Estates Management.ppt

24

description

For education purpose only

Transcript of Estates Management.ppt

Page 1: Estates Management.ppt
Page 2: Estates Management.ppt

DIRECTORATE OF DIRECTORATE OF

ESTATEESTATE MANAGEMENT MANAGEMENT

AND WORKSAND WORKS

Page 3: Estates Management.ppt

ADMINISTRATIVE STRUCTUREADMINISTRATIVE STRUCTURE

DIRECTOR (BS-19)ANCILLIARY STAFF

JT DIRECTOR (ARCH) JT DIRECTOR (EM) CIVIL ENGINEERS ( BS-18) (BS-18) (BS-18)

DY. DIRECTOR (ADMN) DY DIRECTOR (EM) DY.DIRECTOR (A/Cs) ASSTT. DIR. (CIVIL) (BS-17) (BS-17) (BS-17) (BS-16) ASSTT. DIRECTOR (ADMN)

(BS-16)

DRAUGHTMAN SUB-ENGINEER (BS-11) (BS-11)

ANCILLIARY STAFF ANCILLIARY STAFF ANCILLIARY STAFF

Page 4: Estates Management.ppt

OBJECTIVESOBJECTIVES

• PLANNING & DEVELOPMENT

• EXECUTION OF CIVIL WORKS IN PSIC

• COLONIZATION OF INDUSTRIAL ESTATES

• INFRASTRUCTURE AND UTILITIES

• GROWTH IN INDUSTRIAL BASE

Page 5: Estates Management.ppt

ACTIVITIES & FUNCTIONSACTIVITIES & FUNCTIONS

• Establishment / Development of Industrial Estates and Export Processing Zones

• Execution of civil works through ADP and PSIC own resources

• Planning and Designing of Small Industries Estates by the staff and professional consultants

• Allotment of plots in SIEs under the supervision of respective Regional Directors.

• Formulation of Development Plan of ADP in respect of PSIC offices, Industrial Estates and CDCs

• Compilation of data regarding industrial plots and related activities in Small Industries Estates

• Enlistment of Contractors and Consultants/Contract Awards.

• Payment to Contractors / Consultants for the services rendered against civil works / services

• Preparation of Concept Papers, Feasibility Reports and PC-I, for setting up of new industrial Estates and Export Processing Zones

Page 6: Estates Management.ppt

SMALL INDUSTRIAL ESTATESSMALL INDUSTRIAL ESTATES(GOVERNMENT FUNDED)(GOVERNMENT FUNDED)

Sr.No.

Estate Plots

Category Total No. of Plots

Total Plots allottedAA A B C D E

1 Jhelum - 60 115 89 - 24 288 288

2 Gujjar Khan - - 32 59 56 36 183 182

3 Chakwal - 18 51 51 - - 120 120

4 Gulranwala-I 86 104 116 - - 102 408 408

5 Gujranwala-II 67 82 146 148 108 - 551 551

6 Gujrat-I - 85 112 201 24 - 422 422

7 Daska 37 63 50 - - - 150 150

8 Sialkot-I 71 95 164 - - 50 380 380

9 Lahore-I - 12 19 9 - - 40 40

10 Faisalabad 148 185 183 366 138 - 1020 1013

11 Sargodha 29 36 67 76 - 50 258 254

12 Sahiwal 27 58 71 - - 32 187 187

13 Bahawalpur - 79 75 51 - - 205 204

Total 465 877 1201 1050 334 294 4212 4199

Page 7: Estates Management.ppt

SMALL INDUSTRIAL ESTATESSMALL INDUSTRIAL ESTATES(SELF FINANCING)(SELF FINANCING)

Sr.No

.Estate Plots

Category Total No. of Plots

Total No. of Plots allotted

AA A B C D E

1 Taxila 41 107 167 69 - - 384 384

2 Gujranwala-III (EPZ)

- 96 48 25 43 - 212 212

3 Sialkot-II (EPZ) 83 152 156 25 - - 416 416

4 Sialkot-III (EPZ) 103 127 201 34 - - 465 465

5 Gujrat=II - - - - - - - -

6 SIE-II (Sundar) LHR

55 110 166 17 - - 348 348

7 Kasur - 87 156 62 24 - 326 326

8 Mian Channu - 59 64 34 - - 157 157

9 Khanewal - 103 162 48 - - 313 289

Total: 282 841 1120 314 64 - 2621 2597

Page 8: Estates Management.ppt

DEVELOPMENT WORKS COMPLETED DEVELOPMENT WORKS COMPLETED DURING 2011-2012 (ADP SCHEMES)DURING 2011-2012 (ADP SCHEMES)

Sr.No Name of Scheme

Description of work

Cost in Million

Physical Status

1 SIE, Sargodha Up-gradation of water supply systgem

8.411 Completed

2 MIE, Chakwal Provision of outside sewerline

2.589 Completed

3 SIE, Daska Improvement of Roads 11.811 Completed

4 SIE, Sahiwal Improvement of Roads 4.840 Completed

5 MIE, Gujjar Khan Water Supply System (Tunbewell)

2.494 Scheme dropped due to non-availability of land being private land

6 CDC, Murree Up-grdation of facilities 1.550 Completed

Page 9: Estates Management.ppt

DEVELOPMENT WORKS DURING 2012-13DEVELOPMENT WORKS DURING 2012-13

Sr.No

Name of Scheme

Description of work Cost in Million

Physical Status

2 SIE, Daska Repair of Outer drain 1.25 Completed

3 SIE-I-Gujranwala

RCC Roads. 5.00 Completed

Page 10: Estates Management.ppt

DEVELOPMENT WORKS IN PROGRESS DEVELOPMENT WORKS IN PROGRESS DURING 2013-2014DURING 2013-2014

Sr.No

Name of Scheme

Description of work Cost in Million

Physical Status

1 SIE, Khanewal

Provision of missing facility of force main pressure line from SIE-Khanewal to TMA disposal station.

2.00 Funds Not Released.

Page 11: Estates Management.ppt

Industrial Incubator Cum Service Centres

•Back ground and concept

•Brief of the Scheme

•Present Status

Page 12: Estates Management.ppt

PSIC HOUSEPSIC HOUSE• Name of Project PSIC House• Location Davis Road, Lahore• Area / Land 6 Kanal 5 Marla & 32 sqft• Year of Purchase 1975• Consultants M/S. NESPAK (Pvt) Ltd.• Agreement 25th January, 2007• Covered Area 86770 Sq.ft• Estimated Cost 217.00 Million on 25th January, 2007• No. of Floors 2 Basement & 6 Above• Fee:• Preliminary & Detail Design 4.50 million lump sum• Resident Supervision 2.75 % of tendered cost of the project

based on construction period of 24 months.

Design Approved. In 68th PSIC Board Meeting 2007Fee already paid to consultant Rs. 1.80 millionon account of services rendered by them as per agreement

Page 13: Estates Management.ppt

PSIC HOUSE (Cont.)

Front Elevation

Page 14: Estates Management.ppt

DETAIL OF COVERED AREA(Cont.)

•LOWER BASEMENT 12857 Sq.ft•UPER BASEMENT 12857 Sq.ft•LOWER GROUND 10127 Sq.ft• UPPER GROUND 8709 Sq.ft

•FIRST FLOOR 10178 Sq.ft•SECOND FLOOR 10327 Sq.ft•3RD FLOOR 10512 Sq.ft•4TH FLOOR 10750 Sq.ft•MUMTY PLAN 494 Sq.ft•TOTAL COVERED AREA 86770 Sq.ft

Page 15: Estates Management.ppt

PSIC HOUSE (Cont.)

PSIC has requested the Consultants for preparation of detailed designing, tender documents, PC-I and estimate etc as per schedule of agreement and follow-up for approval of building plans already submitted to TMA.

 

The Consultant has requested to enhance their fee as under:-

Consultancy remuneration as per signed agreement Rs.4.50 million.

Proposed revised fee Rs. 10 million

Already paid Rs.1.80 million.

Balance amount payable Rs.8.2 million.

Increase in fee Rs.6.5 million.

The above increase in fee has been approved by the PSIC Board in its 87 th meeting held on 6-02-2014.

Page 16: Estates Management.ppt

NEW INITIATIVES

Power Generation Unit

At Small Industries Estate , Faisalabad, on

“Public-Private” partnership basis.

Page 17: Estates Management.ppt

BACKGROUND:

In view of the energy crises in Punjab, Punjab Small Industries Corporation (PSIC) and Energy Department, Govt. of the Punjab, decided to jointly explore the possibility of providing un-interrupted power supply to Industrial units located in Small Industries Estates

Page 18: Estates Management.ppt
Page 19: Estates Management.ppt

NEW INITIATIVES

Construction / Extension of Small Industries Estate, Daska.

Page 20: Estates Management.ppt

NEW INITIATIVES

GIS MAPPING IN COLLABORATION WITH URBAN UNIT

Page 21: Estates Management.ppt

NEW INITIATIVES

Establishment of industrial estate for

Rock Salt Products

at Quaidabad, District Khushab.

Page 22: Estates Management.ppt

NEW INITIATIVES

Establishment of new Small Industrial Estates / Zones

On the instructions of Government of the Punjab, PSIC is working on establishment of new SIEs at Districts Mandi-Bahauddin,Mianwali, Wazirabad, Sialkot, Bhakkar, Chiniot and Attock.

Page 23: Estates Management.ppt

Pending Issues Pending Issues

• SIE Sundur II Electrification• Extention SIE Daska-Presentation to Minister• De-notification of SIE-III (EPZ)• Double Taxation in certain estates-DG Excise & Taxation• Issue of SIE Taxila- cantonment board fee on transfer• SIE Mandi Baha-ud-din• Redundant property • Cleanliness issues of SIE Faisalabad & Gujranwala