PROJECT REPORT 1 NAME AND ADDRESS :- DNYANESHWAR BHAGU DEVGE OF THE AT/PT-PISHOR (SHFEPUR ) APPLICANT TAL-KANNAD DIST-AURANGABAD 2 LOCATION OF :- PISHOR THE UNIT 3 EDUCATION :- S S C 4 DATE OF BIRTH :- 6/1/1972 5 CAST :- O B C (MALI) 6 ACTIVITY :- KIRANA DUKAN 7 EMPLOYMENT :- 1 8 COST OF PROJECT :- 150000 9 FINANCE TO BE :- SAMAJ KALYAN SEED MONEY RAISED HANDICAPPED LOAN TERM LOAN :- YES CASH CRIDET :- NO 10 SCOPE :- THERE IS GOOD SCOPE FOR ABO BUSINESS 11 EXPERIENCE :- GOOD EXPERIENCE IN THE SO CAN RUN THE UNIT SMOOTHL

description

formulated only need to change name and address put the values of assets. it is used for govt. schemes of dic

Transcript of formulated project report

Page 1: formulated project report

1

PROJECT REPORT

1 NAME AND ADDRESS :- DNYANESHWAR BHAGU DEVGEOF THE AT/PT-PISHOR (SHFEPUR )APPLICANT TAL-KANNAD

DIST-AURANGABAD

2 LOCATION OF :- PISHORTHE UNIT

3 EDUCATION :- S S C

4 DATE OF BIRTH :- 6/1/1972

5 CAST :- O B C (MALI)

6 ACTIVITY :- KIRANA DUKAN

7 EMPLOYMENT :- 1

8 COST OF PROJE :- 150000

9 FINANCE TO BE :- SAMAJ KALYAN SEED MONEY RAISED HANDICAPPED LOAN

TERM LOAN :- YES

CASH CRIDET :- NO

10 SCOPE :- THERE IS GOOD SCOPE FOR ABOVE BUSINESS

11 EXPERIENCE :- GOOD EXPERIENCE IN THE LINE

SO CAN RUN THE UNIT SMOOTHLY.

Page 2: formulated project report

2

COST OF PROJECT

FINANCIAL ASPECTS AMOUNT

LAND 0

BULDING 0

MACHINERY/EQUIPMENTS 150000

FURNITURE

TOTAL 150000

WORKING CAPITIAL

required material of proposedbusiness

KIRANA DUKAN

TOTAL 0

GRAND TOTAL ABHOV 150000

MEANS OF FINANCE % AMOUNT

APPLICANT 0 0

SAMAJ KALYAN HANDICAP LOAN 20 30000

BANK LOAN 80 120000

TOTAL 100 150000

Page 3: formulated project report

3EXPENDITURE DETAILS

1 RECURRING EXPENDITURE Nos SALARY RATE PM PA

A] STAFF & LABOURA)MARKETING & SALES 0 0 0 21600STAFF

B) OFFICE STAFF 0 0 0 0

C) SUPERVISIOR 0 0 0 0

D) SKILLED WORKER 0 0

E) HELPER / UNSKILLED 1 3500 3500 42000

F) WATCHMAN 0 0 0 0

G) OTHER 0 0 0 0

T O T A L 1 3500 63600

B] MATERIALS PM PA

REQUIRED 80000

MATERIALS

T O T A L 0 80000

C] OTHER EXPENSES PM PA

1) ELECTRICTY 600 7200

2) RENT / TAX / INSURANCES / etc 1000 12000

3) CONVEYANCE 300 3600

4) ADVERTISING 300 3600

5) PACKING 0 0

6) MISC 500 6000

7) MAINTAINACE 600 7200

8) TRANSPORT 500 6000

Page 4: formulated project report

9) TELEPHONE 700 8400

T O T A L Rs 4500 54000

Page 5: formulated project report

LOAN REPAYMENT SCHEDULEBANK LOAN

YEAR OPENING RECOVERY CLOSING INTREST

BALANCE INSTALL BALANCE 12

MENT %

P..A

1 120000 6000 114000 3600

114000 6000 108000 3420

108000 6000 102000 3240

102000 6000 96000 3060

24000 13320

2 96000 6000 90000 2880

90000 6000 84000 2700

84000 6000 78000 2520

78000 6000 72000 2340

24000 10440

3 72000 6000 66000 2160

66000 6000 60000 1980

60000 6000 54000 1800

54000 6000 48000 1620

24000 7560

4 48000 6000 42000 1440

42000 6000 36000 1260

36000 6000 30000 1080

30000 6000 24000 900

24000 4680

5 24000 6000 18000 720

Page 6: formulated project report

18000 6000 12000 540

12000 6000 6000 360

6000 6000 0 180

24000 1800

PROFITABILITY STATEMENT PAR YEAR DATA

PARTICULARS Y E A R S

A] INCOME 1 2 3 4 5

FROM THE ACTIVITY AS 262500 300000 337500 375000 412500NOTED ON FIRIDT PAGE

T O T A L 262500 300000 337500 375000 412500

B] EXPENDITURE

1) STAFF LABOUR 63600 66780 70119 73625 92031

2) MATRAIL PURCHASES 80000 83200 86528 89989 93589

3) OTHER EXPENSES 54000 56160 58406 60743 63172

4) DEPRICIATION 0 0 0 0 0

INTEREST ON

5) BANK LOAN 13320 10440 7560 4680 1800

T O T A L 210920 216580 222613 229037 250592

PROFIT ( A- B ) 51580 83420 114887 145963 161908

LESS I / TAX PROVISON 0 0 17233 21894 24286

PROFIT AFTER TAX 51580 83420 97654 124069 137622

ADD DEPRICIATION 0 0 0 0 0

CASH PROFIT …. 51580 83420 97654 124069 137622

Page 7: formulated project report

LESS BANK LOAN 24000 24000 24000 24000 24000

B A L A N C E 27580 59420 73654 100069 113622

DSCR NET

Page 8: formulated project report

0 0 0 0