Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to...

58
Introduction to the Last Planner® System Lean Construction Institute 1 What is The Last Planner System? Introduction to the Last Planner® System Rich Seiler 9-20-16

Transcript of Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to...

Page 1: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 1

What is The Last Planner System?

Introduction to the Last Planner® System Rich Seiler 9-20-16

Page 2: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Today’s Objectives: 1. Examine why creating and maintaining reliable

workflow on projects is important

2. Observe how using the Last Planner® System will create and maintain reliable workflow

3. Practice and learn the techniques of the LPS

2

Page 3: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 3

Principle Elements of Lean

Page 4: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

A Lean Definition

A visual approach for creating quality, steady and level workflow within a

process (value stream)

4

Page 5: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 5

Where most companies start . . . and stall

Toyota’s 4 P Model

Page 6: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Reliable, Level Workflow

Remove all non-value-added activities (waste) from our processes (value streams)

6

Page 7: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Steady, Level Flow?

7

Page 8: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 8

Page 9: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 9

Jack’s Hooch

Page 10: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 10

Page 11: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Constraints = Variations

11

Page 12: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

12

(WIP)

Page 13: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

• Rework – Punchlist • Failed inspections • Requests for Information • Change orders • Submittals - Shop drawings • Inadequate Resources • Inefficient work flow • Work arounds • Multiple handling of material • Excess material • Waiting on supplies • Waiting on another trade • Safety losses • Improper sequencing of work

13

Page 14: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Value Stream

A sequence of interdependent actions that together create the path forward to satisfy the need of a customer

14

Page 15: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Value

15

Transforming pieces, parts and information in a manner in which the customer is willing to pay

Page 16: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

How to Improve Flow

• Eliminate waste and add value • Eliminate, reduce and manage

variation in the value stream • See the big picture - lose sub-

optimization or “silo” thinking

16

Page 17: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 17

Reliable Hand-Offs

Page 18: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Unify Stakeholders

18

Bridge Gaps Horizontally Across Internal and External Silo’s

Owners/User Designers Constructors Trades

Page 19: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 19

Operating System

© Lean Construction Institute

THE THREE DOMAINS

Page 20: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 20

Executives Senior Management

Middle Management

Front-Line Workers

Gaps

Page 21: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 21

Add PM’s

Success Failure

Most Valuable Resource

Servant Leadership

Value Creators

Page 22: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 22

Page 23: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 23

How Productive Are We?

Page 24: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 24

Page 25: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

How Good is Our Planning?

25

Page 26: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Studies Show and Our Guts Know

26

Percent Plan Complete (PPC)

53%

Page 27: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 27

46 Weeks: Average PPC is 85%

Page 28: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 28

Page 29: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Three Theories: • Traditional planning doesn’t

produce predictable workflow

• Workflow reliability directly affects system speed and cost

• Plans are forecasts - all forecasts are unreliable

© 2009 Lean Construction Institute 29

Page 30: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

“Plans are useless, Planning is everything” -Dwight Eisenhower

30

Page 31: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

• Break

31

Page 32: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Let’s Examine LPS:

32

Page 33: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

THE LAST PLANNER® SYSTEM OF PRODUCTION CONTROL

5 - CONNECTED CONVERSATIONS Set milestones & strategy Identify long lead items

Specify handoffs Identify operational constraints

Make work ready & launch re-planning when needed

Make reliable promises

Calculate & analyze PPS-act on reasons for non-completion

SHOULD

CAN

WILL

DID

Weekly Work Planning

Make Work Ready Planning

Learning

Master Scheduling Milestones

Phase “Pull” Planning

33

Page 34: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 34

Phase Pull Plan

6 Week Look-ahead Weekly Work Plan

Set five RTU’s on lower level area A

Master

Percent Plan Complete (PPC)

Should Do

(Can Do)

(Will Do)

(Did Do)

Page 35: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Daily Huddle

35

Page 36: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

• Front-Line manager • Accountable for

assigning and completing the work

• Empowered to make

commitments …or not

• Foreman and supt’d 36

WHO IS THE LAST PLANNER?

Page 37: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Quality Assignments

37

Page 38: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

1) Definition: 2) Soundness: • Specific and

measurable • Work can be

coordinated

• They are workable

• They are clear and understandable

• You have what you

need from others

38

Page 39: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

3) Sequence: 4) Size: • They are in the right

order • They will release other

work? • You have identified

workable backlog

• They are sized to the productive capability of each crew or vice versa

39

Page 40: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

They Come in the Form of Sticky-Tags

40

Page 41: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Establishing Solid Target Conditions

41

• Important to internal and external clients

• Be sure they are clear

and specific • In-line with contract

Page 42: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Objectives of a Reliable Phase “Pull-Plan”

42

1. Understand the general scope of the planning horizon

2. Establish the sequence and flow of the work

3. Validate the durations in relationship to the master

4. Benchmark this to see how you are tracking as the job progresses

Page 43: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

DOCUMENTATION OPTIONS:

MOVABLE HARD COPY PHOTO EXCEL LPS Softwares VISIO SURETRAK MICROSOFT PROJECT NETPOINT

Example courtesy of Pankow Builders 43

Good Practice: Electronic version should be accompanied by a record photograph of Pull Schedule on wall

Document your work

Page 44: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Delta’s: • Milestone is too long • Not all players present • Too long 4 hours +

• PP is disregarded

Pluses: • Starts team formation

• Constraints are identified

• CPM is validated…or not

• Strong planning start

• Continual tracking device

Plus and Delta’s of a Pull Planning Session

44

Page 45: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Objectives of Look- Ahead & Weekly Work Plan

45

• Identify & clear constraints

• Calculate PPC - Variance

• Populate out six weeks • Make work ready

• Analyze resources • Consider hand-offs

Page 46: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 46

Page 47: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

The Magic’s in the Talks Among the Trades

47

Page 48: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 48

Page 49: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 49

Page 50: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 50

Page 51: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 51

Page 52: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

52

Session Roles & Responsibilities Project Leader

Project Manager Production

Manager Sup’td

Process Administrator

Project Engineer

Last Planner Foreman

Clear constraints

Lead the 6WLA

Manage the logs & room

Make commitments-assignments

Serve the value creators

Challenge the planning claims

Walk Gemba Identify constraints

Lead up and down the chain of command

Takes extreme ownership of project & team

Support sup’td

Share planning objectives with the field

Page 53: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Master Schedule Pull Planning Lookahead Plan &

Constraint Analysis

Percent Plan Complete Daily Huddles Weekly Work Planning

Page 54: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

Benefits • Clears constraints on your work • Makes work ready for you • Gives you a voice at the table • Eliminates reworks & waiting • Improves accountability • Gets decisions from upstream • Eliminates stress • Make the money you expected

54

Page 55: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 55

Page 56: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute

• Conduct a mock LPS exercise - on a small ground up project • Phase Pull Plan • 6WLA – “around the horn” screening

• Quality assignments • Workable backlog

• WWP • Constraints, PPC, Variance, (Explanation and Analysis) • Parking Lot

• Opportunities and Threats to implementing

56

Page 57: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 57

Questions?

Page 58: Introduction to the Last Planner® · PDF fileQuality Assignments . 37 . Introduction to the Last Planner® System . Lean Construction Institute . 1) ... • Constraints, PPC, Variance,

Introduction to the Last Planner® System

Lean Construction Institute 58

Plus/Delta