Hurricane Preparation and Response › sma_hurricane_prep › docs › ... · 2018-06-08 ·...
Transcript of Hurricane Preparation and Response › sma_hurricane_prep › docs › ... · 2018-06-08 ·...
Hurricane Preparation and ResponseJohnson Space Center – 2018
Linda Spuler
JSC Emergency Manager
2
Harvey Impacts to JSC
Risk Mitigation Strategies
Hurricane Response Overview
Harvey Response
Personal Preparedness
AGENDA
3
• Hurricane Harvey impacted the Johnson Space Center main campus, Ellington Field, and Sonny Carter Training Facility for 5 days (August 25th-29th, 2017)
• 50mph winds • 43 inches of rain caused flooding and widespread infrastructure damage
• Average annual rainfall in Houston is ~50 inches, average monthly total is ~ 4 inches• During Harvey we experienced rain at the rate of 4 inches per hour
IMPACT SUMMARY
• Major to moderate impacts to Sonny Carter Training Facility (SCTF), Ellington Field (EFD), the 200 area, the 300 area, B30, B32, and 13 other buildings on JSC’s main campus. Building 265 will be demolished due to severe water damage
• Many other buildings and equipment impacted to a lesser degree
OVERVIEW OF HARVEY IMPACTS
Recorded Rainfall at B30
5
DAMAGE MAP OVERVIEWJSC Main, SCTF, and EFD
Extensive Major Moderate Minor
Work Orders #
SCTF 91300 Area** 53
32 50200 Area** 45
E276 39350 Area 32
30 318 31
45 23400 Area 22
EFD Other 2120 19
265* 195 19
E135 187 184 16
21 1610 1544 1549 14
2 1410 13
325 1314 1217 12
37* 12Gilruth 10
JSC Other 100
Total 793
JSC Main
SCTF
EFD
6
HURRICANE PREPARATIONS
Preventative measures to protect critical flight hardware, equipment, and facilities
7
SONNY CARTER TRAINING FACILITYAerial View
NBL
LMF
SDIL
Retention pond overflowed and
flooded all sections of SCTF
Guard Shack was under 6’ of water
Roof leaks
8
SONNY CARTER TRAINING FACILITYNeutral Buoyancy Lab, Logistics and Mockup Facility,
and Software Development and Integration Lab
• Houses key JSC Program facilities
• Entire facility flooded
• Extensive roof leaks causing elevator damage, mold growth, lighting damage, furniture & equipment damage
• Replace roof & guard shack
9
BUILDING 30Mission Control Center
• Significant roof leaks causing water damage to floors, ceilings, and mold growth
• Needs roof replacement
10
BUILDING 32Aerial View
B32 Roof
11
• No significant impacts to James Webb Space Telescope testing
• Significant roof leaks causing water damage to floors, ceilings, and mold growth
• Water on electrical equipment
BUILDING 32Vacuum Chamber A, JWST Testing, & Labs
12
ELLINGTON FIELDAircraft Operations, Hangers, and Offices
• Significant water and mold
• Roof leaks and damage to ceilings, walls, and floors/equipment
• Water in elevator
13
• Roof leaks causing water damage to tile, mold, and equipment
BUILDING 8Photographic Technology Laboratory
14
GUARD SHACKSJSC Main, SCTF, and EFD
• Significant flooding, water damage, mold damage, and roof leaks
15
Environmental Overview:• Clean-up• Mold/Asbestos Mitigation• Mold/Asbestos Remediation• Asbestos Abatement
Major Impacted Buildings: 200 Area, 4, SCTF, EFD, and 30
Containment & Cleanup
Abatement/Remediation
On-Going Remediation
ENVIRONMENTAL
16
RISK MITIGATION / HARDENING
Raised tunnel air intake
Flood gates outside B30
Flood doors on tunnel exhaust vents
Sealed doors in facilities throughout Center to protect mechanical rooms
All new facilities are rated to withstand 130mph winds
Past flood mitigation & hardening projects successfully prevented additional damage during Hurricane Harvey
17
COD Preparedness Levels
Level 5 – AWARENESS (Jun-1 through Nov 30)
Level 4 – CONCERN (impact to JSC in ~72 hrs)
Level 3 – PREPARATION (impact in ~48 hrs)
Level 2 – CLOSURE (impact to JSC in ~36 hrs)
Level 1 – RIDEOUT
Assessment
Recovery
PLANNED HURRICANE REPONSE
18
PREPAREDNESS CONSIDERATIONS
Concern to Prep….Weekend?
Holidays? Flex Days?
What are schools doing?
Storm speed, size, and track?
Prep to ClosureEmployees in mandatory
evacuation zones
Different personal needs, timeframes
Riding it Out• Systematic plant shut down (~ 6 hours)
• Hard shut down (minimum 3 day recovery)
• 2 hour emergency shut down of MCC
• Ride-out
• Depends on strength of storm
• 5 man security team
• 50 man recovery squad
• Merrill Center (Katy) contingency plan
• Away team to North Austin
Recovery• Safety
• Status of Community services & infrastructure
• STAY AWAY UNTIL RECALLED
19
National Incident Management System Scalable
Common response protocol
Standardized communication
Incident Command System (ICS)Specialized team mobilizes for emergency and recovery
Does not follow organizational lines
Incident Commander (IC) changes with event phase
Incident Action Plan (IAP)Blueprint of response
NIMS/INCIDENT COMMAND
20
jscsos.com Information geared to all employees in plain English
Can use @JSCSOS twitter to broadcast messages
Open/Closed Status of Center is posted
(some employees may still report to work when “JSC is Closed”)
EPR distribution listUsed to disseminate emergency information to orgs
Used to inform orgs of Center Ops timeline and level changes
Weather information for orgs to use to trigger their own plans
ENSEmergency notifications sent to all employees
Accountability check in survey sent to Civil Service only
COMMUNICATION
21
jscsos.com
22
SAMPLE OF EMAIL TO EPR
******************************************NOT A REAL MESSAGE – FOR EXAMPLE ONLY******************************************
Please forward to the appropriate people in your organization:
JSC Center Operations has declared Hurricane preparation Level 3 (Advanced Center Preparation) in anticipation of Hurricane Pretense
The current forecast and projected path show JSC at risk from Hurricane Pretense. Expected impact to JSC is in approximately 48
hours.
Hurricane Pretense is currently a Category 1 Hurricane with winds clocked at around 85 mph. Storm surge may reach 4-6 feet.
Level 3 preparations require all loose articles to be tied down or moved inside.
If your organization needs assistance with this task call the Work Control Center at x32038.
(Please utilize your own resources to move articles, and only rely on Work Control if you cannot move something safely.)
Employees should cover computers in plastic, move items off the floor and raise the blinds in their office.
Refer to the FMOD SOP for Hurricane Preparation for a full listing of Level 3 tasks.
If you have any questions regarding the SOP or related tasks, you can call the Communication Unit leader Ken Chevalier at x33177.
Configure all equipment and systems to minimize adverse effects from a loss of power, as cooling and power may intentionally or
inadvertently be shut down.
Remember storms are volatile and conditions may change rapidly. JSC management will continue to monitor the storm and send status
updates as necessary.
Weather forecasts and the latest advisory information are contained in a separate email you should receive from the Spaceflight
Meteorology Group via the JENS (from [email protected]) and posted on jscsos.com.
****************************************** NOT A REAL MESSAGE – FOR EXAMPLE ONLY ******************************************
To: JSC-DL-JSC-EPRFrom: Linda M. Spuler
23
SAMPLE OF EMAIL TO EPR
24
Telecom Schedule
1:00am National Hurricane Center interim advisory (new graph)4:00am NHC Advisory (new graph and discussion)7:00am NHC interim advisory (new graph)
8:00am Incident Management Team telecon (JA, IA, SMG, FOD)
Develop Incident Action Plan (IAP) for the day
10:00am NHC Advisory and Senior Staff telecon (publish IAP)
10:30am JLT telecon
1:00pm National Hurricane Center interim advisory (new graph)
3:30pm Incident Management Team telecon (JA, IA, SMG, FOD)
4:00pm NHC Advisory and Senior Staff telecon
4:30pm JLT telecon
7:00pm NHC interim advisory (new graph)
9:30pm Incident Management Team telecon (JA, IA, SMG, FOD)
10:00pm NHC Advisory and Senior Staff telecon
10:30pm JLT telecon
25
HARVEY TIMELINE
Expected Impacts
from Harvey “10-
15 inches of rain may fall Friday through
Monday”
Impact to JSC
“expected to be
mainly rain”
Flash Flood Warning for
JSC
5” so far, 15” more possible
Situation Worsens at JSC…Closed
to Non Essential
Personnel
22” so far, 2-4 more possible
JSC Today Special: 31.66
inches of rain, 3-5
more today; 5-7
more tomorrow
All JSC sites remain
closed –Damage
Assessment Team
reports
42.6 inches at JSC so
far
FMs Report Announcing Center will re-open on
9/5
JSCRe-Opens
Recovery continues
Fri 8/25 Sat 8/26 Sun 8/27 Mon 8/28 Tue 8/29 TOTAL
JSC B30 1.80 7.24 20.72 10.22 3.01 42.99
Ellington
Field1.61 10.96 13.10 9.46 4.10 39.23
University
Green PWS1.90 8.88 18.29 11.06 3.55 43.68
Nassau Bay
FD PWS1.61 6.53 18.17 10.17 3.64 40.12
27
ENS was not used as advertised
ENS Survey was not used for contractors
OPEN/CLOSE Notifications were not sent to employees
Hurricane Plan triggers were not met in this scenario
Preparation Levels were not declared
Away team did not deploy
Full Rideout Team was not in play
Mission Control remained at JSC
Need for redundancy and training exposed
Tropical Storm impacts are harder to predict
Flex Friday plays into decision making and communication
HARVEY RESPONSE
28
NASA PERSONNEL IMPACTS
• All personnel accounted for• ~950 had significant damage to
their homes
29
NASA PERSONNEL IMPACTS
30
Agency wide systemMessages can be sent to all or specialized groupsAll PIV Badged employees get the message
Email, desk phone, cell phone, personal cell, home phone, home email, texts
Center closure notification (via email and text)HR check in survey (email and phone to Civil Servants )
Are you OK? Can you return to work?JSCSOS is not the ENS!
You can follow @JSCSOS on twitter to get textsYou do not need a twitter account to follow
ENS (Emergency Notification System)
Update Your Emergency Contact Info to Receive Messages!
31
Emergency Contact Information
What am I updating? Emergency Contact InformationWhere can I find it? Personal Section of id.nasa.govWhen should I do it? Now! Why should I do it? To receive JSC emergency notifications How do I do it? Log into id.nasa.gov and click the edit button on your personal profile.
You may need help from a security officer or admin. (whoever placed your badge request)
Civil Servants will be rerouted to Employee Express www.employeeexpress.gov
Click here to log in.
Edit button will be enabled.
33
ENS Tips
PIV badged with confidence level of 40 or above
Contact info pulled from id.nasa.gov
Calls come from an unknown number
615 area code
save as NASA Emergency after you get a call
You must say “Hello” to receive the message
Listen to the entire message
You may get the same message more than once Follow prompts from the system to avoid duplicate messages
Check in survey is no longer used for contractors
34
Should I Stay or Should I Go?
35
What to Consider
If officials recommend or order evacuation, Evacuate.
If you decide to stay, plan to be without
power
fire & ambulance services
hospitals
ATMs
grocery stores
schools
If you evacuate, don’t expect a quick returnCommunities may be closed to return
Debris and damage may make block routes
36
What to Consider
38
If You Go
Secure your home – take inventory
Take important papers with you:Insurance policies…DL (proof of residency)….birth certificate…marriage certificate…passport…SS Card…wills….deeds…stocks/bonds…photos…love letters…lotto tickets
Plan a route…and an alternate route
Have a POC in the safe zone
Pack an emergency kit for your carFoodWaterBlankets Medications
Don’t forget pets and their needs
Don’t forget kids and their needs
Plan for special needs (register with 211 if you need help)
39
Road Closures
41
If You Stay
Plan for power outageflashlights...lanterns…flash charges…batteries.... medication… food safety… generator…gas powered tools…can opener…ice
Plan for water outageLaundry…fill tubs and sinks…flush buckets…gallon per person and pet per day…Boil notices
Don’t Expect Help Don’t overextend yourselfDon’t forget pets/kids
42
If You Stay
43
If You Stay
We have already had our first 2018 storm
“Landfall” refers to the center, not the edge
Slow moving hurricanes produce more rainfall and can cause more damage from flooding than faster-moving, “more powerful” hurricanes.
Loss of power may mean loss of running water
Storm surge precedes the storm by as much as 24 hours
DON’T COME TO JSC UNLESS YOU ARE ASKED TO DO SO
A large hurricane can release the energy of 10 atomic bombs – every second
Leg injuries are common after a storm
44
Things I Can do Today
Develop an evacuation plan
Have an insurance checkup:Standard homeowners’ insurance does not cover flooding.
Take inventory
Assemble your disaster supplies
Strengthen your home:Make repairsThe garage door is the most vulnerable part of the home. Consider storm shutters
Make a plan:Where to stayWhat to takeHow to protect what you leave behind
Know where your home’s water shut off valve is located
Named
StormsHurricanes
Major
Hurricanes
( Cat 3 +)
“Normal” Season 12 6 3
2017 17 10 6
Colorado State
2018 forecast14 7 3
NOAA / NWS
2018 forecast10-16 5-9 1-4
ATLANTIC OUTLOOK