European Offshore Wind 2009

19
European Offshore Wind 2009 A description and analysis of the new competitive regime for the provision of grid connections for UK offshore wind farms

description

European Offshore Wind 2009. A description and analysis of the new competitive regime for the provision of grid connections for UK offshore wind farms. Overview. Financing Offshore Transmission – an emerging issue in Europe The UK Offshore Transmission Regime a description - PowerPoint PPT Presentation

Transcript of European Offshore Wind 2009

Page 1: European Offshore Wind 2009

European Offshore Wind 2009

A description and analysis of the new competitive regime for the provision of grid connections for UK offshore wind farms

Page 2: European Offshore Wind 2009

Overview

• Financing Offshore Transmission – an emerging issue in Europe

• The UK Offshore Transmission Regime

– a description

– an offshore wind developer’s perspective

– an OFTO bidder’s perspective

• Who will the new offshore transmission owners be?

• How does the regime impact on offshore grid design?

– a grid system planner’s perspective

Page 3: European Offshore Wind 2009

Financing Offshore Transmission – an emerging issue in Europe

Page 4: European Offshore Wind 2009

Growth in Capex Requirements for Offshore Transmission

• The pace of offshore wind growth is picking up• Even conservative estimates envisage 20-

40GW by 2020• To date rule of thumb of €500m capex on

offshore transmission for every 1000MW of offshore wind capacity (15-20% total capex)

• Farther offshore wind farms will require even greater transmission capex

• So minimum of €10bn in Europe by 2020• UK government /Ofgem estimating UK offshore

transmission market may be worth €15bn-€20bn on its own

• Greater interconnection will increase capex requirements, and benefits even more so

Installed European Offshore Wind Capacity (GW)

0

5

10

15

20

25

30

35

40

45

2006 2010 2015 2020

Delivering Offshore Wind Power in Europe, Offshore Wind Industry Group, EWEA, 2007

Page 5: European Offshore Wind 2009

New Challenges for Transmission Companies

• Onshore grids largely built by state owned monopolies• Many grids now in private hands• Private finance required to fund offshore transmission expansion• Investment requirement offshore may be greater than existing asset base (cf UK)• Investors may not be willing to fund or at least to commit to funding expansion• Particularly in current “credit crunch” climate• Hence different models required …. UK first of these …

Page 6: European Offshore Wind 2009

The new UK offshore transmission regime

Page 7: European Offshore Wind 2009

Description

• By summer 2010 it will be prohibited in the UK to transmit electricity offshore at 132kV or above without an offshore transmission licence

• Ofgem will be the licence awarding entity• Currently no offshore transmission licences exist• Licences will be awarded following a competitive tender on a project-by-project basis• The criteria for licence award will be 60% finance based and 40% non-finance• Existing and under construction offshore transmission assets will be transferred to

new offshore transmission owners (OFTOs) – TRANSITIONAL REGIME• New offshore transmission assets will be procured, constructed and owned by new

OFTOs – ENDURING REGIME

Page 8: European Offshore Wind 2009

Scope of OFTO

Offshore Transmission Owner (OFTO)Onshore TO Generator

Offshore Platform

Connection to onshore

network

132 kV Cable 33 kV Inter Array Cables

Onshore Substation

Page 9: European Offshore Wind 2009

Industry Relationships

OFTO

GBSO

O&M Contract

Ofgem

Offshore Generator

Crown Estate

Lease

Sale and Purchase

Agreement

Transmission Licence

Bid revenue stream

Transmission Use of System Charges

Insurance

Financing

Page 10: European Offshore Wind 2009

Transitional Regime Projects

Project Developer Size (MW) Exp. Completion

1. BarrowDong Energy / Centrica

90 Operating

2. Robin Rigg E.ON 180 Jul 09

3. Gunfleet Sands I & II Dong Energy 172 2009

4. Thanet Vattenfall 300 *

5. Greater Gabbard SSE / RWE Innogy 504 Mar 11

6. Ormonde Vattenfall 150 Nov 10

7. Walney I & II Dong Energy 360 *

8. Sheringham Shoal Statoil Hydro / Statkraft 315 Jun 10

Project Developer Size (MW)

9. London Array E.ON / Dong / Masdar 1000

10. Lincs Centrica 250

11. Gwynt y Mor RWE Innogy 750

12. Docking Shoal Centrica 500

13. Race Bank Centrica 500

Projects likely to qualify for First Transitional Tender (£1.15bn)

Projects that may qualify for Final Transitional Tender (up to £1.5bn)

1

2

34

5

67

9

1011

1213

8

Page 11: European Offshore Wind 2009

An offshore wind developer’s perspective …

• Good bits– Offshore wind developers don’t need to finance offshore transmission connection– Rate of return requirements will be less than for offshore wind farm – offshore

wind developers will benefit (customer taking the risk of default of the offshore wind farm)

– Energy production metered offshore

• Bad bits– No significant compensation if offshore transmission is unavailable– No significant compensation if offshore transmission is late

• Clarification needed in some areas– When to seek appointment of the OFTO?– How many OFTOs for a large multi-site project?

Page 12: European Offshore Wind 2009

An OFTO bidder perspective

• Good bits– Credit risk minimal, 20-yr fixed revenue stream subject RPI indexation

– Availability incentive/penalty (capped at 10% of annual revenue)

– O&M and insurance costs, generally small and can be estimated and fixed

– Most significant repair costs should be insured or under manufacturer’s warranties

– Some cost items are pass-through

• Bad bits– A long time coming (regime first consulted on in 2004)

– Complex, costly and lengthy tendering process

• Clarification needed in some areas– Lack of clarity as to when committed financing required

– Indeterminate timing gap between licence award and takeover of asset

– Requirement for compliance with utilities contract regulation (OJEU)

– Level playing field with respect to generator-affiliated OFTO bidders

Page 13: European Offshore Wind 2009

Who will the new offshore transmission owners be?

Page 14: European Offshore Wind 2009

Who might the new OFTOs be?

• Transitional– Offshore wind generators (for their own projects)

– Existing onshore TOs

– New entrants backed by infrastructure/pension funds

• Enduring– Offshore wind generators (subject to unbundling)

– Existing onshore TOs

– New entrants - to the extent cut-their-teeth on the transitional rounds

– New entrants - with offshore construction management experience

Page 15: European Offshore Wind 2009

UK regime impact on offshore grid design

Page 16: European Offshore Wind 2009

Offshore Wind Farm Connections or offshore grids?

Page 17: European Offshore Wind 2009

A grid system planner’s perspective

• UK regulatory enduring regime still being developed• Some positives

– Information to be published by TSO

– Co-ordination by controlling body (landlord)

– Co-operation between developers

• Some way to go though …– Connection application process requires individual treatment of offshore wind farms

– Offshore wind developers incentivised to be selfish in some circumstances

– Interconnection has to be merchant

• Some of these issues will be addressed through forthcoming UK consultation processes

• What can EU do to help or hinder?– Cross-border planning standards

– Clear and certain mechanism for recovering costs of interconnection (including return on investment)

Page 18: European Offshore Wind 2009

Conclusions

• Financing offshore transmission is a growing challenge• New models for funding being tried• UK model has acceptable risk/return profile for low return capital• Some issues still need to be resolved in the tender process but otherwise attractive

for investors• Some issues less than ideal for offshore wind developers and enduring regime still

being devised• A competitive process expected with new entrants in the transmission ownership

space• EU has a role to play in facilitating cross-border connections leading to an optimal

offshore grid design

Page 19: European Offshore Wind 2009

Contact details:

Email: [email protected]: 07768 036613Web: www.transmissioncapital.com