Environmental Monitoring Report...CURRENCY EQUIVALENTS (as of 31 December 2019) Currency unit –...
Transcript of Environmental Monitoring Report...CURRENCY EQUIVALENTS (as of 31 December 2019) Currency unit –...
Environmental Monitoring Report
# Semiannual Report July-December 2019 December 2019
INO: West Kalimantan Power Grid Strengthening
Project
Prepared by Pusat Manajemen Proyek (Pusmanpro) for the PT PLN and the Asian Development
Bank.
CURRENCY EQUIVALENTS (as of 31 December 2019)
Currency unit – Indonesian rupiah (Rp) Rp1.00 = $0.000071849
$1.00 = Rp13,918
NOTE
(i) In this report, "$" refers to US dollars. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
PT PLN (PERSERO) UIP KALBAGBAR Jl. Letjend. Suprapto No. 50 G, Pontianak Kalimantan Barat
West Kalimantan Power Grid Strengthening Project
Semi-Annual Environmental Monitoring Report
July to December 2019
ADB Loan No. 3015-INO
AFD Loan No. CID102401B
Submitted by:
PT PLN (Persero)
January 2020
ii
ABBREVIATIONS
ADB - Asian Development Bank
AFD - Agence Française de Développment
EHS - Environmental Health and Safety
EMF - Electromagnetic Fields
EMP - Environmental Management Plan
HIV/AIDS - Human Immunodeficiency Virus/Acquired Immune Deficiency Syndrome
HVTL High Voltage Transmission Line
IEE - Initial Environmental Examination
SS - Substation
TL - Transmission Line
UPP KBB - PT PLN (Persero) Unit Pelaksana Proyek Kalimantan Bagian Barat (West of Kalimantan Region)
UIP KALBAGBAR
- PT PLN (Persero) Unit Induk Pembangunan Kalimantan Bagian Barat (West of Kalimantan Region)
UIP KALBAGTIM
PT PLN (Persero) Unit Induk Pembangunan Kalimantan Bagian Timur (East of Kalimantan Region)
OHSMS - Occupational Health and Safety Management System (known as Sistem Manajemen Keselamatan Kerja or SMK3 according to the requirement of Indonesian Government)
PIC - Project Implementation Consultant
PLN - PT Perusahaan Listrik Negara (Persero) is the state-owned electricity company
PMU Project Management Unit
ROW - Right of Way
UKL -UPL - Upaya Pengelolaan Lingkungan and Upaya Pemantauan Lingkungan (environmental management and monitoring effort document)
UP3B KALBAR
- Unit Pelaksana Penyaluran dan Pengaturan Beban (West of Kalimantan Region)
iii
Table of Contents
PT PLN (PERSERO) UIP KALBAGBAR .................................................................................... 1
ABBREVIATIONS ....................................................................................................................... ii
List of Tables ............................................................................................................................. iv
List of Appendices ....................................................................................................................... v
Chapter 1 Introduction ................................................................................................................ 1
Chapter 2 Summary of the Project’s Progress............................................................................ 3
Chapter 3 Environmental Mitigation Measures and Status ......................................................... 4
3.1 Package 1: Bengkayang-Jagoibabang Transmission Lines .......................................... 5
3.2 Package 2: Bengkayang Substation ............................................................................. 8
3.3 Package 3: Bengkayang-Ngabang-Tayan Transmission Lines ....................................11
3.4 Package 4: Ngabang and Phase 1 Extension of Tayan Substation .............................13
3.5 Package 5: Sanggau and Sekadau Substations, and Phase 2 Extension of Tayan
Substation ...................................................................................................................16
3.6 Packages 6 and 7: Tayan-Sanggau-Sekadau Transmission Lines ..............................25
Chapter 4 Environmental Monitoring Status ..............................................................................34
4.1 Package 1: Bengkayang-Jagoibabang Transmission Lines .........................................35
4.2 Package 2: Bengkayang Substation ............................................................................36
4.3 Package 3: Bengkayang-Ngabang-Tayan Transmission Lines ....................................37
4.4 Package 4: Ngabang Substation and Phase I Extension of Tayan Substation .............38
4.5 Package 5: Phase 2 Extension of Tayan Substation, and Sanggau and Sekadau
Substations .................................................................................................................39
4.6 Packages 6 and 7: Tayan-Sanggau and Sanggau-Sekadau Transmission Lines ........43
Chapter 5 Findings on EMP Implementation and Corrective Actions .........................................47
Chapter 6 ADB Mission Findings ..............................................................................................52
Chapter 7 Conclusions and Recommendations.........................................................................55
iv
List of Tables
Table 2.1 Summary of the Work Progress .................................................................................. 3
Table 3.1 Environmental Mitigation Status of Package 1 ............................................................ 5
Table 3.2 Environmental Mitigation Status of Package 2 ............................................................ 8
Table 3.3 Environmental Mitigation Status of Package 3 ...........................................................11
Table 3.4 Environmental Mitigation Status of Package 4 ...........................................................13
Table 3.5 Environmental Mitigation Status of Package 5 ...........................................................16
Table 3.6 Environmental Mitigation Status of Packages 6 and 7 ...............................................25
Table 4.1 Environmental Monitoring Status of Package 1 .........................................................35
Table 4.2 Environmental Monitoring Status of Package 2 .........................................................36
Table 4.3 Environmental Monitoring Status of Package 3 .........................................................37
Table 4.4 Environmental Monitoring Status Package 4 .............................................................38
Table 4.5 Environmental Monitoring Status of Package 5 .........................................................39
Table 4.6 Environmental Monitoring Status of package 6 and 7 ................................................43
Table 5.1 Findings on EMP Implementation and Required Corrective Actions ..........................48
Table 6.1 ADB Mission Findings ...............................................................................................52
v
List of Appendices
Appendix 1 Project Organization Chart
Appendix 2 Mitigation Implementations of 275 kV Bengkayang – Jagoibabang
Transmission Lines (Operation Phase)
Appendix 3 Mitigation Implementations of 275/150 kV Bengkayang Substation (Operation
Phase)
Appendix 4 Mitigation Implementations of 150 kV Bengkayang – Ngabang – Tayan
Transmission Lines (Operation Phase)
Appendix 5 Mitigation Implementations of 150/20 kV Ngabang Substation and Tayan
Extension Substation (Operation Phase)
Appendix 6 Mitigation Implementations of 150/20 kV Tayan Extension, Sanggau, and
Sekadau Substations (Construction Phase)
Appendix 7 Mitigation Implementations of 150 kV Tayan – Sanggau and Sanggau –
Sekadau Transmission Lines (Construction Phase)
Appendix 8 Monitoring Results
Appendix 9 Mission Findings Evidence
1
Chapter 1 Introduction
Project Background. The Government of the Republic of Indonesia has signed the loan
agreements with the Asian Development Bank (ADB) and the Agence Française de
Développement (AFD) to provide funding required by PT Perusahaan Listrik Negara (Persero)
for the West Kalimantan Power Grid Strengthening Project (“the project”). The project primarily
includes construction of power transmission lines and substations, and expansion of existing
substations as shown in Map 1.
The project covers the following construction packages:
Package 1: 82-km long (estimate) of 275 kV power transmission line from Bengkayang to
Jagoibabang (the border with Sarawak, Malaysia);
Package 2: 275/150 kV Bengkayang substation;
Package 3: 150 kV power transmission line from Bengkayang to Ngabang (estimated 92-km
long), and from Ngabang to Tayan (estimated 53-km long);
Package 4: 150/20 kV Ngabang substation and 1st extension of Tayan substation;
Package 5: 150/20 kV Sanggau and Sekadau substations and 2nd extension of Tayan
substation;
Package 6: 71-km long (estimate) of 150/20 kV power transmission line from Tayan to
Sanggau; and
Package 7: 48-km long (estimate) of 150/20 kV power transmission line from Sanggau to
Sekadau.
Scope of this Monitoring Report. Pusat Manajemen Konstruksi (PUSMANKON), as the
construction management unit of PT Perusahaan Listrik Negara, or PLN (Persero), has been
conducting project supervision including environmental, health and safety (EHS) monitoring of
the project since August 2017, replacing the joint venture of Tractebel Engineering Ltd. and
Power Grid International Limited (Thailand). Since then, PUSMANKON as the Project
Implementation Consultant (PIC) has also been producing the semi-annual environmental
monitoring reports (SAEMR) for the implementation of the project’s Environmental Management
Plan (EMP). Since September 2018, the name of PUSMANKON has been changed to Pusat
Manajemen Proyek (PUSMANPRO).
The implementation of EMP associated with the project is managed by PLN Headquarters, as
the Project Management Unit (PMU). The PMU is supported by Project Implementation Unit. PT
PLN (Persero) UIP KALBAGTIM, for Packages 1 and 2, is located in Balikpapan (East
Kalimantan) and PT PLN (Persero) UIP KALBAGBAR is located in Pontianak (West
Kalimantan) for Packages 3 to 7, in which the working areas are divided as such: Environmental
and OSH supervision is controlled by PLN UPP KBB 3 located in Singkawang (West
Kalimantan) for Packages 3 and 4; and UPP KBB 2 located in Sintang (West Kalimantan) for
Packages 5, 6 and 7. The project’s organization charts including EHS responsibilities is presented in Appendix 1.
This SAEMR includes description/elaboration of the following aspects:
Chapter 2 Summary of the project’s progress for the reporting period; Chapter 3 Environmental mitigation measures and status;
2
Map 1 PLN Power Grid Strengthening Project in West Kalimantan
Source: PT PLN (Persero)
81.3 km
95.6 km
46.8 km
77.58 km 46.7 km
275/150 kV Bengkayang SS
150/20 kV Ngabang SS
150/20 kV Sanggau SS
150/20 kV Sekadau SS
WEST KALIMANTAN, INDONESIA
MALAYSIA
Jagoibabang
150/20 kV Tayan SS
3
Chapter 2 Summary of the Project’s Progress
The status and progress of the implementation of West Kalimantan Power Grid Strengthening
Project for July - December 2019 period is summarized in Table 2.1. The project activities
conducted in this period included operation of transmission lines and substations for Packages
1, 2, 3, and 4; foundation, equipment installation and control panel building works for substation
under Package 5; and foundation, tower erection, and stringing work of transmission lines under
Packages 6 and 7.
Table 2.1 Summary of the Work Progress (as of December 2019)
Project Packages Status Responsible Party
Package 1: 275 kV Bengkayang –
Jagoibabang Power Transmission
Lines
Operation since May 31, 2016 UP3B KALBAR (Power
Dispatch Unit)
Package 2: 275/150 kV
Bengkayang Substation
Operation since November 1, 2017 UP3B KALBAR (Power
Dispatch Unit)
Package 3: 150 kV Bengkayang -
Ngabang – Tayan Power
Transmission Lines
Operation since May 28, 2018 UP3B KALBAR (Power
Dispatch Unit)
Package 4: 150/20 kV Ngabang
Substation and 1st Extension of
Tayan Substation
Operation since September 10,
2018
UP3B KALBAR (Power
Dispatch Unit)
Package 5: 150/20 kV Sanggau
and Sekadau Substations and 2nd
extension of Tayan substation
Under construction –
commissioning of the extended
Tayan substation; foundation work,
installation of the equipment at the
switchyard and control panel
building. The overall progress was
83.51%.
PT Siemens Indonesia and
Siemens Malaysia Bhd
(Contractor) supervised by
UIP KALBAGBAR (Project
Implementation Unit)
Package 6: 150/20 kV Tayan –
Sanggau Power Transmission Line
Under construction – tower
foundation and erection including
stringing of transmission lines. The
overall progress was 83.94%.
PT Krakatau Engineering
and PT Citramas Heavy
Industries (Contractors)
supervised by UIP
KALBAGBAR (Project
Implementation Unit) Package 7: 150/20 kV Sanggau –
Sekadau Power Transmission Line
Under construction – tower
foundation and erection. The
overall progress was 69.63%.
4
Chapter 3 Environmental Mitigation Measures and Status
This chapter elaborates the mitigation measures implemented for the project’s activities and its
compliance status with the requirements of the environmental management plan (EMP) for the
period of July to December 2019.
The requirements of the environmental mitigation measures for Packages 1 to 4 (i.e. power
transmission lines from Bengkayang to Tayan and the associated substations) are defined in
the EMP of the project’s Initial Environmental Examination or IEE (2011) The mitigation measures implemented for Packages 1 to 4 are those for the operation of corresponding
transmission lines and substations are reported in sub-chapters 3.1 to 3.4.
In addition, the EMP of project’s IEE (2016) applies for the construction of: 150 kV Sanggau and
Sekadau substations and 2nd extension of Tayan substation (Package 5), 150 kV Tayan –
Sanggau power transmission lines (Package 6), and Sanggau – Sekadau power transmission
line (Package 7). Therefore, the environmental mitigation defined in Construction Phase section
of Table 28 Environmental Management Plan of the IEE should be conducted. The mitigation
measures implemented by the project for Packages 5 to 7 including its compliance status are
reported in sub-chapters 3.5 to 3.6.
5
3.1 Package 1: Bengkayang – Jagoibabang Transmission Lines
The transmission lines from Bengkayang to Jagoibabang have been in operation since May 2016 and UP3B KALBAR oversees this
operation. Table 3.1 describes the mitigation measures implemented by the project for the operation of the transmission lines, including
its compliance status against the mitigation requirements defined in the IEE (2011). Some requirements defined in this table are
intended for the mitigation of impacts due to substation operation and, therefore not applicable for that of the transmission lines.
Table 3.1 Environmental Mitigation Status of Package 1
No Potential Impacts / Mitigation Requirements Mitigation Implemented Compliance Status / Remarks
1 Electric and Magnetic Fields/EMF (HVTL alignment)
Monitor to ensure EMF are within national and international
standards/guidelines
The status of EMF monitoring is discussed in the
environmental monitoring chapter of this report.
The mitigation implemented with
this regard is in compliant with its
requirement.
2 Noise (substation)
The mitigation requirements for noise impacts are intended for substation operations, and therefore not applicable for
those of the transmission lines reported in this table.
Not applicable.
3 Soil and Water Contamination (substation)
The mitigation requirements for soil/water contamination impact are intended for substation operations, and therefore
not applicable for those of the transmission lines reported in this table.
Not applicable.
4 Vegetation Management (HVTL alignment, RoW)
Vegetation removal will only be allowed within the
designated width of the RoW and to achieve the required
clearances.
Tree removal and trimming will only be undertaken by
hand tools, including chain saws.
There was no vegetation removal conducted, and
therefore these mitigation requirements were not
applicable for the reporting period.
Not applicable.
The use of herbicides will be strictly prohibited. This requirement is on process with UP3B KALBAR and
the results will be reported in S1/2020.
Not compliant – due to the
absence of documentation with
this regard.
5. Restriction on Development in RoW (HVTL alignment, RoW)
Payment of compensation to affected people during the
LARP processes.
Implementation of this mitigation requirement is
reported separately in the social monitoring report
submitted to ADB.
Not applicable.
6
No Potential Impacts / Mitigation Requirements Mitigation Implemented Compliance Status / Remarks
6. Fragmentation of Land Use (HVTL alignment)
Siting HVTL alignment is sited so as to avoid, as far as
practicable, such fragmentation by following existing roads
and boundaries and avoiding cutting across individual land
use plots.
The Bengkayang – Jagoibabang transmission lines
have been in operation since 2016, and therefore this
mitigation requirement is no longer applicable.
Not applicable.
7. Increased Access (HVTL alignment)
No permanent access roads to RoW.
Any temporary access roads to be decommissioned and
restored to natural conditions once construction has been
completed.
The access roads have been naturally and overgrown
with local vegetation, following completion of the tower
construction (as shown in Appendix 2.a), except for the
existing road.
The mitigation implemented with
this regard is in compliant with its
requirement.
8. Health and Safety (HVTL alignment, substation)
Operation phase occupational health & safety (OHS) and
community health & safety (CHS) plans developed.
The procedures for the operation phase of substation
have been established in the OHSMS PLN’s West Kalimantan Dispatch Unit (No.SMK3/AP2B/U/P/16
dated on June 21, 2017), covering, among others:
- Emergency response procedures;
- Conductor transfer on tower emergency;
- Taking unwanted objects on High Voltage and
Extra High Voltage Transmission Lines;
- Handling and storage of hazardous materials
In the UP3B Kalbar’s Maintenance Procedure, the
community health and safety was added to point 5.7
which refer to PERDIR No. 0252.P/DIR/2016 about
general safety guidelines (as shown in Appendix
2.b).
The mitigation implemented with
this regard is in compliant with its
requirement.
Towers to be fitted with anti-climbing devices and
substations will have security fence and full-time security
fence and full-time security personnel on site.
Each transmission tower has been installed with anti-
climbing device and lock nut (as shown in Appendix
2.b).
The mitigation implemented with
this regard is compliant with its
corresponding requirements.
Substations to be equipped with fire suppression systems
and, as noted above, emergency response plans to be
developed.
These mitigation requirements are intended for
substation operations, and therefore do not apply for the
operation of transmission lines reported in this table.
Not applicable.
9. Avian Collisions (HVTL alignment)
Monitoring will include asking local people and
maintenance personnel to report occurrences of dead
birds or other dead animals under the line.
The HSE supervisor (PIC) conducted interviews with
the community around selected locations of
transmission towers, and the results suggested that no
The mitigation implemented with
this regard is compliant with its
requirements.
7
No Potential Impacts / Mitigation Requirements Mitigation Implemented Compliance Status / Remarks
dead birds and animals were observed.
Related evidence of this activity is shown in Appendix
2.c.
If a location is to be identified with frequent occurrence,
then action will be taken e.g., installing line markers to
reduce the incidence.
Due to the above circumstances, installing the line
markers has not been conducted and unnecessary.
Not applicable.
8
3.2 Package 2: Bengkayang Substation
The Bengkayang substation has been operation since December 2015 and UP3B KALBAR in charge of this operation. Table 3.2
describes the corresponding mitigation measures implemented by the project including its compliance status against the mitigation
requirements defined in the IEE (2011). Some requirements defined in this table are intended for the mitigation of impacts due to
operation of the transmission line and, therefore not applicable for that of the substation.
Table 3.2 Environmental Mitigation Status of Package 2
No Potential Impacts / Mitigation Requirements Mitigation Implemented Compliance Status / Remarks
1. Electric and Magnetic Fields/EMF (HVTL alignment, substation)
Monitor to ensure EMF are within national and
international standards/guidelines
The status of EMF monitoring is discussed in the
environmental monitoring chapter of this report.
The mitigation implemented with this
regard is in compliant with its
requirement.
2. Noise (Substation)
High noise operations enclosed in noise-proofed
building that effectively contain the noise.
The Bengkayang substation does not generate high
noise operation. Further, the substation site is not close
to residential areas and schools. (The related noise
monitoring result is presented in Appendix 3.a.)
The mitigation implemented with this
regard is compliant with its
requirement.
3. Soil and Water Contamination (Substations)
Transformers and equipment selected will meet
international standards and will be routinely
maintained.
The transformer and equipment selected for the
substation meets the 1999 International Electrical
Community (IEC) Standard 60076 1 and 2. Further, the
transformer is routinely maintained following the Decree
of PLN Director No. 0520-2.K/DIR/2014 on Transformer
Maintenance.
The mitigation implemented with this
regard is compliant with its
requirement.
PCB will not be used in transformers and other
electrical equipment
According to PLN letter No. 0203
Facs./KLH.01.01/DIVK3L/2018 (dated on April 30,
2018) on Persyaratan Pengadaan Material/Peralatan
(Trafo, Kapasitor, Minyak Trafo) Bebas PCBs, the
transformer procurement process owned by PLN must
be free from PCB.
The mitigation implemented with this
regard is compliant with its
requirement.
Areas around substation transformers and areas
where oils, fuels, and hazardous wastes are stored
will be encased in an impervious bund capable of
holding 150% of those in that area.
Discharge from these bunds and other areas with
the potential to be oil contaminated will be directed
The 275 kV transformers at Bengkayang substation
is equipped with oil pit structure made of concrete.
Construction of the oil pit refers to PLN Standard
SPLN T5.009: 2015 (dated on May 13, 2016) - sub-
chapter 6.2.3 Fire Control. The oil pit can
accommodate approximately 70% of oil transformer
The mitigation implemented with this
regard is compliant with its
requirement.
9
No Potential Impacts / Mitigation Requirements Mitigation Implemented Compliance Status / Remarks
to oil-water separators.
Any oil contaminated material will be disposed of at
a proper waste disposal approved as required by
authorities.
An emergency spill response plan will be
established, and staff will be trained on spill
response procedures.
when spilled (as shown in Appendix 3.b).
At the time of substation operation there was no oil
spill from the transformer was observed.
The training for operator of the substation related to
oil spill response procedures was conducted in 19
December 2019 (as shown in Appendix 3.b)
4. Vegetation Management (HVTL alignment, ROW)
The mitigation requirements defined herein are intended for the operation of transmission lines, and therefore it is
not applicable for the operation of substation reported in this table.
Not applicable.
5. Restriction on Development in RoW (HVTL alignment, ROW)
Payment of compensation to affected people during the
LARP processes.
Implementation of this mitigation requirement is
reported separately in the social monitoring report
submitted to ADB.
Not applicable.
6. Fragmentation of Land Use (HVTL alignment, ROW)
The mitigation requirements defined herein are intended for the operation of transmission lines, and therefore not
applicable for the operation of substation reported in this table.
Not applicable.
7. Increased Access (HVTL alignment)
The mitigation requirements defined herein are intended for the operation of transmission lines, and therefore not
applicable for the operation of substation reported in this table.
Not applicable.
8. Health and Safety (HVTL alignment, Substations)
Operation phase occupational health & safety (OHS)
and community health & safety (CHS) plans
developed.
The procedures for the operation phase of substation
have been established in the OHSMS PLN’s West Kalimantan Dispatch Unit (No.SMK3/AP2B/U/P/16
dated on June 21, 2017), covering, among others:
- Emergency response procedures;
- Conductor transfer on tower emergency;
- Taking unwanted objects on High Voltage and
Extra High Voltage Transmission Lines;
- Handling and storage of hazardous materials
In the UP3B Kalbar’s Maintenance Procedure, the community health and safety was added to point 5.7
which refer to PERDIR No. 0252.P/DIR/2016 about
general safety guidelines (as shown earlier in
Appendix 2.b).
The mitigation implemented with this
regard is in compliant with its
requirement.
10
No Potential Impacts / Mitigation Requirements Mitigation Implemented Compliance Status / Remarks
Towers to be fitted with anti-climbing devices and
substations will have security fence and full-time
security personnel on site.
Bengkayang substation has been completed with
security fence and full-time security personnel on site
(as shown in Appendix 3.c).
The mitigation implemented with this
regard is compliant with its
requirements.
Substations to be equipped with fire suppression
systems and emergency response plans.
Bengkayang Substation has been provided with fire
extinguisher and emergency response procedures (as
shown in Appendix 3.c).
The mitigation implemented with this
regard is compliant with its
requirements.
9. Avian Collisions (HVTL alignments)
The mitigation requirements for avian collision impact are intended for the operation of transmission lines, and
therefore not applicable for the operation of substation reported in this table.
Not applicable.
11
3.3 Package 3: Bengkayang – Ngabang – Tayan Transmission Lines
The Bengkayang – Ngabang – Tayan transmission lines has been in the operation phase since May 2018 and UP3B KALBAR is in
charge of this. Table 3.3 describes the mitigation measures implemented by the project for the operation activity, including its
compliance status against the mitigation requirements defined in the IEE (2011). Some requirements defined in this table are intended
for the mitigation of impacts due to substation operation and, therefore not applicable for those of the transmission lines.
Table 3.3 Environmental Mitigation Status of Package 3
No Potential Impacts / Mitigation Requirements Mitigation Implemented Compliance Status / Remarks
1 Electric and Magnetic Fields/EMF (HVTL alignment)
Monitor to ensure EMF are within national and international
standards/guidelines
The status of EMF monitoring is discussed in the
environmental monitoring chapter of this report.
Not applicable.
2 Noise (substation)
The mitigation requirements defined herein are intended for the operation of substation, and therefore not applicable for
the operation of transmission line reported in this table.
Not applicable.
3 Soil and Water Contamination (substation)
The mitigation requirements defined herein are intended for the operation of substation, and therefore not applicable for
the operation of transmission line reported in this table.
Not applicable.
4 Vegetation Management (HVTL alignment, RoW)
Vegetation removal will only be allowed within the
designated width of the RoW and to achieve the required
clearances.
Tree removal and trimming will only be undertaken by
hand tools, including chain saws.
There was no vegetation removal conducted, and
therefore these mitigation requirements were not
applicable for the reporting period.
Not applicable.
The use of herbicides will be strictly prohibited. This requirement is on process with UP3B KALBAR and
the results will be reported in S1/2020.
The absence of required
document is not compliant with
the mitigation requirement.
5. Restriction on Development in RoW (HVTL alignment, RoW)
Payment of compensation to affected people during the
LARP processes.
Implementation of this mitigation requirement is
reported separately in the social monitoring report.
Not applicable.
6. Fragmentation of Land Use (HVTL alignment)
Siting HVTL alignment is sited so as to avoid, as far as
practicable, such fragmentation by following existing roads
and boundaries and avoiding cutting across individual land
use plots.
The Bengkayang – Ngabang – Tayan transmission lines
have been in operation since May 2018, and therefore
this mitigation requirement is no longer applicable.
Not applicable.
12
No Potential Impacts / Mitigation Requirements Mitigation Implemented Compliance Status / Remarks
7. Increased Access (HVTL alignment)
No permanent access roads to RoW.
Any temporary access roads to be decommissioned and
restored to natural conditions once construction has been
completed.
There was no permanent access road to the RoW of the
transmission lines. The temporary access road has
been naturally and gradually overgrown with local
vegetation following completion of the tower
construction (as shown in Appendix 4.a).
The mitigation implemented with
this regard is in compliant with its
requirements.
8. Health and Safety (HVTL alignment, substation)
Operation phase occupational health & safety (OHS) and
community health & safety (CHS) plans developed.
The procedures for the operation phase of substation
have been established in the OHSMS PLN’s West Kalimantan Dispatch Unit (No.SMK3/AP2B/U/P/16
dated on June 21, 2017), covering, among others:
- Emergency response procedures;
- Conductor transfer on tower emergency;
- Taking unwanted objects on High Voltage and
Extra High Voltage Transmission Lines;
- Handling and storage of hazardous materials
In the UP3B Kalbar’s Maintenance Procedure, the
community health and safety was added to point 5.7
which refer to PERDIR No. 0252.P/DIR/2016 about
general safety guidelines (as shown earlier in
Appendix 2.b).
The mitigation implemented with
this regard is in compliant with its
requirement.
Towers to be fitted with anti-climbing devices and
substations will have security fence and full-time security
fence and full-time security personnel on site.
Each transmission tower has been installed with anti-
climbing device and lock nut (as shown in Appendix
4.b).
The mitigation implemented with
this regard is compliant with its
corresponding requirements.
Substations to be equipped with fire suppression systems
and, as noted above, emergency response plans to be
developed.
These mitigation requirements are intended for
substation operations, and therefore do not apply for the
operation of transmission lines reported in this table.
Not applicable.
9. Avian Collisions (HVTL alignment)
Monitoring will include asking local people and
maintenance personnel to report occurrences of dead
birds or other dead animals under the line.
The HSE supervisor (PIC) conducted interviews with
the community around selected locations of
transmission towers, and the results suggested that no
dead birds and animals were observed. Related
evidence of this activity is shown in Appendix 4.c.
The mitigation implemented with
this regard is compliant with its
requirements.
If a location is to be identified with frequent occurrence,
then action such as installing line markers to reduce the
incidence.
Due to the above circumstances, installing the line
markers has not been conducted and unnecessary.
Not applicable.
13
3.4 Package 4: Ngabang and Phase 1 Extension of Tayan Substation
The Ngabang substation and the phase 1 extension Tayan substation have been in operation since October 2018 and under the
responsibility of UP3B KALBAR. Table 3.4 describes the mitigation measures implemented by the Project for the operation of these
substations, including its compliance status against the mitigation requirements defined in the IEE (2011). Some requirements defined in
this table are intended for the mitigation of impacts due to operation of the transmission line and, therefore it is not applicable for
mitigating the impacts due to the operation of substation.
Table 3.4 Environmental Mitigation Status of Package 4
No Potential Impacts / Mitigation Requirements Mitigation Implemented Compliance Status / Remarks
1. Electric and Magnetic Fields/EMF (HVTL alignment, substation)
Monitor to ensure EMF are within national and
international standards/guidelines
The status of EMF monitoring is discussed in the
environmental monitoring chapter of this report.
The mitigation implemented with this
regard is in compliant with its
requirement.
2. Noise (Substation)
High noise operations enclosed in noise-proofed
building that effectively contain the noise.
The operation of Ngabang substation does not generate
high noise levels. Further, the nearest residential area
is about 500 m from the substation. (The noise
monitoring result within the substation is presented in
Appendix 5.a).
The mitigation implemented with this
regard is compliant with its
requirement.
3. Soil and Water Contamination (Substations)
Transformers and equipment selected will meet
international standards and will be routinely
maintained.
The transformer and equipment selected for the
substation meets the 1999 International Electrical
Community (IEC) Standard 60076 1 and 2. Further, the
transformer is routinely maintained following the Decree
of PLN Director No. 0520-2.K/DIR/2014 on Transformer
Maintenance.
The mitigation implemented with this
regard is compliant with its
requirements.
PCB will not be used in transformers and other
electrical equipment.
According to PLN letter No. 0203
Facs./KLH.01.01/DIVK3L/2018 (dated on April 30,
2018) on Persyaratan Pengadaan Material/Peralatan
(Trafo, Kapasitor, Minyak Trafo) Bebas PCBs. In the
transformer procurement process that owned by PLN
must be free from PCB.
The mitigation implemented with this
regard is compliant with its
requirement.
Areas around substation transformers and areas
where oils, fuels, and hazardous wastes are stored
will be encased in an impervious bund capable of
The transformers at Ngabang and Tayan substation
(1st extension) is equipped with oil pit structure made
of concrete. Construction of the oil pit refers to PLN
Standard SPLN T5.009: 2015 (dated on May 13,
The mitigation implemented with this
regard is compliant with its
requirement.
14
No Potential Impacts / Mitigation Requirements Mitigation Implemented Compliance Status / Remarks
holding 150% of oils, fuels, and hazardous wastes in
that area.
Discharge from these bunds and other areas with
the potential to be oil contaminated will be directed
to oil-water separators.
Any oil contaminated material will be disposed of at
a proper waste disposal approved as required by
authorities.
An emergency spill response plan will be
established, and staff will be trained on spill
response procedures.
2016) - sub-chapter 6.2.3 Fire Control. The oil pit is
able to accommodate approx. 110% of oil
transformer volume in the event of spill.
At the time of the inspection, there was no oil spill
from the transformer.
Nine drums (~1,800 liters) of used oil were stored on
concrete floor surrounded by drainage system
connected to a sump pit. The lids of the drums were
corroded. These drums transported to Singkawang
substation according to material handling and
storage procedures point 6.8 (as shown in Appendix
5.b).
The training for operator of the substation related to
oil spill response procedures was conducted in 19
December 2019 (as shown in Appendix 3.b)
4. Vegetation Management (HVTL alignment, ROW)
The mitigation requirements defined for vegetation management impact are intended for the operation of
transmission lines, and therefore not applicable for the operation of substations reported in this table.
Not applicable.
5. Restriction on Development in RoW (HVTL alignment, ROW)
Payment of compensation to affected people during the
LARP processes.
Implementation of this mitigation requirement is
reported separately in the social monitoring report
submitted to ADB.
Not applicable.
6. Fragmentation of Land Use (HVTL alignment, ROW)
The mitigation requirements for impact on land use fragmentation are intended for the operation of transmission
lines, and therefore not applicable for the operation of substation reported in this table.
Not applicable.
7. Increased Access (HVTL alignment)
The mitigation requirements for impact on increased land access are intended for the operation of transmission
lines, and therefore not applicable for the operation of substation reported in this table.
Not applicable.
8. Health and Safety (HVTL alignment, Substations)
Operation phase occupational health & safety (OHS)
and community health & safety (CHS) plans
developed.
The procedures for the operation phase of substation
have been established in the OHSMS PLN’s West Kalimantan Dispatch Unit (No.SMK3/AP2B/U/P/16
dated on June 21, 2017), covering, among others:
- Emergency response procedures;
- Conductor transfer on tower emergency;
- Taking unwanted objects on High Voltage and
The mitigation implemented with this
regard is in compliant with its
requirement.
15
No Potential Impacts / Mitigation Requirements Mitigation Implemented Compliance Status / Remarks
Extra High Voltage Transmission Lines;
- Handling and storage of hazardous materials
In the UP3B Kalbar’s Maintenance Procedure, the community health and safety was added to point 5.7
which refer to PERDIR No. 0252.P/DIR/2016 about
general safety guidelines (as shown earlier in
Appendix 2.b).
Towers to be fitted with anti-climbing devices and
substations will have security fence and full-time
time security personnel on site.
Ngabang substation has been completed with security
fence and full-time security personnel on site (as shown
in Appendix 5.c).
The mitigation implemented with this
regard is compliant with its
requirement.
Substations to be equipped with fire suppression
systems and emergency response plans.
Ngabang Substation has been provided with fire
extinguisher. The emergency response plan was
included in the OHSMS procedure No.
SMK3/AP2B/U/IK/10.01 (dated 21 June 2017) on Fire
Work Instruction (as shown in Appendix 5.c).
The mitigation implemented with this
regard is compliant with its
requirement.
9. Avian Collisions (HVTL alignments)
The mitigation requirements for avian collision impact are intended for the operation of transmission lines, and
therefore not applicable for the operation of substation reported in this table.
Not applicable.
16
3.5 Package 5: Sanggau and Sekadau Substations, and Phase 2 Extension of Tayan Substation
As of the end of December 2019, the construction of Sanggau and Sekadau substations was progressing, and 2nd extension of Tayan
substation was nearly complete. The overall progress of 83.51% was reported in this reporting period for Package 5. UIP KALBAGBAR
is responsible for the development of these substations. Table 3.5 describes the mitigation measures implemented for the construction
activities of this package including its compliance status against the mitigation requirements defined in the IEE (2016).
Table 3.5 Environmental Mitigation Status of Package 5
No Potential Impacts / Mitigation Requirements
as per IEE (2016) Mitigation Implemented Compliance Status / Remarks
1. Vegetation Clearing
Vegetation clearing will be conducted with the
combination of cutting trees with hand and
chainsaw, while the stump removal will be
conducted by bulldozer.
Local people will be allowed access to cleared
vegetation.
Burning of cleared vegetation will not be allowed;
instead this material will be used to protect the soil
from erosion, particularly in steeper slope areas,
until permanent measures are in place.
Vegetation clearing for the substation site has been
completed, and therefore these mitigation
requirements are no longer applicable.
Not applicable.
The use of herbicides will be strictly prohibited. At each construction site the warning sign and the
awareness about the prohibition of herbicide use was
delivered by the contractor in the toolbox meeting.
Relevant evidence is included in Appendix 6.a.
The mitigation implemented with this
regard is compliant with its
requirement.
2. Soil Erosion
Compaction the soil will be conducted in the
embankment areas, and re-vegetated with local
grasses, and covered with protecting layers of rice
straw or similar material to guard against rapid gully
and rill erosion.
The soil compaction was already conducted based on
specification in the acknowledgement of work
inspection No. 013/BAPP/SKDU/VIII/2018 dated 31
August 2018 as shown in Appendix 6.b.
The mitigation implemented with this
regard is compliant with its
requirement.
Construction of slope protection (e.g. retaining wall,
gabions etc.) and planting of vegetation strips
shrubs and grasses across contours of exposed
slopes.
In the second semester of 2019, there was no
construction in the slope area. The retaining wall design
is under approval by PLN UPP 2 Sintang.
Not applicable.
Under the outdoor equipment there will be deployed
gravel over the land; the unused open area will be
The gravel over the land will be deployed after civil
works in the switchyard area finished. The mitigation is
Not applicable.
17
No Potential Impacts / Mitigation Requirements
as per IEE (2016) Mitigation Implemented Compliance Status / Remarks
covered with grass and small plants. not yet applicable for this period.
The soil erosion control measures will be regularly
inspected and maintained during construction and
until the area is stabilized or re-vegetated.
Soil erosion control have been carried out and
monitored regularly during this construction period.
The implementation of soil erosion control measure
has been reported in the HSE quarterly report. The
checklist related to this mitigation is shown in
Appendix 6.b.
The mitigation implemented with this
regard is compliant with its
requirements.
3. Drainage
Site drainage plans will be developed in accordance
with good drainage practices management for each
substation, including constructing above flood levels
and ensuring drainage around the site is provided for
high storm flows.
The contractor has submitted the site drainage
plan/drawing of Sanggau substation, and this
drawing has been approved by PLN on 5 September
2018. The drawing/plan for Sekadau substation can
be seen in Appendix 6.c.
The site drainage at Sanggau and Sekadau
substations was still under construction for the
reporting period (as shown in Appendix 6.c).
Construction of the perimeter drainage at Tayan
substation has been completed.
The mitigation implemented with this
regard is compliant with its
requirements.
4. Water Quality Impacts
To protect water quality from spillage of oil, fuel
and other hazardous materials, good international
practices will be adopted, including:
These mate rials will be stored in designated
areas with temporary impermeable bunds in
accordance with international standards and at
distance of at least 100 m from any water course.
Refueling of machinery, equipment and vehicles
will be undertaken at distance of at least 100 m
from any water course.
Oil changing and engine maintenance will be done
in designated areas at distance of at least 100 m
from any water course with containment to prevent
any oil spills washing.
Waste oil shall be collected and taken away for
recycling.
Fuel, oil and hazardous materials and wastes were
stored in the temporary storage with some
segregation at the contractor’s warehouse. Refueling of vehicles was undertaken at the public
fuel station.
Oil changing was conducted on site, and to prevent
the potential for oil to be spilled, the oil was flowed
through the hose and protected using basic
containment underneath.
Relevant evidences related to the above
descriptions are shown in Appendix 6.d.
The sub-contractor which is PT Suberindo Sukses
Sarana will take over the used oil from oil
changing.
The mitigation implemented with this
regard is compliant with its
requirements.
18
No Potential Impacts / Mitigation Requirements
as per IEE (2016) Mitigation Implemented Compliance Status / Remarks
Oil contaminated material shall be disposed at
designated waste disposal facilities.
Herbicides will not be used in the project. Prohibition of using herbicides has been implemented.
On each construction site, the warning sign has been
made and the awareness on this matter was delivered
during toolbox meeting for workers. Related evidence is
shown earlier in Appendix 6.a.
The mitigation implemented with this
regard is compliant with its
requirement.
5. Air Quality Impacts
Spray the dusty soil within substation construction
area with water
The contractor sprayed the construction site using
water periodically or when the dust level considered
high. Related evidence is shown in Appendix 6.e.
The mitigation implemented with this
regard is compliant with its
requirement.
Accumulated soil and debris should be cleaned
from adjacent asphalt roads in the entrance of
substation.
During this reporting period, there was no import soil
conducted by the contractor. Usually, contractor’s load truck closed using tarpaulin to prevent the soil to spill.
Not applicable.
Truckloads with dusty soil should be covered,
except for on-site or local trips.
During this reporting period, there was no requirement
to transport soil from/to Sanggau and Sekadau
substation sites. Therefore, this migration requirement
is no longer applicable.
Not applicable.
Cut and fill should be balanced to the maximum
extent possible at each site in order to minimize
the need for fill and spoil disposal.
In the Sanggau SS, based on the engineering
calculation of cut and fill, it needed to fill from other
quarries. The relevant evidence had been reported in
the previous semester. In the meantime, cut material in
Sekadau SS has been used for fill material, and this
eliminates the need for spoil disposal.
The mitigation implemented with this
regard is compliant with its
requirement.
Construction waste and garbage burning are
prohibited.
The contractor has provided the warning sign that the
burning of cleared vegetation and waste is prohibited
during this project. The awareness about the prohibition
of burning vegetation and waste was delivered by the
contractor in the toolbox meeting. Relevant evidence
related to the above descriptions can be seen in
Appendix 6.a.
The mitigation implemented with this
regard is compliant with its
requirement.
6. Construction Waste Management
Solid wastes generated from construction
activities should not be haphazardly left around
The contactor provided separate trash bins for
organic and non-organic wastes, placed at
The mitigation implemented with this
regard is compliant with its
19
No Potential Impacts / Mitigation Requirements
as per IEE (2016) Mitigation Implemented Compliance Status / Remarks
construction sites.
Construction waste will be contained in a
designated area on each site (tower site,
substation).
Wastes will be routinely collected and disposed of
at safe waste disposal facilities indicated by the
District Environmental agencies
Construction waste burning is prohibited.
designed areas within the construction site. Trash
bins that have been full of construction waste on
regular basis have been disposed to the Sei Kosak
waste disposal site (near Sanggau substation) and
Sekadau waste disposal site (near Sekadau
substation). Supporting documents related to this
mitigation are shown in Appendix 6.f.
The contractor has provided the warning sign that
the burning of waste is prohibited during this
project. The awareness about the prohibition of
burning vegetation and waste is delivered by the
contractor in the toolbox meeting. Supporting
documents related to Relevant evidence related to
this mitigation are included in Appendix 6.a.
requirements.
7. Domestic Waste Management
Temporary worker camps will be required to be
provided with appropriate sanitation facilities,
including water supply, and washing facilities,
temporary toilets, and waste containers.
The contractors for the Tayan, Sanggau, and Sekadau
substations rented houses from the local community for
its employees. The houses are equipped with adequate
water supply (obtained from groundwater), washing and
toilet facilities, and trash bins. Related evidence is
shown in Appendix 6.g.
The mitigation implemented with this
regard is compliant with its
requirement.
Domestic waste will be routinely collected and
disposed of at safe waste disposal facilities
Domestic wastes were collected in trash bags and
regularly disposed to Sei Kosak and Sanggau waste
disposal sites as described earlier.
Garbage burning is prohibited. The prohibition on garbage burning is the same as that
for construction waste described earlier.
8. Roads and Infrastructure Impacts
A mapping of the locations of expected heavy
equipment mobilization is needed versus
settlement area locations. This is to monitors the
potential damage to existing roads.
In this reporting period, there was no heavy
equipment mobilization.
Not applicable.
Any damaged infrastructure, after heavy
equipment mobilization, will be repaired to at least
the same standard and condition on completion of
the project.
As stated above, there was no heavy equipment
mobilization.
Not applicable.
20
No Potential Impacts / Mitigation Requirements
as per IEE (2016) Mitigation Implemented Compliance Status / Remarks
9. Encroachment into Protected Forests, Hunting, Wood Collection
Hunting extraction by workers of forest products
such as firewood, and keeping of firearms on the
project, will be prohibited.
The awareness on prohibition of hunting, wood
collection, and keeping firearms was delivered by the
contractor in the toolbox meeting. Relevant evidence
on this mitigation can be seen in Appendix 6.h.
The mitigation implemented with this
regard is compliant with its
requirement.
To avoid impact on ecological valuable sites,
habitats, natural forest, flora and fauna, this risk
should be particularly be monitored along the
ecologically sensitive alignments of the
transmission line:
along the 35 km between Tayan and Sosok
where the alignment passes close by
secondary/production forest reserves; and
along the alignment which runs close (3.5. and
11 km) to the primary forest within Gunung
Tiong Kandang and Gunung Sanggau; and
along the alignment which passes close (1.5-
km distant) to the primary forests of the ‘Pancur Aji’ Forest Recreation Reserve.
The sites of the Tayan, Sanggau, and Sekadau
substations are not located in the forest area or close
to the sensitive areas mentioned earlier.
Nevertheless, the contractor has provided the signs
stating that hunting is prohibited in the project areas
and also awareness on this matter as described
earlier. Relevant evidence on this mitigation can be
seen in Appendix 6.h.
10. Impacts on Cultural Heritage Sites
The Project area falls closely adjacent several
notable heritage sites:
Although, it is unlikely to suffer impact from Project
due to separation distance (as a mitigation
measure for these sites), Project workers should
be made aware that these sites should not be
disturbed, or material extracted if visited.
Project construction traffic and heavy equipment
should also not be routed anywhere near these
sites to avoid vibration damage.
During this monitoring period, there was no cultural
heritage found. However, the contractor already
delivered awareness related to cultural heritage
during toolbox meeting for workers. The evidence
related to this mitigation can be seen in Appendix
6.i.
Not applicable.
The transmission line construction should also
take care not to make impact on the potential un-
mapped locally important cultural sites, such as
community sacred forest groves (hutan adat) and
sacred grave sites (tempat keramat). Consultation
should be conducted with local Traditional Leaders
To anticipate the existence of the potential un- mapped
locally important cultural sites, the contractor has
consulted on this matter with the customary head and
conducted the Ngudas event prior to the start of the
construction activities. The conduct of this event did
not indicate that such culturally important sites were
present within the construction site. The Ngudas event
Not applicable.
21
No Potential Impacts / Mitigation Requirements
as per IEE (2016) Mitigation Implemented Compliance Status / Remarks
(Temengung) for each indigenous ethnic group to
identify and avoid any such sites prior to
construction of all project works.
was no longer conducted in this reporting period.
11. Occupational Health and Safety
Prior to the commencement of civil works a
construction phase Occupational Health and Safety
Plan (OHSP) will be developed. The OHSP should:
identify and minimize, so far as reasonably
practicable, the causes of potential hazards to
workers, including communicable diseases and
vector borne diseases;
provide preventive and protective measures,
including modification, substitution, or elimination
of hazardous conditions, with attention to live
power lines, working at height, working during
thunderstorms (lightning strikes), EMFs, and
exposure to chemicals;
provide measures for the management and
appropriate disposal of B3 wastes;
provide the provision of appropriate personal
protective equipment (PPE) to minimize risks;
provide training for workers, and establish
appropriate incentives to use and comply with
health and safety procedures and utilize PPE;
include procedures for documenting and reporting
occupational accidents, diseases, and incidents;
include emergency prevention, preparedness, and
response arrangements in place.
PT Siemens as the contractor of Tayan, Sanggau
and Sekadau substations (Package 5) have
developed an environmental health & safety (EHS)
plan (covering OHS) that has been reviewed and
approved by PLN UPP 2 Sintang and
PUSMANPRO on 16 October 2018.
The Siemens’ EHS plan provides guidance and
procedures which are considered adequate for
mitigating environmental and OHS risks associated
with the construction of 150 kV substations.
PT Siemens has implemented the EHS plan by,
among others:
Providing safety induction to workers on OSH
rules and appropriate PPE to workers;
Submitting monthly reports including
documenting and reporting occupational
accidents, diseases, and incidents;
Conducting HIV/ AIDS awareness session for
workers; and
Establishing emergency response procedures
including provision of first-aid kits, fire
extinguishers, and emergency call lists at
construction sites
Relevant evidence of this event is included in
Appendix 6.j.
The mitigation implemented with this
regard is compliant with its
requirements.
22
No Potential Impacts / Mitigation Requirements
as per IEE (2016) Mitigation Implemented Compliance Status / Remarks
12. Community Health and Safety
Prior to the commencement of civil works a
construction phase Community Health and Safety
Plan (CHSP) will be developed. The CHSP should
include:
procedures to identify and minimize, so far as
reasonably practicable, the causes of potential
project related hazards to local communities,
including communicable diseases such as
HIV/AIDs and vector borne diseases;
specific emergency response procedures
relevant emergency equipment.
protocols for emergency vehicle services; and
put safety sign.
PT Siemens have developed community health
and safety procedures included in its Community
Health, Safety, and Security Management Plan
that has been reviewed and approved by PLN UPP
2 Sintang and PUSMANPRO on 4 July 2019.
In the contractor’s CHSP explained the hazards
that are likely to occur around the project area and
their handling for safety of community near the
project area.
Contractor has conducted health safety awareness
related to dengue hemorrhagic fever in Tayan Hilir
in 16 February 2019 and about syphilis diseases to
the community on 13 August 2019 in Mungguk
Village. The villages chosen because it’s near the substation construction area.
Relevant evidence of these mitigation measures is
shown in Appendix 6.k.
The mitigation implemented with this
regard is compliant with its
requirements.
the settlements in close location from the
transmission line should be clearly mapped in
order to better inventory and address the EMF
(electro-magnetic fields) health & safety risks.
an effective socialization program should follow in
this at the mapped locations to address
community concerns on the EMF effects of
transmission line operation.
These mitigation requirements are not applicable for
the construction of substations reported in this table.
Not applicable.
13. Employment Opportunities
To communicate about employment opportunities
on a regular basis and to demonstrate the efforts
are made to accommodate as many people as
possible.
Be clear about the limited possibility and
communicate this limitation during the meetings.
Give priority to impact affected people to
participate with the project works e.g. in
transmission work the material transportation from
The contractor has delivered the message on
employment opportunity with the village officials
before the construction started.
Local people who have been hired to become
laborers in the project have the skills as needed,
such as earthworks and construction work. In
second semester of 2019, the project need skilled,
non-local workers to install mechanical and electrical
equipment at the substation, thus the percentage of
The mitigation implemented with this
regard is compliant with its
requirement.
23
No Potential Impacts / Mitigation Requirements
as per IEE (2016) Mitigation Implemented Compliance Status / Remarks
roadside to tower site, and other unskilled and
semi-skilled available labor either transmission
line or substation works.
workers employed are 40% local and 60% non-local
people.
14. Physical Cultural Resources
Awareness to all workers concerning chance find
physical cultural resources during construction
implementation:
If physical cultural resources are encountered
during the construction phase, all works at the find
site should be immediately halted.
The find should be assessed by a competent
expert, and procedures to avoid, minimize or
mitigate impacts to the physical cultural resources
should be developed by the expert in cooperation
with the relevant local heritage authority,
proportionate to the value of the resource in
question and the nature and scale of the Project’s potential adverse impacts on it.
The find should be assessed in consultation with
local Traditional Leaders (Temenggung) for each
indigenous ethnic group to identify the local
cultural significance and obtain guidance on what
follow-up actions to conduct under supervision of
local communities.
Work should not begin until the procedures to
avoid, minimize or mitigate impacts to the physical
cultural resources have been implemented.
In case avoidance is not feasible, no alternatives
to removal exist, and the Project benefits outweigh
the anticipated cultural heritage loss from removal;
the physical cultural resource should be removed
and preserved according to the best available
technique.
Any removal should be conducted in accordance
with relevant provisions of national and/or local
laws.
Records should be maintained of all finds,
A chance find procedure from PT Siemens has
been developed (Ref: page 50 chapter 5.32 about
Unexpected Discovery of the EHS plan). The
contractor has conducted the awareness to the
employee during toolbox meeting. Relevant
documents related to this mitigation are shown
earlier in Appendix 6.i.
During 2nd
semester of 2019 reporting period, there
were no cultural physical resources found at the
substation sites.
The mitigation implemented with this
regard is compliant with its
requirement.
24
No Potential Impacts / Mitigation Requirements
as per IEE (2016) Mitigation Implemented Compliance Status / Remarks
including chain of custody for movable finds.
All Project workers and staff should be made
aware of the chance-find procedure.
25
3.6 Packages 6 and 7: Tayan-Sanggau-Sekadau Transmission Lines
The Tayan – Sanggau (Package 6) and Sanggau - Sekadau (Package 7) power transmission lines were under the the construction
phase with foundation work, tower erection and stringing work as the primary activities in the semester 2/2019. UIP KALBAGBAR is
responsible for the development of these transmission lines. The progress of these works was reported 83.94% for Package 6 and
69.63% for Package 7 (as of the end of December 2019). Table 3.6 describes the mitigation measures implemented by the project
including its compliance status against the mitigation requirements defined in the IEE (2016).
Table 3.6 Environmental Mitigation Status of Packages 6 and 7
No Potential Impacts / Mitigation Requirements
per IEE (2016) Mitigation Implemented Compliance Status / Remarks
1. Vegetation Clearing
Vegetation removal will be allowed with the
designated width of the ROW and the minimum
area required for other infrastructure and activities.
Vegetation cutting within the ROW will be
undertaken to achieve the required clearances.
Tree removal and trimming will only be undertaken
by hand tools, including chain saws.
Local people will be allowed to access to cleared
vegetation for the collection of building materials
and firewood.
Burning of cleared vegetation will not be allowed;
instead this material will be used to protect the soil
from erosion, particularly in steeper slope areas,
until permanent soil protection measures are in
place.
The use of herbicides will be strictly prohibited.
Vegetation cutting within the ROW of the
transmission line was conducted to achieve the
required clearance according to the requirements
of MEMR Regulation No. 18/2015.
In the PT Krakatau Engineering (KE) HSE plan
(page 27, chapter 7.22), it is stated that vegetation
cutting can only be done manually and using
chainsaw. Subsequently, the local people are
allowed to collect the remaining vegetation (as
shown in Appendix 7.a).
In the KE’s HSE plan (page 28, chapter 7.22) it is stated that the use of herbicides is prohibited in
vegetation clearing process. The prohibition on the
use of herbicides was also made in the form of
warning sign and communicated to the workers at
the toolbox talk at each construction site (as
shown in Appendix 7.a).
The mitigation implemented with this
regard is compliant with its requirement.
2. Soil Erosion
Soil erosion control measures have been
incorporated into the engineering design, including
the use of adjustable height tower which allow the
tower to conform to the slope of the site, thereby
reducing land cutting and erosion.
Due to requirement of RoW clearances, adjusting of
tower height has been applied to Tower T.05R at
Sei Mawang Village. It allowed the tower to conform
that the slope of the site and reduces soil erosion as
well. Relevant evidence of this mitigation is shown
in Appendix 7.b.
The mitigation implemented with this
regard is compliant with its requirement.
26
No Potential Impacts / Mitigation Requirements
per IEE (2016) Mitigation Implemented Compliance Status / Remarks
In addition, mitigations, designed in accordance
with relevant guidelines and good construction
practices adapted to suit the requirements at each
site as follows:
- On steep slope: minimizing the extent and
duration of land disturbance; using sandbags,
banks or channels to divert water flows from
upslope around the disturbed area; and using
vegetation cut or foliage to protect disturbed
ground on a temporary basis.
- On dry flat area: using vegetation cut or foliage to
protect disturbed ground from rainwater impact
on a temporary basis.
- On rice field and wet area: no significant erosion
is anticipated.
In the KE’s HSE plan (page 28, chapter 7.22) it is
stated that soil erosion management would be
implemented during construction.
- On steep slope: installed the embankment,
before construction began to prevent erosion;
and use vegetation cut or foliage to protect
disturbed ground on a temporary basis.
- On dry flat area: using vegetation cut or foliage to
protect disturbed ground from rain-water impact
on a temporary basis.
Relevant evidence of this mitigation is shown in
Appendix 7.b.
The mitigation implemented with this
regard is compliant with its requirement.
The soil erosion control measures will be regularly
inspected and maintained during construction and
until the area is stabilized or re-vegetated.
In the KE’s HSE plan (page 28, chapter 7.22) it is stated that soil erosion will be monitored regularly
during the construction stage until the area is
stabilized and re-vegetated
The soil erosion control measure has been reported
in the monthly monitoring report as shown in
Appendix 7.b.
The mitigation implemented with this
regard is compliant with its requirement.
3. Drainage (substations)
The mitigation requirements for drainage are intended for the operation of substations, and therefore it not
applicable for the operation of transmission lines reported in this table.
Not applicable.
4. Water Quality Impacts
Mitigation measures to protect water quality from
erosion are the same as “Vegetation Clearing” and “Soil Clearing”, above
The prevention to protect water quality from erosion
during vegetation clearing is as described before in
sub-chapter 3.2, numbers 1 and 2.
The mitigation implemented with this
regard is compliant with its
requirement.
To protect from impacts on water quality arising
from spillage of oil, fuel and other hazardous
materials to be taken away by licensed third party.
KE's HSE plan (page 29, chapter 7.22) states that
fuel, oil and hazardous materials must be taken
away by licensed third party and managed
according to Government Regulation no. 101/2014.
At this moment, the hazardous waste is still in small
quantity and stored in the dedicated temporary
storage area, away from any water courses.
The mitigation implemented with this
regard is compliant with its
requirement.
27
No Potential Impacts / Mitigation Requirements
per IEE (2016) Mitigation Implemented Compliance Status / Remarks
Related evidence of this mitigation is presented in
Appendix 7.c.
Refueling of machinery, equipment and vehicles will
be undertaken at distance of at least 100 m from
any water course.
Refueling of the construction vehicles was
undertaken at the public fuel station. However,
refueling the concrete mixer machine was carried
out on site and provided with some secondary
containment to accommodate in case of oil spill (as
shown in Appendix 7.c).
The mitigation implemented with this
regard is compliant with its
requirement.
Any major work including oil changing and engine
maintenance with the potential for oil to be spilled
will be done in designated areas at distance of at
least 100 m from any water course with
containment to prevent any oil spills washing away.
Any oil changing and engine maintenance carried
out at the off-site workshop, except for the
concrete mixer conducted on site similar like
refueling.
The mitigation implemented with this
regard is compliant with its
requirement.
During the construction of tower sites at rice fields
and wet areas, extra measures shall be applied to
prevent water contamination by the oil drip or
spilled wastewater from cement mixers and
concrete.
Since there was no construction work located at rice
field and wet areas during this period, therefore this
mitigation requirement is no applicable.
Not applicable.
Herbicides will not be used in the project In the contractor's HSE plan (page 28, chapter 7.22)
it is stated that herbicides are prohibited in vegetation
clearing process. The prohibition on the use of
herbicides was also made in the form of warning sign
and has been delivered to the workers in each
construction site, as described earlier.
The mitigation implemented with this
regard is compliant with its requirement.
5. Air Quality Impacts
Truckloads with dusty soil should be covered, with
the exception of on-site or local trips.
Cut and fill should be balanced to the maximum
extent possible at each site in order to minimize the
need for fill and for spoil disposal.
During the construction of tower foundation,
excavated soil was not transported from the
construction site and used as a fill material when the
tower construction has been completed. Therefore,
this mitigation requirement is not applicable.
Not applicable.
Construction waste and garbage burning are
prohibited.
In the KE's HSE plan (page 17, chapter 7.8) it is stated
that the waste should not be burned. The prohibition
on burning of cleared vegetation and waste was made
in the form of warning sign and delivered to the
workers at the toolbox meeting as described earlier.
The mitigation implemented with this
regard is compliant with its requirement.
28
No Potential Impacts / Mitigation Requirements
per IEE (2016) Mitigation Implemented Compliance Status / Remarks
6. Construction Waste Management
Solid wastes generated from construction activities
should not be haphazardly left on site.
Construction waste will be contained in a
designated area on each construction site.
Wastes will be routinely collected and disposed of
at safe waste disposal facilities indicated by the
District Environmental agencies.
The contractor has provided a trash bag to collect the
garbage contained at each tower construction site and
routinely dispose of the waste routinely to Sei Kosak
waste disposal site and Sekadau waste disposal site.
The disposal only temporary stored and there was no
leachate treatment tank, as shown in Appendix 7.d.
The mitigation implemented with this
regard is compliant with its requirement.
7. Domestic Waste Management
Temporary worker camps will be required to be
provided with appropriate sanitation facilities,
including water supply, and washing facilities,
temporary toilets, and waste containers.
For Package 6, the contractor’s worker rented houses
from local people in Binjai Village (Tayan Hulu district).
The houses are equipped with adequate water supply
(obtained from groundwater), washing and toilet
facilities, and trash bins. Related evidence is shown
in Appendix 7.e; meanwhile the contractor’s workers for Package 7 are hired from the local community and
therefore no camps are provided for them.
The mitigation implemented with this
regard is compliant with its requirement.
Domestic waste will be routinely collected and
disposed of at safe waste disposal facilities.
The domestic wastes are managed and disposed in the
same way as the construction wastes.
The mitigation implemented with this
regard is compliant with its requirement.
Garbage burning is prohibited. In the KE's HSE plan (page 17, chapter 7.8) it is stated
that wastes should not be burned. The prohibition on
burning of wastes was made in the form of warning
sign and reminder at the toolbox meeting (as shown in
Appendix 7.a).
The mitigation implemented with this
regard is compliant with its requirement.
8. Roads and Infrastructure Impacts
A mapping of the locations of expected heavy
equipment mobilization is needed versus settlement
area locations. This needs inventory and monitors
the potential damage to existing roads.
Mapping of equipment mobilization route and nearby
settlement areas have been undertaken and reported
in the previous monitoring.
The mitigation implemented with this
regard is compliant with its requirement.
Any damaged infrastructure after heavy equipment
mobilization will be repaired to at least the same
standard and condition on completion of the project,
especially caused by the transportation of heavy
equipment e.g. 150 kV power transformer.
In the TL construction site, the access road is not
always in the form of pavement, some of them still
a dirt road. The contractor has made a temporary
access road to avoid the damage to the road. If
the damaged road occurred, it would be
immediately repaired by the contractor. The
The mitigation implemented with this
regard is compliant with its requirement.
29
No Potential Impacts / Mitigation Requirements
per IEE (2016) Mitigation Implemented Compliance Status / Remarks
documentation is presented in Appendix 7.f.
9. Encroachment into Protected Forests, Hunting, Wood Collection
Hunting extraction by workers of forest products
such as firewood and keeping of firearms on the
project, will be prohibited.
To avoid impact on ecological valuable sites,
habitats, natural forest, flora and fauna, this risk
should be particularly be monitored along the
ecologically sensitive alignments of the
Transmission line: along the 35 km between Tayan
and Sosok where the alignment passes close by
secondary forest within production forest reserves;
along the alignment which runs close (3.5. and 11
km) to the primary forest within Gunung Tiong
Kandang and Gunung Sanggau; and along the
alignment which passes close (1.5 km distant) to
the Pancur Aji Forest Recreation Reserve.
In the KE’s HSE plan (chapter 7.22, page 31), it is
stated that the project work does not interfere with
or pass through areas that have status as
protection forests, wildlife reserves, national parks
or other ecologically sensitive areas.
Although that the project site is not located in the
forest area, the contractor has provided the warning
sign that hunting is prohibited during this project to
avoid impact on ecological valuable sites.
The awareness about the prohibition of hunting and
wood collection was delivered by the contractor in
the toolbox meeting.
Relevant evidence related to this mitigation is shown in
Appendix 7.g.
The mitigation implemented with this
regard is compliant with its requirement.
10. Impacts on Cultural Heritage Sites
The project area falls closely adjacent several notable
heritage sites:
Although unlikely to suffer impact from project due
to separation distance, as a mitigation measure for
these sites, the project workers should be made
aware that these sites should not be disturbed, or
material extracted if visited.
Project construction traffic and heavy equipment
should also not be routed anywhere near these
sites to avoid vibration damage.
Contractors have been transported heavy equipment
and materials away from cultural heritage sites.
Further, awareness related to this mitigation has
been delivered during toolbox meeting.
The mitigation implemented with this
regard is compliant with its requirement.
The project construction should also take care not
to make impact on the potential unmapped locally
important cultural sites, such as community sacred
forest groves (hutan adat) and sacred grave sites
(tempat keramat). Consultation should be
conducted with local Traditional Leaders
(Temengung) for each indigenous ethnic group to
identify and avoid any such sites prior to
The Ngudas ceremony was conducted before cutting
trees along the ROW path in the village. The evidence
related to this activity is included in Appendix 7.h.
The mitigation implemented with this
regard is compliant with its requirement.
30
No Potential Impacts / Mitigation Requirements
per IEE (2016) Mitigation Implemented Compliance Status / Remarks
construction of all project works.
11. Occupational Health and Safety (HVTL alignments, substations)
Prior to the commencement of civil works a
construction phase Occupational Health and Safety
Plan (OHSP) will be developed. The OHSP should:
identify and minimize so far as reasonably
practicable, the causes of potential hazards to
workers, including communicable diseases and
vector borne diseases;
provide preventive and protective measures,
including modification, substitution, or elimination of
hazardous conditions, with particular attention to
live power lines, working at height, working during
thunderstorms (lightning strikes), EMFs, and
exposure to chemicals;
provide preventive and protective measures,
including modification, substitution, or elimination of
hazardous conditions, with particular attention to
live power lines, working at height, working during
thunderstorms (lightning strikes), EMFs, and
exposure to chemicals;
PT KE has developed an environmental health &
safety (EHS) plan, covering OHS aspects. The EHS
plan has been reviewed and approved by PLN UPP 2
in October 2017, and found to be adequate in terms
of providing procedures on:
The procedure to identify potential hazard for
workers is available in HIRAC (Hazard
Identification Risk Assessment Control) and JSA
(Job Safety Analysis), as seen in Appendix 7.i.
Eliminating hazardous condition with attention to
high risk activities, including working at height and
handling of hazardous chemical and materials;
Management related to disposal of hazardous
wastes;
Personal protective equipment to minimize risk;
and
Communication and training establish awareness
on site.
The mitigation implemented with this
regard is compliant with its requirement.
Provide measures for the management and
appropriate disposal of hazardous wastes to ensure
protection of the workforce and the prevention and
control of releases and accidents;
In PT KE’s HSE plan (page 26, chapter 7.21) it is stated that the Contractor has established
procedures for the management and appropriate
disposal of hazardous wastes.
The contractor has made a temporary hazardous
waste storage area. The wastes are labelled
according to its type and characteristic (as shown in
Appendix 7.i).
The mitigation implemented with this
regard is compliant with its requirement.
Provide appropriate personal protective equipment
(PPE) to minimize risks;
In implementation workers have used PPE in
accordance with the type of work. When on concrete
pouring work, the worker using safety helmet, boots,
and safety vests and during erection work, the
worker using full body harness, safety boots, safety
helmet and safety gloves. The documentation is
shown in Appendix 7.i.
The mitigation implemented with this
regard is compliant with its requirement.
31
No Potential Impacts / Mitigation Requirements
per IEE (2016) Mitigation Implemented Compliance Status / Remarks
Provide training for workers, and establish
appropriate incentives to use and comply with
health and safety procedures and utilize PPE;
During this period the contractor had held in house
training regarding to working at height, as the
documentation shown in Appendix 7.i.
The mitigation implemented with this
regard is compliant with its requirement.
Include procedures for documenting and reporting
occupational accidents, diseases, and incidents;
and
The contractor makes a report related to accidents,
disease and incidents and reports it to the HSE
supervisor monthly, as the documentation shown in
Appendix 7.i.
The mitigation implemented with this
regard is compliant with its requirement.
Include emergency prevention, preparedness, and
response arrangements in place.
In the contractor's HSE document on page 34
chapter 8 concerning Emergency Condition, the
contractor has provided procedure for emergency
prevention, preparedness and response
arrangements in place.
The contractor has set up the emergency team
which equipped with some equipment (first aid kid
box, fire extinguisher, evacuation route, safety sign,
etc.) that can be used in emergency conditions (as
shown in Appendix 7.i).
The mitigation implemented with this
regard is compliant with its requirement.
12. Community Health and Safety
Prior to the commencement of civil works a
construction phase Community Health and Safety Plan
(CHSP) will be developed. The CHSP should include:
Procedures to identify and minimize, so far as
reasonably practicable, the causes of potential
Project related hazards to local communities,
including communicable diseases such as HIV/AIDs
and vector borne diseases;
Specific emergency response procedures;
Relevant emergency equipment;
Protocols for emergency vehicle services; and
Put safety sign.
PT Krakatau Engineering has developed a
community health and safety procedure in the
Community Health, Safety, and Security
Management Plan (CHSSMP) that has been
reviewed and approved by PLN UPP 2 Sintang
and PUSMANPRO on 4 July 2019 (as shown in
Appendix 7.j).
The contractor’s CHSSMP includes procedures
related to communicable diseases such as
HIV/AIDS and vector-borne disease; and specific
emergency response procedures.
Each construction site has been equipped with
emergency equipment in the form of first aid kit that
can be used in minor accident and also fire
extinguisher (as shown earlier in Appendix 7.i).
The contractor has provided the as transportation in
case of emergency (as shown in Appendix 7.j).
Safety signs have been installed, to warn the
The mitigation implemented with this
regard is compliant with its requirement.
32
No Potential Impacts / Mitigation Requirements
per IEE (2016) Mitigation Implemented Compliance Status / Remarks
community on the potential risk of entering the
project sites. Location that having potential danger,
as shown in Appendix 7.j.
Contractor already conduct CHSSMP
dissemination to the local people in Parindu
Village as shown in Appendix 7.j. This village
chosen because the transmission lines mostly
pass through it. There are 64 towers in this village.
The houses and settlements in close location from
the transmission line should be clearly spatially
mapped in order to better inventory and address the
EMF (electro-magnetic fields) health and safety
impact risk.
An effective socialization program should follow in
this, at the mapped locations to address community
concerns in regard to the EMF effects of
transmission line operation.
Houses and settlements located close to the
transmission lines can be identified using ROW field
map, and the mapping is still on process as the
construction is ongoing.
PLN has conducted the dissemination regarding
EMF for the construction of the transmission line.
The socialization regarding to EMF always
incorporated in the compensation, land payment,
and ROW socialization in each village traversing by
Transmission line.
The evidence related to above description can be
seen in Appendix 7.j
The mitigation implemented with this
regard is compliant with its requirement.
13. Employment Opportunities
Communicate about employment opportunities on a
regular basis and demonstrate the efforts being
made to accommodate as many people as possible.
Be clear about the limited possibility and
communicate this limitation during the meetings.
Give priority to impact affected people to participate
with the project works e.g. in transmission work the
material transportation from roadside to tower site,
and other unskilled and semi-skilled available labor
either transmission line works, or substation works.
At the beginning the contractors started to recruit
local people for unskilled work, such as transporting
materials and then they also trained for making
concrete. Before starting work on the project, safety
induction was carried out first by the HSE team. The
current composition of the workforce for the
Package 6 is 53% of local people and 47% from
outside the project area, and Package 7 is 45%of
local people and 55% from outside the project area
The mitigation implemented with this
regard is compliant with its requirement.
14. Physical Cultural Resources
Awareness to all workers concerning chance find
physical cultural resources during construction
implementation:
In the KE’s HSE plan page 31, chapter 7.22 there are procedures incorporated for finding chance
regarding physical cultural resources. This
procedure gives guidance for someone who worked
The mitigation implemented with this
regard is compliant with its requirement.
33
No Potential Impacts / Mitigation Requirements
per IEE (2016) Mitigation Implemented Compliance Status / Remarks
If physical cultural resources are encountered
during the construction phase, all works at the find
site should be immediately halted.
The find should be assessed by a competent
expert, and procedures to avoid, minimize or
mitigate impacts to the physical cultural resources
should be developed by the expert in cooperation
with the relevant local heritage authority,
proportionate to the value of the resource in
question and the nature and scale of the Project’s potential adverse impacts on it.
The find should be assessed in consultation with
local Traditional Leaders (Temenggung) for each
indigenous ethnic group to identify the local
cultural significance and obtain guidance on what
follow-up actions to conduct under supervision of
local communities.
Work should not begin until the procedures to avoid,
minimize or mitigate impacts to the physical cultural
resources have been implemented.
Where avoidance is not feasible, no alternatives to
removal exist, and the Project benefits outweigh the
anticipated cultural heritage loss from removal; the
physical cultural resource should be removed and
preserved according to the best available
technique.
Any removal should be conducted in accordance
with relevant provisions of national and/or local
laws.
Records should be maintained of all finds, including
chain of custody instructions for movable finds.
All Project workers and staff should be made
aware of the chance-find procedure.
on the project and found a physical cultural
resource, then he had to stop all the activities within
the discovery, marking the site area found, secured
the site area, prevented the collection of objects by
labor or other person, notified the nearest cultural
management agency within 24 hours, reminded all
project personnel of the findings and carried out
temporary protection measures, submitted the
object found to local cultural management agency,
recorded all the findings and actions taken.
The contractor has conducted the awareness to the
employee related physical resources during toolbox
meeting.
The evidence related to the above description is
shown in Appendix 7.h.
34
Chapter 4 Environmental Monitoring Status
The outcomes of the environmental mitigation conducted for the Work Packages 1 to 7 in the
period of July – December 2019 were monitored to ensure its effectiveness and compliance with
the requirements of the environmental monitoring plan defined in the Project’s IEE. The work packages that are in the construction and operation phases are required to implement
environmental monitoring as defined in the IEE.
The environmental monitoring requirements of Packages 1 to 4 (i.e. power transmission lines
from Bengkayang to Tayan including associated substations) are defined in Table 9.2 of the IEE
(2011). The monitoring implemented is described in sub-chapters 4.1 to 4.4.
The environmental monitoring requirements of Packages 5 to 7 (i.e. power transmission lines
from Tayan to Sekadau including associated substations) are defined in Table 29 of the IEE
(2016). The monitoring implemented is described in sub-chapters 4.5 to 4.6.
35
4.1 Package 1: Bengkayang-Jagoibabang Transmission Lines
Table 4.1 describes the environmental monitoring conducted for the operation of Bengkayang to Jagoibabang transmission lines
including its compliance status against the monitoring requirements defined in the IEE (2011) in the period of July to December 2019.
Table 4.1 Environmental Monitoring Status of Package 1
No Aspects, Means, and Frequency of Monitoring Monitoring Implemented Compliance Status / Remarks
1. Electrical and Magnetic Fields/EMF (RoW)
Monitoring to determine if EMFs generated by the
transmission lines are within national and international
standards (once every 5 years).
During this semester, the EMF monitoring was not
conducted, because the first monitoring has been
conducted and reported in the 2nd
semester environmental
monitoring report of 2018 and the next monitoring is
needed in 5-year interval.
Not applicable
2. Vegetation Management (RoW)
Ensure that vegetation removal mitigations are
implemented (monitoring on quarterly basis).
No vegetation removal was conducted during the
reporting period, and therefore monitoring was not
conducted.
Not applicable.
3. Health and Safety (RoW)
Ensure operation phase OHS and CHS have been
develop and are being implemented (monitoring on
quarterly basis).
The implementation of health and safety included in the
ground patrol inspection based on SK DIR No. 0520-
1.K/DIR/2014 in the guidelines book for Maintenance of
High and Extra High Voltage Transmission Lines,
according to the attached inspection form as shown in
Appendix 8.a.
The monitoring implemented with
this regard is compliant with its
requirement.
Ensure towers fitted with anti-climbing devices, and
substations fitted with security fences (monitoring
on quarterly basis).
The monitoring indicated that every transmission tower
has been equipped with anti-climbing devices (as shown
in Appendix 2.b).
The monitoring implemented with
this regard is compliant with its
requirement.
4. Bird Collision (RoW)
Monitor bird collision occurrences (monitoring on
quarterly basis).
The monitoring through interview and field observations at
selected transmission towers/ROW indicated that no death
of birds was seen or known Appendix 2.c provides the
photo showing the personnel conducts the interview and
reports the results of the mentioned monitoring.
The monitoring implemented with
this regard is compliant with its
requirement.
36
4.2 Package 2: Bengkayang Substation
Table 4.2 describes the environmental monitoring conducted for the operation of the Bengkayang substation including its compliance
status against the related requirements defined in the IEE (2011) in the period of July to December 2019.
Table 4.2 Environmental Monitoring Status of Package 2
No Aspects, Means, and Frequency of Monitoring Monitoring Implemented Compliance Status / Remarks
1. Electrical and Magnetic Fields/ EMF
Monitoring to determine if EMFs within national and
international standards/guidelines (once every 5
years)
During this semester, the EMF monitoring was not
conducted, because the first monitoring has been
conducted and reported in the 2nd
semester
environmental monitoring report of 2018 and the next
monitoring is needed in 5-year interval.
Not applicable
2. Oil, Fuel and Hazardous Materials Management
Ensure mitigation measures are in place with respect
to oil, fuel and other hazardous materials storage,
handling, disposal; and fueling and maintenance of
equipment (monitoring on quarterly basis).
The monitoring indicated that the OHS management
system (locally known as SMK3) of PLN Unit Pelaksana
Penyaluran dan Pengaturan Beban (UP3B) Kalimantan
was implemented i.e. oil pit is provided underneath it and
no evidence of spills in its surrounding reported for the
Semester 2/2019 reporting.
The monitoring implemented with
this regard is compliant with its
requirement.
3. Health and Safety (RoW)
Ensure operation phase OHS and CHS have been
develop and are being implemented (monitoring on
quarterly basis).
The monitoring is intended for the operation of
transmission line, and therefore not applicable for that of
the substation.
Not applicable.
Ensure towers fitted with anti-climbing devices,
and substations fitted with security fences
(monitoring on quarterly basis).
The monitoring by HSE supervisor indicates that
substation has been fitted with security fence and full-time
security personnel. Relevant evidence is included in
Appendix 3.c.
The monitoring implemented with
this regard is compliant with its
requirement.
37
4.3 Package 3: Bengkayang-Ngabang-Tayan Transmission Lines
The Bengkayang – Ngabang – Tayan transmission lines has entered the operation phase since May 2018 and since then are under
the responsibility of UP3B KALBAR. Table 4.3 describes the environmental monitoring conducted by the project including its
compliance status against the monitoring requirements defined in the IEE (2011).
Table 4.3 Environmental Monitoring Status of Package 3
No Aspects, Means, and Frequency of Monitoring Monitoring Implemented Compliance Status / Remarks
1. Electrical and Magnetic Fields/EMF
Monitoring to determine if EMFs within national and
international standards/guidelines (once every 5
years).
During this semester, the EMF monitoring was not
conducted, because the first monitoring has been
conducted and reported in the 2nd
semester
environmental monitoring report of 2018 and the next
monitoring is needed in 5-year interval.
Not applicable
2. Vegetation Management
Ensure that vegetation removal mitigations are
implemented (monitoring on quarterly basis).
No vegetation removal was conducted during the
reporting period, and therefore monitoring was not
conducted.
Not applicable.
3. Health and Safety
Ensure operation phase OHS and CHS have been
develop and are being implemented (monitoring on
quarterly basis).
The implementation of health and safety included in the
patrol grounding inspection based on SK DIR No. 0520-
1.K/DIR/2014 in the guidelines book for Maintenance of
High and Extra High Voltage Transmission Lines,
according to the attached inspection form as shown in
Appendix 8.a.
The monitoring implemented with
this regard is compliant with its
requirement.
Ensure towers fitted with anti-climbing devices,
and substations fitted with security fences
(monitoring on quarterly basis).
The monitoring indicated that every tower has been
equipped with anti-climbing devices. Relevant evidence of
this monitoring is shown in Appendix 4.b.
The monitoring implemented with
this regard is compliant with its
requirement.
4. Bird Collision
Monitor bird collision occurrences (monitoring on
quarterly basis).
The monitoring of bird collisions has been conducted by
the PIC supervisor and obtained the results that no one
reported occurrence of death birds within the ROW.
Appendix 4.c provides the photo showing the personnel
conducts the interview and reports the results of the
mentioned monitoring.
The monitoring implemented with
this regard is compliant with its
requirement.
38
4.4 Package 4: Ngabang Substation and Phase I Extension of Tayan Substation
The Ngabang substation and Phase 1 extension of Tayan substation have been in operation phase since 2017 and under the
responsibility of UP3B KALBAR. Table 4.4 describes the environmental monitoring implemented by the Project for the operation of
these substations, including its compliance status against the mitigation requirements defined in the IEE (2011).
Table 4.4 Environmental Monitoring Status Package 4
No Aspects, Means, and Frequency of Monitoring Monitoring Implemented Compliance Status / Remarks
1. Electrical and Magnetic Fields/EMF (RoW)
Monitoring to determine if EMFs within national and
international standards/guidelines (once every 5
years).
During this semester, the EMF monitoring was not
conducted, because the first monitoring has been
conducted and reported in the 2nd
semester
environmental monitoring report of 2018 and the next
monitoring is needed in 5-year interval
Not applicable
2. Oil, Fuel and Hazardous Materials Management (Substation)
Ensure mitigation measures are in place with respect
to oil, fuel and other hazardous materials storage,
handling, disposal; and fueling and maintenance of
equipment.
The monitoring indicates that the OHS management
system (locally known as SMK3) of UP3B KALBAR was
implemented i.e. oil pit was provided underneath it and
there was no evidence of spills in its surrounding.
Ngabang Environmental Commission (DLH) has
surveyed the location, due to insignificant quantity of
hazardous waste; permission related to management
waste material in accordance with the requirement of
Government Regulation No. 101/2014 on Hazardous
and Toxic Waste Management was not required.
In the implementation, the hazardous waste was
already separated and labeled as shown in Appendix
8.b
The monitoring implemented with
this regard is compliant with its
requirement.
3. Health and Safety (RoW)
Ensure operation phase OHS and CHS have been
develop and are being implemented.
The monitoring is intended for the operation of
transmission line, and therefore not applicable for that
of the substation.
Not applicable.
Ensure towers fitted with anti-climbing devices,
and substations fitted with security fences.
The substation has been fitted with the security fence
and guarded by security personnel. Relevant evidence
is shown in Appendix 5.c.
The monitoring implemented with
this regard is compliant with its
requirement.
39
4.5 Package 5: Sanggau and Sekadau Substations and Phase 2 Extension of Tayan Substation
As of the end of December 2019, the construction of Sanggau and Sekadau substations was progressing, and the phase 2 extension
of Tayan substation was nearly complete. UIP KALBAGBAR is responsible for the development of these substations. Table 4.5
describes the environmental monitoring implemented for this package including its compliance status against the monitoring
requirements defined in the IEE (2016).
Table 4.5 Environmental Monitoring Status of Package 5
No Aspect and Means of Monitoring Monitoring Implemented Compliance Status / Remarks
1. Vegetation Clearing (RoW)
Ensure that vegetation removal mitigations are
implemented.
Monitor effectiveness of vegetation removal
control measures.
This monitoring was intended for the construction of
transmission lines, and therefore not applicable for the
construction of substation reported herein.
Not applicable.
2. Drainage (Substations)
Ensure drainage plans are implemented.
Monitor effectiveness of drainage system.
The drainage channels at Sanggau and Sekadau
substations have been constructed according to the
approved drawings. The approved drainage drawing is
presented before in Appendix 6.c.
These drainage channels are cleaned if remains of
plants, weeds, or other obstructions that disrupt water
flow and monitored periodically. Related evidence is
presented in Appendix 8.c.
The monitoring implemented
with this regard is compliant
with its requirement.
3. Soil Erosion (Tower and Substation Sites)
Ensure soil erosion control measures are
applied.
Monitor effective ness of soil erosion control
measures.
The monitoring conducted by the PIC’s environmental
supervisor at Sanggau substation indicated that erosion
prevention has been carried out by creating an
embankment that functions as a sediment trap. Evidence
of this monitoring is shown in Appendix 6.b.
Sediment traps could restrain the dugout soils before
flowing out into the nearby natural watercourses, and
these traps are quite effective. Evidence of this
monitoring is shown in Appendix 8.d.
The monitoring implemented
with this regard is compliant
with its requirement.
40
No Aspect and Means of Monitoring Monitoring Implemented Compliance Status / Remarks
4. Water Quality (Construction Sites and Storage Areas)
Ensure mitigation measures are in place with
respect to oil, fuel and other hazardous materials
storage, handling, disposal; and fueling and
maintenance of equipment.
Monitor effectiveness of mitigation on water
quality
The oil, fuel and other hazardous materials storage and
handling were monitored at Sanggau and Sekadau
substations to ensure that secondary containment to
prevent oil spills provided and therefore protect nearby
water quality (as shown in Appendix 6.d).
In addition, based on the results of measurements of
water quality at the Sanggau substation conducted on 9
November 2018 in collaboration with the University of
Tanjung Pura, it was stated that all parameters were still
under the threshold for water quality grade 1, according
to Government Regulation 82/2001. The water quality
measurement result is shown in Appendix 8.e.
The implementation of this
monitoring is compliant with its
requirement.
5. Air Quality (Construction Sites and Storage Areas)
Ensure mitigation measures with respect to dust
control, truck cleaning, load covering, and soil
and spoil pile management are in place.
Dust control with spraying water at the construction site of
the substation periodically was monitored and reported.
Related evidence is shown in Appendix 6.e.
The implementation of this
monitoring is compliant with its
requirement.
Monitor effectiveness of mitigation on air quality. Ambient air quality monitoring was conducted by PT
Sucofindo (in November 2019) at Sei Mawang village, near
the Sanggau substation. The monitoring result below
indicated that all air quality parameters are below the
threshold values of ambient air quality standards stipulated
in Government Regulation No. 41/1999, indicating that water
spraying is effective in mitigating impact on the air quality at
the village nearby the substation.
Parameter Unit Result Threshold
value
Dust µg/Nm3 70.22 230
Nitrogen Oxide (NOx) µg/Nm3 60.06 400
Sulfur Dioxide (SO2) µg/Nm3 28.70 900
Carbon Monoxide (CO) µg/Nm3 143.20 30,000
The ambient air quality monitoring conducted at Mungguk
village, near Sekadau Substation (in November 2019), and
the monitoring results are similar with those of Sanggau
The implementation of this
monitoring is compliant with its
requirement.
41
No Aspect and Means of Monitoring Monitoring Implemented Compliance Status / Remarks
substation.
Parameter Unit Result Threshold
value*
Dust µg/Nm3 87.74 230
Nitrogen Dioxide (NO2) µg/Nm3 76.26 400
Sulfur Dioxide (SO2) µg/Nm3 32.10 900
Carbon Monoxide (CO) µg/Nm3 193.18 30,000
Relevant air quality measurement results are shown in
Appendix 8.f.
6. Waste Management (Construction Sites and Worker Camps)
Ensure construction and domestic waste
management collection, storage and disposal
mitigations are in place.
Monitor effectiveness of mitigation on waste
management
The contractor provided a separate trash bins for organic
and non-organic wastes generated by construction activities
and the worker’s camp. The organic wastes will be piled up in the worker camp backyard, and non-organic wastes to Sei
Kosak and Sekadau final disposal. Monitoring indicated that
these waste management practices are implemented as
required (as shown in Appendix 6.f and 6.g).
The implementation of this
monitoring is compliant with its
requirement.
7. Roads and Infrastructure (Construction Sites, Access Roads, Relevant District Roads)
Ensure mitigation measures are in place with
respect to road and infrastructure damage by
heavy equipment transport (monthly during
construction).
Ensure any damage is documented and repaired
Monitor effectiveness of mitigation on road and
infrastructure
During this monitoring period, there was no heavy
equipment mobilization. Therefore, this monitoring
requirement is not applicable.
Not applicable.
8. Encroachment (Gunung Condong in West Kalimantan, Areas adjacent to RoW)
Ensure mitigation measures are in place with
respect to no hunting or wildlife collection, plant
or timber collection, or lighting of fires, or
possession of firearms, traps or snares, by
workers.
Monitor effectiveness of mitigation on
encroachment impact.
The monitoring conducted in the construction area during
the working hours, indicates that no hunting, wildlife
collection or other encroachment incidences are known or
reported for this reporting period (as shown in Appendix
8.g).
The implementation of this
monitoring is compliant with its
requirement.
9. Occupational and Community Health and Safety (Construction Sites and Worker Camps)
42
No Aspect and Means of Monitoring Monitoring Implemented Compliance Status / Remarks
Ensure mitigation measures are in place with
respect to construction phase and OHS and CHS
have been developed and are being implemented
The OHS for the construction of substations have been
implemented as reported in Sub-chapter 3.1 of this report.
The contractor have been conducted the socialization either
for workers and local people related to this subject.
The implementation of this
monitoring is compliant with its
requirement.
Monitor effectiveness of mitigation on
Occupational and Community Health and Safety.
The mitigation of OHS has been effectively implemented as
evidenced because there were no OHS incidents reported
during this reporting period.
10. Physical Cultural Resources (Construction Sites)
Ensure mitigation measures are in place with
respect to implementation of chance-finding
physical cultural resources awareness and
applied if required.
Monitor effectiveness of mitigation on physical
cultural resources.
Monitoring indicated that procedures on the chance-find of
physical cultural resources were in place. There were no
findings on physical cultural resources reported during this
reporting period.
The implementation of this
monitoring is compliant with its
requirement.
43
4.6 Packages 6 and 7: Tayan-Sanggau and Sanggau-Sekadau Transmission Lines
The Tayan-Sanggau and Sanggau-Sekadau transmission lines were in the construction phase with foundation and tower erection as
the primary activity in the Semester 2/2019 period. These construction works are under the responsibility of UIP KALBAGBAR. Table
4.6 describes the environmental monitoring implemented by the project at the construction phase during this reporting period,
including its compliance status against the mitigation requirements defined in the project’s IEE (2016).
Table 4.6 Environmental Monitoring Status of Packages 6 and 7
No Aspect and Means of Monitoring Monitoring Implemented Compliance Status / Remarks
1. Vegetation Clearing (RoW)
Ensure that vegetation removal mitigations are
implemented.
Monitor effectiveness of vegetation removal
control measures.
Monitoring conducted by Pusmanpro, indicated that
mitigation measures related to vegetation removal
control/cutting using hand tools has been well-implemented
and effective Related evidence is shown in Appendix 7.a.
The implementation of this
monitoring is compliant with its
requirement.
2. Drainage (Substations)
The monitoring requirement defined under this subject is intended for the construction of substation, and therefore it
is not applicable for that of transmission lines reported herein.
Not applicable.
3. Soil Erosion (Tower and Substation Sites)
Ensure soil erosion control measures are applied.
Monitor effectiveness of soil erosion control
measures.
Implementation of mitigation measures related to soil erosion
control has been well-implemented and effective since there
was no significant soil erosion occurred in the tower base that
has been constructed which is monitored periodically by
Pusmanpro. Related evidence is shown in Appendix 8.h.
The implementation of this
monitoring is compliant with its
requirement.
4. Water Quality (Construction Sites and Storage Areas)
Ensure mitigation measures are in place with
respect to oil, fuel and other hazardous materials
storage, handling, disposal; and fueling and
maintenance of equipment.
Monitor effectiveness of mitigation on water
quality
The oil, fuel and other hazardous materials storage and
handling were monitored at Sanggau and Sekadau
substations to ensure that secondary containment and
storage area at the contractor’s warehouse are provided to
prevent oil spills and therefore protect nearby water quality.
Related evidence is shown in Appendix 7.c.
The implementation of this
monitoring is compliant with its
requirement.
5. Air Quality (Construction Sites and Storage Areas)
Ensure mitigation measures with respect to dust
control, truck cleaning, load covering, and soil
and spoil pile management are in place.
Most mitigation measures were not applicable for the
construction of transmission lines, because the excavated
soil was used as a fill material when the tower construction
Not applicable.
44
No Aspect and Means of Monitoring Monitoring Implemented Compliance Status / Remarks
has been completed.
Monitor effectiveness of mitigation on air quality. Ambient air quality monitoring was conducted by PT
Sucofindo (in November 2019) at Sanggau District for
Package 6. The monitoring result below indicated that all air
quality parameters are below the threshold values of ambient
air quality standards stipulated in Government Regulation No.
41/1999, indicating that water spraying is effective in
mitigating impact on the air quality at the village near
transmission.
Parameter Unit Result Threshold
values* T.08 T.45
Dust µg/Nm3 40.51 43.16 230
Nitrogen Dioxide
(NO2)
µg/Nm3 36.20 37.50 400
Sulfur Dioxide (SO2) µg/Nm3 18.10 18.77 900
Carbon Monoxide
(CO)
µg/Nm3 163.80 153.86 30,000
The ambient air quality monitoring conducted at Sekadau
Subsistrict for Package 7 (in November 2019), and the
monitoring results are similar with those of Package 6.
No Parameter Unit Result Threshold
value* T.103 T. 116
1. Dust µg/Nm3 115.95 129.97 230
2. Nitrogen
Dioxide
(NO2)
µg/Nm3 88.90 110.10 400
3. Sulfur
Dioxide
(SO2)
µg/Nm3 42.10 48.90 900
4. Carbon
Monoxide
(CO)
µg/Nm3
193.62 183.70 30,000
Relevant air quality measurement result is shown in
Appendix 8.i.
The implementation of this
monitoring is compliant with its
requirement.
45
No Aspect and Means of Monitoring Monitoring Implemented Compliance Status / Remarks
6. Waste Management (Construction Sites and Worker Camps)
Ensure construction and domestic waste
management collection, storage and disposal
mitigations are in place.
Monitor effectiveness of mitigation on waste
management.
The monitoring conducted indicates that the construction
sites have been provided with trash bags to collect the
wastes. The wastes collected are disposed regularly to the
final disposal site operated by Sekadau Regency. Relevant
evidences of the monitoring described are shown in
Appendix 7.d and 7.e.
The implementation of this
monitoring is compliant with its
requirement.
7. Roads and Infrastructure (Construction Sites, Access Roads, Relevant District Roads)
Ensure mitigation measures are in place with
respect to road and infrastructure damage by
heavy equipment transport.
The contractor has provided maps of the material transport
process from port to warehouse and site that passes
through settlement area location. The map regarding
material transport processing has already submitted in the
previous report.
The mitigation implemented
with this regard is compliant
with its requirement.
Ensure any damage is documented and repaired. The monitoring indicated that there was no significant road
damage occurred and the contractor has repaired the
damage road immediately, as shown in Appendix 7.f.
The mitigation implemented
with this regard is compliant
with its requirement.
Monitor effectiveness of mitigation on road and
infrastructure.
The access road was not always in the form of pavement,
some of them still dirt road. The monitoring indicated that, if
the damaged road occurred, it would be immediately repaired
and there was no complaint filed by community, as presented
earlier in Appendix 7.f.
The mitigation implemented
with this regard is compliant
with its requirement.
8. Encroachment (Gunung Condong in West Kalimantan, Areas adjacent to RoW)
Ensure mitigation measures are in place with
respect to no hunting or wildlife collection, plant
or timber collection, or lighting of fires, or
possession of firearms, traps or snares, by
workers.
Monitor effectiveness of mitigation on
Encroachment impact.
The monitoring indicated that the project site constructed
to date was not located in the forest area and the
contractor has provided the warning sign that hunting is
prohibited during this project to avoid impact on ecological
valuable sites.
The awareness about the prohibition of hunting and wood
collection was delivered by the contractor in the toolbox
meeting, as shown earlier in Appendix 7.g, and there
have been no cases with this regard reported.
The implementation of this
monitoring is compliant with the
mean of monitoring defined
herein.
9. Occupational and Community Health and Safety (Construction Sites and Worker Camps)
Ensure mitigation measures are in place with
respect to construction phase and OHS and CHS
have been developed and are being
The monitoring results showed that the OHS plans have
been developed and well implemented in the construction
phase. The use of PPE was monitored before the work
The implementation of this
monitoring is compliant with the
mean of monitoring defined
46
No Aspect and Means of Monitoring Monitoring Implemented Compliance Status / Remarks
implemented. started.
The statistical data from the contractor HSE report,
informed that in December 2019, the total amount of worker
is 291 people and there was no accident occurred, based
on the related report in the Appendix 8.j.
The contractor has been informed workers related to this
mitigation, such as using PPE and obeys the procedure in
the construction area.
The Community Health, Safety, and Security Management
Plan were provided by the contractor to cover the CHS
procedure. The CHSSMP is considered to be implemented
well, because the contractor inform to the community in the
most crossed tower’s village (Parindu) related to this
issues.
The relevant evidence related to above description can be
seen in Appendix 7.i and 7.j.
herein.
Monitor effectiveness of mitigation on
Occupational and Community Health and Safety.
The mitigation of OHS has been effectively implemented as
evidenced there is no accident reported during this
monitoring period. On the other side, the CHS mitigation has
been implemented by the contractor with conducting the
socialization to the community.
10. Physical Cultural Resources (Construction Sites)
Ensure mitigation measures are in place with
respect to implementation of chance find physical
cultural resources awareness and applied if
required.
Monitoring indicated that the chance-find procedures on the
cultural resources are in place and the construction workforce
have been informed on this matter during the toolbox meeting
(as shown in Appendix 7.h).
The implementation of this
monitoring is compliant with its
requirement.
Monitor effectiveness of mitigation on physical
cultural resources.
During this monitoring report, it was not applicable because
there were no physical cultural resources found in this
reporting period.
Not applicable.
47
Chapter 5 Findings on EMP Implementation and Corrective Actions
As elaborated in Chapters 3 and 4 of this monitoring report, both PLN and its contractors have
put their efforts to comply with most environmental mitigation and monitoring requirements
defined in the project’s IEEs. However, few items remain partially compliant due to legacy from
the former PIC or overlook during the transition from project to operational personnel. Table 5.1
summarizes these items including recommended corrective actions, responsible party and
timeline to bring them into compliance.
48
Table 5.1 Findings on EMP Implementation and Corrective Actions
No Aspects / Findings Corrective Actions Responsible Parties
(and Due Date) Remarks
Operation Phase
Package 1: Bengkayang-Jagoibabang Transmission Lines
Package 2: Bengkayang Substation
Package 3: Bengkayang-Ngabang-Tayan Transmission Lines
Package 4: Ngabang Substation and 1st Extension of Tayan Substation
1. Vegetation Management (HVTL alignment, RoW)
There was no evidence suggesting the
prohibition for the use herbicides as anticipation
if vegetation management is undertaken.
Develop a related document e.g. instruction
prohibiting the project to use herbicides; and
reportthe monitoring of this in the site
inspection record, minutes of meeting or other
documents as appropriate. Until now, this
mitigation is undergoing discussion with
UP3B KALBAR.
PLN UP3B KALBAR
(Q2/2018)
This aspect
remains pending
from the previous
semesters.
2. Occupational and Community Health and Safety (HVTL alignment, Substations)
The current OHSMS of PLN’s UP3B was also
used as the community health & safety plan, and
it does not include specific procedures on,
among others: live power line, working at height,
electromagnetic field; and community safety.
The procedures for the operation phase of
substation have been established in the
OHSMS PLN’s West Kalimantan Dispatch
Unit (No.SMK3/AP2B/U/P/16 dated on
June 21, 2017), covering, among others:
- Emergency response procedures;
- Conductor transfer on tower
emergency;
- Taking unwanted objects on High
Voltage and Extra High Voltage
Transmission Lines;
- Handling and storage of hazardous
materials
In the UP3B Kalbar’s Maintenance Procedure, the community health and
safety was added to point 5.7 which refer
to PERDIR No. 0252.P/DIR/2016 about
general safety guidelines (as shown earlier
in Appendix 2.b).
PLN UP3B KALBAR
(Q2/2018)
The mitigation
implemented with
this regard is
compliant with its
requirement.
49
No Aspects / Findings Corrective Actions Responsible Parties
(and Due Date) Remarks
Package 3: Bengkayang – Ngabang – Tayan Transmission Lines (Operation Phase)
1. Vegetation Removal (HVTL alignment)
There is no formal documentation indicating that
the Project does not use herbicides for pest
management.
Develop a related document e.g. instruction
prohibiting the project to use herbicides; and
report the monitoring of this in the site
inspection record, minutes of meeting or other
documents as appropriate.
KEC International Ltd
(Q2/2018)
Until the construction
has been finished,
the contractor has
not closed this issue.
Therefore, this
aspect remains
pending from the
previous
semesters.
2. Acid sulphate soils (HVTL alignment)
There was no formal documentation, procedures
or awareness on mitigation requirements related
to the potential acid sulphate soils in the project
areas.
Conduct awareness to workers regarding the
potential presence of acid sulphate soil at the
construction site and provide management
directions if this type of soil is encountered.
Evidence can be delivered in the form of MoM
meetings, attendance list and handout of
capacity building.
PLN UIP KALBAGBAR
KEC International Ltd
(Q1/2018)
Until the construction
has been finished,
the contractor has
not closed this issue.
Therefore, this
aspect remains
pending from the
previous
semesters.
3. Encroachment into Protected Forest, Hunting and Wood Collection
There was no sign or procedure to all workers
about the prohibition to accessing forest and
forest products, including maintaining firearms
on the Project areas
Develop the required instruction and
communicate it through safety or minutes of
meeting as appropriate
PLN UIP KALBAGBAR,
KEC International Ltd
(Q2/2018)
Until the construction
has been finished,
the contractor has
not closed this issue.
Therefore, this
aspect remains
pending from the
previous
semesters.
4. Occupational Health and Safety
EHS plan did not provide identification and
minimization of potential hazards to worker,
including corresponding preventive and
Develop a related procedure or other
documents as appropriate and consistently
enforce the implementation of the procedures
KEC International Ltd
(Q2/2018)
Until the construction
has been finished,
the contractor has
50
No Aspects / Findings Corrective Actions Responsible Parties
(and Due Date) Remarks
protective measures. and increase its supervision. not closed this issue.
Therefore, this
aspect remains
pending from the
previous
semesters.
5. Community Health and Safety
There was no procedure for interaction with
local and regional emergency and health
authorities in EHSP document.
Contractor submitted procedures for
interaction with local and regional
emergency and health authorities in EHSP
document.
KEC International Ltd
(Q2/2018)
Until the construction
has been finished,
the contractor has
not closed this issue.
Therefore, this
aspect remains
pending from the
previous
semesters.
6. Physical Cultural Resources
The chance to find procedures to identify and
manage physical cultural resources in the
project area has not been developed.
Develop a chance find procedure considering
the requirements of the Project’s IEE (2011). PLN UIP KALBAGBAR,
KEC International Ltd
(Q2/2018)
Until the construction
has been finished,
the contractor has
not closed this issue.
Therefore, this
aspect remains
pending from the
previous
semesters.
Package 5: Tayan (2nd
Extension), Sanggau and Sekadau Substation (Construction Phase)
1. Water Contamination
Sanggau and Sekadau SS - Submit the
engineering drawing of the undergound oil-water
separator to be constructed for the transformer.
The drawing should be reviewed by the
Contractor and PLN prior to submission to ADB.
Develop the engineering drawing of the
underground oil-water separator as required
in the IEE.
UIP KALBAGBAR
The engineering
drawing of the
underground oil-
water separator has
not been submitted
yet.
51
No Aspects / Findings Corrective Actions Responsible Parties
(and Due Date) Remarks
Package 6: Tayan – Sanggau Transmission Lines (Construction Phase)
1. Impact on Peat Land Areas
Obtain formal advice from MoEF to confirm
whether specific permit is required by PLN to
construct towers in peat land areas.
Follow up the formal advice from MoEF to
confirm whether specific permit is required by
PLN to construct towers in peat land areas.
DIV PPT – PLN PLN trough HSSE
Division has followed
up to process the
formal advice to
confirm whether
specific permit was
required for PLN to
construct the towers
in peat land areas
based on letter No.
0007/KLH.01.01/
010405/2020 dated 9
January 2020. It is
still waiting for the
response from the
MoEF.
Package 7: Sanggau – Sekadau Transmission Lines
1. Community Health and Safety
Provide a detailed review of the EHS and
community risk and corresponding mitigation of
PT Krakatau Engineering’s EHS plan, particularly for the tower construction that will
cross Kapuas River. The results of the review
should be appropriately communicated to key
Project’s stakeholder.
Develop the detail review of the EHS and
community risk, particularly for the tower
construction that will cross Kapuas River and
communicated this issues to the community
near the Kapuas River.
UIP KALBAGBAR Partially – The
related JSA (Job
Safety Analysis)
including the EHS of
Packages 6 & 7 was
submitted in the
previous report. The
socialization to the
community will be
conducted before the
constructions begin.
It is scheduled on
semester 1/2020.
52
Chapter 6 ADB Mission Findings
A joint review mission from ADB and PLN was conducted on 6-monthly basis, with the last
mission was conducted in in October 2019 to assess the project’s performance including safeguard aspects. Key findings of the mission including corresponding corrective actions up to
the last mission and responsible party are presented in Table 6.1. The findings of the previous
missions that have been completed in the period of 1st semester/2019 monitoring report are no
longer presented in this report.
Table 6.1 ADB Mission Findings (Cumulative up to December 2019)
No Findings Responsible
Party
Corrective Action
(and status)
Pending Items from the Previous Missions
1 Tayan substation - provide the valid
license for the excavator.
UIP
KALBAGBAR
Completed – the contactor had provided the
valid license for the excavator as shown in
Appendix 9.a.
2 Sanggau substation - submit the
engineering drawing of the undergound oil-
water separator to be constructed for the
transformer. The drawing should be
reviewed by the Contractor and PLN prior to
submission to ADB. The same issue was
identified during last ADB mission.
UIP
KALBAGBAR
Pending – The engineering drawing of the
underground oil-water separator has not been
submitted yet until the 2nd
semester of 2019
reporting.
3 Tayan, Sanggau and Sekadau
substations - Community Health & Safety
Plan for the substation
construction/operation has not been
developed.
UIP
KALBAGBAR
Completed – Both of the contractors already
submit Community Health, Safety and
Security Management Plan regarding to
CHSP and approved in July 2019
(Appendices 6.k and 7.j).
4 Tayan-Sanggau-Sekadau transmission
lines - Overlay in a map the location of all
tower sites (Packages 6 and 7) that are
potentially located in forest and peat land
areas prohibited for development according
to the Forest/Peat land Moratorium Map
Revision XV (issued by MOEF in December
2018). The same issue was identified during
last ADB mission.
UIP
KALBAGBAR
Completed – PLH has obtained the overlay
map according to letter from Balai
Pemantapan Hutan Wilayah III No.
S.699/BPKH.III/PKH/PLA.1/11/2019 dated on
11 November 2019 (as shown in Appendix
9.b)
5 Tayan-Sanggau-Sekadau transmission
lines - provide a detailed review of the EHS
and community risk and corresponding
mitigation of PT Krakatau Engineering’s EHS plan, particularly for the tower
construction that will cross Kapuas River.
The results of the review should be
appropriately communicated to key
Project’s stakeholder.
UIP
KALBAGBAR
Partially – The related JSA (Job Safety
Analysis) including the EHS of Packages 6 &
7 was submitted in the previous report. The
socialization to the community will be
conducted before the constructions begin. It is
scheduled on semester 1/2020.
53
No Findings Responsible
Party
Corrective Action
(and status)
Items Identified at the October 2019 Mission
Bengkayang – Ngabang – Tayan transmission lines
6 Report the implementation on monitoring of
tree growth along the RoW of the
transmission line.
UP3B
KALBAR
Completed – UP3B have the monitored the
tree growth along the ROW of the
transmission line as shown in Appendix 9.c
Ngabang Substation and Phase I Extension of Tayan Substation (Package 4)
7 Provide evidence e.g. slide presentation
and attendance list related to dissemination
on waste management practice conducted
for the employees at Ngabang substation.
UP3B
KALBAR
Completed - UP3B already conducted waste
management practice for the employees at
Ngabang Substation as shown in Appendix
9.d.
8 Remove the used oil stored at Ngabang
substation to Singkawang substation
dedicated to store used oil/hazardous
waste.
UP3B
KALBAR
Completed - These drums have been
transported to Singkawang substation (As
shown earlier in Appendix 5.b).
Sanggau and Sekadau Substations and Phase II Extension of Tayan Substation (Package 5)
9 Tayan substation - clean up remaining
construction waste; and install hazard
warning signs at the fence of the switch
yard.
UIP
KALBAGBAR
Completed – The contractor already clean up
construction waste remaining in the
substation and install warning signs at the
fence of the switch yard, as shown in
Appendix 9.e.
10 Sanggau substation - periodically remove
the sediment from the permanent drainage
channel as part of maintenance
UIP
KALBAGBAR
Completed – The contractor has periodically
conduct drainage cleaning and made this
issues as part of maintenance, as shown in
Appendix 9.f.
11 Sanggau and Sekadau substation -
construct the oil containment (bund wall)
facility and associated oil-water separator
as required by IEE. The same issue was
identified during previous ADB mission.
UIP
KALBAGBAR
Pending – The engineering drawing of the
underground oil-water separator has not been
submitted yet.
12 Sekadau substation - construct a
temporary drainage channel and sediment
trap to control contaminated runoff from
stockpile of cut materials (at the back of the
substation site).
UIP
KALBAGBAR
Completed – the construction of temporary
drainage channel and sediment trap for the
back of the substation has conducted to
control containment runoff from stockpile of
cut materials as shown in Appendix 9.g.
14 Sekadau substation - reinforce the
mandatory use of proper PPE including
safety shoes to the employees of PT Mitra
Kalbar (Siemens’ civil contractor at Sekadau) and smoking prohibition at works.
UIP
KALBAGBAR
Completed – the socialization related to the
use of proper PPE was conducted on 3
November 2019 as shown in Appendix 9.h.
Tayan – Sanggau Transmission Lines (Package 6) and Sanggau – Sekadau Tranmission Line (Package 7)
15 Obtain formal advice from MoEF to confirm
whether specific permit is required by PLN
to construct towers in peatland areas.
DIV PPT –
PLN
Partailly – PLN trough HSSE Division has
followed up to process the formal advice to
confirm whether specific permit was required
54
No Findings Responsible
Party
Corrective Action
(and status)
for PLN to construct the towers in peat land
areas based on letter No.
0007/KLH.01.01/010405/2020 dated 9
January 2020. It is still waiting for the
response from the MoEF (as shown in
Appendix 9.i).
16 Document the decision including
justification (e.g photo and EHS personnel
assessment) to install or not to install a
retaining wall (turap) at each tower site
subject to future construction; Use the
existing HSE reporting mechanism to
document this solution this solution at each
tower site
UIP
KALBAGBAR
Completed – The decision related to this
issues already reported in the Request for
Inspection (RFI) document based on the
tower site condition as shown in Appendix
9.j.
Semi-annual Environmental Monitoring Report
17 Action items that are identified as pending,
partially complete or not yet undertaken as
of S2/2018 and S1/2019 reports should be
reported in subsequent environmental
monitoring report.
From S2/2019 report onwards
55
Chapter 7 Conclusions and Recommendations
The 2nd semester/2019 environmental monitoring report describes the environmental mitigation
and monitoring conducted by the PLN West Kalimantan Power Grid Strengthening Project for
the period of July to December 2019 and evaluates its compliance against the Initial
Environmental Examination (IEE) documents of 2011 and 2016.
Related PLN units i.e., UIP KALBAGBAR (in charge of the construction of packages 5 to 7) and
UP3B KALBAR (in charge of the operation of packages 1 to 4) have been primarily
implementing the environmental mitigation and monitoring, and therefore considered compliant
with the requirements of IEE.
Nevertheless, there is a non-compliant with the requirements of IEE, identified as those related
to vegetation management due to the absence of documentation with this regard.
The key issues associated with the above shortfalls are incomplete evidence and delays in the
preparation of herbicides prohibition procedures as specified in the IEE.
The contractors shall improve their performance in presenting monthly reports submitted to
PLN, including: complete and accurate data of the mitigation items in accordance with the
requirements mentioned in the IEE 2011 and IEE 2016 documents completely; and complete
evidence of the implementation of mitigation measures in the form of photos, supporting
documents as well as relevant drawing.
Related PLN units in charge of the project and operations for West Kalimantan areas should
cooperate closely in addressing the key non-compliances or outstanding items that have not
been addressed since 2017.
APPENDIX 1
PROJECT ORGANIZATION CHART
PROJECT ORGANIZATION CHART
Note:
TL : Transmission Line
SS : Substation
APPENDIX 2
IMPLEMENTATION OF MITIGATION MEASURES
AT 275 kV BENGKAYANG-JAGOIBABANG TRANSMISSION LINE
(OPERATION PHASE)
2.a Increased Access
The access road to tower is returned to its original after the construction completed in T.10 Tiga Berkat
Village, Bengkayang District.
No permanent access roads to RoW in T.10 Tiga Berkat Village, Bengkayang District.
2.b Health and Safety
Maintenance procedures point 5.7 refer to PERDIR No. 0252.P/DIR/2016
PT PLN (Persero) UNIT PELAKSANA PENYALURAN DAN PENGATUR BEBAN SISTEM KALIMANTAN BARAT
PROSEDUR PEMELIHARAAN No. Dokumen SMK3/UP3B/P/22 Edisi / Revisi 00 / 01 Berlaku Efektif 1 Juli 2019 Halaman 6 dari 7
Dokumen ini tidak dapat digandakan tanpa izin tertulis dari WMK3
4.5. Working Permit atau ijin kerja : formulir yang berisi tentang uraian Pekerjaan, JSA/ SOP/ Instruksi kerja yang menjelaskan cara bekerja aman, Ketersediaan APD.
5. TANGGUNG JAWAB
5.1. Manager PT PLN (Persero) Unit Pelaksana Penyaluran dan Pengatur Beban Sistem Kalbar bertanggung jawab terhadap seluruh rangkaian prosedur pemeliharaan dan operasional sistem kelistrikan khatulistiwa di PT PLN (Persero) Unit Pelaksana Penyaluran dan Pengatur Beban Sistem Kalbar.
5.2. Manager Bagian Penyaluran bertanggung jawab terhadap pelaksanaan prosedur pemeliharaan di PT PLN (Persero) Unit Pelaksana Penyaluran dan Pengatur Beban Sistem Kalbar.
5.3. Manager Bagian Keuangan dan Administrasi bertanggung jawab terhadap realisasi anggaran. 5.4. Pengawas K3 bertanggung jawab terhadap Keselamatan dan Kesehatan Kerja (K3) pada prosedur
pemeliharaan, sehingga keselamatan manusia dan keselamatan instalasi listrik terjamin. 5.5. Pengawas Pekerjaan bertanggung jawab terhadap mutu pemeliharaan agar sesuai dengan prosedur
pemeliharaan dan laporan hasil pekerjaan. 5.6. Pengawas Manuver bertanggung jawab terhadap proses manuver (pembebasan / pemberian tegangan) pada
instalasi listrik tegangan menengah, tinggi / ekstra tinggi, sehingga keselamatan peralatan dan operasi sistem terjamin.
5.7. Pengawas K3 dan Pekerjaan bertanggung jawab untuk memastikan keselamatan masyarakat umum (Sekitar) yang ada di dekat sarana /objek pemeliharaan pada saat proses pemeliharaan dan sesudah pemeliharaan .
Kondisi Khusus : Apabila tidak terpenuhi dalam satu pekerjaan jumlah pengawas pekerjaan dan pengawas K3, maka dalam hal khusus (pekerjaan dengan tingkat resiko ringan) 2 fungsi pengawasan tersebut bisa dirangkap oleh satu pengawas yang berkompeten untuk melakukan kedua obyek pengawasan tersebut. Proses Pemeliharaan menjunjung kaidah keselamatan kerja,instalasi,umum ,lingkungan
6. URAIAN PROSEDUR
6.1. Perencanaan 6.1.1 Masing-masing bagian membuat Perencanaan Pemeliharaan mengacu pada RKAP tahunan untuk
membuat jadwal pemeliharaan rutin dan Non-rutin di wilayah kerja PT PLN (Persero) Unit Pelaksana Penyaluran dan Pengatur Beban Sistem Kalbar. Perencana pemeliharaan melakukan Identifikasi bahaya, penilaian resiko dan pengendalian terhadap rencana kegiatan pemeliharaan dengan menggunakan formulir Identifikasi bahaya.
6.1.2 Masing-masing bagian selanjutnya membuat perencanaan aktivitas pemeliharaan serta membuat RAB dan selanjutnya diserahkan kepada masing-masing Supervisor sebagai pelaksana pekerjaan pemeliharaan, RAB pemeliharaan Rutin dan Korektif yang kemudian disampaikan kepada Manager untuk disetujui anggaran.
6.2. Pengorganisasian 6.2.1 Pengajuan working permit maksimal setiap H-3 tanggal dimulai pekerjaan untuk pekerjaan yang
mengharuskan ada pemadaman. Manager Bagian terkait mengeluarkan nota dinas susunan pelaksana, pengawas dan jenis pemeliharaan dan surat perintah kerja kepada Manager Tragi / Spv terkait.
6.2.2 Manager Bagian menginventarisir ketersediaan dan kelengkapan material dan peralatan pemeliharaan.
Anti-Climbing Devices (ACD) in T.10 Tiga Berkat Village, Bengkayang District.
The tower has been equipped with lock nut and warning sign in T.10 Tiga Berkat Village, Bengkayang
Dsitict.
2.c Avian Collisions
Avian Collisions Report
The supervisor was interviewing local people about dead bird or other dead animals under the line of T.03
in Sebalo Village, Bengkayang District.
APPENDIX 3
IMPLEMENTATION OF MITIGATION MEASURES
AT 275 kV BENGKAYANG SUBSTATIONS (OPERATION PHASE)
3.a Noise
Noise Monitoring Result
3.b Soil and Water Contamination
The oil containment below the transformer in 275 kV Bengkayang Substation
The oil trap in 275 kV Bengkayang Substation
Training for Substation’s Operator
/ /
PRO“EDUR “MK PENANGANAN BAHAN B
PLN UP B PONTIANAK
Apa Itu B ?? • B Baha Ber ahaya da Bera u adalah ahaya g kare a sifat da atau ko se trasi ya daatau ju lah ya aik se ara la gsu g auputidak la gsu g dapat e e arka da atauerusak li gku ga hidup da atau dapate ahayaka li gku ga hidup, kesehata ,
kela gsu ga hidup a usia serta akhluk hiduplai ya.
Klasifikasi B PP No. 7 Th . Mudah Meledak. Pe goksidasi. “a gat Mudah “ekali Me yala. Me yala. A at “a gat Bera u. “a gat Bera u. Bera u. Ber ahaya. Korosif. Bersifat Iritasi. Ber ahaya Bagi Li gku ga. Karsi oge ik. Teratoge ik. Mutage ik
MSDS Material Safety Data Sheet . Dise ut juga Le ar Data Kesela ata Baha. Merupaka i for asi atas sifat ki ia da fisika
dari aha ki ia terse ut, ter asuk erisii for asi e ge ai kesehata dakesela ata , pe yi pa ga da pe ua gali ah da ke asa sehu u ga de gape ggu aa aha terse ut
I for asi dala M“D“
I for asiu ute ta gaha
I for asi ko po e er ahaya
Reakti itas aha
“ifat udah ter akar ya
aha“ifat fisika & ki ia aha
Da pak kesehata
Pertolo ga perta a Pe yi pa a
Pe a ga a Baha BPetugas di erikapelatiha terkait
M“D“Me gide tifikasi
je is ahaMelokalisir te pat
tu paha
Pe yerapatu paha
Pe etralatu paha
Pelaporakejadia
Pe a tauaBaha B
Me gide tifikasi je is baha. Bila terjadi tu paha segera lhat ta le ide tifikasi pada ke asa
terse ut. “egera a a M“D“ dari aha terse ut u tuk eyaki ka ahaya
ya g di iliki aha ya g tu pah terhadap a usia da li gku ga. Dari M“D“ segera ke ali pula sifat aha terse ut apakah korosif,
udah ter akar, era u , dll
Note : U tuk aha ya g udah ter akar atau udah eledak segerasiapka alat pe ada api ri ga ya g sesuai saat e a ga itu paha tadi
/ /
Melokalisir Te pat Tu paha. U tuk aha er e tuk ser uk atau utira segera upayaka
ti daka e ghala gi ya agar tidak tertiup a gi. U tuk aha air ya g tu pah di darat, pelokalisira dapat
e ggu aka lap kai atau pasir de ga tujua aira tidake ye ar
. U tuk aha air ya g tu pah di su gai, teruta a solar, segeralokalisir de ga e ggu aka a apu g ya g tidak e iliki elahagar aha air tidak e ye ar
. Pega ai / ora g ya g tidak erkepe ti ga dilara g ele ati areatu paha ya g di eri ta da pita/tali ku i g de ga peri gataAWA“ TUMPAHAN
Pe yerapa Tu paha. U tuk aha er e tuk ser uk segera ersihka de ga a tua
sapu atau alat seje is. U tuk sisa ser uk dapat dia gkat de gakai ya g telah di asahi le a . Kai ya g sudah digu ka tidakoleh digu aka ke ali u tuk kegiata lai da ter asuk
dia ggap li ah.. U tuk aha er e tuk air, segera serap de ga kai keri g ya g
e iliki daya hisap ya g aik. Pe yerapa dilakuka sa paiper ukaa e ar‐ e ar keri g
. U tuk aha solar ya g tu pah disu gai pe yerapa dilakukade ga usa, apa ila tu paha solar diatas per ukaa air ukupte al aka pe yerapa dapat di a tu de ga po pa. Tahap akhirarulah diserap de ga usa. Busa ha is pakai dia ggap se agai
li ah
Pe etrala Tu pahaPe etrala dilakuka ila dia ggap diperluka kare a aha er ahayaterse ut dia ggap terlalu ti ggi ko se trasi ya atau dipersyaratka olehM“D“ aha ya g tertu pah tadi
Pelapora KejadiaPelapora kejadia e ggu aka for pelapora i side / accident
Pelapora Kejadia“e ara periodik “uper isor logisti elakuka pe a taua terhadappe akaia da pe yi pa a B da hasil ya di atat pada For ulirChe klist I speksi da Nera a
TERIMA KASIH
3.c Health and Safety
Fences and Security post in 275 kV Bengkayang Substation
Fire Extinguisher in 275 kV Bengkayang Substation
APPENDIX 4
IMPLEMENTATION OF MITIGATION MEASURES
AT 150 kV BENGKAYANG-NGABANG-TAYAN TRANSMISSION LINE
(OPERATION PHASE)
4.a Increased Access
The vegetation near RoW grows naturally after the construction has been finished in T.38 Mayak Village
There is no permanent access roads towards RoW in T.13 Sebalo sub-district.
4.b Health and Safety
Warning signs in tower T.38 Bengkayang – Ngabang 150kV TL
Tower has been equipped with anti-climbing devices in T. tower T.38 Bengkayang – Ngabang 150kV TL
4.c Avian Collisions
Avian Collisions Report
The supervisor was interviewing local people about dead bird or other dead animals under the line along Bengkayang – Ngabang 150kV TL
APPENDIX 5
IMPLEMENTATION OF MITIGATION MEASURES
AT 150 kV NGABANG AND TAYAN SUBTATIONS (OPERATION PHASE)
5.a Noise
Noise Monitoring Result
5.b Soil and Water Contamination
The oil containment below the transformer in 150 kV Ngabang Substation
The oil pit in 150 kV Ngabang Substation
Nine drums of used oil were stored on concrete floor surrounded by drainage system connected to
a sump pit.
The used oil drums were transported to Singkawang Substation.
Material Handling and Storage Procedures Point 6.8
PT PLN (Persero)
UNIT PELAKSANA PENYALURAN DAN PENGATUR BEBAN SISTEM KALIMANTAN BARAT
PROSEDUR PENANGANAN DAN PENYIMPANAN BAHAN
No. Dokumen SMK3/UP3B/P/16
Edisi / Revisi 00 / 00
Berlaku Efektif 1 Juli 2019
Halaman 10 dari 10
Dokumen ini tidak dapat digandakan tanpa izin tertulis dari WMK3
6.8. Pembuangan Bahan / Limbah
6.8.1. Melaksanakan pembersihan, pengeluaran dan pengangkutan bahan atau limbah sesuai peraturan yang
berlaku.
6.8.2. Bahan atau limbah yang belum dibuang, disimpan sementara di tempat penyimpanan sementara sesuai
dengan peraturan yang berlaku.
6.8.3. Mencatat bahan atau limbah yang telah dibersihkan, dikeluarkan dan diangkut.
6.8.4. Fungsi logistik dan atau K3L melaporkan data bahan atau limbah kepada Manager Bagian terkait dan
Manager UP3B untuk dilakukan verifikasi dan dilaporkan setiap 3 bulan sekali.
7. LAMPIRAN
7.1 Formulir daftar bahan B3 (SMK3/UP3B/F/16.001)
5.c Health and Safety
Warning sign in the switchyard of 150 kV Ngabang Substation
Security Personnel at the 150 kV Ngabang Substation
PPE for the visitors in 150 kV Ngabang Substation
Fire extinguishers in the switchyard area of 150 kV Ngabang Substation
APPENDIX 6
THE MITIGATION IMPLEMENTATIONS OF
150 kV TAYAN EXTENSION, SANGGAU AND SEKADAU
SUBSTATIONS (CONSTRUCTION PHASE)
6.a Vegetation Clearing
Attendance List of Toolbox Meeting for socializing the prohibition of herbicides use and burning
vegetation and waste
Prohibition of herbicide usage around the Sanggau Substation (20 November 2019)
Prohibition of burning waste around the Sekadau Substation (21 November 2019)
6.b Soil Erosion
Sand Cone Test Acknowledgement
The Checklist Related to Soil Erosion Control in Quarterly Report
No Item Pemeriksaan Terpe
nuhi
Tidak
Terpe
nuhi
Detil Temuan Usulan
Tindakan Perbaikan Photo
2. EROSI TANAH
2B b) Area Gardu Induk:
Pemadatan tanah di daerah tanggul, harus ditanami kembali dengan rumput lokal, dan ditutupi dengan lapisan jerami padi atau bahan serupa untuk mencegah erosi.
Pembangunan perlindungan lereng (misalnya dinding penahan, bronjong dll). Dan penanaman semak belukar vegetasi dan rumput di kontur lereng yang terbuka.
area terbuka yang tidak digunakan akan ditutupi rumput dan tanaman kecil.
Langkah-langkah pengendalian erosi tanah akan secara teratur diperiksa dan dipelihara selama konstruksi dan sampai area tersebut stabil atau ditanami kembali.
√
√
Gardu Induk Sanggau
Pada area gardu induk
dilakukan pemadatan tanah
dan di buatkan sediment trap
(drainase temporary) sebagai
upaya pengendalian erosi.
Gardu Induk Sekadau
Pada area gardu induk
dilakukan pemadatan tanah
dan di buatkan sediment trap
(drainase temporary) sebagai
upaya pengendalian erosi.
Di lakukan perawatan
berkala terhadap saluran
sediment trap agar selalu
bekerja efektif.
Perawatan berupa
pengambilan endapan jika
sudah menumpuk,
pembersihan dari sampah
dan juga pembersihan dari
rumput atau vegetasi lainnya
yang dapat mengganggu
efektifitas saluran.
6.c Drainage
Drainage Approved Drawing Plan in Sekadau Substation
Drainage cleaning in the Sanggau Substation (24 October 2019)
Drainage construction in the Sekadau Substation (1 November 2019)
6.d Water Quality Impacts
Temporary oil and fuel storage at Sanggau SS A container wrapped with tarpaulin is used to
prevent oil spill during oil changing in Sanggau SS
Oil changing using hose in the Sekadau SS, to prevent oil spill using oil secondary containment
underneath.
Temporary oil and fuel storage at Sekadau SS
equipped with sign, MSDS, spill kit, and fire
protection system (Portable Fire Extinguisher
type DCP) (14 November 2019)
6.e Air Quality Impacts
The water spraying was conducted at the Sanggau SS construction site, since dust level is considered
high
Spraying water on the road to remove the remaining soil in Sanggau Substation
6.f Construction Waste Management
Organic and non-organic waste has already separated in Sekadau SS (15 October 2019)
Sekadau Final disposal facilities, in Sekadau-Sanggau street Km. 6, Sekadau Hilir Sub-district
6.g Domestic Waste Management
Worker camp in Sekadau (21 November 2019) Sanitation facilities in the Sekadau’s work camp ( 21
November 2019)
Trash bin in Sanggau’s worker camp Sekadau Final disposal in Sekadau-Sanggau st.
Km. 6, Sekadau Hilir Sub-district
6.h Encroachment into Protected Forests, Hunting, Wood Collection
Attendance List of Toolbox Meeting for socializing the prohibition of hunting and wood collection
Prohibition of hunting in Sanggau Substation
6.i Impacts on Cultural Heritage Sites
Attendance List of Toolbox Meeting for Socializing Related to Cultural Heritage
Awareness regarding cultural heritage and resources during toolbox meeting in Sekadau Substation (30 July 2019)
6.j Occupational Health and Safety
PPE usage for the workers (28 November 2019) First aid kit (22 November 2019)
EHS statistic board (1 November 2019) Emergency response procedures
Training attendance list regarding to HIV/AIDS awareness
6.l Community Health and Safety
PT Siemens Indonesia’s Community Health, Safety and Security Management Plan
Scanned by CamScanner
Emergency vehicle services in Sanggau Substation (20 November 2019)
Emergency vehicle services in Sekadau Substation ( 27 November 2019)
Provide Fire Extinguisher in Sanggau Substation Fire Extingusher Inspection in Sekadau Substation
(26 October 2019)
Safety sign around construction site in Sanggau substation
Safety sign around construction site in Sekadau substation (29 November 2019)
Community Health, and Safety Socialization to Local People
Socialization related to communicable disease (Dengue Hemorrhagic Fever) in Tayan Hilir (16 February 2019)
Socialization related to communicable disease (Syphilis) in Mungguk Village (13 August 2019)
APPENDIX 7
THE MITIGATION IMPLEMENTATIONS OF
150 kV TAYAN – SANGGAU – SEKADAU TRANSMISSION LINE
(CONSTRUCTION PHASE)
7.a Vegetation Clearing
The remaining vegetation removal woods will be
used by the people around the project (7
September 2019)
The remaining vegetation removal woods will be
used by the people around the project in T. 41 (10
October 2019)
Warning sign related to the prohibition of herbicide and hunting animal in T. 182, Temiang Taba Village
(26 November 2019)
Attendance list of toolbox meeting for socializing prohibition of herbicides use, hunting animal
and burning vegetation and waste
7.b Soil Erosion
Tower adjusting was done in the location that the land is steep, it located in T.05R Sei Mawang Village
The vegetation cut was used to prevent land slide in T. 30 Tebang Benua Village
The Soil Erosion Report in the Contractor’s Monthly Report
7.c Water Quality Impacts
Temporary hazardous waste shelter located in
Sosok Village (30 October 2019)
Secondary containment in construction site T.166
Palem Jaya Village (6 August 2019)
Refueling of machinery using external drum to
prevent oil spill contaminate soil in T.61, Kebadu
Village (11 July 2019)
Under the drum engine for stringing work is
covered by tarp to prevent oil spill in T.116
(30 October 2019)
7.d Construction Waste Management
Trash bags that are distinguished based on type of
the waste in T. 136 Binjai Village, Sanggau District
(5 October 2019)
Waste collected, routinely dispose to the nearest
final disposal
Waste disposal to Sei Kosak disposal in Sanggau
District
Waste disposal to Sekadau disposal in Sekadau
District
7.e Domestic Waste Management
Mess for stringing worker in Binjai Village, Sanggau
District (25 October 2019)
Trash already provided in the worker camp
(26 October 2019)
Place workers to rest in the worker camp (26
October 2019)
Sanitation conditions in the worker camp that
rented from the local community (26 October 2019)
7.f Roads and Infrastructure Impacts
The bridge was damaged by material transportation in the Menyabo Village access roads
The contractor has been repaired the access road in Menyabo Village, Sanggau District
7.g Encroachment into Protected Forest, Hunting and Wood Collection
Attendance List of Toolbox Meeting for Hunting and Wood Collection
7.h Impacts on Cultural Heritage Sites
Attendance List of Toolbox Meeting for Socializing Related to Cultural Heritage
Ngudas was (traditional ceremony) performed before land clearance for ROW conducted in Menyabo Village, Sanggau District (16 October 2019)
7.i Occupational Health and Safety
PT Krakatau Engineering Job Safety Analysis
Scanned with CamScanner
The disposal of hazardous waste have been labelled based on its type
PPE usage during working at height in Palem Jaya Village (2 August 2019)
Stringing final check in T.166 First aid kit in T.47 Senyabang Village (17 July
2019)
PT Krakatau Engineering Internal Training
7.j Community Health and Safety
PT Krakatau Engineering Community Health, Safety and Security Management Plan
Emergency vehicle that provide by contractor (16 July 2019)
Safety sign related to erection tower in T.43 in Hilir Village (20 November 2019)
Safety line installation in T. 72 Senyabang Village (26 October 2019)
Socialization related to Community, Health, and Safety in Parindu Village
Community, health and safety socialization in Parindu Village (18 June 2019)
ROW Field Map for Mapping Community near Project Location
ROW Socialization Acknowledgement
APPENDIX 8
ENVIRONMENTAL MONITORING RESULT
8.a Health and Safety
Ground Patrol Inspection Form
DOKUMEN
PT PLN (PERSERO)
NOMOR : PDM/STT/10:2014
Lampiran Surat Keputusan Direksi
PT PLN (Persero) No. 0520-1.K/DIR/2014
BUKU PEDOMAN PEMELIHARAANSALURAN UDARA TEGANGANTINGGI DAN EKSTRA TINGGI
(SUTT/SUTET)
PT PLN (PERSERO)
JALAN TRUNOJOYO BLOK M-I/135 KEBAYORAN BARU
JAKARTA SELATAN 12160
SALURAN UDARA TEGANGAN TINGGIDAN EKSTRA TINGGI (SUTT/SUTET)
123
Lampiran 3 Formulir Inspeksi Level 1: Ground Patrol Transmisi
SALURAN UDARA TEGANGAN TINGGIDAN EKSTRA TINGGI (SUTT/SUTET)
124
VI PENGAMAN DARI ANCAMAN AKIBAT MANUSIA
1 ACD ( Penghalang Panjat ) Normal Korosi Kendor Hilang Patah
2 Plat rambu bahaya Normal Korosi Rusak Hilang Tidak terpasang
VII MONITORING
1 Baut panjat ( Step bolt ) Normal Korosi Kendor Hilang Patah
2 Plat informasi tower
Plat tanda penghantar Normal Korosi Rusak Hilang Tidak terpasang
KET : = Diisi dengan centang
CATATAN
(……………………………………….. )
Approval Pelaksana
( …………………………………………. )
8.b Oil, Fuels, Hazardous Materials
Hazardous waste was separated and labeled
8.c Drainage
Drainage cleaning periodically in the Sanggau Substation
8.d Soil Erosion
Temporary sediment trap to prevent soil erosion in the Sanggau Substation
8.e Water Quality
Water Quality Monitoring for Package 5 (Sanggau SS) in Collaboration with Senayan
Pembangunan
8.f Air Quality
Air Quality Monitoring for Package 5 in Collaboration with PT Sucofindo
8.g Encroachment
Supervisor Monitoring
No Item Pemeriksaan Terpe
nuhi
Tidak
Terpe
nuhi
Detil Temuan Usulan
Tindakan Perbaikan Photo
9. PERAMBAHAN KE HUTAN PRODUKSI, BERBURU, KOLEKSI KAYU
9A Perburuan, ekstraksi oleh pekerja dari hasil hutan seperti kayu bakar, dan pemeliharaan senjata api di Proyek, akan dilarang. Untuk menghindari dampak pada situs, habitat, hutan alam, ekologis flora dan fauna yang bernilai, risiko ini harus dipantau secara khusus selama pembangunan jalur Transmisi untuk melindungi ekologis sensitif: sepanjang 35 km antara Tayan dan Sosok di mana penyelarasan melewati dekat hutan sekunder. dalam cadangan hutan produksi; sepanjang penjajaran yang membentang (3,5 dan 11 km) ke hutan primer di Gunung Tiong Kandang dan Gunung Sanggau; dan sepanjang penjajaran yang melewati (1,5 km jauh) ke hutan primer dari Cagar Rekreasi Hutan Pancur Aji. (Transmisi)
√
Kontraktor melakukan upaya
pencegahan perburuan dan
perambahan hutan dengan
memasang rambu serta
melakukan sosisalisasi ke
pekerja melalui toolbox
meeting.
Dilakukan juga pengamatan
bersama oleh kontraktor dan
pengawas terhadap pekerja
selama jam kerja di lokasi
proyek bahwa pekerja tidak
melakukan perburuan dan
perambahan hutan
8.h Soil Erosion
Supervisor Monitoring
PT PLN (PERSERO) PUSAT MANAJEMEN PROYEK
SISTEM MANAJEMEN K3
FORMULIR CHECK LIST INSPEKSI LINGKUNGAN
TEMPAT KERJA - PROYEK JARINGAN
Tgl. Berlaku : No. Dok. : Edisi : Q4 Hal :5 dari 26
1E Penggunaan herbisida sangat dilarang keras. Dan tidak digunakan di lokasi kontruksi. (Transmisi)
√ Tidak digunakan herbisida pada saat pembersihan lahan tapak tower karena dilakukan secara manual.
Serta telah dilakukan pemasangan rambu – rambu dan safety talk terkait larangan penggunaan bahan Kimia seperti herbisida dan larangan pembakaran sisa vegetasi kepada pekerja.
Lampiran 1
1F Pembakaran vegetasi yang sudah dibersihkan tidak akan diizinkan; bahan ini akan digunakan untuk melindungi tanah dari erosi. (Transmisi)
√ Sisa vegetasi digunakan sebagai penahan erosi dengan cara tetap membiarkannya di dalam jalur ROW dan melakukan pengarahan untuk tidak melakukan pembakaran sisa vegetasi kepada pekerja.
Lampiran 1
2. EROSI TANAH
2A Langkah-langkah pengendalian erosi tanah telah dimasukkan ke dalam desain rekayasa, (misalnya ketinggian kaki menara yang dapat disesuaikan). (Transmisi)
√ Langkah pengendalian erosi dengan melakukan rekayasa panjang kaki tower yang disesuaikan dengan kontur tanah. Selain itu juga dilakukan pemasangan cerucuk untuk pengendalian erosi tanah fungsinya untuk menahan longsoran tanah.
Lampiran 2
PT PLN (PERSERO) PUSAT MANAJEMEN PROYEK
SISTEM MANAJEMEN K3
FORMULIR CHECK LIST INSPEKSI LINGKUNGAN
TEMPAT KERJA - PROYEK JARINGAN
Tgl. Berlaku : No. Dok. : Edisi : Q4 Hal :6 dari 26
2B Mitigasi telah dirancang mengikuti pedoman
dan praktik konstruksi yang baik yang
disesuaikan untuk setiap Lokasi, misalnya:
a) Jalur transmisi:
(1) Pada kemiringan yang curam:
meminimalkan luas dan durasi gangguan lahan
menggunakan karung pasir, bank atau saluran untuk mengalihkan aliran air dari lereng di sekitar area yang terganggu;
menggunakan potongan vegetasi atau dedaunan untuk melindungi tanah yang terganggu secara sementara
(2) Pada daerah datar kering,
menggunakan potongan vegetasi atau
dedaunan untuk melindungi tanah yang
terganggu dari dampak air hujan untuk
sementara
(3) Sawah dan lahan basah tidak ada erosi
yang signifikan diantisipasi. (Transmisi)
√
Kontraktor telah melaksanakan mitigasi dengan membangun retaining Wall untuk menahan tanah sekitar area tower di T. 86. Pembanguan dilakukan karena lokasi tower berdekatan dengan lereng curam.
Lampiran 2
8.i Air Quality
Air Quality Monitoring for Package 6 in Collaboration with PT Sucofindo
Air Quality Monitoring for Package 7 in Collaboration with PT Sucofindo
8.j Occupational and Community Health and Safety
Data Statistic in PT Krakatau Engineering HSE Monthly Report
APPENDIX 9
Mission Findings
9.a License for Excavator
License for Excavator in Tayan Construction Site
SIO OPERATOR ALAT BERAT PACKAGE 5
9.b Implementation report to MoEF
Overlay Map according to Letter No. S.699/BPKH.III/PKH/PLA.1/11/2019
9.c ROW Monitoring
Tree Growth Monitoring along the ROW Transmission Line
UNIT UP3B SISTEM KALBAR
GARDU INDUK -
JENIS PERALATAN -
PENGHANTAR TRS 150 KV BENGKAYANG - NGABANG
TOWER / JOINT -
GROUNDPATROL -
JENIS FORMULIR FORMULIR TEGAKKAN
PILIHAN WAKTU RENTANG WAKTU
DARI TANGGAL 16-12-2019
SAMPAI TANGGAL 23-12-2019
LAPORAN INSPEKSI INTERNAL
No. PENGHANTAR TANGGAL PELAPOR LOKASI OBJEK JML X Y Z U KATEGORI KET. PHOTO
1 TOWER BENGKAYANG - NGABANG 170 23-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 5 15 12 3 BAHAYA I 171-172
2 TOWER BENGKAYANG - NGABANG 170 23-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I 171-172
3 TOWER BENGKAYANG - NGABANG 171 23-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF BUAH 3 15 3 13 2.3 BAHAYA I 172-173
4 TOWER BENGKAYANG - NGABANG 171 23-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 5 15 8 7 NORMAL 173-174
5 TOWER BENGKAYANG - NGABANG 172 23-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I 174-175
6 TOWER BENGKAYANG - NGABANG 172 23-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 5 15 15 0 - 173-174
7 TOWER BENGKAYANG - NGABANG 173 23-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 1 15 3 14 1.3 KRITIS 174-175
8 TOWER BENGKAYANG - NGABANG 173 23-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 5 15 7 8 NORMAL 174-175
9 TOWER BENGKAYANG - NGABANG 05A 23-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - LAINNYA 3 15 3 13 2.3 BAHAYA I pohon kayu span 05-06
10 TOWER BENGKAYANG - NGABANG 04A 23-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - LAINNYA 3 15 3 13 2.3 BAHAYA I pohon kayu span 04-05
LAPORAN INSPEKSI INTERNAL
No. PENGHANTAR TANGGAL PELAPOR LOKASI OBJEK JML X Y Z U KATEGORI KET. PHOTO
11 TOWER BENGKAYANG - NGABANG 109 23-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF BUAH 5 13 3 8 5.34 NORMAL pohon sawit. kayu lokal
12 TOWER BENGKAYANG - NGABANG 109 23-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I pohon karet
13 TOWER BENGKAYANG - NGABANG 107 23-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF BUAH 5 13 8 5 NORMAL pohon sawit
14 TOWER BENGKAYANG - NGABANG 055 23-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 8.5 3 5.5 3.51 BAHAYA II belum di ketahui
15 TOWER BENGKAYANG - NGABANG 055 23-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 8.5 3 5.5 3.51 BAHAYA II belum diketahui
16 TOWER BENGKAYANG - NGABANG 051 23-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 8.5 3 5.5 3.51 BAHAYA II pohon karet
17 TOWER BENGKAYANG - NGABANG 051 23-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 8.5 3 5.5 3.51 BAHAYA II pohon karet
18 TOWER BENGKAYANG - NGABANG 173 21-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I 174-175
19 TOWER BENGKAYANG - NGABANG 173 21-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 5 15 8 7 NORMAL 174-175
20 TOWER BENGKAYANG - NGABANG 175 21-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I 177-178
21 TOWER BENGKAYANG - NGABANG 175 21-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 3 15 16 - 177-178
22 TOWER BENGKAYANG - NGABANG 174 21-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - BAMBU 3 15 3 13 2.3 BAHAYA I 175-176
LAPORAN INSPEKSI INTERNAL
No. PENGHANTAR TANGGAL PELAPOR LOKASI OBJEK JML X Y Z U KATEGORI KET. PHOTO
23 TOWER BENGKAYANG - NGABANG 174 21-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I 175-176
24 TOWER BENGKAYANG - NGABANG 176 21-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I 177-178
25 TOWER BENGKAYANG - NGABANG 176 21-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - BAMBU 5 15 7 8 NORMAL 178-179
26 TOWER BENGKAYANG - NGABANG 177 21-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 5 15 12 3 BAHAYA I 179-180
27 TOWER BENGKAYANG - NGABANG 177 21-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I 179-180
28 TOWER BENGKAYANG - NGABANG 178 21-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 5 15 12 3 BAHAYA I 179-180
29 TOWER BENGKAYANG - NGABANG 178 21-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 6 15 2 13 2.13 BAHAYA I 179-180
30 TOWER BENGKAYANG - NGABANG 191 19-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 2 15 1 14 1.03 KRITIS jengkol
31 TOWER BENGKAYANG - NGABANG 191 19-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I tanaman liar
32 TOWER BENGKAYANG - NGABANG 190 19-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF BUAH 6 15 8 7 10 NORMAL kelapa sawit
33 TOWER BENGKAYANG - NGABANG 190 19-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF BUAH 3 15 7 8 NORMAL kelapa sawit
34 TOWER BENGKAYANG - NGABANG 189 19-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 17 10 6 4 BAHAYA II tanaman liar
LAPORAN INSPEKSI INTERNAL
No. PENGHANTAR TANGGAL PELAPOR LOKASI OBJEK JML X Y Z U KATEGORI KET. PHOTO
35 TOWER BENGKAYANG - NGABANG 189 19-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 2 10 4 6 4.77 NORMAL tanaman liar
36 TOWER BENGKAYANG - NGABANG 116A/276 19-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 13 4 9 4.6 NORMALada pohon kayu diluar jalur line 1 dan 2 pak jarak kayu tersebut ke konduktor sekitar 4 meter no span 278 ke
279 terima kasih.
37 TOWER BENGKAYANG - NGABANG 117/274 19-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 2 13 3 10 3.34 BAHAYA II ada pohon di luar jalur line 1 pak jarak pohon ke konduktor sekitar 3 meter.no span 276 ke 277
38 TOWER BENGKAYANG - NGABANG 117/274 19-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 1 13 10 3 BAHAYA I ada pohon di luar jalur line 2 pak.jarak pohon ke konduktor sekitar 3 meter no span 276 ke 277
39 TOWER BENGKAYANG - NGABANG 051 19-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 8.5 2 6.5 2.23 BAHAYA I pohon karet
40 TOWER BENGKAYANG - NGABANG 051 19-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 8.5 2 6.5 2.23 BAHAYA I pohon karet
41 TOWER BENGKAYANG - NGABANG 133 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 5 13 3 10 3.34 BAHAYA II kayu lokal
42 TOWER BENGKAYANG - NGABANG 133 18-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - BAMBU 5 13 10 3 BAHAYA I bambu
43 TOWER BENGKAYANG - NGABANG 132 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF BUAH 10 13 3 10 3.34 BAHAYA II pohon durian. nangka. kayu lokal
44 TOWER BENGKAYANG - NGABANG 132 18-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - BAMBU 3 15 3 13 2.3 BAHAYA I pohon sagu. jengkol karet
45 TOWER BENGKAYANG - NGABANG 131 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF BUAH 1 13 3 9 4.34 NORMAL pohon langsat
46 TOWER BENGKAYANG - NGABANG 186 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I pohon liar
LAPORAN INSPEKSI INTERNAL
No. PENGHANTAR TANGGAL PELAPOR LOKASI OBJEK JML X Y Z U KATEGORI KET. PHOTO
47 TOWER BENGKAYANG - NGABANG 186 18-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - BAMBU 3 15 3 13 2.3 BAHAYA I bambu
48 TOWER BENGKAYANG - NGABANG 078 18-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - BAMBU 3 15 3 13 2.3 BAHAYA I kritis
49 TOWER BENGKAYANG - NGABANG 078 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I kritis
50 TOWER BENGKAYANG - NGABANG 077 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 4 8.5 3 5.5 3.51 BAHAYA II rawan
51 TOWER BENGKAYANG - NGABANG 077 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 4 8.5 3 5.5 3.51 BAHAYA II rawan
52 TOWER BENGKAYANG - NGABANG 185 18-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 20 15 5 10 NORMAL tanaman liar
53 TOWER BENGKAYANG - NGABANG 185 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I pohon liar
54 TOWER BENGKAYANG - NGABANG 184 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF BUAH 1 15 3 13 2.3 BAHAYA I pohon durian
55 TOWER BENGKAYANG - NGABANG 184 18-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 30 15 5 10 NORMAL tanaman liat
56 TOWER BENGKAYANG - NGABANG 074 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 8.5 2 6.5 2.23 BAHAYA I rawan
57 TOWER BENGKAYANG - NGABANG 074 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 8.5 2 6.5 2.23 BAHAYA I rawan
58 TOWER BENGKAYANG - NGABANG 049 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - BAMBU 3 15 3 13 2.3 BAHAYA I span 54 ke 55
LAPORAN INSPEKSI INTERNAL
No. PENGHANTAR TANGGAL PELAPOR LOKASI OBJEK JML X Y Z U KATEGORI KET. PHOTO
59 TOWER BENGKAYANG - NGABANG 045 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - LAINNYA 3 15 3 13 2.3 BAHAYA I span 50 ke 51
60 TOWER BENGKAYANG - NGABANG 124 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 4 13 3 10 3.34 BAHAYA II pohon karet
61 TOWER BENGKAYANG - NGABANG 046 18-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I span 51 ke 52
62 TOWER BENGKAYANG - NGABANG 064 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 1 8.5 3 5.5 3.51 BAHAYA II pohon karet
63 TOWER BENGKAYANG - NGABANG 064 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 1 8.5 3 5.5 3.51 BAHAYA II pohon karet
64 TOWER BENGKAYANG - NGABANG 061 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 8.5 2 6.5 2.23 BAHAYA I rawan
65 TOWER BENGKAYANG - NGABANG 061 18-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I rawan
66 TOWER BENGKAYANG - NGABANG 061 18-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 8.5 2 6.5 2.23 BAHAYA I rawan
67 TOWER BENGKAYANG - NGABANG 061 18-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I rawan
68 TOWER BENGKAYANG - NGABANG 121 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF BUAH 7 15 3 10 5.3 NORMAL pohon karet, durian, langsat
69 TOWER BENGKAYANG - NGABANG 121 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF BUAH 5 15 9 6 NORMAL pohon manggis, langsat, durian
70 TOWER BENGKAYANG - NGABANG 120 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 7 13 7 6 NORMAL pohon kayu lokal, karet
LAPORAN INSPEKSI INTERNAL
No. PENGHANTAR TANGGAL PELAPOR LOKASI OBJEK JML X Y Z U KATEGORI KET. PHOTO
71 TOWER BENGKAYANG - NGABANG 119 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 10 15 5 12 3.81 BAHAYA II pohon karet
72 TOWER BENGKAYANG - NGABANG 207 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I pohon mati mendekati kabel
73 TOWER BENGKAYANG - NGABANG 118 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 13 5 10 3.93 BAHAYA II pohon kayu lokal
74 TOWER BENGKAYANG - NGABANG 118 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - BAMBU 5 13 8 5 NORMAL bambu
75 TOWER BENGKAYANG - NGABANG 256 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 1 13 4 9 4.6 NORMAL ada pohon akasia di luar jalur line 1 pak.no span 258 ke 259.
76 TOWER BENGKAYANG - NGABANG 117 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 5 13 3 10 3.34 BAHAYA II pohon karet. kayu lokal
77 TOWER BENGKAYANG - NGABANG 117 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF BUAH 5 13 10 3 BAHAYA I pohon jengkol. sawit. karet
78 TOWER BENGKAYANG - NGABANG 203 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I pohon mendekati kabel
79 TOWER BENGKAYANG - NGABANG 202 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I pohon di luar jalur
80 TOWER BENGKAYANG - NGABANG 201 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I pohon di luar jalur
81 TOWER BENGKAYANG - NGABANG 115 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 1 13 3 10 3.34 BAHAYA II pohon kayu lokal
82 TOWER BENGKAYANG - NGABANG 114 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 13 3 8 5.34 NORMAL pohon kayu lokal
LAPORAN INSPEKSI INTERNAL
No. PENGHANTAR TANGGAL PELAPOR LOKASI OBJEK JML X Y Z U KATEGORI KET. PHOTO
83 TOWER BENGKAYANG - NGABANG 06A 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - LAINNYA 3 12 3 10 2.37 BAHAYA I akasia
84 TOWER BENGKAYANG - NGABANG 05A 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - LAINNYA 3 12 8 10 4.42 NORMAL pohon _ayu
85 TOWER BENGKAYANG - NGABANG 169 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 11 15 2 13 2.13 BAHAYA I 171-172
86 TOWER BENGKAYANG - NGABANG 169 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I 171-172
87 TOWER BENGKAYANG - NGABANG 196 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I tower ke 198 mau ke 199
88 TOWER BENGKAYANG - NGABANG 168 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 6 15 3 13 2.3 BAHAYA I 169-170
89 TOWER BENGKAYANG - NGABANG 168 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 5 15 12 3 BAHAYA I 170-171
90 TOWER BENGKAYANG - NGABANG 170 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I 172-173
91 TOWER BENGKAYANG - NGABANG 170 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 5 15 3 13 2.3 BAHAYA I 172-173
92 TOWER BENGKAYANG - NGABANG 171 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF BUAH 3 15 3 13 2.3 BAHAYA I 172-173
93 TOWER BENGKAYANG - NGABANG 171 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 5 15 7 8 NORMAL 173-174
94 TOWER BENGKAYANG - NGABANG 109 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 7 13 12 1 KRITIS pohon karet
LAPORAN INSPEKSI INTERNAL
No. PENGHANTAR TANGGAL PELAPOR LOKASI OBJEK JML X Y Z U KATEGORI KET. PHOTO
95 TOWER BENGKAYANG - NGABANG 109 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF BUAH 4 13 3 8 5.34 NORMAL pohon sawit
96 TOWER BENGKAYANG - NGABANG 172 17-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 2 13 2.13 BAHAYA I 174-175
97 TOWER BENGKAYANG - NGABANG 172 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF KAYU 2 15 15 0 - 173-174
98 TOWER BENGKAYANG - NGABANG 107 17-DEC-19 GP BKY - NGABANG OBJEK DIBAWAH JALUR POHON - PRODUKTIF BUAH 5 13 8 5 NORMAL pohon sawit
99 TOWER BENGKAYANG - NGABANG 034 16-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 6 15 3 13 2.3 BAHAYA I span 39-40 kayu
100 TOWER BENGKAYANG - NGABANG 034 16-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 3 15 3 13 2.3 BAHAYA I span 39-38 pohon karet
101 TOWER BENGKAYANG - NGABANG 016 16-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - LAINNYA 2 12 8 10 4.42 NORMAL pohon kayu
102 TOWER BENGKAYANG - NGABANG 032 16-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 6 15 3 13 2.3 BAHAYA I span 37-36 pohon karet
103 TOWER BENGKAYANG - NGABANG 030 16-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - PRODUKTIF KAYU 10 15 3 13 2.3 BAHAYA I span 35-35 pohon karet
104 TOWER BENGKAYANG - NGABANG 022 16-DEC-19 GP BKY - NGABANG OBJEK DILUAR JALUR POHON - LAINNYA 2 15 3 13 2.3 BAHAYA I phn kayu
9.d Waste Management Socialization
30-Jan-20
1
PROSEDUR PENGELOLAAN SAMPAH (LIMBAH PADAT)
PLN UP3B PONTIANAK
SAMPAH???• UU No 18 Tahun 2008 ttg Pengelolaan Sampah
sisa kegiatan sehari-hari manusia dan/atau prosesalam yang berbentuk padat
• SNI 19-2452-2002 merupakan limbah yangbersifat padat terdiri dari bahan organik danbahan anorganik yang dianggap tidak berguna lagidan harus dikelola agar tidak membahayakanlingkungan dan melindungi investasipembangunan
SUMBER & KLASIFIKASI SAMPAH
Sampah Basah (Garbage)• Sampah organik yang mudah busuk (degradable)
Sampah Kering (Rubbish)• Sampah anorganik yang tidak mudah
Sampah Lembut• Sampah yang merupakan partikel ukuran kecil, ringan dan
mudah diterbangkan angin, berbentuk debu dan abu
Sampah Besar (Bulky Waste)• Sampah yang berukuran besar misalnya kursi, meja, dll
Identifikasi Sampah Perkantoran
• Sampah yang dihasilkan dari lokasi ini biasanya berupa kemasan makanan, sisa makanan (organik), dll
Pantry/Dapur
• Sampah yang dihasilkan berupa limbah kertas, alat2 tulis kantor rusak, plastik, cartridge tinta, dll
Area Kerja
• Sampah yang dihasilkan berupa daun-daun kering, ranting, dllLingkungan
Jenis SampahSarana & Prasarana Pengelolaan Sampah
1. Pejabat Pelaksana K3L bertanggung jawab untuk menyediakantempat pembuangan limbah padat individual sesuai dengankarakteristik limbah antara lain organik, anorganik, dan B3 yangdiletakkan di lokasi strategis
2. Pejabat Pelaksana K3L melakukan sosialisasi dan memasang mediakomunikasi pada area lingkungan kerja terkait pemisahan sampah
30-Jan-20
2
Pengumpulan Sampah1. Petugas kebersihan melakukan pengumpulan dengan pewadahan
sampah sesuai dengan klasifikasi / jenis sampah2. Penempatan wadah diletakkan di lokasi yang mudah dijangkau dan
terlihat3. Pengambilan sampah dilakukan secara periodik maksimal 3 hari
tergantung dari timbulan sampah ke tempat pembuanganindividual
4. Timbulan sampah kemudian dipindahkan ke lokasi wadah komunal(kontainer)
5. Wadah komunal ditempatkan pada lokasi yang mudah dijangkauoleh alat pengangkut (truk) dan tidak menggangu sarana umum
6. Pengangkutan sampah ke pembuangan akhir (TPA) dilakukanapabila timbulan sampah mencapai kapasitas maksimum ataukesepakatan dengan petugas pelaksana pengumpul sampah
Larangan
Membakar sampah
Mencampur sampah dengan limbah berbahaya beracun
Membuang sampah sembarangan
TERIMA KASIH
Scanned by CamScanner
Dissemination on waste management practice to the Ngabang SS employees
9.e Construction Management
Cleaning the construction waste around Tayan Substation Site
Warning sign in the switchyard
9.f Drainage
Maintenance Procedures
29cfb7c89773fb527751ed1026becb89 Persiapan Activitas
Standar Operasional Prosedur SIEMENS(SOP)
Reference No.: Contract No.:No. Referensi: No. Kontrak:
Division, Department / Contractor Company: Production Line / Project: Paket 5 ProjectDivisi, Departemen / Perusahaan Kontraktor: Lini Produksi / Proyek:
Title of Person who does Job: New / Revision:Jabatan orang yang Mengerjakan Pekerjaan: Baru / Revisi:
Job:Pekerjaan:
Work Location: Date:Lokasi Kerja: Tanggal:
Name, position and signature of the SOP team members.Nama, jabatan dan tanda tangan dari anggota tim SOP
Heru Aprijadi ; Site Supervisor
Rahmat Amar ; Koordinator EHS.
SOP Pemeliharaan Berkala Saluran Terbuka Drainase dan Sediment Trap
SOP Pemeliharaan Berkala Saluran Terbuka Drainase dan Sediment Trap
Pekerjaan berkala pada saluran terbuka meliputi pekerjaan membersihkan dan mengangkat sedimen dari saluran gorong-gorong, membersihkan sampah pada saringan
penahan sampah seperti ijuk dan karung penahan yang sudah diisi dengan pasir sebagai media filtrasi, serta pembersihan vegetasi dan pengangkatan endapan erosi
tanah pada bak control saluran sedimen trap. Umumnya dilakukan setiap 2 minggu sekali
Pekerjaan:
a) Membersihkan dan mengangkut sampah yang tertahan dalam saluran open drainase
b) Membersihkan dan mengangkat vegetasi serta sedimen/endapan tanah yang ada di bak control saluran sedimen trap
Kegiatan pemeliharaan dilakukan secara berkala 2 minggu sekali
Cara Pelaksanaan:
a) Membersihkan dan mengangkat sampah yang tertahan dalam saluran open drainase
Persiapan :
Peralatan yang diperlukan
• Serokan,gancu,karung plastic,gerobak dorong• Alat angkut truck, Excavator• Sumber daya manusia/manpower terbagi menjadi regu, dimana setiap regu terdiri atas 1 mandor dan 4-5 pekerja
Pelaksaan :
• Melakukan penjelasan terhadap para pekerja tata cara maupun segala sesuatu pekerjaan yang akan dikerjakan• Angkat sampah dan tumbuh-tumbuhan yang ada dalam saluran• Tarik pohon-pohon yang hanyut dan angkat, apabila kayunya besar sebaiknya dipotong-potong lebih dahulu dengan gergaji• Angkat sampah ke tepi saluran dan kumpulkan dalam satu tempat sebelum diangkut• Bawa sampah tersebut ke tempat pembuangan yang telah ditentukan
b) Membersihkan dan mengangkat vegetasi serta sedimen/endapan tanah yang ada di bak control saluran sedimen trap
Persiapan :
Peralatan yang diperlukan
• Serokan,gergaji,gancu,karung,gerobak dorong• Alat angkut Excavator/dump truck• Serokan,gancu,karung plastic,gerobak dorong• Alat angkut truck, Excavator• Sumber daya manusia/manpower terbagi menjadi regu, dimana setiap regu terdiri atas 1 mandor dan 4-5 pekerja
Pelaksaan :
• Melakukan penjelasan terhadap para pekerja tata cara maupun segala sesuatu pekerjaan yang akan dikerjakan• Angkat sampah dan tumbuh-tumbuhan yang ada dalam saluran serta endapan erosi tanah yang tertahan di bak control sediment trap dengan menggunakan bantual alat berat Excavator
• Tarik pohon-pohon yang hanyut dan angkat, apabila kayunya besar sebaiknya dipotong-potong lebih dahulu dengan gergaji• Angkat sampah ke tepi saluran dan kumpulkan dalam satu tempat sebelum diangkut• Bawa sampah tersebut ke tempat pembuangan yang telah ditentukan
SOP 01-L44008
Sanggau - Kalimantan Barat
0691.PJ/DAN.02.02/DIR/2017
E T TS / PT. Siemens Indonesia
Site Supervisor and Engineer
OHSE 11.06 Job Safety Analysis Worksheet Sheet / Lembar ..... /.....
9.g Temporary Drainage
Temporary drainage channel and sediment trap to control containment run off
9.h PPE Implementation
The socialization and implementation of PPE usage
9.i Tower Construction in Peat Lands
Letter from PLN (DIV HSSE) No. 0007/KLH.01.01/010405/2020
# plw
KANTOR PUSAT
Jl.Trunoioyo Blok M/]35 Kebayoran Baru Jakarta 12160
T 1021) 7 26187 5, 7 261 1 22, 7 262234, 7251 234, 7250ss0
F (021) 7221330,73971 50 w www.pln.co.id
09 J a,lrrarj- 2O2Oo_oo1 IKLr.-oL.ot/ o:.ouos t 2o2oPenting
1 (satu) berkas
Permohonan Arahan prosedur perizinan
Pengelolaan Area Gambut di Lokasi proyek
SUTT 1 50kV Tayan - Sanggau - Sekadau.
Kepada Yth.:
Direktur Jenderal PlanologiKehutanan dan Tata
Lingkungan
c.q. Direktur lnventarisasi &Pemantauan Sumber Daya
Hutan
Gedung Manggala Wanabakti
Jl Gatot Subroto No_ 7
Senayan, Jakarta Pusat
DKI Jakarta '10270
Sehubungan dengan pembangunan Saluran Udara Tegangan Tinggi (SUTT) 150 kVTayan-sanggau-sekadau yang merupakan proyek ketenagaristrikan untuk kepentinganumum, bersama ini dengan hormat kami sampaikan hal_hal sebagai berikut:
1. Jalur SUTT 150 kV Tayan-sanggau telah memperoleh izin lingkungan berdasarkanSurat Keputusan Kepara Kantor penanaman Modar dan perayanan perizinan
Kabupaten sanggau Nomor: 503/009/pMpp-D ,L'2ols tanggal 15 Mei 201 5 tentangPernberian lzin Lingkungan Kegiatan pembangunan SUTT 150 kV Tayan_Sanggau,
Gardu lnduk Tayan dan Gardu lnduk Sanggau Atas Nama pT pLN (persero) Unitlnduk Pembangunan X Di Kecamatan Tayan Hilir, Kecamalan Barai, KecamatanTayan Hulu, Kecamatan parindu dan Kecamatan Kapuas Kabupaten Sanggau
Provinsi Kalimantan Barat;
2. Jalur surr 150 kV Sanggau - sekadau terah memperoreh izin ringkungan
berdasarkan Keputusan Gubernur Karimantan Barat Nomor 'r 56/8LHD/2013 tentang
lzin Lingkungan Atas Kegiatan pembangunan Saluran Udara Tegangan Tinggi
(surr) 150 kV sanggau - sekadau - sintang dan Gardu rnduk rerkait (paket SL 08)
oleh PT PLN (Persero) Unit lnduk pembangunan Jaringan sumatera ll di Kecamatan
Kapuas dan Mukok Kabupaten Sanggau, Kecamatan Sekadau Hilir Kabupaten
Sekadau serta Kecamatan Sepauk, Tempunak, dan Sungai Tebelian Kabupaten
Sintang Provinsi Kalimantan Barat;
ParafJv
Nomor
Sifat
Lampiran
Perihal
a I
*PLNKANTOR PUSAT
3' Merujuk pada Surat Direktorat lnventarisasi dan pemantauan sumber Daya HutanNomor s'412lrpsDH/pDTK/pLA .1t,t2o1g tanggar 13 Agustus 2019 periharTanggapan terhadap permohonan Klarifikasi Lokasi proyek surr 150 kV Tayan _sanggau terhadap penundaan rzin Baru, dijeraskan bahwa arear yang dimohon orehPT PLN (Persero) Unit lnduk pembangunan Kalimantan Bagian Barat termasuk dalampengecuarian PrpprB dan untuk ditindakranjuti sesuai dengan peraturan yang berraku;
4' Merujuk pada surat Barai pemantapan Kawasan Hutan wirayah ,r Nomor:s'699/BPKH.r/pKHtpLA.1
r 1 1 t201 9 tanggar 1 1 November 201 9 tentang TeraahanTeknis Fungsi Kawasan Hutan Terhadap Titik Koordinat Saluran Udara TeganganTinggi (SUTT) Tayan - sanggau, sanggau - sekadau dan Kendawangan _sukamaran Provrnsi Karimantan Barat, rokasi yang dimohon terindikasi berada padaMoratorium Gambut yaitu pada (data terlampir):
a. SUTT 150 kV Tayan - Sanggau pada titik koordinat T.g sampai dengan T. 12
b. SUTT 150 kV Sanggau - Sekadau pada titik koordinat T.90 sampai dengan T. 100
Mengacu pada:
- Perpres RI Nomor 14 Tahun 201r tangar 14 Februari 2017 tentang perubahan
atas Peraturan presiden Nomor 4 Tahun 2016 tentang percepatan pembangunan
I nfrastruktur Ketenagalistrikan; dan
- lnpres No 5 Tahun 2019 tanggal 07 Agustus 2019 tentang penghentian
Pemberian lzin Baru dan penyempurnaan Tata Kelola Hutan Alam primer danLahan Gambut, diktum kedua poin b yang berkaitan dengan penghentian
pemberian izin baru dengan pengecualian pada: ,,pelaksanaan pembangunan
nasional yang bersifat vital yaitu panas bumi, minyak dan gas bumi,
ketenagalistrikan, ...."
sehubungan dengan har tersebut di atas, dengan ini kami mohon arahan terhadap proses
perizinan dilokasi tersebut yang harus dipenuhi oleh pr pLN (persero) sebagar bentuk
penaatan terhadap peraturan perundang-undangan
Jl. Trunojoyo Blok M/1 35 Kebayoran Ba ru Jakarta 121 60
I lo21) 726187 5,7261122,7 262234,7 251234, 7 2sO550
F (O2ll 7221330,73971 50 W www.pln.co.id IParaf -Ao, +
PLN
KANTOR PUSAT
Demikian disampaikan, atas perhatian dan bantuannya kami ucapkan terima kasih
EXECUTIVE VICE PRESIDENTHEALTH, SAFETY, SECURITY
AND ENVIRONMENT
Tembusan:
1. Kepala Balai Pemantapan Kawasan Hutan lll _ pontianak
2. Direktur Pencegahan Dampak Lingkungan Usaha Kegiatan3. EVP PPT PLN Kantor pusat
4. General Manager Ulp Kalimantan Bagian Barat5. General Manager pLN pusmanpro
Jl. Trunojoyo Blok M/1 35 Kebayoran Baru Jakarta 1 21 60
T (02 1 ) 7 261 87 5, 7 261 1 22, 7 26223 4, 7 251 234, 72505 50
F (021) 7221330,7397150 t/t/ www.pln.co.id Paraf +t-.}r
*+
9.j Soil Erosion
Request for Inspection Document