilled Water System

    75/314

    No Secondary Flow

    100 GPM @ 45F

    Secondary

    Pump

    Off

    A B100 GPM @ 45F

    100 GPM @ 45FPrimary

    Pump

  • 8/10/2019 Large Chilled Water System

    76/314

    Primary = Secondary

    100 GPM @ 45F0 GPM

    Pump On

    A B

    100 GPM @ 45F 100 GPM @ 55F

    100 GPM @ 55F

  • 8/10/2019 Large Chilled Water System

    77/314

    Primary > Secondary

    Pump On

    A B

    Mixing at Tee B

    100 GPM @ 45F

    50 GPM @ 45F

    100 GPM @ 50F

    50 GPM @ 55F

    50 GPM @ 45F

  • 8/10/2019 Large Chilled Water System

    78/314

    Pump On

    A B

    Mixing at Tee A

    100 GPM @ 45F 100 GPM @ 55F

    100 GPM @55F

    200 GPM @ 50F 200 GPM @ 55F

    Primary < Secondary

  • 8/10/2019 Large Chilled Water System

    79/314

    Two-way Valve

    Control Valve in Secondary

    Primary-Secondary Pumping

  • 8/10/2019 Large Chilled Water System

    80/314

    C

    H

    IL

    L

    E

    R

    C

    H

    IL

    L

    E

    R

    C

    H

    IL

    L

    E

    R

    Return

    Primary-SecondaryCommon

    SupplyPrimary Loop

    Production

    Secondary Loop

    Distribution

  • 8/10/2019 Large Chilled Water System

    81/314

    Common Pipe Design Criteria

    Use the flow of the largest chiller

    Chiller staging at half of this flow is

    common

    Head loss in common

  • 8/10/2019 Large Chilled Water System

    82/314

    Return

    Supply

    PumpController

    SecondaryConstant Speed

    Pumps

    Common

    Chiller3

    Chiller2

    Chiller1

    Design of the Common Pipe

    10 dia.

    Common Pipe Configurations

  • 8/10/2019 Large Chilled Water System

    83/314

    A B

    C D

    Secondary System Curve

  • 8/10/2019 Large Chilled Water System

    84/314

    Head

    F1 F2 F3

    H1

    H2

    H3

    Flow

    Control Valves

    Closing

    Control Valves

    Opening

    Typical System

  • 8/10/2019 Large Chilled Water System

    85/314

    From Loads

    Common

    To LoadsProduction

    Secondary Pumps

    1500 gpm each

    Distribution

    Ch

    iller2,off

    Chiller1,on

    1500 gpm

    each

    45F

    Production = Distribution

  • 8/10/2019 Large Chilled Water System

    86/314

    Common -- No Flow

    SecondaryPumps

    1500

    1500

    1500 15000

    CHWS Temp45oF

    CHWR Temp

    55

    o

    F

    ECW Temp

    55

    o

    F

    1500

    Chille

    r2,off

    Chille

    r1,on

    Distribution > Production

  • 8/10/2019 Large Chilled Water System

    87/314

    Common -- 500

    Secondary

    Pumps

    1500

    2000

    1500 20000

    CHWS Temp

    47.5oF

    CHWR Temp

    55o

    F

    ECW Temp

    55o

    F

    Mixing (1500 @ 45) + (500 @ 55)

    Chiller

    2,off

    Chiller

    1,on

    2000

    Check Valve in Common?

  • 8/10/2019 Large Chilled Water System

    88/314

    >1500 GPM

    Return

    Common

    Supply

    >1500 GPM

    0 GPM

    >1500 GPM

    @ 47.5oF

    >1500 GPM

    @ 55oF

    Be Careful!

    C

    hiller2,off

    C

    hiller1,on

    What can we do?

  • 8/10/2019 Large Chilled Water System

    89/314

    Step

    Function

    Linear

    Function

    Return

    Primary/Secondary

    Common

    Supply

    Production

    Distribution

    Chiller3

    Chiller2

    Chiller1

    Typical Load Profile

  • 8/10/2019 Large Chilled Water System

    90/314

    0-10 30-40 60-70 90-100

    0

    5

    10

    15

    20

    25

    30

    0-10 30-40 60-70 90-100

    %T

    ime

    % Load

    Multiple Chillers

  • 8/10/2019 Large Chilled Water System

    91/314

    Chiller2

    ,

    60%

    Chiller1

    ,

    40%

    % Load

    % Time

    100

    80

    60

    40

    20

    100755025

    Chiller 1

    Chiller 2

    1

    12 2

    What else can we do?

    Reset S ppl Temperat re

  • 8/10/2019 Large Chilled Water System

    92/314

    Reset Supply Temperature

    Lower chiller set point when mixing occurs to

    maintain a constant temperature to the system. Allows us to mix colder water and maintain supply

    temperature to secondary. (coils)

    Expect increases in cost of chiller operation atlower set point: 1-3% per degree of reset.

    Adds to control complexity.

    Delays start of the next chiller.

    Production > Distribution

  • 8/10/2019 Large Chilled Water System

    93/314

    Common -- 900

    Secondary

    Pumps

    3000

    2100

    15002100

    1500

    CHWS Temp

    45oF

    CHWR Temp

    55o

    F

    ECW Temp

    52o

    F

    Mixing (2100 @ 55) + (900 @ 45)

    (Flow in GPM)

    P/S Chiller Bridge - Front Loaded Common

    Chiller1,on

    Chiller2,on

    Loading a Chiller

  • 8/10/2019 Large Chilled Water System

    94/314

    Loading a Chiller

    A chiller is a heat transfer device. Like

    most equipment, it is most efficient at

    full load.

    To load a chiller means: Supply it with its rated flow of water

    Insure that water is warm enough to permit

    removal of rated Btu without freezing thewater

    Chiller Performance Curve

  • 8/10/2019 Large Chilled Water System

    95/314

    Chiller Performance Curve1.1

    20 30 40 50 60 70 80 90 10010

    1.0

    0.9

    0.8

    0.7

    0.6

    0.5

    KWper

    Ton

    Percent Load

    Typical Load Profile

  • 8/10/2019 Large Chilled Water System

    96/314

    0-10 30-40 60-70 90-100

    0

    5

    10

    15

    20

    25

    30

    0-10 30-40 60-70 90-100

    %T

    ime

    % Load

    Typical Load Profile

    60/40 Chiller Split to Help Minimize

    Low Part Load Operation

  • 8/10/2019 Large Chilled Water System

    97/314

    Chiller

    2,60%

    Chiller

    1,4

    0%

    % Load

    % Time

    100

    80

    60

    40

    20

    100755025

    Chiller 1

    Chiller 2

    1

    1

    2 2

    Low Part Load Operation

    Three Unequally Sized Chillers

  • 8/10/2019 Large Chilled Water System

    98/314

    % Load

    % Time

    100

    80

    60

    40

    20

    100755025Chiller 1

    or

    Chiller 2

    Chiller 3

    Chiller 1and

    Chiller 2

    Chiller 1 orChiller 2and

    Chiller 3

    Chiller

    2,4

    0%

    Chille

    r1,4

    0%

    Chiller

    3,60%

    Three Unequally Sized Chillers

    Approaching Flow = Load

  • 8/10/2019 Large Chilled Water System

    99/314

    % Load

    Time

    Approaching Flow = Load

    Applying a Variable Speed Chiller

  • 8/10/2019 Large Chilled Water System

    100/314

    % Load

    % Flow

    100755025

    100

    75

    50

    25

    Ch 1Ch 2 Ch 3 Ch 4

    Ch 1Ch 2 Ch 3

    Ch 1Ch 2

    Ch 1

    Applying a Variable Speed Chiller

    Back Loaded Common

  • 8/10/2019 Large Chilled Water System

    101/314

    From loads

    Common

    To Loads

    Chiller3

    Chiller2

    Chiller1

    Production = Distribution

  • 8/10/2019 Large Chilled Water System

    102/314

    Common

    0 Flow

    Secondary

    Pumps

    1500

    CHWS Temp

    45oF

    CHWR Temp

    55o

    F

    Chiller2,off

    Chiller1,on

    1500

    1500

    15001500

    Distribution > Production

  • 8/10/2019 Large Chilled Water System

    103/314

    Common

    500 gpm

    SecondaryPumps1500

    2000

    1500 20000

    CHWS Temp47.5oF

    CHWR Temp

    55o

    F

    500

    Mixing (1500 @ 45) + (500 @ 55)

    500

    Chille

    r1,on

    Chille

    r2,off

    Production > Distribution

  • 8/10/2019 Large Chilled Water System

    104/314

    Common900

    SecondaryPumps1500

    2100

    1500

    2100

    1500 GPM

    @ 49oF

    CHWS Temp45oF

    CHWR Temp55oF

    Mixing (900 @ 45) + (600 @ 55)

    900 600

    900 GPM@ 45oF

    600 GPM@ 55oF

    1500 GPM

    @ 55oF

    Chiller2,on

    Chille

    r1,on

    Maximize Free Cooling

  • 8/10/2019 Large Chilled Water System

    105/314

    Return

    Supply

    PumpController

    Secondary

    Pumps

    Primary-SecondaryCommon

    Chiller3

    Chiller2

    FreeCooling

    Primary-Secondary System

  • 8/10/2019 Large Chilled Water System

    106/314

    Return

    Supply

    PumpController

    SecondaryPumps

    Primary-SecondaryCommon

    Chiller3

    Chiller2

    Chiller1

    Pump Horsepower Comparison

  • 8/10/2019 Large Chilled Water System

    107/314

    BHP

    125

    100

    75

    50

    25

    150

    25 50 75 100

    Design Coil Flow

    %

    Primary Pumps = V/V

    Secondary Pumps +

    Constant Flow Primary Pumps, only

  • 8/10/2019 Large Chilled Water System

    108/314

    2012 ASHRAE Handbook - HVAC Systems and Equipment, p 44.11

    140

    150 Pump Over-headed by 150%Constant Flow, C/S Pump

    (3 Way Valve)

    Constant vs Variable Volume

  • 8/10/2019 Large Chilled Water System

    109/314

    % Flow

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0 10 1009080706050403020

    100

    110

    120

    130

    BaseDesign

    HP %

    % Full Load

    (Design) HP

    Constant Flow, C/S Pump

    (3 Way Valve)

    C/S Pump

    (2 Way Valve)

    Pump Head Matchedto System @

    Design Flow

    Impact of Piping Length and Overheading

  • 8/10/2019 Large Chilled Water System

    110/314

    0

    50

    100

    150

    200

    250

    300

    350

    0 1000 2000 3000 4000 5000 6000 7000 8000 9000

    Pipe Length , Feet

    Yearly

    Opera

    tingCostx

    $1

    000

    c/s @ 1.0

    c/s @ 1.25

    c/s @ 1.50

    c/s @ 2.0

    Always Size the Pump to the System!

  • 8/10/2019 Large Chilled Water System

    111/314

    But...

    Uncertainties

    Coils

    Control valves Primary data

    Lead times

    Dealing With an Overheaded Pump

  • 8/10/2019 Large Chilled Water System

    112/314

    Throttle at the discharge valve

    Limits on the valve

    Flow balance & trim pump impeller

    Required by ASHRAE/IES 90.1

    Additional Concerns

  • 8/10/2019 Large Chilled Water System

    113/314

    Pump Protection at minimum flow

    Chiller Staging and De-staging

    instrumentation.

    Pump Protection

  • 8/10/2019 Large Chilled Water System

    114/314

    Minimum recommended flow from ESP Plus = 900 gpm

    Bypass Options

    1. Establish a minimum flow equal to or greater than

  • 8/10/2019 Large Chilled Water System

    115/314

    q g

    the minimum required to protect the pump.

    2. Install a bypass at the end of the mains with a

    balance valve to set minimum flow.

    3. Install a bypass at ends of zones.

    4. In retrofits, leave a three way valve at the end of the

    system.

    5. Use P or flow sensing to open pump bypass only

    when needed.

    6. V/S pumps are not as big a problem because oflower head at reduced flow.

    System Bypass Options3

  • 8/10/2019 Large Chilled Water System

    116/314

    6

    Return

    Supply

    Pump

    Controller

    Secondary

    Constant Speed

    Pumps

    PrimarySecondary

    Common

    Chiller3

    Chiller2

    Chiller1

    2

    5

    T

    Chiller Staging Instrumentation

  • 8/10/2019 Large Chilled Water System

    117/314

    From Loads

    Common

    To Loads

    Production

    Secondary/Pumps

    Distribution

    Chille

    r2,off

    Chiller

    1,on

    FP

    FSTS-S

    TS-RTP-R

    TP-S

    Common Pipe Flow Indication

    Distribution

  • 8/10/2019 Large Chilled Water System

    118/314

    From LoadsCommon

    To Loads

    Production

    Secondary/PumpsChiller2

    Chiller1

    Flow

    Swi

    tches

  • 8/10/2019 Large Chilled Water System

    119/314

  • 8/10/2019 Large Chilled Water System

    120/314

    Large Chilled Water Design Seminar

    Variable Speed Pumping

    Why variable speed?

  • 8/10/2019 Large Chilled Water System

    121/314

    y p

    1. When should I use it?

    2. How does it work?

    3. What about variable primary flow?

    Typical operating load profile

  • 8/10/2019 Large Chilled Water System

    122/314

    2% 3%5%

    15%

    20%

    30%

    15%

    5%3%

    2%

    Bell & Gossett 70V

    1970s

  • 8/10/2019 Large Chilled Water System

    123/314

  • 8/10/2019 Large Chilled Water System

    124/314

    Adjustable Frequency Drives

    Rectifier section

    t AC t DC

  • 8/10/2019 Large Chilled Water System

    125/314

    converts AC to DC

    several varieties available Inverter section

    forms a synthetic sine wave

    several varieties available

    maintains a controlled frequency/voltage ratio

    Requires an automatic control system Adds to the initial cost of the system

    Affinity Laws

  • 8/10/2019 Large Chilled Water System

    126/314

    1. Capacity varies as the RPM change ratio:

    FLOW 2 = FLOW 1 ( SPEED2 / SPEED 1)

    2. Head varies as the square of the RPM change ratio:

    HEAD 2 = HEAD 1 (SPEED 2 / SPEED 1)2

    3. Brake horsepower varies as the cube of the RPM change ratio:

    BHP 2 = BHP 1 (SPEED 2 / SPEED 1)3

    Affinity Laws for Centri fugal Pumps

  • 8/10/2019 Large Chilled Water System

    127/314

    0

    10

    20

    3040

    50

    60

    70

    80

    90

    100

    0 10 20 30 40 50 60 70 80 90 100

    Flow/Speed, Percent

    P

    ercent

    Flow

    Head

    Horsepower

    Theoretical Savings120

    110

    100

    120

    110

    100

    Pump Curves 100% Speed

    90% Design

  • 8/10/2019 Large Chilled Water System

    128/314

    %H

    ead

    %B

    HP

    % Design Flow

    90

    80

    5040

    30

    2010

    70

    60

    90

    80

    50

    40

    30

    2010

    70

    60

    0 0

    80%

    70%

    60%

    50%

    40%

    30%

    Head

    Flow

    BHP

    10 20 30 40 50 60 70 80 90 1000

    HP Draw

    Head

    Required Differential Pressure

  • 8/10/2019 Large Chilled Water System

    129/314

    P Sensor/Transmitter25 Ft. Head

    System Curve

    & V/S Control System

  • 8/10/2019 Large Chilled Water System

    130/314

    Flow

    piping headloss curve

    Distribution

    Pum

    pTDH

    Overallsystem curve

    Head

    80

    60

    40

    20

    110

    0200 400 600 800 1000 1200 1400 16000

    100

    Set Point

    25 FT Differential HeadMaintained Across Load

    (Set Point)

    Effect of Constant* Set Point110

    100

    As the valve closes,

    the pump slows down

  • 8/10/2019 Large Chilled Water System

    131/314

    piping headloss curve

    Distribution

    PumpT

    DH

    Overall system curve

    Head

    80

    60

    40

    20

    0200 400 600 800 1000 1200 1400 16000

    Flow

    Control curveSet point,

    25 FT

    *Whats Constant?

    AB

    Pump

    Initial Speed

    Control Curve

  • 8/10/2019 Large Chilled Water System

    132/314

    Q1Q2Flow, Q

    (gpm)

    Head, H

    (feet)

    Decrease in Heat Load Results in Troom < T set pointCauses Two Way Valves to Throttle Flow

    Pipe, Fitting

    Friction Loss

    AB

    Pump

    CurveControl Curve

    Speed 1

    Speed 2

  • 8/10/2019 Large Chilled Water System

    133/314

    Q1Q2Flow, Q(gpm)

    Head, H(feet)

    Decrease in Pump Speed Reduces Flow, Reduces Error

    Speed 2

    C

    Q3

    Pipe, Fitting

    Friction Loss

    AB

    Control CurveSpeed 1

  • 8/10/2019 Large Chilled Water System

    134/314

    System Operation on Control Curve at Lower Speed

    Q1Flow, Q(gpm)

    Head

    (ft) Pipe, Fitting

    Friction LossFinal Speed C

    Q4

    V i bl H d L

    Constant Head Loss

    Variable vs Constant Head Loss

  • 8/10/2019 Large Chilled Water System

    135/314

    Return

    C

    HI

    L

    L

    E

    R

    C

    HI

    L

    L

    E

    R

    C

    HI

    L

    L

    E

    R

    Supply

    Variable Head Loss

    PumpController

    Adjustable Freqy. Drives

    90

    100C/S, Constant Flow System Pump Head Matched to

    System at Design FlowBase

    Variable Head Loss Ratio

  • 8/10/2019 Large Chilled Water System

    136/314

    PercentD

    esignBHP

    % Flow

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0 10 1009080706050403020

    C/S, Variable Flow V/S, 0% Variable Hd Loss, 100% Constant Hd

    V/S, 25% Variable Hd Loss, 75% Constant Hd

    V/S, 50% Variable Hd Loss, 50% Constant Hd

    V/S, 75% Variable Hd Loss, 25% Constant Hd

    V/S, 100% Variable Hd Loss, 0% Constant Hd

    Variable Head Ratio w/

    Overheading

    140

    150 Pump OHeaded by 150%Constant Flow, C/S Pump

    (3 Way Valve)

    C/S P

  • 8/10/2019 Large Chilled Water System

    137/314

    90

    80

    70

    60

    50

    40

    30

    20

    10

    0 10 1009080706050403020

    100

    110

    120

    130

    Base

    Design

    HP %

    % Full Load

    (Design) HP

    Constant Flow, C/S Pump

    (3 Way Valve)

    C/S Pump

    (2 Way Valve)

    Pump HD Matched

    to System @Design Flow

    * 25/75 Means:25 % Variable HD Loss

    75 % Constant HD Loss

    120

    11080 %

    85 %80 %70 %60 %

    50 %

    85 %

    % Efficiency

    V/S Curves

  • 8/10/2019 Large Chilled Water System

    138/314

    100

    90

    80

    50

    40

    30

    20

    10

    70

    60

    0100 200 300 400 500 600 700 800 900 10000

    100 %

    90 %

    80 %

    70 %

    60 %

    50%

    40 %

    30 %

    80 %

    % Speed Curves

    ConstantEfficiencyCurve

    Head

    ,Feet

    GPM

    120

    11080 %

    85 %80 %70 %60 %

    50 %

    85 %

    % Efficiency

    Efficiency Changes

  • 8/10/2019 Large Chilled Water System

    139/314

    100

    90

    80

    50

    40

    30

    20

    10

    70

    60

    0

    100 200 300 400 500 600 700 800 900 10000

    100 %

    90 %

    80 %

    70 %

    60 %

    50%

    40 %

    30 %

    80 %

    % Speed Curves

    Constant

    Efficiency

    Curve

    Head

    ,Feet

    GPM

    Minimum Drive Speed120

    110

    100 100 %

    80 %85 %80 %

    70 %60 %50 %

    85 %

    % Efficiency

  • 8/10/2019 Large Chilled Water System

    140/314

    90

    80

    50

    40

    30

    20

    10

    70

    60

    0

    100 200 300 400 500 600 700 800 900 10000

    90 %

    80 %

    70 %

    60 %

    50%

    40 %

    30 %

    % Speed Curves

    ConstantEfficiency

    Curve

    Head,

    Feet

    GPM

    Variable Head Loss

    Constant Differential Head Loss

    Multiple Pump System Staging

  • 8/10/2019 Large Chilled Water System

    141/314

    Return

    C

    HI

    L

    L

    E

    R

    C

    HI

    L

    L

    E

    R

    C

    HI

    L

    L

    E

    R

    Supply

    Variable Head Loss

    PumpController

    Adjustable Freqy. Drives

    Parallel V/S Operation

  • 8/10/2019 Large Chilled Water System

    142/314

    Control Curve

    Pump 1

    Pumps 1 & 2 Pumps 1, 2 & 3

    1770 RPM

    600 RPM 900 RPM

    1150 RPM

    1450 RPM

    Set PointTechnologic

    P

    AdjustableFrequency

    3f , 60 Hz Power

    (Control Agent)

    Set Point+/- error

    Variable Speed Pumping Equipment

  • 8/10/2019 Large Chilled Water System

    143/314

    Set Point(Input Signal)

    PumpController

    FrequencyDrive

    (Controlled Device)

    SystemSensor/

    Transmitter

    3f, Variable FrequencyVariable Voltage

    FeedbackSignal

    ControlledVariable

    The Controlled Variable Determines the Type of Sensor

    Pressure

    Differential

  • 8/10/2019 Large Chilled Water System

    144/314

    DifferentialPressure

    DifferentialTemperature

    Flow

    PumpController

    Temperature

    4-20ma

    signal

    Set PointTechnologic

    Pump

    AdjustableFrequency

    3f , 60 Hz Power

    (Control Agent)

    Set Point+/- error

  • 8/10/2019 Large Chilled Water System

    145/314

    (Input Signal)Pump

    Controller

    q yDrive

    (Controlled Device)

    SystemSensor/

    Transmitter

    3f, Variable FrequencyVariable Voltage

    FeedbackSignal

    ControlledVariable

    Technologic Pump

    Controller

    Controls pumps and drives

  • 8/10/2019 Large Chilled Water System

    146/314

    Controls pumps and drives

    Accept set point, analyze sensor input

    PID function

    Pump staging

    Pump alternation Recognize and react to component failure

    Provide message display

    Central management system link Safeguard system

    PID Control Eliminates offset from set point

  • 8/10/2019 Large Chilled Water System

    147/314

    Eliminates offset from set point

    Allows for timely speed change

    Handles large, sudden disturbances

    Prevents oscillation and over-damping

    Set Point( S )

    TechnologicPump

    Adjustable

    Frequency

    3f , 60 Hz Power

    (Control Agent)

    Set Point+/- error

  • 8/10/2019 Large Chilled Water System

    148/314

    (Input Signal)Pump

    Controller Drive

    (Controlled Device)

    SystemSensor/

    Transmitter

    3f, Variable FrequencyVariable Voltage

    FeedbackSignal

    ControlledVariable

    Adjustable Frequency Drive

    ConstantVoltage &F

    RectifierSection

    DirectCurrent

    InverterSection

    VariableVoltage &Frequency

    PumpMotor

  • 8/10/2019 Large Chilled Water System

    149/314

    Frequency

    Power

    Section Current Section Frequency

    Power

    Motor

    Some important issues:

    Rectifier and Inverter Design

    Drive EfficiencyRFI and EMI Noise

    Audible Noise

    Size and Cost

    Manual drive bypass

    100

    120

    Typical Efficiency Range

    Variable Speed Drives

  • 8/10/2019 Large Chilled Water System

    150/314

    0

    20

    40

    60

    80

    0 20 40 60 80 100

    Design Speed, %

    E

    fficiency,% Currently AvailableAFDs

    Typical Older AFDs

    Other Types

    Pump and Motor

  • 8/10/2019 Large Chilled Water System

    151/314

    The Pump

    Minimum Flow

  • 8/10/2019 Large Chilled Water System

    152/314

    Minimum Flow

    Minimum Speed

    Inverter Duty

    Motors

    Motor Couplers

    Maintaining Minimum Flow120

    110

    100

    90

    100 % Speed

  • 8/10/2019 Large Chilled Water System

    153/314

    80

    50

    40

    30

    20

    10

    70

    60

    0

    10 20 30 40 50 60 70 80 90 1000

    % Flow

    Head

    30% Speed

    EPDM couplers on variable-speed pumps

  • 8/10/2019 Large Chilled Water System

    154/314

    Failed Hytrel Coupler from a Variable

    Speed Pump

  • 8/10/2019 Large Chilled Water System

    155/314

  • 8/10/2019 Large Chilled Water System

    156/314

    Variable FlowThrough

    The Evaporator

    Variable Head Loss

    Constant Differential Head Loss

    Primary-Secondary System

  • 8/10/2019 Large Chilled Water System

    157/314

    Return

    C

    HI

    L

    L

    E

    R

    C

    HI

    L

    L

    E

    R

    C

    HI

    L

    L

    E

    R

    Supply

    PumpController

    Adjustable Freqy. Drives

    Primary-Secondary

    Common Practice.

  • 8/10/2019 Large Chilled Water System

    158/314

    Why?

    Protection. Nuisance shutdowns.

    Freezing.

    Costly downtime.

    Variable Primary Flow

    Flow Meter, optionTwo-position Control Valves

  • 8/10/2019 Large Chilled Water System

    159/314

    AFD AFD AFD

    CHILLER

    CHILLER

    CHILLER

    Modulating

    Valve

    DP

    Sensor

    Controller

    DPSensor D

    PSensorD

    PSensor

    Whats different? Primary pumps only Flow meters or p sensors at each

  • 8/10/2019 Large Chilled Water System

    160/314

    chiller.

    Two-position isolation valves at each

    chiller Minimum flow bypass with a modulating

    control valve.

    Smarter controller.

    Alternative #1

    Minimum Flow Bypass at Chillers

  • 8/10/2019 Large Chilled Water System

    161/314

    Minimum Chiller Flow

    Minimum Pump flow

    Ganged Pumps

    DPSENSOR

    FLOWMETER

    DPSENSOR

    DPSENSOR

    DPSENSOR

    DPSENSOR

    SIGNALTO TECH

    SIGNAL SIGNAL BYPASS:

    T

    FFF

    CHILLER CHILLER CHILLER

    SUPPLY

  • 8/10/2019 Large Chilled Water System

    162/314

    AFD AFD AFD

    SIGNALSTO TECH

    SIGNAL

    TO TECH

    SIGNAL

    TO TECH

    NOTE:

    ALL SENSORSIGNALS WIRED TOTECHNOLOGIC5500

    BYPASS:

    FOR SYSTEMS WITHEXTENDED LIGHT

    LOADS/WEEKENDSHUTDOWNS. SETBALANCE VALVEFOR LOW FLOW TOREDUCE THERMALSTRATIFICATIONAND ALLOW QUICKSTART UP AFTER

    SHUT DOWN.

    T

    SIGNALSTO TECH

    SIGNALSTO TECH

    F

    T

    FLOWMETER/TRANSMITTER

    TEMPERATURE SENSOR

    ISOLATION VALVE

    CHECK VALVE

    RETURN

    TDV TDV TDV

    Monitoring Chiller Flow

    P sensors - Technologic controller ensures the chilleris in proper working condition by monitoring each

    working chillers differential pressure. Flow through the

  • 8/10/2019 Large Chilled Water System

    163/314

    chiller is calculated using the values defined in the usersetup.

    OR

    Flow sensors - Technologic controller ensures the chiller

    is in proper working condition by monitoring each

    working chillers flow rate.

    Technologic 5500 Initial programming is

  • 8/10/2019 Large Chilled Water System

    164/314

    crucial. Must use accurate data

    from the chiller

    manufacturer. Start-up coordination

    should include the BMS

    too.

    Technologic 5500 Control Variables

    1. Monitor zone differential pressure sensors,

    compare actual values to the required set points.

  • 8/10/2019 Large Chilled Water System

    165/314

    Pump speed is modulated to maintain set point. Pump staging will occur as required to meet set point.

    Control sequence is exactly as described earlier.

    Technologic 5500 Control Variables2. Determine if the minimum flow requirements are

    being met for all working chillers.

    Prevents freeze-up or chiller low-flow trips

    If chiller flow is too low, controller opens minimum flow

  • 8/10/2019 Large Chilled Water System

    166/314

    , p

    bypass valve in programmed increments. Size the valve

    for system p.

    Requests de-staging action from the chiller control

    system or BMS.

    Allows for operator intervention, decision making.

    Required by code in some areas.

    Ganged pumps allow operation of two chillers with one

    pump.

    Technologic 5500 Control Variables

    3. Monitors chiller flow rate to prevent operation

    above the maximum flow for the chillers and the

    pumps.

  • 8/10/2019 Large Chilled Water System

    167/314

    Excess chiller flow generates a request to stage on anadditional chiller. Minimum flow bypass valve is closed.

    Operator or BMS intervention required.

    Ganged pumps allow operation of one chiller, twopumps.

    Optional system flow meter provides end-of-curve

    protection for the pumps

    Alternative #2

    Bypass at End of System

  • 8/10/2019 Large Chilled Water System

    168/314

    Minimum chiller flow

    Minimum pump flow

    Ganged Pumps

    DPSENSOR

    FLOWMETER

    DPSENSOR

    DPSENSOR

    DPSENSOR

    DPSENSOR

    SIGNALTO TECH

    T

    FFF

    SUPPLY

    CHILLER CHILLERCHILLER

  • 8/10/2019 Large Chilled Water System

    169/314

    AFD AFD AFD

    SIGNALSTO TECH

    SIGNALTO TECH

    SIGNALTO TECH

    NOTE:ALL SENSORSIGNALS WIRED TOTECHNOLOGIC5500

    T

    SIGNALSTO TECH

    SIGNALSTO TECH

    F

    T

    FLOWMETER/TRANSMITTER

    TEMPERATURE SENSOR

    ISOLATION VALVE

    CHECK VALVE

    RETURN

    TDV TDV TDV

    Alternative #2

    Minimum flow bypass valve is controlledto protect both the pumps and the

    chillers.

  • 8/10/2019 Large Chilled Water System

    170/314

    Pump requires >25% BEP flow

    Minimum flow of largest chiller

    Size the bypass valve using the zonep.

    Best for systems with extended light

    loads or weekend shut-down.

    Alternative #3

    Primary pumps piped directly to chillers.

  • 8/10/2019 Large Chilled Water System

    171/314

    More common in retrofit systems.

    Easier for applying un-equally sizedchillers in parallel.

    DPSENSOR

    FLOWMETER

    DPSENSOR

    DPSENSOR

    DPSENSOR

    DPSENSOR

    SIGNAL

    TO TECH

    SIGNAL

    TO TECH

    SIGNAL

    TO TECH BYPASS:

    T

    FFF

    CHILLER CHILLER CHILLER

    SUPPLY

  • 8/10/2019 Large Chilled Water System

    172/314

    AFD AFD AFD

    SIGNALS

    TO TECH

    TO TECH TO TECH

    NOTE:

    ALL SENSOR

    SIGNALS WIRED TOTECHNOLOGIC5500

    BYPASS:FOR SYSTEMS WITHEXTENDED LIGHT

    LOADS/WEEKENDSHUTDOWNS. SETBALANCE VALVE

    FOR LOW FLOW TOREDUCE THERMAL

    STRATIFICATIONAND ALLOW QUICKSTART UP AFTER

    SHUT DOWN.

    T

    SIGNALS

    TO TECH

    SIGNALS

    TO TECH

    F

    T

    FLOWM ETER/TRANSMITTER

    TEMPERATURE SENSOR

    CHECK VALVE

    ISOLATION VALVE

    TDV TDV TDV

    RETURN

    Pump Selection Equal size pumps. Redundancy.

    P t

  • 8/10/2019 Large Chilled Water System

    173/314

    Parts. Maintenance.

    Unequal size pumps.

    Control issues.

    Flow issues.

    Premature failure, large pump at low flow.

    Chiller Selection Equal size chillers.

    R d d

  • 8/10/2019 Large Chilled Water System

    174/314

    Redundancy. Parts.

    Maintenance.

    Unequal size chillers.

    Control issues.

    Flow issues Additional equipment.

    Design Considerations

    Size bypass for minimum flow of largest chiller.

    Minimum building load?

    Size bypass modulating valve

  • 8/10/2019 Large Chilled Water System

    175/314

    for system p, if its installed near the chillers

    for zone p, if its out in the system.

    Program the controller with the chiller

    p setpoints for minimum and maximum chiller flow.

    Verify with chiller manufacturer.

    Design Considerations

    Sequence chillers based on p or temperature

    sensors.

    Use accurate calibrated flow meter or p sensors

  • 8/10/2019 Large Chilled Water System

    176/314

    Use accurate, calibrated flow meter or p sensorsat each evaporator

    Allow for operator training.

    Initial

    On-going

    Consider this design if:

    System flow can be reduced by 30%.

    System can tolerate modest changes in water

    temperature

  • 8/10/2019 Large Chilled Water System

    177/314

    temperature.

    Operators are well trained.

    Demonstrates a greater cost savings.

    High proportion of operating hours at:

    Part load.

    Full load with low entering condenser water.

    Turn-down Ratio

    Chiller manufacturers publish 3 - 11 fps

    evaporator velocity range (typically).

    You may have to increase your

  • 8/10/2019 Large Chilled Water System

    178/314

    You may have to increase your

    acceptable head loss targets, use more

    pump head. Nominal base of 7 fps desirable.

    Variation of 1 to 2 fps.

    Work with the manufacturer.

    Rate of Change*Maximum rate of flow change, % design flow per minute

    Source Vapor Compression Absorption

    #1 4-12 **

    #2 20 30 2 5

  • 8/10/2019 Large Chilled Water System

    179/314

    #2 20-30 2-5

    #3 ** 30

    #4 2 **

    #5 ** 1.67

    *Table 2-2

    ARTI-21CR/611-20070-01, 2004, Bahnfleth & Peyer

    ** Information not provided

    Do not use if:

    Supply temperature is critical.

    Three way valves are used throughout

  • 8/10/2019 Large Chilled Water System

    180/314

    Three-way valves are used throughout.

    Existing controls are old, inaccurate.

    Operators are unlikely to operate the

    system as designed.

    Supply Water Temperature

    Dependant on : System volume.

    Rate of flow change.

    A li ti ifi

  • 8/10/2019 Large Chilled Water System

    181/314

    Application specific.

    Consider thermal storage

    Operator Ability

    Within operators ability?.

    Commercial buildings may not have well

  • 8/10/2019 Large Chilled Water System

    182/314

    Commercial buildings may not have wellqualified operators.

    Training is mandatory.

    Initial

    Periodic, in view of operator turnover.

    Start-Up & Shut-down

    In systems that start-up and shut-down, it

    may be advisable to anticipate, and

    avoid rapid changes in flow as control

  • 8/10/2019 Large Chilled Water System

    183/314

    avoid, rapid changes in flow as controlvalves all tend to act together.

    Control system, BMS, manual

    procedures.

    Use slow opening/closing valves at the

    chiller, 60-90 seconds.(?)

    Controls Complexity

    Additional controls for the chillers

    Additional controls the pumps

  • 8/10/2019 Large Chilled Water System

    184/314

    Additional controls the pumps. Pumps operate on flow, temperature, and

    P.

    Chiller P.

    Sensor Calibration

    Multiple sensors control:

    Flow.

  • 8/10/2019 Large Chilled Water System

    185/314

    Flow. Temperature.

    Delta p

    Maintenance.

    Calibration.

    Summary

    Evaluate all the options.

    Read some articles:

  • 8/10/2019 Large Chilled Water System

    186/314

    Read some articles: Variable Primary Flow CHW: Potential Benefits and Application Issues

    by Bahnfleth and Peyer. Pennsylvania State University, ARTI-

    21CR/611-20070-01

    Chilled Water System for University Campus by Stephen W. Duda, PE,

    ASHRAE Journal May, 2006

    Another tool for the toolbox.

  • 8/10/2019 Large Chilled Water System

    187/314

    Large Chilled Water System Design Seminar

    Primary-Secondary-Tertiary Pumping Systems

  • 8/10/2019 Large Chilled Water System

    188/314

    Zone A

    Zone C

    Primary-Secondary-Tertiary

  • 8/10/2019 Large Chilled Water System

    189/314

    C

    H

    I

    L

    L

    E

    R

    C

    H

    I

    L

    L

    E

    R

    Zone B

    Variable Speed Pump

    Zone AZone B Zone C

    WRONG !

    Direct Pumped Zones

  • 8/10/2019 Large Chilled Water System

    190/314

    C

    H

    I

    L

    L

    E

    R

    C

    H

    I

    L

    L

    E

    R

    DP Controller

    WRONG !

    WRONG !

    Zone A Zone B Zone C

    T

    Constant Demand Zones

  • 8/10/2019 Large Chilled Water System

    191/314

    WRONG !

    Automatic

    Flow Control

    ValveHard set valve

    C

    H

    I

    L

    L

    E

    R

    C

    H

    I

    L

    L

    E

    R

    Zone A

    Zone C

    Primary-Secondary-Tertiary

    RIGHT !

  • 8/10/2019 Large Chilled Water System

    192/314

    C

    H

    I

    L

    L

    E

    R

    C

    H

    I

    L

    L

    E

    R

    Zone B

    Variable Speed Pump

    RIGHT !

    Three Different Buildings

    A has coils selected for 44F.

    B has coils selected for 45F.

    C has coils selected for 46F

  • 8/10/2019 Large Chilled Water System

    193/314

    C has coils selected for 46 F.

    Therefore, the supply water temperaturemust be at least 44F for A.

    But what about B and C?

    Zone A

    Zone B

    Zone C

    Primary-Secondary-Tertiary

    can be even more useful

  • 8/10/2019 Large Chilled Water System

    194/314

    C

    H

    I

    L

    L

    E

    R

    C

    H

    I

    L

    L

    E

    R

    Zone B

    Optional Variable

    Speed Pump

    ?

    LoadMV

    LoadMV

    LoadMV

    Temperature Sensor Locations

  • 8/10/2019 Large Chilled Water System

    195/314

    T3

    T1Load

    Common T2

    T4

    Chilled

    Water

    Return

    Pumped

    Chilled

    Water

    Supply

    Tertiary

    ZonePump

    T2 T3 T4T1

    Circuit Setter

    T1

    LoadMV

    LoadMV

    LoadMV

    T4

    Tertiary Bridge

  • 8/10/2019 Large Chilled Water System

    196/314

    T3

    T1

    Common

    T2

    T4

    Chilled

    Water

    Return

    Pumped

    Chilled

    Water

    Supply

    Tertiary

    Zone

    Pump

    Tertiary Bridge

    LoadMV

    LoadMV

    LoadMV

    Temperature Sensor Locations

  • 8/10/2019 Large Chilled Water System

    197/314

    T3

    T1

    Common T2

    T4

    Chilled

    Water

    Return

    Pumped

    Chilled

    Water

    Supply

    Tertiary

    ZonePump

    T2 T3 T4T1

  • 8/10/2019 Large Chilled Water System

    198/314

    1. Temperature of return water is unknown

    2. Temperature of return water to chiller may be too high

    3. Will not recognize increased supply water temperature

    DISADVANTAGES

  • 8/10/2019 Large Chilled Water System

    199/314

    T1

    Load

    MV

    LoadMV

    Load

    MV

    T4T1 T2 T3 T4

    T2 Operation

  • 8/10/2019 Large Chilled Water System

    200/314

    T3

    Common T2

    ChilledWaterReturn

    PumpedChilledWaterSupply

    TertiaryZonePump

    1. Maintains chilled water return temperature at setpoint

    2. Will not overload the chiller

    ADVANTAGES

  • 8/10/2019 Large Chilled Water System

    201/314

    1. No control of zone supply water temperature

    2. Could lose humidity control

    3. Will not recognize increased supply water temperature

    DISADVANTAGES

  • 8/10/2019 Large Chilled Water System

    202/314

    T1

    LoadMV

    LoadMV

    LoadMV

    T4T1 T2 T3 T4

    T3 Operation

  • 8/10/2019 Large Chilled Water System

    203/314

    T3

    T1

    Common T2

    T4

    Chilled

    Water

    Return

    Pumped

    Chilled

    Water

    Supply

    Tertiary

    Zone

    Pump

    T1 T2 T3 T4

  • 8/10/2019 Large Chilled Water System

    204/314

    1. Little, if any, valve modulation unless it is set to

    close on sensing supply temperature lower than

    permissible in the zone

    DISADVANTAGES

  • 8/10/2019 Large Chilled Water System

    205/314

    T1

    LoadMV

    LoadMV

    LoadMV

    T4T1 T2 T3 T4

    T4 Operation

  • 8/10/2019 Large Chilled Water System

    206/314

    T3

    Common T2

    Chilled

    Water

    Return

    Pumped

    Chilled

    Water

    Supply

    Tertiary

    Zone

    Pump

    T1 T2 T3 T4

    1. Maximizes coil flow rate

    2. Ensures good humidity control

    ADVANTAGES

  • 8/10/2019 Large Chilled Water System

    207/314

    1. Temperature of return water is unknown

    2. Temperature of return water to chiller may be too high3. Will not recognize increased supply water temperature

    DISADVANTAGES

  • 8/10/2019 Large Chilled Water System

    208/314

    No single sensor locationsatisfies all design criteria

    SO

  • 8/10/2019 Large Chilled Water System

    209/314

    SO........

    T1

    LoadMV

    LoadMV

    LoadMV T2 T3T1

    Applying Zone Valve Controller

  • 8/10/2019 Large Chilled Water System

    210/314

    T3Common T2

    Chilled

    Water

    Return

    Pumped

    Chilled

    Water

    Supply

    Tertiary

    Zone

    Pump

    1. Temperature control to the zone (T1 sensing).

    2. If T1 is satisfied, return water temperature to the chiller

    plant (T2 sensing).3. Monitor secondary chilled water supply temperature

    Control Algorithm

  • 8/10/2019 Large Chilled Water System

    211/314

    3. Monitor secondary chilled water supply temperature

    (T3 sensing) for temperature increase due to secondary

    return water recirculation or temperature decrease due tochiller leaving water temperature reset.

    4. Reference point for automatic reset andT (T2 - T3)

    control T3 sensin .

    So what?

    Satisfy zone cooling requirement at themaximum possible supply temperature

  • 8/10/2019 Large Chilled Water System

    212/314

    Minimize secondary flow rate

    Optimize return water temperature

    3-way Valve Application

  • 8/10/2019 Large Chilled Water System

    213/314

    ChillerPlant

    Secondary Pumps

    Tertiary

    Pump

    Tertiary

    PumpTertiary

    Pump

    Problems

    Bypass returns cold water to chillers,

    reduces system t.

    Linear valve characteristics can cause

    i d fl t t l d

  • 8/10/2019 Large Chilled Water System

    214/314

    increased flow at part load.

    Balancing required in bypass pipe andcoil-to-coil.

    High cost per ton at the chiller.

    T1

    MVLoad

    Load MV

    Load MV

    T2T1 T3

    3-way Valve System

  • 8/10/2019 Large Chilled Water System

    215/314

    Common

    T2

    T3

    Flow

    MeterSmall

    By-Pass

    Secondary Supply

    Secondary Return

    T3

    Common

    T3

    CommonCommonT3

    Zone SupplyTemperature

    Chiller Supply

    Temperature

    Terminal

    Unit Control

    Valve

    Terminal

    Unit Balance

    ValveZone

    (Tertiary)

    Pump

    Zone 3Zone 1 Zone 2 Zone 4

    T1T1 T1T1

    T3GPX

    Multi-zone Application

  • 8/10/2019 Large Chilled Water System

    216/314

    T2 T2T2 T2

    FlowMeter

    T3 T3 T3Temperature

    ]e

    Zone Bias

    Control Valve

    Rolairtrol

    Return

    Water

    Temperature

    C

    o

    m

    m

    o

    n

    3D Valves

    Distribution

    (Secondary)

    Pumps

    T3

    C

    h

    i

    l

    l

    e

    r

    C

    h

    i

    l

    l

    e

    r

    C

    h

    i

    l

    l

    e

    r

    Individual building temperature control

    Static pressure isolation Return water temperature control

    District Cooling Application

  • 8/10/2019 Large Chilled Water System

    217/314

    Btu/hr totalization

    Outdoor temperature reset

    Independent operation

    Independent pressure control

    District Cooling Application

    with GPX

  • 8/10/2019 Large Chilled Water System

    218/314

    HVAC fluid isolation

    T3

    Common

    T3

    CommonCommonT3

    Zone SupplyTemperature

    Chiller Supply

    Temperature

    Terminal

    Unit Control

    Valve

    Terminal

    Unit Balance

    ValveZone

    (Tertiary)

    Pump

    Return

    Zone 3Zone 1 Zone 2 Zone 4

    T1T1 T1T1

    T3GPX

    VPF Application

  • 8/10/2019 Large Chilled Water System

    219/314

    T2 T2T2 T2

    FlowMeter

    p

    Zone

    BalanceValve

    Zone BiasControl Valve

    Rolairtrol

    Return

    Water

    Temperature

    3D Valves

    C

    h

    i

    l

    l

    e

    r

    C

    h

    i

    l

    l

    e

    r

    C

    h

    i

    l

    l

    e

    r

    Comments?Questions?

  • 8/10/2019 Large Chilled Water System

    220/314

    Questions?

    Observations?

    Large Chilled Water System Design Seminar

    Primary-Secondary Zone Pumping Systems

  • 8/10/2019 Large Chilled Water System

    221/314

    Zone A Zone B Zone C

    Primary-Secondary Zone Pumping

  • 8/10/2019 Large Chilled Water System

    222/314

    CHILLER

    CHILLER

    Return

    Supply

  • 8/10/2019 Large Chilled Water System

    223/314

    Shared Piping

    Zone A Zone B Zone C

  • 8/10/2019 Large Chilled Water System

    224/314

    CHILLE

    R

    CHILLE

    RReturn

    Supply

    Shared Pipe

    Zone A Zone B Zone C

    Shared Piping

  • 8/10/2019 Large Chilled Water System

    225/314

    CHILLE

    R

    CHILLE

    RReturn

    Supply

    Shared Pipe

    Zone A Zone B Zone C

    1500 gpm 1500 gpm (1500 gpm)

    Current = 3000Future = 4500

    Flow :

    Present and Future Piping

  • 8/10/2019 Large Chilled Water System

    226/314

    CHILLER

    CHILLER

    Return

    Supply

    Current = 1500Future = 3000

    Current = 0Future = 1500 Future Zone C

    Zone A Zone B Zone C

    (1500 gpm) (1500 gpm)1500 gpm @ 80

    Zone A Requirements

  • 8/10/2019 Large Chilled Water System

    227/314

    Return

    SupplyA1 A2 A3

    B1 B2 B3

    Pressure drop:A to A1+B to B1

    Present = 20.8

    *Future = 45.2

    A

    B

    Zone A

    4500 gpm*

    4500 gpm*

    Table 9-1 Zone A calculations

    Zone A A to A1 + B to B1 Future Flow 4500 m Present Flow 3000 mPi e Size 14 14

    Pressure Dro - ft / 100 ft 2.26 1.04

    E uivalent Len th

    Zone A Calculations

  • 8/10/2019 Large Chilled Water System

    228/314

    su l & return 1000 ft x 2 = 2000 ft 1000 ft x 2 = 2000 ft

    Pressure dro 45.2 ft 20.8 ftZone ressure dro 80 ft 80 ft

    Total ressure dro 125.2 ft 100.8 ftPum Selection 1500 m 1510-6G 56.4 h = 75 h * 1510-6G 45.8 h = 60 h *

    Note: 15 h additional for future re uirements* Nominal horsepower motor for NOL pump

  • 8/10/2019 Large Chilled Water System

    229/314

    Zone A Zone B Zone C

    1500 gpm @ 80 (1500 gpm)1500 gpm @ 80

    Zone B Requirements

  • 8/10/2019 Large Chilled Water System

    230/314

    Return

    SupplyA1 A2 A3

    B1 B2 B3

    Pressure drop: Zone B

    AtoA1+ BtoB1 + A1toA2 + B1toB2

    Present =20.8 9.0*Future = 45.2 33.4

    A

    B

    4500 gpm* 3000 gpm*

    4500 gpm* 3000 gpm*

    Table 9-2 Zone B calculations

    Zone B A1to A2+B1 to B2 Future Flow 3000 m Present Flow 1500 m

    Pi e Size 12 12Pressure Dro - ft / 100 ft 1.67 0.45

    E uivalent Len th

    su l & return 1000 ft x 2 = 2000 ft 1000 ft x 2 = 2000 ft

    P d 33 4 ft 9 0 ft

    Zone B Calculations

  • 8/10/2019 Large Chilled Water System

    231/314

    Pressure dro 33.4 ft 9.0 ft

    Previous ressure dro 45.2 ft 20.8 ftZone ressure dro 80 ft 80 ft

    Total ressure dro 158.6 ft 109.8 ftPum Selection 1500 m 1510-6G 71.4 h = 100 h * 1510-6G 49.6 h = 60 h *

    Note: 40 additional h re uired for future re uirements

    *Nominal horsepower motor for NOL pump

    Zone A Zone B Zone C

    1500 gpm @ 80 1500 gpm @ 80 1500 gpm @ 80

    Zone C Requirements

  • 8/10/2019 Large Chilled Water System

    232/314

    Return

    SupplyA1 A2 A3

    B1 B2 B3

    Pressure drop: Zone C

    AtoA1+ BtoB1 + A1toA2 + B1toB2 + A2toA3+ B2toB3

    Present = 45.2 + 33.4 + 21.4

    Future = Present

    A

    B

    4500 gpm3000 gpm 1500 gpm

    4500 gpm 3000 gpm 1500 gpm

    Zone C (A2 to A3 + B2 to B3) Future Flow @ 1500 gpm Present Flow @ 0 gpm

    Pipe Size 10Pressure Drop - ft / 100 ft 1.07Equivalent Length(supply & return) 1000 ft x 2 = 2000 ftPressure drop 21.4 ftPrevious pressure drop 78.6 ft

    Zone C Calculations

  • 8/10/2019 Large Chilled Water System

    233/314

    p p(A to A2, B to B2)Zone pressure drop 80 ft

    Total pressure drop 180.0 ftPump Selection @ 1500 gpm 1510-6G @ 82.7 hp = 125 hp*; Note: 50 hp more

    than Zone A

    Zone Pumping Summary

    Present Requirement Future RequirementSummary Duty Pump Standby Pump Duty Pump Standby Pump

    Zone A 1 @ 75 hp 1 @ 75 hp 1 @ 75 hp 1 @ 75 hpZone B 1 @ 100 hp 1 @ 100 hp 1 @ 100 hp 1 @ 100 hp

    Zone C 1 @ 125 hp 1 @ 125 hp2 @ 175 hp 2 @ 175 hp 3 @ 300 hp 3 @ 300 hp

    Total 4 @ 350 hp 6 @ 600 hp* Nominal horsepower motor for NOL pump

  • 8/10/2019 Large Chilled Water System

    234/314

    0 0

    Zone

    Pump AZone

    Pump B ZonePump C

    Load

    FrictionLoss

    Pressure Diagram - Zone Pumped

    System

  • 8/10/2019 Large Chilled Water System

    235/314

    0

    Friction Loss

    Supply Header

    Friction Loss

    Return Header

    Supply

    C C C

    3000 GPM 1500 GPM

    1500 GPM 1500 GPM

    A

    A1 A2 A3

    (1500 GPM)

    Primary-Secondary Equivalent

  • 8/10/2019 Large Chilled Water System

    236/314

    Return

    PumpController

    AFDs

    Ch

    iller3

    Ch

    iller2

    Ch

    iller1

    3000 GPM1500 GPM

    A

    BB1 B2 B3

    Primary-Secondary pressure drop calculation:

    Pi e Se ment Pressure Dro

    Present, feet

    Pi e Se ment Pressure Dro

    Future, feet

    A to A1 + B to B1 20.8 A to A1 + B to B1 45.2

    A1 to A2 + B1 to B2 9 0 A1 to A2 + B1 to B2 33 4

    P-S Calculations

  • 8/10/2019 Large Chilled Water System

    237/314

    A1 to A2 + B1 to B2 9.0 A1 to A2 + B1 to B2 33.4

    A2 to A3 + B2 to B3 DNA A2 to A3 + B2 to B3 21.4Zone B 80.0 Zone C 80.0

    Total 109.8 Total 180

    Distribution pump selection:

    Present = 3000 gpm @ 109.8 feet, increase impeller to 13.5 for future head requirements:

    2 @ VSCS 8x10x17L @ 111.0 hp 125 NOL1 @ VSCS 8x10x17L @ 111.0 hp 125 NOL, standby

    Total 3 Pumps 375 NOL, Total

    Future = 4500 gpm @ 180 feet:

    P-S Calculations

  • 8/10/2019 Large Chilled Water System

    238/314

    Future = 4500 gpm @ 180 feet:

    3 @ VSCS 8x10x17L @ 114.4 hp 375 NOL1 @ VSCS 8x10x17L @ 114.4 hp 125 NOL

    Total 4 Pumps 500 NOL

    Comparison

    Zone Pumping

    Present

    350 hp

    Future

    600 hp

    P/S Pumping

    Present

    375 hp

    Future

    500 hp

  • 8/10/2019 Large Chilled Water System

    239/314

    Primary-Secondary Zone

    Pumping Cautions Excessive initial horsepower

    Initial equipment investment

  • 8/10/2019 Large Chilled Water System

    240/314

    Future considerations

    Reduced Horsepower

    Comments?Questions?

  • 8/10/2019 Large Chilled Water System

    241/314

    Observations?

    Large Chilled Water System Design Seminar

    Variable Speed Sensor Selection and Location

  • 8/10/2019 Large Chilled Water System

    242/314

    Supply

    Pump

    C t ll

    Differential

    Pressure

    SensorCh

    Ch

    Ch

    Direct Return Piped System

  • 8/10/2019 Large Chilled Water System

    243/314

    Return

    Controller

    AFDs

    iller3

    h

    iller2

    h

    iller1

    Supply

    Chi

    Ch

    Ch

    WRONG!Single

    Point

    Pressure

    Sensor

    Single Point Pressure Sensor

  • 8/10/2019 Large Chilled Water System

    244/314

    Return

    Pump

    ControllerAFDs

    iller3

    iller2

    iller1

    Head

    90

    80

    50

    40

    70

    60

    1750 RPM

    Constant Pressure

    Design PointShut-off head

    Control Curve Using Single Point

    Pressure Sensor

  • 8/10/2019 Large Chilled Water System

    245/314

    ,FT

    40

    30

    20

    10

    0200 400 600 800 1000 1200 1400 16000

    Flow, gpm

    (Maximum rpm)

    1480 RPM

    (Minimum rpm)

    Single Point Pressure Sensor

    in a CHW System A rise in the average water temperature

    results in a net expansion of the water. This net expansion volume flows into

    the compression tank, raising the

  • 8/10/2019 Large Chilled Water System

    246/314

    system pressure.

    The pump slows down.

    What if?

    CHI

    CHI

    CHI

    Supply

    P Sensor here

    Zone A Zone B Zone C

  • 8/10/2019 Large Chilled Water System

    247/314

    Return

    I

    LLER

    I

    LLER

    I

    LLER

    PumpControllerAFDs

    Sensor Across Mains At Pump

    Whats the set point?

    Its the greatest branch and distribution

    piping head loss calculated at design

    flow. In other wordsdesign head.

    What will the flow be in each zone?

  • 8/10/2019 Large Chilled Water System

    248/314

    Determined by the zone path CV

    Head

    90

    80

    50

    40

    70

    60

    Maximum rpm

    Design Point

    Differential Pressure Sensor

    at the Pump

  • 8/10/2019 Large Chilled Water System

    249/314

    ,FT

    30

    20

    10

    0200 400 600 800 1000 1200 1400 16000

    Flow, gpm

    Minimum rpm

    Variable Head Loss Ratio

    P

    ercentDesig

    90

    80

    70

    60

    50

    100 C/S, Constant Flow System Pump Head Matched toSystem at Design Flow

    C/S, Variable FlowV/S, 0% Variable Hd Loss, 100% Constant Hd

    V/S, 25% Variable Hd Loss, 75% Constant Hd

    V/S, 50% Variable Hd Loss, 50% Constant Hd

    Base

  • 8/10/2019 Large Chilled Water System

    250/314

    nBHP

    % Flow

    40

    30

    20

    10

    0 10 1009080706050403020

    V/S, 75% Variable Hd Loss, 25% Constant Hd

    V/S, 100% Variable Hd Loss, 0% Constant Hd

    Coil or Valve?

  • 8/10/2019 Large Chilled Water System

    251/314

    25 Head

    P

    Supply

    Variable Head Loss

    Constant Head Loss

    Pump

    Controller

    Differential

    Pressure

    SensorChi

    Ch

    Ch

    Maximizing Variable Head Loss

  • 8/10/2019 Large Chilled Water System

    252/314

    Return

    AFDs

    ller3

    iller2

    iller1

    CH

    I

    CH

    I

    CH

    I

    DP Sensor

    Zone 1

    20 ft

    Zone 2

    20 ft

    A B C D

    Control Area

  • 8/10/2019 Large Chilled Water System

    253/314

    LL

    E

    R

    LL

    E

    R

    LL

    E

    RPump

    ControllerAFDs

    EF

    P AB+EF

    20FT

    P Zone 1

    20FT

    P BC+DE

    20FT

    P Zone 2

    20FT

    Pressure Drops in Piping (Table 11-1)

  • 8/10/2019 Large Chilled Water System

    254/314

    TDH = P AB + EF + BC + DE + P ZONE 2 = 60 FT

    Control Area CalculationTable 11-2 Control Area Calculation

    Flow

    Zone 1

    Flow

    Zone 2

    Friction

    Loss

    AB+EF

    Friction

    Loss

    Zone 1

    P

    Zone 1

    Friction

    Loss

    BC+DE

    Friction

    Loss

    Zone 2

    P

    Zone 2

    TDH

    0 gpm 600 gpm 5 0 40 20 20 20 45300 gpm 300 gpm 5 5 25 5 20 20 30

    600 gpm 0 gpm 5 20 20 0 0 20 25

    0 gpm 0 gpm 0 0 20 0 0 20 20

    600 gpm 600 gpm 20 20 40 20 20 20 60

  • 8/10/2019 Large Chilled Water System

    255/314

    What pump head is required at:

    zero flow?

    full flow?

    less than full flow?

    20

    30

    40

    50

    60

    Head,FT

    Lower Limit

    U Li i

    Control Area

  • 8/10/2019 Large Chilled Water System

    256/314

    0

    10

    0 100 300 500 600 900 1100 1200

    Flow, gpm

    Upper Limit

    Single Point

    So What...?

    Staging pumps in a closed loop HVAC

    system by flow alone may not work

    because of different head requirementsfor a given flow.

    Wire to water pump efficiency

    l l ti t t l d d d h il

  • 8/10/2019 Large Chilled Water System

    257/314

    calculations at part load depend heavilyon the assumptions made about the

    nature and shape of the control curve.

    Single Sensor, IncludingBalance Valve Pressure Drop

    Zone 1

    25 ft

    Zone 2

    20 ft

    AB (50) C

  • 8/10/2019 Large Chilled Water System

    258/314

    E (10)F

    D

    What do you mean...?

    The head loss across the coil and the

    wide open valve in zone 1 is 25 feet at

    full flow.

    If thats true, then we need to add an

    t 15 f t f h d l i th b l

  • 8/10/2019 Large Chilled Water System

    259/314

    extra 15 feet of head loss in the balancevalve to insure adequate flow out to

    Zone 2 when the Zone 1 valve is wide

    open.

    Set Point, Zone 1, 40 ft

    Flow Zone 1 Flow Zone 2 Friction Loss

    AB+EF

    Friction Loss

    BC+DE

    Head Required

    Zone 2

    Setpoint -

    Friction Loss

    0 gpm 600 gpm 5 20 20 0

    300 gpm 300 gpm 5 5 5 30

    600 gpm 0 gpm 5 0 0 40

  • 8/10/2019 Large Chilled Water System

    260/314

    Excess head means wasted energy

    CH

    I

    LL

    CH

    I

    LL

    CH

    I

    LL

    DP Sensor

    Zone 1 Zone 2

    A B C D

    Sensor Location

  • 8/10/2019 Large Chilled Water System

    261/314

    LL

    E

    R

    LL

    E

    R

    LL

    E

    RPump

    ControllerAFDs

    EF

    Single Sensor in Zone 2

    Flow

    Zone 1

    Flow

    Zone 2

    Friction Loss

    AB+EF

    Friction Loss

    Zone 1

    Friction Loss

    BC+DEP Zone1,

    Available

    P Avail -

    Friction Loss

    Zone 1

    0 m 600 m 5 0 20 40 40

    300 m 300 m 5 6.25 5 25 13.75

    600 m 0 m 5 25 0 20 - 5

    Zone 1 requires 600 gpm at 25 ft

    Zone 2 requires 600 gpm at 20 ft

  • 8/10/2019 Large Chilled Water System

    262/314

    600 m 0 m 5 25 0 20 5

    Inadequate head for Zone 1

    Sensor in Zone 1

    Flow Zone 1 Flow Zone 2 Friction Loss

    AB+EF

    Friction Loss

    BC+DE

    Head Re uired

    Zone 2Setpoint -

    Friction Loss

    0 m 600 m 5 20 20 5

    300 gpm 300 gpm 5 5 5 20

    600 m 0 m 5 0 0 25

    Zone 1 requires 600 gpm at 25 ft

    Zone 2 requires 600 gpm at 20 ft

  • 8/10/2019 Large Chilled Water System

    263/314

    600 m 0 m 5 0 0 25

    Inadequate flow in Zone 2

    What can we do...?In this system:

    Single sensor in Zone 2 at 20 ft fails toprovide adequate flow only when

    load in Zone 2 < 50% and

    load in Zone 1 > 75%

    Is this a predictable, recurring situation?

    manual adjustment

  • 8/10/2019 Large Chilled Water System

    264/314

    manual adjustment programming

    Add a second sensor

    CHI

    LL

    CHI

    LL

    CHI

    LL

    Supply

    DP Sensors

    Zone A Zone B Zone C

    Applying Multiple Sensors

  • 8/10/2019 Large Chilled Water System

    265/314

    Return

    LER

    LER

    LER

    PumpControllerAFDs

    Use Multiple Sensors?

    Load Similarity

    Priority

    Diversity

    One building or several

    Redundancy

  • 8/10/2019 Large Chilled Water System

    266/314

    Redundancy First cost vs operating cost

    The Active Zone

    Zone set points do not have to be thesame.

    Technologic pump controller scans all

    zones often, comparing process

    variable to set point in each case.

    Pumps are controlled to satisfy the

  • 8/10/2019 Large Chilled Water System

    267/314

    Pumps are controlled to satisfy theworst case.

    What happens to the rest of the zones?

    Effect of Sensor Location

    Zone 1 Zone 2

    A

    BC

    OR

  • 8/10/2019 Large Chilled Water System

    268/314

    EF

    D

    Multiple sensors, set point across Zone 1, = 25 FT and setpoint across Zone 2 = 20 FT, (Table 11-6)

    Flow

    Zone

    1

    Flow

    Zone

    2

    Friction Loss

    AB+EF

    Minimum

    Reqd

    P Zone 1,

    P

    Zone1

    Available

    Friction Loss

    BC+DE

    Minimum

    Reqd

    P Zone2

    P

    Zone 2

    Available

    0 600 5 0 40 20 20 20

    300 300 5 6.25 25 5 5 20600 0 5 25 25 0 0 25

    Multiple Sensors & Setpoints

    Row 1. Sensor 2 is controlling, Zone 1 is over pumped.

    Row 3. Sensor 1 is controlling, Zone 2 is over pumped.T t l h d i d

  • 8/10/2019 Large Chilled Water System

    269/314

    g, p pTotal pump head required:

    row 1 45 ft

    row 2 30 ft

    row 3 30 ft

    C

    H

    I

    L

    Supply

    Reverse Return Piped System

  • 8/10/2019 Large Chilled Water System

    270/314

    L

    L

    E

    R

    Return

    Reverse Return Systems

    If all the circuits are the same length,will the pump still change speed?

    Suppose a coil with a high

    prequirement and another with a lower p

    requirement are served by the same

    reverse return piping system. OK?

  • 8/10/2019 Large Chilled Water System

    271/314

    reverse return piping system. OK? If the coils are serving different sides of

    the building, could we have a problem?

    C

    H

    I

    L

    L

    C

    H

    I

    L

    L

    Zone A Zone CZone B

    Tertiary Piped System

  • 8/10/2019 Large Chilled Water System

    272/314

    L

    E

    R

    L

    E

    R

    Return

    C

    HI

    C

    HI

    Supply

    Zone A Zone B Zone C

    Zone Piped System

  • 8/10/2019 Large Chilled Water System

    273/314

    L

    L

    E

    R

    L

    L

    E

    R

    Return

    Summary Give priority to the needs of the branch.

    The rule of sensor location is simple and easyto apply:

    If you have to use a single sensor, put it across

    the critical branch.

    Whats the critical branch?

    Its the same one that determined the pump head.A th l i i i t t

  • 8/10/2019 Large Chilled Water System

    274/314

    p p As weve seen, the analysis is more important

    than the rule.

    Comments?Questions?

    Observations?

  • 8/10/2019 Large Chilled Water System

    275/314

    Observations?

    Large Chilled Water System Design Seminar

    Achieving Hydronic System Balance

  • 8/10/2019 Large Chilled Water System

    276/314

    Systems Approach

    M

    Load

    Air ManagementDistribution

    Verification

    Control

  • 8/10/2019 Large Chilled Water System

    277/314

    Source

    Philosophy

    Systems Approach

    All components work together as team

    Components interact and work as well as we

    understand them

    A collection of mismatched components will

    not perform as expected

    Owner, engineer, architect, contractor, and

  • 8/10/2019 Large Chilled Water System

    278/314

    operators are part of the system too!

    Hydronic Balancing

    We worry about balance because:

    Load calculations are approximate

    Piping circuitry analysis is approximate

    Control valve selection is approximateApproximations will lead to underflow andoverflow situations

    Results of overflow or underflow Design Dt cannot be achieved

  • 8/10/2019 Large Chilled Water System

    279/314

    Design Dt cannot be achieved

    Supply temperature controller hunts (?)

    Sequence of operation can be upset.

    For example:

    Published by

    ASHRAE &

    Hydraulic

    Institute

    Darcy-

    Weisbach

    Equation.

  • 8/10/2019 Large Chilled Water System

    280/314

    Add 15%!

    Its test, adjust & balance

    Test: The system, now built, is verified in

    operation to perform to the expected level.

    What do we measure? temperature, flow, pressure drop, energy

    consumption.

    What do we test with? Can we test with what is installed?

    What Is Balancing?

  • 8/10/2019 Large Chilled Water System

    281/314

    Can we test with what is installed?

    Can we obtain accurate readings?

    What level of adjustment, and for what

    purpose?

    Create comfort conditions

    Minimize energy consumption Prevent equipment damage

    Adjust: tested in operation, the system isfound lacking and needs fine tuning.

    Adjust

  • 8/10/2019 Large Chilled Water System

    282/314

    q p g

    How do we adjust?

    Balance

    Balance is often interpreted to mean 10%

    of design flow.

    This generalization may or may not yieldsatisfactory heat transfer required for

    comfort conditions

  • 8/10/2019 Large Chilled Water System

    283/314

    Redefining Balance

    Evaluate System Operation

    If the goal is occupant comfort, then heat

    transfer becomes the key concern.

    We control heat transfer as a sensible

    temperature control process between controller,

    control valve and coil

    Analysis should account for interaction of all key

    components, and how they affect the rest of the

    t

  • 8/10/2019 Large Chilled Water System

    284/314

    system

    Balanced Hydronic Systems

    All terminals receive enough flow to produce

    satisfactory heat transfer (97.5% - 102.5%)

    At design conditions, all terminals receive

    satisfactory flow with the pump in a specifiedrange of operation

    Under temperature control modulation to

    match load, circuit flow does not exceeddesign flow accuracy

  • 8/10/2019 Large Chilled Water System

    285/314

    design flow accuracy

    Chilled Water Coil Flow vs. Heat Transfer

    %

    40%

    60%