ESCA Remediation Program Update

5
Fort Ord Reuse Authority (FORA) Environmental Services Cooperative Agreement (ESCA) Remediation Program (RP) 1 ESCA Remediation Program Update Presentation by: Stan Cook, Program Manager October 11, 2013 Board of Directors Meeting

description

Fort Ord Reuse Authority (FORA) Environmental Services Cooperative Agreement (ESCA) Remediation Program (RP). ESCA Remediation Program Update. Presentation by: Stan Cook, Program Manager. October 11, 2013 Board of Directors Meeting. 1. “Known” MEC field work now complete. - PowerPoint PPT Presentation

Transcript of ESCA Remediation Program Update

Page 1: ESCA Remediation Program Update

Fort Ord Reuse Authority (FORA)Environmental Services Cooperative Agreement (ESCA)

Remediation Program (RP)

1

ESCA Remediation Program Update

Presentation by:Stan Cook, Program Manager

October 11, 2013 Board of Directors Meeting

Page 2: ESCA Remediation Program Update

Status / Challenges

2

1. “Known” MEC field work now complete.2. Regulators may request further investigation.3. Lengthy document review process (160 days).4. U.S. government shut down delays.

Page 3: ESCA Remediation Program Update

Interim Action Ranges Habitat Restoration

February 2013

January 2013

3

September 2013

Sand Gilia

Page 4: ESCA Remediation Program Update

Community Resources

4

Website: www.fora-esca-rp.com Newsletters & Technical Fact Sheets Facebook and Twitter: FORA ESCA RPHotline Weekly Updates: (831) 883-3506 Maps showing access corridors Kiosks at access corridor trailheads Email: [email protected] Address: 920 2nd Ave Suite A, Marina, CA 93933

Page 5: ESCA Remediation Program Update

5