Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to...
Transcript of Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to...
Introduction to the Last Planner® System
Lean Construction Institute 1
What is The Last Planner System?
Introduction to the Last Planner® System Rich Seiler 9-20-16
Introduction to the Last Planner® System
Lean Construction Institute
Today’s Objectives: 1. Examine why creating and maintaining reliable
workflow on projects is important
2. Observe how using the Last Planner® System will create and maintain reliable workflow
3. Practice and learn the techniques of the LPS
2
Introduction to the Last Planner® System
Lean Construction Institute 3
Principle Elements of Lean
Introduction to the Last Planner® System
Lean Construction Institute
A Lean Definition
A visual approach for creating quality, steady and level workflow within a
process (value stream)
4
Introduction to the Last Planner® System
Lean Construction Institute 5
Where most companies start . . . and stall
Toyota’s 4 P Model
Introduction to the Last Planner® System
Lean Construction Institute
Reliable, Level Workflow
Remove all non-value-added activities (waste) from our processes (value streams)
6
Introduction to the Last Planner® System
Lean Construction Institute
Steady, Level Flow?
7
Introduction to the Last Planner® System
Lean Construction Institute 8
Introduction to the Last Planner® System
Lean Construction Institute 9
Jack’s Hooch
Introduction to the Last Planner® System
Lean Construction Institute 10
Introduction to the Last Planner® System
Lean Construction Institute
Constraints = Variations
11
Introduction to the Last Planner® System
Lean Construction Institute
12
(WIP)
Introduction to the Last Planner® System
Lean Construction Institute
• Rework – Punchlist • Failed inspections • Requests for Information • Change orders • Submittals - Shop drawings • Inadequate Resources • Inefficient work flow • Work arounds • Multiple handling of material • Excess material • Waiting on supplies • Waiting on another trade • Safety losses • Improper sequencing of work
13
Introduction to the Last Planner® System
Lean Construction Institute
Value Stream
A sequence of interdependent actions that together create the path forward to satisfy the need of a customer
14
Introduction to the Last Planner® System
Lean Construction Institute
Value
15
Transforming pieces, parts and information in a manner in which the customer is willing to pay
Introduction to the Last Planner® System
Lean Construction Institute
How to Improve Flow
• Eliminate waste and add value • Eliminate, reduce and manage
variation in the value stream • See the big picture - lose sub-
optimization or “silo” thinking
16
Introduction to the Last Planner® System
Lean Construction Institute 17
Reliable Hand-Offs
Introduction to the Last Planner® System
Lean Construction Institute
Unify Stakeholders
18
Bridge Gaps Horizontally Across Internal and External Silo’s
Owners/User Designers Constructors Trades
Introduction to the Last Planner® System
Lean Construction Institute 19
Operating System
© Lean Construction Institute
THE THREE DOMAINS
Introduction to the Last Planner® System
Lean Construction Institute 20
Executives Senior Management
Middle Management
Front-Line Workers
Gaps
Introduction to the Last Planner® System
Lean Construction Institute 21
Add PM’s
Success Failure
Most Valuable Resource
Servant Leadership
Value Creators
Introduction to the Last Planner® System
Lean Construction Institute 22
Introduction to the Last Planner® System
Lean Construction Institute 23
How Productive Are We?
Introduction to the Last Planner® System
Lean Construction Institute 24
Introduction to the Last Planner® System
Lean Construction Institute
How Good is Our Planning?
25
Introduction to the Last Planner® System
Lean Construction Institute
Studies Show and Our Guts Know
26
Percent Plan Complete (PPC)
53%
Introduction to the Last Planner® System
Lean Construction Institute 27
46 Weeks: Average PPC is 85%
Introduction to the Last Planner® System
Lean Construction Institute 28
Introduction to the Last Planner® System
Lean Construction Institute
Three Theories: • Traditional planning doesn’t
produce predictable workflow
• Workflow reliability directly affects system speed and cost
• Plans are forecasts - all forecasts are unreliable
© 2009 Lean Construction Institute 29
Introduction to the Last Planner® System
Lean Construction Institute
“Plans are useless, Planning is everything” -Dwight Eisenhower
30
Introduction to the Last Planner® System
Lean Construction Institute
• Break
31
Introduction to the Last Planner® System
Lean Construction Institute
Let’s Examine LPS:
32
Introduction to the Last Planner® System
Lean Construction Institute
THE LAST PLANNER® SYSTEM OF PRODUCTION CONTROL
5 - CONNECTED CONVERSATIONS Set milestones & strategy Identify long lead items
Specify handoffs Identify operational constraints
Make work ready & launch re-planning when needed
Make reliable promises
Calculate & analyze PPS-act on reasons for non-completion
SHOULD
CAN
WILL
DID
Weekly Work Planning
Make Work Ready Planning
Learning
Master Scheduling Milestones
Phase “Pull” Planning
33
Introduction to the Last Planner® System
Lean Construction Institute 34
Phase Pull Plan
6 Week Look-ahead Weekly Work Plan
Set five RTU’s on lower level area A
Master
Percent Plan Complete (PPC)
Should Do
(Can Do)
(Will Do)
(Did Do)
Introduction to the Last Planner® System
Lean Construction Institute
Daily Huddle
35
Introduction to the Last Planner® System
Lean Construction Institute
• Front-Line manager • Accountable for
assigning and completing the work
• Empowered to make
commitments …or not
• Foreman and supt’d 36
WHO IS THE LAST PLANNER?
Introduction to the Last Planner® System
Lean Construction Institute
Quality Assignments
37
Introduction to the Last Planner® System
Lean Construction Institute
1) Definition: 2) Soundness: • Specific and
measurable • Work can be
coordinated
• They are workable
• They are clear and understandable
• You have what you
need from others
38
Introduction to the Last Planner® System
Lean Construction Institute
3) Sequence: 4) Size: • They are in the right
order • They will release other
work? • You have identified
workable backlog
• They are sized to the productive capability of each crew or vice versa
39
Introduction to the Last Planner® System
Lean Construction Institute
They Come in the Form of Sticky-Tags
40
Introduction to the Last Planner® System
Lean Construction Institute
Establishing Solid Target Conditions
41
• Important to internal and external clients
• Be sure they are clear
and specific • In-line with contract
Introduction to the Last Planner® System
Lean Construction Institute
Objectives of a Reliable Phase “Pull-Plan”
42
1. Understand the general scope of the planning horizon
2. Establish the sequence and flow of the work
3. Validate the durations in relationship to the master
4. Benchmark this to see how you are tracking as the job progresses
Introduction to the Last Planner® System
Lean Construction Institute
DOCUMENTATION OPTIONS:
MOVABLE HARD COPY PHOTO EXCEL LPS Softwares VISIO SURETRAK MICROSOFT PROJECT NETPOINT
Example courtesy of Pankow Builders 43
Good Practice: Electronic version should be accompanied by a record photograph of Pull Schedule on wall
Document your work
Introduction to the Last Planner® System
Lean Construction Institute
Delta’s: • Milestone is too long • Not all players present • Too long 4 hours +
• PP is disregarded
Pluses: • Starts team formation
• Constraints are identified
• CPM is validated…or not
• Strong planning start
• Continual tracking device
Plus and Delta’s of a Pull Planning Session
44
Introduction to the Last Planner® System
Lean Construction Institute
Objectives of Look- Ahead & Weekly Work Plan
45
• Identify & clear constraints
• Calculate PPC - Variance
• Populate out six weeks • Make work ready
• Analyze resources • Consider hand-offs
Introduction to the Last Planner® System
Lean Construction Institute 46
Introduction to the Last Planner® System
Lean Construction Institute
The Magic’s in the Talks Among the Trades
47
Introduction to the Last Planner® System
Lean Construction Institute 48
Introduction to the Last Planner® System
Lean Construction Institute 49
Introduction to the Last Planner® System
Lean Construction Institute 50
Introduction to the Last Planner® System
Lean Construction Institute 51
Introduction to the Last Planner® System
Lean Construction Institute
52
Session Roles & Responsibilities Project Leader
Project Manager Production
Manager Sup’td
Process Administrator
Project Engineer
Last Planner Foreman
Clear constraints
Lead the 6WLA
Manage the logs & room
Make commitments-assignments
Serve the value creators
Challenge the planning claims
Walk Gemba Identify constraints
Lead up and down the chain of command
Takes extreme ownership of project & team
Support sup’td
Share planning objectives with the field
Introduction to the Last Planner® System
Lean Construction Institute
Master Schedule Pull Planning Lookahead Plan &
Constraint Analysis
Percent Plan Complete Daily Huddles Weekly Work Planning
Introduction to the Last Planner® System
Lean Construction Institute
Benefits • Clears constraints on your work • Makes work ready for you • Gives you a voice at the table • Eliminates reworks & waiting • Improves accountability • Gets decisions from upstream • Eliminates stress • Make the money you expected
54
Introduction to the Last Planner® System
Lean Construction Institute 55
Introduction to the Last Planner® System
Lean Construction Institute
• Conduct a mock LPS exercise - on a small ground up project • Phase Pull Plan • 6WLA – “around the horn” screening
• Quality assignments • Workable backlog
• WWP • Constraints, PPC, Variance, (Explanation and Analysis) • Parking Lot
• Opportunities and Threats to implementing
56
Introduction to the Last Planner® System
Lean Construction Institute 57
Questions?
Introduction to the Last Planner® System
Lean Construction Institute 58
Plus/Delta