Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

15
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009

description

3 ExCR – Overview Part A covers “Transitional Exit Period”. Essentially the same as last years ExCR, but with some updating. Part B covers “Enduring Exit Period”. Concentrates on release of Enduring Annual NTS Exit (Flat) Capacity: Application Processes; annual, ad-hoc and ARCA. Reduction Process. User Commitment. General Introduction. Covers common sections applicable to both the Transitional and Enduring Exit Periods: e.g. contact for connection services, Licence obligations.

Transcript of Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

Page 1: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

Exit Capacity Release Methodology Statement - ExCRTransmission Workstream – 5th Feb 2009

Page 2: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

2

Exit Capacity Release Methodology Statement.

Requirement of the Gas Transporter Licence.Special Condition C18:

– The licensee shall, before 1 April, prepare and submit for approval by the Authority an

NTS exit capacity release methodology statement setting out the methodology by

which it will determine how it will release NTS exit capacity to gas shippers or DN

operators.

– National Grid is required to consult (28 days) on it proposals and provide a

conclusions report to Ofgem.

– Proposed statement is effective upon approval or, if not vetoed, after 2 months.

This means that the ExCR:- Informs on how and when National Grid will make capacity available for Users to

obtain.Links obligations under both the Licence and UNC and provides extra information

where there is lack of detail. Is particularly important in respect of the release of “obligated incremental”

capacity as this often has lead-time and funding implications.

Page 3: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

3

ExCR – Overview

Part A covers “Transitional Exit Period”. Essentially the same as last years ExCR, but with some updating.

Part B covers “Enduring Exit Period”.Concentrates on release of Enduring Annual NTS Exit (Flat) Capacity:

• Application Processes; annual, ad-hoc and ARCA.• Reduction Process. • User Commitment.

General Introduction.Covers common sections applicable to both the Transitional and Enduring Exit Periods:

e.g. contact for connection services, Licence obligations.

Page 4: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

4

ExCR – Part A

Part A covers “Transitional Exit Period”.

Main changes are:

ARCA terms (paragraph 21) •To ensure consistency with the Enduring Exit Period the User Commitment will be based on four years of exit capacity charges.

Forwards and Options (paragraph 28) •Mitigating actions that may be explored (to enable release of capacity) include; forwards and options.

Lead-times (paragraph 36) •Section B applies to requests for capacity beyond investment lead times and for release in the Transitional Exit Period. So the section has limited scope; applying only to offers made before 1st July 2009.

Page 5: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

5

ExCR – Part B

Part B covers “Enduring Exit Period”.

Concentrates on release of Enduring NTS Exit (Flat) Capacity: • Application Processes;

• Annual Application Window;• Non-window (“Ad-hoc”); and • ARCA applications.

• Reduction Process• User Commitment

also covers release of:• Annual, Daily and Non-Obligated NTS Exit (Flat) Capacity: and• NTS Exit (Flexibility) Capacity

Page 6: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

6

Part B: Major Points

a) Capacity Terminology (paragraphs 4 – 8). Capacity terms used in the Licence and UNC are complex and

not totally aligned. – We are currently pursuing possible changes to the Licence.

Until, any changes are implemented the ExCR refers to existing terminology. A revision may be required in Q2 2009.

Diagrams provide a simplified explanation of the terms used.

– But the Licence and UNC definitions prevail.

b) Planning Process (paragraphs 10 – 16). Long term User signals are the driver to investment. Exit Capacity Substitution obligation is intended to reduce

unnecessary investment.

– NG expects the obligation to be deferred.

Page 7: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

7

Part B: Major Points

c) Principles (Chapter 1) National Grid will release NTS Exit Capacity (including baseline

capacity) having regard to:– Overriding obligations in the Gas Act and the Licence; e.g. where

safe and efficient to do so.

– Reasonable endeavours obligation in the Licence.

National Grid will release Enduring Annual NTS Exit (Flat) Capacity subject to a User Commitment.– Other forms of exit capacity will not require a User Commitment.

Page 8: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

8

Part B: Allocation of Enduring Annual NTS Exit (Flat) Capacity (Chapter 2)

d) Initialisation (paragraphs 26-30). The ExCR refers to UNC Transition Document for initialisation

rules.

For NTS Supply Points and NTS Connected System Exit Points– the maximum firm capacity utilised is the highest value of capacity

booking for any Gas Day in Gas Year 2007/8: and– the maximum interruptible capacity utilised is the highest value of

any interruptible gas allocation for any Gas Day in Gas Year 2007/8:– where either of the above two values would be in excess of the

baseline the values will be pared back to the baseline - firstly interruptible and then firm on a pro rata basis

– where an ARCA has been agreed with a capacity release date within the Transitional Exit Period, the value specified in the ARCA is used: and

– For new NTS Exit Points that are not subject to an ARCA the registered allocation at 30th September 2012 is used.

For DN Offtakes– The 2008 OCS is used– New offtakes / ARCA treated same as Supply Points

Page 9: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

9

Part B: Allocation of Enduring Annual NTS Exit (Flat) Capacity (Chapter 2)e) Increases

Three processes

Subject to User Commitment (paragraph 33)– But the User Commitment is not applicable to the initialisation quantity, unless

increased (see paragraph 34).

Exit Point must be in Licence (paragraph 36),

National Grid will only be obliged to release incremental capacity, where there is a revenue driver in the Licence (paragraph 36) – May need six months notice before application / ARCA.

National Grid may enter into a PWA if an applicant is unable to provide long term signal (see paragraph 38).

Annual Window Ad-hoc ARCA

Release dates 1st Oct Y+4, Y+5,

Y+6

1st Month, M+7 to 1st

Oct Y+4

As for ad-hoc

(para 58)

Application Dates 1st – 31st July 1st Oct – 30th June Any time

Page 10: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

10

Part B: Allocation of Enduring Annual NTS Exit (Flat) Capacity (Chapter 2)

f) Reductions. Requests can only be made in the annual reduction window (1st

– 15th July) or in response to an ad-hoc request from National Grid (paragraph 63).

Only permitted if there is no outstanding User Commitment and normally requires 14 months notice (paragraph 61).

Reduction before Oct Y+2 (i.e. less than 14 months) permitted at National Grid discretion where this would mitigate the need to release incremental capacity at the exit point (paragraph 65).

Reductions must be effective on 1st of month and no earlier than Oct Y+1 (paragraph 64).

Applies to initial allocation as at 1st Oct 2012 (paragraph 62).

Page 11: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

11

Part B: Allocation of Enduring Annual NTS Exit (Flat) Capacity (Chapter 2)g) User Commitment (paragraphs 68-73).

This requires the User to be the registered User of (and hence to pay for) the allocated capacity for four years.

It applies to all tranches/increases in an application and applies to the total allocation (incremental plus existing).

The User Commitment Amount is only relevant if the allocated quantity is reduced early (generally this is not permitted); except

The User Commitment Amount is paid by a Reservation Party if all the reserved capacity is not allocated or is allocated late.

h) User Commitment Amount (paragraphs 74-79) Only determined if needed.

Is based on the indicative price in the offer / ARCA.

Calculated as Price * Quantity * Days (for which capacity not allocated)– Calculated from reduction effective date to 4th anniversary of

release for Users;– Calculated from release date to date of allocation for non-Users.

Page 12: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

12

Part B: Allocation of Enduring Annual NTS Exit (Flat) Capacity (Chapter 2)i) Multiple ad-hoc applications & ad-hoc applications

overlapping the annual window (paragraphs 50-52).

Applications for capacity made in the annual application window will be considered in aggregate, whereas

Ad-hoc and ARCA applications will be considered individually as they are subject to an offer / acceptance process.

Each ad-hoc / ARCA application can affect the offer to made in respect of other ad-hoc / ARCA applications or those in the annual window.

Hence in respect of interacting / overlapping applications process National Grid will seek to amend offer / acceptance timelines and they will be considered sequentially.

If agreement on timelines cannot be agreed then the offer will be based on all outstanding offers being accepted (i.e. assume worst case). This will also apply in respect of the annual application window process.

Page 13: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

13

Part B: Allocation of Enduring Annual NTS Exit (Flat) Capacity (Chapter 2)

j) Default Capacity Release Lead-Times. Where incremental capacity is required to be released this will

normally be from 1st October Y+4.

Permits may shorten or extend the default time-line

– Early contact needed

Page 14: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

14

Part B: Allocation of Other Capacity Products (Chapters 3, 4, 5)

k) Annual NTS Exit (Flat) Capacity. Refers to UNC processes.

l) Daily NTS Exit (Flat) Capacity. Refers to UNC processes. National Grid may release non-obligated capacity. This will be in

accordance with incentives and obligations in the Licence. “Off-peak” released in accordance with UNC.

m) NTS Exit (Flexibility) Capacity. Available to DNO Users only. Shippers obtain flow flexibility via OPNs. Incremental NTS Exit (Flexibility) Capacity will not be released if this

would increase costs, adversely impact safety, trigger reinforcement, or exceed the baseline quantity.

National Grid may release non-obligated capacity. This will be in accordance with incentives and obligations in the Licence.

Page 15: Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.

15

Timeline and Next Steps

Presentation on draft ExCR. 05th February at Transmission Workstream.

With Ofgem.

Review/Amend draft ExCR to resolve issues raised as

appropriate. 23rd February commence consultation (28 days). Submit proposed ExCR to Authority (by 31st March 2009) 01 May 2009 ExCR effective.

Assumes approval within 1 month (Licence allows 2 months).