ISEN 315Spring 2011

Dr. Gary Gaukler

Page 2: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Inventory Control

• Deterministic inventory control• Stochastic inventory control• MRP / Lot sizing / JIT• Supply chain management

Page 3: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Reasons for Holding Inventories

Page 4: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Relevant Costs

• Holding Costs - Costs proportional to the quantity of inventory held.

Page 5: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Relevant Costs (continued)

• Ordering Cost (or Production Cost).

Can include both fixed and variable components.

slope = c

K

Page 6: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Relevant Costs (continued)

• Penalty or Shortage Costs. All costs that accrue when insufficient stock is available to meet demand.

Page 7: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Simple EOQ Model

• Assumptions:

1. Demand is fixed at l units per unit time.

2. Shortages are not allowed.

3. Orders are received instantaneously.

4. Order quantity is fixed at Q per cycle.

5. Cost structure:

a) Fixed and marginal order costs (K + cx)

b) Holding cost at h per unit held per unit time.

Page 8: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Inventory Levels for the EOQ Model

Page 9: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Cost Equation for the EOQ Model

Page 10: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

The Average Annual Cost Function G(Q)

Page 11: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

The Average Annual Cost Function G(Q)

Page 12: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Properties of the EOQ Solution

2KQ

h

Page 13: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Example

• Desk production rate = 200 per month• Each desk needs 40 screws• Screws cost $0.03• Fixed delivery charges are $100 per order• 25% interest rate for holding cost

• What is the optimal order size?

Page 14: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Example

Page 15: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

EOQ Cost Function

Page 16: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Quantity Discount Models

• All Units Discounts: the discount is applied to ALL of the units in the order.

• Incremental Discounts: the discount is applied only to the number of units above the breakpoint.

Page 17: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

All-Units Discount Order Cost Function

Page 18: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Incremental Discount Order Cost Function

Page 19: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

All-unit Discount

• Compute EOQs for all discounts• Find realizable EOQ values• Compare cost of realizable EOQ with cost

at breakpoints

Page 20: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

All-Units Discount Average Annual Cost

Page 21: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

All-unit Discount Optimality

Page 22: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Incremental Discount• Cost structure:

Page 23: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Incremental Discount

• Establish C(Q) curve• Determine “cost per unit” C(Q)/Q• Substitute C(Q)/Q into G(Q)• Compute G(Q) for each range• Pick feasible solution with lowest cost

Page 24: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Average Annual Cost Function for Incremental Discount Schedule

Page 25: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Incremental Discount Example

• Demand 600 bags / year• Setup cost for ordering: $8• Unit cost

– Up to 500: $0.30– Up to 1000: first 500 at $0.30, remaining at $0.29– Over 1000: first 500 at $0.30, next 500 at $0.29,

remaining at $0.28

• Holding cost: 20%

Page 26: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Incremental Discount Example

Page 27: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Incremental Discount Example

Page 28: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Incremental Discount Example

Page 29: ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.

Properties of the Optimal Solutions

• For all units discounts, the optimal will occur at the bottom of one of the cost curves or at a breakpoint. One compares the cost at the largest realizable EOQ and all of the breakpoints succeeding it.

• For incremental discounts, the optimal will always occur at a realizable EOQ value. Compare costs at all realizable EOQ’s.