description

Automated 402-2 OUTLAY REPORT. The 402-2 is an Excel spreadsheet which is used to track all funds related to the project, from beginning to end. - PowerPoint PPT Presentation

Transcript of Automated 402-2 OUTLAY REPORT

Page 1: Automated 402-2 OUTLAY REPORT

Automated 402-2OUTLAY REPORT

Page 2: Automated 402-2 OUTLAY REPORT

The 402-2 is an Excel spreadsheet which is used to track all funds related to the

project, from beginning to end.

Page 3: Automated 402-2 OUTLAY REPORT

The upper section of the 402-2 is used to change contract amounts (Change Orders),

engineering amounts (Eng. Amendments), to track interest earnings (and final balancing).

Interest

Change Orders

Engineering Amendments

Page 4: Automated 402-2 OUTLAY REPORT

The lower section of the 402-2 is used like a checkbook. You insert dates, payees names and purpose, and amounts. The totals are

calculated automatically.

Dates

Payees Amounts

Page 5: Automated 402-2 OUTLAY REPORT

The lower left section of the 402-2 is divided into columns formulated to keep running

totals of dollar amounts for line items.

“Project Control” is a protected column which keeps a running total of individual entries, and the balances for the overall budget

The protected, shaded areas of the columns directly to the right of Column C contain formulas which keep a running total of line item costs

Page 6: Automated 402-2 OUTLAY REPORT

The lower right section of the 402-2 is divided into columns formulated to keep running

totals of dollar amounts for funding sources.

“Funds Control” is a protected column which keeps a running total of individual draws and the balances for the overall funding

The protected, shaded areas of the columns directly to the right of Column P contain formulas which keep a running total of funding dollars

Page 7: Automated 402-2 OUTLAY REPORT

The 402-2 will be set up with basic information (names, beginning balances of funds and line

items, etc.)

The project, owner’s name, address and bank account information are included in this area

The beginning balances are shown on the yellow shaded row

The contractors are listed

Page 8: Automated 402-2 OUTLAY REPORT

During the Construction period you will be responsible for entering interest earnings,

change orders and engineering amendments……….

Interest

Change Orders

Engineering Amendments

Page 9: Automated 402-2 OUTLAY REPORT

You will also enter the dates of payments, the payees and the purpose, the amounts of

the invoices and pay estimates, and the source of funding

Dates

Payee & purpose Amount

Amounts from each funding source

Page 10: Automated 402-2 OUTLAY REPORT

Lines 61-64 contain formulas which will display information resulting from entries in the “white” cells of the spreadsheet…

Line 61 - Includes change orders, engineering amendments, transfer of amounts among line items (final balancing) and changes to contingency via additional funding.

Line 62 - Adjusts balance of contracts, agreements, or line items

Line 63 - Totals the amounts spent on invoices, pay estimates, etc.

Line 64 - Shows the balance of funds available for that particular category.

Page 11: Automated 402-2 OUTLAY REPORT

Items entered at the top of the spreadsheet (change orders, interest earnings, etc.) are

automatically reflected on line 61 of the “Contingency” column

The entries for change orders, engineering amendments and interest…

resulting in an adjusted contingency balance.

are totaled together and added to the beginning balance…

Page 12: Automated 402-2 OUTLAY REPORT

Cell B-58 shows funds on hand in the bank after deposits (including earned interest),

and withdrawals.

2 - The corresponding funding source is credited

1 - the entries for individual payments are entered under the appropriate line item

3 - Cell B-58 reflects the amount of funds on hand in the bank

Page 13: Automated 402-2 OUTLAY REPORT

You can modify the spreadsheet to meet your specific need (delete some of the columns, rename

the headings, etc.)

Page 14: Automated 402-2 OUTLAY REPORT

To rename headings, delete columns, etc. you must “Un-Protect” the spreadsheet.

•Click – Tools

•Click – Protection

•Click – Unprotect Sheet

After making needed changes please “Re-Protect” the spreadsheet.

•Click – Tools

•Click – Protection

•Click – Protect Sheet

(the password has been left blank)

Page 15: Automated 402-2 OUTLAY REPORT

However, there are some columns you cannot delete…..

The Funds Control Column

Columns A - CInterest Earnings Column

The Contingency Column

Page 16: Automated 402-2 OUTLAY REPORT

Once you have completed your entries for the month, you should print out a new

Outlay Report for your records.

Page 17: Automated 402-2 OUTLAY REPORT

PRINTING……

Page 18: Automated 402-2 OUTLAY REPORT

NOTE

• You must designate a print area. If you do not, Excel will assume that you want to print the previously selected data, or if no data has been selected, the entire spreadsheet. (The entire spreadsheet is over 500 printed pages, so do not send a print command for the full spreadsheet!)

Page 19: Automated 402-2 OUTLAY REPORT

PRINTING……To print the areas you want shown on your current month’s

outlay report, you should:

• Highlight the area of cells that contain the current month’s entries.

• Click on “file”, then “print.”• Click beside the area titled “selection.”

This will print a report showing the current month’s outlay, complete with revised numbers. The “file, page setup, sheet” menu has been modified to cause rows 50 - 66 to print at the top of each report, so you only need to highlight the current information to make each month’s printout complete.

Page 20: Automated 402-2 OUTLAY REPORT

PRINTING……

You can also customize the print job:

• Click “file”. Then click “page set up” on the pull-down menu.• Once the page setup dialog box is opened, click on the file tab

marked “sheet”.• The print area has a place to type in the range you wish to print.

Page 21: Automated 402-2 OUTLAY REPORT

PRINTING……Example:• If you typed in A67:AJ68, the first two rows of the payment

area of the spreadsheet would be printed. In addition, “50:66” has been pre-filled in the area after “rows to repeat at top.” This tells the computer to print the information in these rows at the top of each sheet; therefore, you only need to insert the current rows you are working on for each report.

• If you wish to print the area at the top of the spreadsheet (change orders, etc.), simply put a comma after the range designated in the print area, and type in “A1:R49.” This will print the section as a separate page. Since the numbers you type in the change order area are reflected in the formulas on row 61, you may not wish to print this area every time you print a report.

• Click on “o.k.”• Click on the print icon on the toolbar.

Page 22: Automated 402-2 OUTLAY REPORT

Saving Your Work

You should save your work each time you make changes to the Outlay Report.

When you first open the spreadsheet, click on “file”, “save as” and give the file a new name. I typically use the date of my report as a part of the name to be able to more easily recognize the report. That way I always know I am working with the most recent report. It also allows me to go back and look at the financial status of a project at a given time.

Be sure to save our work when you close a spreadsheet.

Page 23: Automated 402-2 OUTLAY REPORT

Question and Answers…..