Huyton Lane - King...
Transcript of Huyton Lane - King...
Project name: Huyton Lane
Name of client organisation: Knowsley MBC
Name: Danny Elder
Address: DRN, Yorkon Building, Archway Road,Huyton, L36 9FB
Scheme start and duration: August 2009 – October 2009 – 10 weeks (completed 2 weeks early)
Value: £570,000
Case study
Huyton Lane
Brief description:
The scheme consisted of the construction of a new
highway drain, the reconstruction of the footway, the
resurfacing of the carriageway, and the construction of
18 manholes to allow easier maintenance to the newly
installed highway drain.
The new highway drain included 600m of concrete pipe
work with various diameters ranging from 600mm in
diameter to 225mm in diameter. A total of 44 gullies were
installed and connected to the new highway drain to
reduce surface water on the carriageway.
Along with the drainage works, footway reconstruction
works were completed which involved renewing 1300m
of kerbs and over 2500 sq m of footway reconstruction.
A new ducting system was also installed throughout the
length of the scheme for future traffic signal upgrade and
to link the town centre to the M57 junction 5 at Prescot.
Approximately 20 metres of guardrail was also replaced.
As part of our current Annual Service Contract with
Knowsley Council an area of 9000 sq m of carriageway was
planed out and resurfaced. This consisted of planing from a
depth of 110mm to 50mm and replacing it with HDM binder
course 60mm thick and asphalt concrete surface course
50mm thick with 14/20mm pre-coated chippings.
Due to the location of the scheme and the constraints of
the site it was deemed that a full road closure would be
necessary. The scheme was to commence in the month of
August and a 12 week construction period was allowed by
Knowsley council.
It was vital that the scheme was managed properly as
and kept to a tight programme as Huyton Lane was an
extremely busy route vital for commuters and shoppers
requiring access to Huyton Village. The scheme had
to be completed by the middle of November in a small
timescale in proportion to the amount of work that had
to be undertaken so as not to interrupt the town centre
Christmas shoppers.
Various work teams from our labour force including our
specialist drainage and resurfacing teams who were
employed during various stages of the works and site specific
hazards included in the health and safety file included a 42
inch cast iron Victorian water main that was in close proximity
to certain areas of the scheme that had to be excavated out.
If this water main burst, it would have caused a major flood
that had the potential to have caused millions of pounds of
damage and disruption for the businesses in Huyton Village.
The scheme was completed within the allocated proposed
deadline and to the Client’s budget.
Achievements against targets:
The works were completed within budget and completed
two weeks earlier than the anticipated start date.
T 0151 548 5260 · E [email protected] · W www.kingconstruction.co.uk