G intro to travellator and other requirements 2010work6000/LG intro to travellators and other... ·...
Transcript of G intro to travellator and other requirements 2010work6000/LG intro to travellators and other... ·...
UNIVERSITY OF HONG KONG M.Sc.(Eng) in building services engineering
MEBS6000 2010 Utilities Services
K.F. Chan (Mr.) G of G Page G1 of 8
Travellator
A travellator differs from an escalator in being either horizontal or having a very small
slope of not exceeding 15 o. This makes it unnecessary for it to form steps and
passengers are conveyed on a continuous platform. The upper surface of the platform
must have grooves parallel to the direction of motion which mesh with the combplates.
In other respects a travellator or moving walkway is designed in exactly the same way
as an escalator.
Travellators are used at air terminals, railway stations and shopping centres; they can
be used by infirm, or by people with wheeled baskets or perambulators.
Travellators are set in motion by a key-operated switch, and safety measures include
an emergency stop push button, fitted at each end of the travellator. A powerful
electo-mechanical brake is fitted to the driving mechanism, which stops the travellator
in the event of a fault.
Key parameters:-
Typical inclination – 0o, 10o,11o, 12o ,15o; Typical step width – 800mm, 1000mm;
Typical pit depth – 1150mm;
Typical balustrade height – 900mm.
UNIVERSITY OF HONG KONG M.Sc.(Eng) in building services engineering
MEBS6000 2010 Utilities Services
K.F. Chan (Mr.) G of G Page G2 of 8
Paternosters
Whilst paternosters are a type of lift they have similarities with escalators. A
paternoster is a lift which has a series of small cars running continuously in a closed
loop.
(Adopted from The Vertical Transportation Handbook edited by George R. Strakosch)
The cars are open at the front and move slowly enough for people to step in and out of
them whilst they are in motion, just as they step on and off an escalator. In fact a
paternoster can perhaps be thought of a vertical escalator. To make it safe for people
to step on and off whilst the cars are in motion the speed must be less than 0.3m/s.
UNIVERSITY OF HONG KONG M.Sc.(Eng) in building services engineering
MEBS6000 2010 Utilities Services
K.F. Chan (Mr.) G of G Page G3 of 8
(Adopted from The Vertical Transportation Handbook edited by George R. Strakosch)
The cars are constructed in the same way as ordinary lift cars but do not have doors
and car sizes are limited to not more than one passenger each. In practice this means
that the cars are less than 1m x 1m in plan.
Since the cars move in a continuous loop they provide their own counterweight. Rigid
guides are provided for the cars which have shoes similar to those of ordinary lift cars.
Although they have advantages, paternosters are not used very often. They take up
rather less space than escalators but have a lower carrying capacity.
UNIVERSITY OF HONG KONG M.Sc.(Eng) in building services engineering
MEBS6000 2010 Utilities Services
K.F. Chan (Mr.) G of G Page G4 of 8
Design consideration
→ Refer to ISO 4190 for guidelines of dimensions of lift cars, lift shafts, lift motor
room, etc.
→ Refer to BS EN 81 for lift safety requirements
→ Refer to Hong Kong Fire Services Department Code of Practice regarding
fireman’s lifts, e.g. fireman’s switch, secondary power supply for lifts, fireman’s
lifts to reach top floor from the designated point of entry within 60 seconds
inclusive of lift door closing and opening time.
→ Care must be exercised regarding battery lighting and alarm, emergency
inspection doors not more than 11m apart in lift shafts (Code of Practice on the
Design and Construction of Buildings and Building Works for the Installation
and Safe Use of Lifts and Escalators), machine room artificial ventilation,
machine room lighting level (not less than 200 lux)
→ Electrical power supply and heat dissipation of lift equipment in lift motor room
to be obtained from lift contractor
→ Other services installation not to be routed through lift shafts and lift machine
rooms unless they form part of the lift installation.
→ Watch out for minimum contract load / car platform size as stipulated in
ISO4190.
→ Watch out for the need of EMC filter in power supply.
Before modernization After modernization
UNIVERSITY OF HONG KONG M.Sc.(Eng) in building services engineering
MEBS6000 2010 Utilities Services
K.F. Chan (Mr.) G of G Page G5 of 8
Lift lobby arrangement
Normally decided by architect, not building services engineers, but remember to avoid
arranging more than 3 lifts serving the same zone in a row (take a look at Hopewell
Centre!)
Unacceptable lobby arrangement for six lifts
Preferred lobby arrangement for 6 lifts
A lift machine room
(Adopted from HALL, F.E. Building Services & Equipment)
UNIVERSITY OF HONG KONG M.Sc.(Eng) in building services engineering
MEBS6000 2010 Utilities Services
K.F. Chan (Mr.) G of G Page G6 of 8
Escalator Landing Buffer area
(Adopted from The Vertical Transportation Handbook edited by George R. Strakosch)
UNIVERSITY OF HONG KONG M.Sc.(Eng) in building services engineering
MEBS6000 2010 Utilities Services
K.F. Chan (Mr.) G of G Page G7 of 8
Some general data on lift power requirement / heat dissipation
The data given below serves as an indication only. Actual data may vary with different
makes of lifts.
Contract
load, kg
Contract
speed, m/s
Full load
current, A
Peak
starting
current, A
(*)
Peak
duration, s
Heat
rejection,
kW (#)
1000 0.63 26 82 1.5 2.7
900 1.00 26 82 1.5 3.2
1000 1.60 30 107 2.0 4.9
1250 1.60 50 138 2.0 6.2
1350 2.50 50 138 3.0 7.9
1500 1.60 60 176 2.0 7.4
1500 2.50 60 176 3.0 8.8
(*) Non-soft-start type
(#) Rule of thumb:
Geared machine including most single speed and 2-speed AC machines – 30 to
60% of motor kW
Gearless machine including most DC machines and VVVF machines – 20 to
30% motor kW.
Hydraulic machine – about 20% of motor kW
UNIVERSITY OF HONG KONG M.Sc.(Eng) in building services engineering
MEBS6000 2010 Utilities Services
K.F. Chan (Mr.) G of G Page G8 of 8
Periodic examination and maintenance of lifts and escalators
The following periodic examination and maintenance is required by law in Hong
Kong:
The owner of every lift and escalator shall cause the lift or escalator …. to be
inspected, cleaned, oiled and adjusted by a registered lift contractor or registered
escalator contractor, at intervals not exceeding one month.
The owner shall at intervals not exceeding 12 months cause the lift to be
thoroughly examined by a registered lift engineer (Form 11).
� Instead of keeping a certificate, the owner of the lifts / escalators is required
to keep a logbook and to produce it for inspection on demand by the Director
of Electrical & Mechanical Services Department.
� The owner shall cause the registered contractor or registered engineer to
record details of any maintenance work carried out.
The owner shall cause the safety equipment to be tested by a registered lift
engineer
� at intervals not exceeding 12 months, by the operation of the safety
equipment without any load;
� at intervals not exceeding 5 years, by the operation of the safety equipment
with full rated load;
� at intervals not exceeding 5 years, by the operation of the overload device of
the safety equipment with a load in the car of the lift weighing between 90%
and 110% of the rated load;
� at intervals not exceeding 5 years, by the operation of the brake when the car
or platform of the lift is travelling in the downward direction at its rated
speed:
∗ with a load weighing 110% (before BS5655: Part 1),
∗ with a load weighing 125% in all other cases.