Jeff Florin
Deputy Executive Director, Operations
Virginia Port Authority
Capital Outlay Program & Facilities
Maintenance Overview
Board of Commissioners
Session 348
November 27, 2012
2
Agenda
NIT Gate Improvements
NIT CBP Interchange
NIT Customer Service Area Improvements
NIT Shuttle Road Repair
Commonwealth Railway Road Crossing
Restoration
Craney Island Cross Dikes Stage 2A
Paradise Creek Mitigation
3
NIT Gate Improvements
Security, interchange, and transfer zone
automation, personnel shifted to remote facility
Automation, appointment system and remote
processing
Improves cargo velocity, safety & efficiency
Estimated combined project cost: $10 M
Includes $4.1 M software
4
NIT Gate Improvements
Project 1Interchange &
CBP Improvements
Project 2Chassis
Service/Customer Service Areas
Project 3OCR Portals
Project 3OCR Portals
Completed Transfer Zone
5
NIT CBP Interchange Improvements
Project clear of all utility conflicts;
continuing roadway north of the truck
canopy and starting RPM foundations
Estimated project cost : $2.2 M
Contractor: EV Williams
Project is currently 50% complete
Project completion by March 30, 2012
6
NIT CBP Interchange Improvements
7
NIT Customer Service Area Improvements
Area clearing in process to begin customer
service area renovations
Estimated project cost : $1.25 M
Contractor: Ridley Construction Group
Project is currently 75% complete
Project completion by February 9, 2013
8
NIT Customer Service Area Improvements
Customer Service canopy
9
NIT Shuttle Road Repairs
Pier 2 waterside rail crossingShuttle road progress
10
Commonwealth RailwayRoad Crossing Restoration
Former crossing at Peppercorn DriveRemoving road and rail at Taylor Rd crossing
11
Craney Island Cross Dikes Stage 2A
USACE will begin Stage 2A December 17th
Placing foundation lifts of sand
Land will be visible this time next year
Contractor: Manson Construction Company
Project cost: $26.8 M in federal appropriations
No new VPA money will be appropriated
Low bid came in at $21.5 M
Project completion by April 2013
12
Craney Island Cross Dikes Stage 2A
Division Cross Dike +10 ft
South Cross Dike+10 ft
CIDMMA
13
Paradise Creek Mitigation
Earthwork with beneficial reuse of excavated
materials; planted 11 acres of tidal wetlands
Minor reseeding anticipated next year along
with ongoing phragmites control
Contractor: C.T. Purcell, Inc.
Estimated project cost: $4.6 M
Project is complete
14
Paradise Creek Mitigation
Paradise Creek
Wetlands channel
Approximate limits of excavation and wetlands creation
Wetlands
15
Paradise Creek Mitigation
Wetlands planting