European Offshore Wind 2009
-
Upload
brielle-parsons -
Category
Documents
-
view
20 -
download
3
description
Transcript of European Offshore Wind 2009
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 1
European Offshore Wind 2009
Conceptual Foundation Study
for Kriegers Flak
Göran Loman, Vattenfall
Thomas Stalin, Vattenfall
Helge Gravesen, Grontmij | CarlBro
or
A Marathon race in 15 minutes
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 2
Participants in the project
• Ballast Nedam• Cowi• GrontMij|Carlbro• ISC AS• MT Højgaard• MT Piling• Per Arsleff AS• Pihl & Søns AS• Rambøll• SGS• Skanska• Vattenfall
Financed by Vattenfalls project Kriegers Flak Wind Farm and by the Swedish Energy Agency
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 3
Vattenfall Windpower
Vattenfall • Owned by the Swedish government
Activities• Today
– DK, FI, DE, NL, PL, SE, UK, – 2 TWh/a– One of the leading generators
in the Nordic countries– Significant share of the world
offshore market
• Development– Seven ongoing large projects under
construction– Several under development
• Goal– Climate neutral 2050 (Vattenfall group)
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 4
Kriegers Flak Wind Farm
• 30 km south of Trelleborg
• 17-40 m water depth
• 128 plants
• Each 5 MW
• 2.6 TWh/y
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 5
The scope of work
Aims
• Evaluate existing kinds of foundations
• Develop more cost efficient concepts
Project development
• Open seminar in February 2008presentation of concept
• Some ten consultants and contractors where engaged
• The experts work with design
• Evaluation of fabrication, installation, costs
• Adjustments and final design
• Final presentation at EOW
• Final report
Regular meetings where the concepts where discussed and evaluated
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 6
Actual site assessment was used
• Geotechnical surveys
• Fino2
• Hydrographic measurements
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 7
The concepts
• Foundations
– Steele monopile
– Steele quadroped
– Concrete gravity
– Concrete gravity tripod
– Concrete monopile
• Sea bed preparation robot
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 8
Steel monopileRambøll and MT Højgaard
• Conventional design
• Suitable conditions for monopile
– Drilling needed where boulders occur
• 3.1 M€ (35 m, 5 MW)
– More compatible at shallow depth
• Limited storage area needed
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 9
Steele quadropedRambøll and MT Højgaard
• Design
– Concrete transition piece
– 2 levels of X-braces
• Less wave load
• 3.0 M€ (35 m, 5 MW)
– More competitive at deeper water
• Possibilities for further optimisations
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 11
Concrete gravity Cowi and Aarsleff
• Three designs– Conventional cone– Floating (KIS)– Semi floating
• Conventional– Cost effective, 2.4 M€ (35 m, 5 MW)– Durable and robust– Maintenance friendly– Heavy lifting floating cranes
• Floating– The floating concept need more
concrete and deeper harbour– KIS 4 M€, semi floating 3 M€– No heavy lifting floating crane– Could be improved
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 12
Concrete gravity triopod ISC and Skanska
• Design
– Three legs, triangular shape
– Standardised parts
– Prefab elements, in situ casting
– Total installation concept
• Heavy (>3,000 tons)
• Expensive 3.8 M€ (35 m, 5 MW)
• Need to be improved
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 13
Concrete monopileBallast Nedam and MT Piling
• Design
– Prefab concrete monopile
– Vertical drilling
• Concrete
– Less expensive than steel
– High fabrication capacity
• No uw noise or vibration during installation
• Unproven technique (or?)
• 3,1 M€ (5 MW, 40 pc)
– 2 M€ for 130 pc
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 14
Stone bed preparation robot, Pihl
• No divers needed
• One stop for
– Soil investigation (vibro cores, CPT)
– Final levelling of the sea bed
– Surface measurements
– Creating the stone bed (fall pipe)
2009 09 15 | Kriegers Flak Wind Farm | Göran Loman | PYP 15
Summary
• Several interesting concepts were evaluated and improved
• There is a potential for further optimization
• Need to iterate with turbine suppliers
The foundations, you don’t see them, but you need them!