EnerNOC: Demand Response Solutions Texas Public Utilities Commission – September 15, 2006.
-
Upload
elisabeth-eaton -
Category
Documents
-
view
216 -
download
0
Transcript of EnerNOC: Demand Response Solutions Texas Public Utilities Commission – September 15, 2006.
EnerNOC: Demand Response SolutionsTexas Public Utilities Commission – September 15, 2006
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution2
Agendag
et
more
Texas’ Underlying Needs
Types of Demand Response
EnerNOC Overview
Next Steps
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution3
Record-Breaking Peak DemandAugust 2, 2006, New England“New England consumers set a new record for electricity consumption today…. Regional electricity use reached 28,021 megawatts (MW) this afternoon, surpassing the record of 27,401 MW, set just yesterday.”
August 2, 2006, New York“The statewide demand for electricity reached a record for the second day in a row—and for the third time in two weeks—Wednesday as New Yorkers kept air conditioners humming and fans blowing to beat the heat and humidity of an unrelenting heat wave…. The hourly average peak load hit 33,939 megawatts (MW)…, breaking Tuesday’s record of 33,879 MW.”
August 1, 2006, Midwest“The Midwest Independent Transmission System Operator, Inc. (Midwest ISO)…met its second record demand of the summer, reaching 136,520 megawatts (MWs)…, eclipsing the record of 132,658 MWs set just two weeks ago.”
August 1, 2006, Ontario, Canada“Ontario set a new all-time record for electricity demand of 27,005 megawatts (MW)…, exceeding the previous record of 26,160 MW set on July 13, 2005.”
July 24, 2006, California“Another record peak was set at 50,270 megawatts…. This breaks the record of 49,036 megawatts set just last Friday, July 21.”
July 17, 2006, PJM“PJM Interconnection…set an unofficial record for peak electricity use of 139,746 megawatts today.”
July 17, 2006, Texas“The Electric Reliability Council of Texas, Inc. (ERCOT) region set a new electricity usage record of 62,396 megawatts (MW) of power today, …exceeding the previous all-time peak of 60,274 MW, set on August 23, 2005.”
get
more
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution4
Record-Breaking Peak Demand
July 26, 2006, United States of America
“The United States has seven regional independent operators of electrical grids, stretching from California to New England, and every one of them experienced record power demand in late July…. Regional grid operators reported a new aggregated peak record of electricity usage of 483,233 megawatts during the extreme heat and high humidity, a full 7,500 megawatts above last year’s peak.”
- United States Department of Energy
get
more
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution5
Current Solution: Demand Response
“Today’s peak record would have been hundreds of megawatts higher if it were not for ISO New England’s demand response programs and conservation efforts of consumers.”
- ISO-NEAugust 2, 2006
“The NYISO’s Demand Response customers, however, helped keep the statewide electricity load from climbing even higher by curtailing afternoon usage.”
- NYISOAugust 2, 2006
“Commercial customers…shed an estimated 855 megawatts just as California was setting the new sky-high record demand for electricity on July 24.”
- CAISOAugust 1, 2006
get
more
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution6
Demand Response provides a better solution to meeting peak demand than the traditional solution of over-building generation.
Demand Response Impact Potential
40
80
0
ERCOT Peak Demand: 63 GW
Nuclear
Gas/Oil Steam
Other
ERCOT Generating Capacity: 78.2 GW
Source: EIA Electric Power Annual 2003
8,760 Hours
1% of hoursrequire
~10% of capacity
Hydro
Coal
Renewables
Combined Cycle Gas
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution7
The New Energy Crisis
As much as 50% of the nation’s anticipated load growth over the next decade could be displaced through energy efficiency, pricing reforms, and load management programs.
The DOE’s five National Energy Laboratories concluded that cost-effective energy efficiency investments could displace 15% of the nation’s total electrical demand by the year 2010.
Customer market studies and load-response pilot programs demonstrate that the potential for load management is also quite substantial. Approximately 15% to 17% of commercial load could be managed in response to short-term price signals.
A FERC-commissioned study reported that a moderate amount of demand-response could save about $7.5 billion annually in 2010.
Source: Efficient Reliability: The Critical Role of Demand-Side Resources in Power Systems and Markets. Prepared for the National Association of Regulatory Utility Commissioners. Author - Richard Cowart, Regulatory Assistance Project, June, 2001.
get
more
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution8
Texas’ Underlying Needs
Reserve Margin
0%
5%
10%
15%
20%
25%
30%
2006 2007 2008 2009 2010 2011
Source: Report on Capacity, Demand and Reserves in the ERCOT Region, June 2006.
Projected
AnnouncedAdditions
Reserve Margins in TX are declining
Some suggest mothballed plants will be back online
Demand response is an underutilized resource that can be enabled to respond NOW
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution9
Demand Response in TX an Underutilized Resource
ERCOT load management programs declined significantly between 1998 and 2003.
Of all NERC regions, ERCOT has the lowest existing demand response resource contribution as a percentage of projected summer demand
Source: FERC Assessment of Demand Response and Advanced Metering, August 2006, pp. 22 & 100.
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution10
Texas’s Unrealized Demand Response Potential
Overall DR potential: 5 to 8% of peak load; equivalent to 3 to 5 GW today
Industrial Commercial Residential
Current Status of DR Most utilized resource
Virtually none utilized Some existed previously, but no
longer actively utilized
Potential DR Capacity ~ 1 GW ~ 2 to 3 GW ~ 1 GW
Comments More capacity possible with a few program changes
Capable resources are currently lying untapped but current programs and existing market structures will enable NONE of this potential
More cost effective than new peakers
In need of longer term contracts
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution11
Agendag
et
more
Underlying Needs
Types of Demand Response
EnerNOC Overview
Next Steps
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution12
kW
h’s
24 Hours
$/k
Wh
24 Hours
Demand Response – A familiar slide todayDemand response is achieved when end-users reduce their demand for electricity from the grid in response to market signals.
Reliability/Security – DR can be brought to market more quickly and precisely than comparable generation or T&D, giving grid operators resources needed to better manage reliability NOW while paying end-users to tap into existing resources.
Price – DR can dramatically reduce pricing power of well-positioned generators and incentivizes end users to become active participants in energy markets – active participation keeps markets healthy and prices low.
Efficiency – Demand response raises the specter of efficiency. Increased end user market participation puts energy back on the business planner’s map and, when properly deployed, can save end-users 25% or more on energy bills.
Generation Capacity
Demand
kW
24 Hours
With EnerNOC
With EnerNOC
With EnerNOC
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution13
Demand Response in the Northeast
New York
– Emergency Demand Response
– Installed Capacity / Special Case Resources
– Day-Ahead Demand Response
New England
– Real Time Demand Response
– Real Time Price Response
– Day-Ahead Option
get
more
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution14
NYISO Demand Response Performance
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution15
NYISO EDRP & SCR Capacity Growth – 1450 MWg
et
more
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution16
ISO-NE Energy Management Philosophies
Demand Response Programs© 2005 ISO New England Inc.
Integrated Energy Management
• Energy Efficiency – Managing energy consumption.
• Supply Management – Managing the supplier relationship and risk.
• Demand Response – Managing load shape.
Demand Response Programs© 2005 ISO New England Inc.
Supply and Demand Management
• Yesterday:– Prices set by the Regulator. Customers
had little interest in the wholesale markets.
• Today:– Prices set by the Supplier and Customer.
Customers have an incentive to be connected with the wholesale markets
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution17
ISO-NE Energy Management Philosophies
Demand Response Programs© 2005 ISO New England Inc.
Supply and Demand Management
• A customer’s peak consumption creates a capacity obligation for their supplier
• A Customer who can not control when they use electricity transfer risk to their supplier. – The supplier must assume the risk that at any point in
time the customer can increase their consumption without any consideration for the supplier’s wholesale costs.
• Higher risk translates into a higher retail price.
Demand Response Programs© 2005 ISO New England Inc.
Supply and Demand Management
• Customers who participate in a Demand Response Program can:– Improve their load shape,
– Respond to high wholesale prices or reliability events,
– Earn Capacity Credits to reduce their Capacity Obligation, and
– Help lower their supplier’s risk.
• Lower risk translates into a lower retail price.
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution18
ISO New England/NEPOOLDemand Response Working Group
Meeting© 2005 ISO New England Inc.
1
DR Program Enrollments June 2005 – June 2006
0.0
100.0
200.0
300.0
400.0
500.0
600.0
700.0
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2005 2005 2005 2005 2005 2005 2005 2006 2006 2006 2006 2006 2006
Month/Year
MW
Profile Price 30-Minute 2-Hour
ISO New England Demand Response Capacity – 600 MWg
et
more
2-Hour
30-Minute
Price
Profile
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution19
ISO-NE Experience on August 2, 2006
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution20
What is Demand Response?Demand response actions come in two basic forms.
Self Generation – This can include emergency/backup generation, peaking and continuous-duty distributed generation, or even UPS systems.
Curtailment – Turning off lights, turning up cooling set-points, turning off air handlers, shifting production schedules, escalators, elevators, water features, parking lights, signage, heating elements, etc.
1
2
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution21
What is Demand Response?Demand response can be accomplished manually or automatically (i.e., remotely controlled).
Manual – Personnel receive an EnerNOC phone call, email, and/or page and respond to an event, shutting down devices, turning up set points, and turning on generation.
Automatic –EnerNOC remotely controls relays, ATS’s, and building management systems en masse to reduce demand or self-generate.
1
2
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution22
Agendag
et
more
Underlying Needs
Types of Demand Response
EnerNOC Overview
Total Energy Management
Next Steps
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution23
Proven and growing track record - Over 350 MW’s of demand response capacity managed at more than 600 customer sites. Approximately 1,000 MW’s of peak demand in network monitored by PowerTrak®
Compelling offering – Total Energy Management Solutions Provider encompassing – Demand Response, Demand Management, Data Management, Research, Education, Permitting, Financing, Metering, Aggregation, Enrollment, Installation, Payment Reconciliation, Maintenance Management, Risk Management
Significant and growing market - Currently serving:– ISO New England (Certified IBCS and Demand Response Provider) – NYISO (Responsible Interface Party)– PJM (Emergency Demand Response Provider)– California (Demand Reserves Partnership Provider)– SDG&E, SCE, National Grid, NStar
Distinguished technology - Provides 24/7, real-time metering and web-based device monitoring and control through open architecture technology that leverages customers’ existing assets
Significant resources– Strong balance sheet and impressive financial track record– Deep management team – over 70 employees with more than 85
engineering and management degrees
EnerNOC is the leading technology-enabled, C&I-focused total energy management solutions provider
EnerNOC Overview
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution24
About EnerNOC: A National Clean Tech LeaderThe greenest kWh is the one never used
EnerNOC Recent Cleantech Company Awards
June 27, 2005: Red Herring names EnerNOC one of 10 Cleantech Companies to Watch
April 4, 2005: EnerNOC voted one of Top three companies at Cleantech Venture Network 2005 Forum
EnerNOC profiled in Forbes, May 8, 2006
A Sensible Energy Response
Brett Perlman and Phil GiudiceTuesday, April 25, 2006 –
The recent rolling blackout in Texas highlighted the need for fresh thinking about how the state manages its electric grid.
Last week, the Electric Reliability Council of Texas, the state's electricity grid operator, was forced to cut power to more than 200,000 customers when demand for electricity spiked due to unseasonably warm weather. With temperatures reaching almost 100 degrees and many generation plants still on spring maintenance, ERCOT failed to keep the lights on.
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution25
About EnerNOC: Growth Summary
0
50
100
150
200
250
300
350
400
2004 2005 2006
MW
's
0
50
100
150
200
250
300
Cu
stom
ers
MW Customers
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution26
EnerNOC Examples and ExperienceEnerNOC’s rapid success is based on the value we’ve delivered to our customers through demand response and energy management solutions.
Government
Light Industrial
Education
Food Sales and Storage
Healthcare
Lodging and Resorts
Commercial Office and High Tech
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution27
EnerNOC enables existing assets with inexpensive, scalable technology to accomplish significant and guaranteed reductions in demand.
The Energy Network Operations Center
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution28
EnerNOC Examples and ExperienceAn industry-specific solution should always be deployed to maximize the demand response opportunity.
Supermarket 24 Hour Load Profile and EnerNOC Demand Response Application
0
50
100
150
200
250
300
350
400
12:00 am 2:00 am 4:00 am 6:00 am 8:00 am 10:00 am 12:00 pm 2:00 pm 4:00 pm 6:00 pm 8:00 pm 10:00 pm 12:00 am
Time of Day
kW
ISO Calls “Event” 30 Minutes Prior
to Required Response
EnerNOC Responds
Automatically within 30 Minutes
EnerNOC Restores
Operations Automatically
30 kW from 1/3 Lights
20 kW from Store AC or Air Handler
20 kW from Backup
Generator
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution29
EnerNOC DR Event Summary – February 27, 2006EnerNOC’s aggregate coincident performance was over 100 MW during a demand response event in New England
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
9:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00
Notification by ISO - 9:45 AM Event Start - 10:30 AM Event End - 12:30 PM
Enrolled Capacity - 103,629 kW
kW
Peak Performance - 133,584 kW @ 10:50 AM
Total Performance - 167,134 kWh
Aggregate Coincident Performance
30-Minute Ramp-Up Window
Total Performance - 300,375 kWh
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
9:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00
Notification by ISO - 9:45 AM Event Start - 10:30 AM Event End - 12:30 PM
Enrolled Capacity - 103,629 kW
kW
Peak Performance - 133,584 kW @ 10:50 AM
Total Performance - 167,134 kWh
Aggregate Coincident Performance
30-Minute Ramp-Up Window
Total Performance - 300,375 kWh
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution30
0
100
200
300
400
500
600
11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM
kW
Notification 1:00 PM
Event Start 1:30 PM Event End 6:00 PM
Baseline
Stacked Meter Demand
Commitment: 370 kW
Performance: 416 kW
-100
0
100
200
300
400
500
11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM
Load Curtailment
Provider Summary
• Sites: 5
• Commitment: 370 kW
• Performance:424 kW (non-coincident) 416 kW (coincident)
-100
0
100
200
300
400
500
11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM
Voluntary Extension 7:15 PM
EnerNOC DR Event Summary – July 27, 2005Curtailment: University provider curtails more than 400 kW of load at five individual sites.
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution31
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM
Provider Summary
• Commitment: 1,450 kW
• Performance: 1,727 kW
kW
Notification 1:00 PMEvent Start 1:30 PM Event End 6:00 PM
Baseline
Meter Demand
Commitment: 1,450 kW
Generator Output
Load Curtailment
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
1 13 25 37 49 61 73 85 97 109 121
Performance: 1,727 kW
Voluntary Extension7:15 PM
EnerNOC DR Event Summary – July 27, 2005Generation and curtailment: University provider combines generation with load curtailment to reduce more than 1.7 MW from the electrical grid.
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution32
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM
kW
Notification 1:00 PMEvent Start 1:30 PM Program End 6:00 PM
Baseline
Provider Summary
• Sites: 50
• Commitment: 12,050 kW
• Performance:13,418 kW (non-coincident) 12,980 kW (coincident)
0.00
2000.00
4000.00
6000.00
8000.00
10000.00
12000.00
14000.00
16000.00
Performance: 12,980 kW
Generator Output
Stacked Meter Demand
0.00
2000.00
4000.00
6000.00
8000.00
10000.00
12000.00
14000.00
16000.00
Commitment: 12,050 kW
Voluntary Extension 7:15 PM
EnerNOC DR Event Summary – July 27, 2005Parallel processing: Communications provider simultaneously transfers 50 facilities to backup generators, totaling over 12 MW.
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution33
DR Case Studies – EnerNOC SDG&E Clean Gen Project EnerNOC has deployed a 25 MW “Negawatt Network” in San Diego Gas & Electric service territory in 6 months and hopes to deploy another 25 MW’s in the next 6 months.
25 MW’s currently
Real-time control and monitoring of clean, fully permitted emergency generators
“Single Button” dispatch of entire network within 10 minutes of notification of CAISO reliability or economic event, such as Stage 2 alert
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution34
DR Case Studies – ISO-NE Winter Demand Response EnerNOC deployed a 100 MW “Negawatt Network” in 2 months in New England to avert a potentially disastrous winter peak and dependency on NG-fired central generation.
100 MW’s in 60 days
Real-time control and monitoring of curtailable loads (e.g., lights, BMS, electric heating, process), cogeneration, fuel-switched loads, and emergency generation
“Single Button” dispatch of entire network within 30 minutes of notification from ISO-NE of a OP4 Action 9/12 event
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution35
DR Case Studies – PJM Synchronized ReservesEnerNOC was the first company to enter the newly formed PJM Synchronized Reserves 10-minute market and has enrolled nearly 20 MW’s within first 30 days of program.
20 MW’s in past 30 days. Expected to grow to 500 MW’s
Fully integrated market control – PJM’s signal processed automatically by EnerNOC’s NOC and loads are automatically controlled
10 minute automatic dispatch
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution36
Agendag
et
more
Underlying Needs
Types of Demand Response
EnerNOC Overview
Next Steps
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution37
• Up to 300 MW or more of quick-start peaking capacity to cover demand through 2008 in 54 towns of Southwest Connecticut (Meriden to Greenwich)
• Includes Emergency Generation as an eligible resource
• Participants paid for capacity (kilowatts) and load reductions (kilowatt-hours) in accordance with the ISO-NE Demand Response Program, but also receive supplemental payments for capacity through RFP
• Four-year contract term with an option to extend for one year
• Resources must be capable of responding to DR events within 30-minutes of notification
• Resources required to have an Internet-Based Communication System (IBCS) to transmit energy data to ISO-NE
Consider what other markets have done…EnerNOC won 76 MW’s of demand response in the Southwest Connecticut ISO-NE RFP.
ISO-NE’s SWCT Gap RFP
get
more
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution38
Proposal Summary
Summer Average (MW)Resource Type 2004 2005 2006 2007C&LM 1 10 11 11Demand Response 126 279 348 354Generation 354 719 719 719Total 481 1,008 1,078 1,084
ISO-NE 2004 Gap RFP for 300 MW’s of Supplemental Capacity Targeted For Just 54 Towns in Connecticut
Summary of Proposals Received
Consider what other markets have done….
Source: ISO-NE
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution39
Proposal Summary
ISO-NE 2004 Gap RFP for 300 MW’s of Supplemental CapacityTargeted For Just 54 Towns in Connecticut
Summary of Proposals Selected
Consider what other markets have done….
Resource Type Customer Type 2004 2005 2006 2007C&LM Commercial 0.7 4.3 5.0 5.3C&LM Total 0.7 4.3 5.0 5.3Emergency Generation Commercial 13.9 43.7 49.3 51.8
Education 2.0 2.8 2.8 2.8Healthcare 0.0 9.7 9.7 9.7Municipal 10.2 33.5 33.5 33.5Other 69.3 69.3 69.3 69.3
Emergency Generation Total 95.4 158.9 164.5 167.0Load Reduction Commercial 16.6 26.1 31.1 33.6
Healthcare 0.0 0.3 0.3 0.3Municipal 3.1 3.4 3.4 3.4Residential 0.9 19.1 39.7 40.2Small Commercial 2.5 10.0 10.0 10.0
Load Reduction Total 23.1 58.9 84.5 87.4
Grand Total 119.2 222.1 254.0 259.8
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution40
Next Steps: Pilot ProjectThe following table summarizes key aspects of a program concept
Program Type Demand response resources participating in market as ancillary services
Program Size Address the Market’s Need for 2007, 2008, and beyond
Start Date Demand resources will be ready to respond June 2007
Notification Resources will be able to respond within 10 minutes of dispatch by ERCOT
Program specifications Program must incorporate existing technology to ensure that demand response resources are as reliable as peaking generators
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution41
EnerNOC, Inc.28 West 44th St. Suite 1200
New York, NY 10036212.624.0000 – Phone
212.624.0001 – Fax
EnerNOC, Inc.5155 Sunlight Place
Los Angeles, CA 90016323.937.7888 – Phone323.937.8889 – Fax
EnerNOC, Inc.75 Federal St. Suite 300
Boston, MA 02110617.224.9900 – Phone
617.224.9910 – Fax
get
more
EnerNOC, Inc.1010 Lamar, Suite 1040Houston, Texas 77002
713-933-8836 - Tel713-659-0098 - Fax
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution42
Appendix
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution43
Load and Technical Analysis
Enable and Enroll Facilities
Program Management
Event Management
Conduct facility walk-through– Identify curtailable loads– Identify backup generator
potential– Identify existing metering
systems to integrate and save money
Interview facility engineering and operations staff to identify customer sensitivitiesDevelop technical solution optionsSummarize load analysis, present options for load control and program involvement, and present economic potential
Begin collecting dataResearch, file, and renew all required city and state permits for program participationMaintain all required recordsEnroll load in daily/monthly markets to maximize potential benefit while minimizing riskPresent real-time meter data to ERCOT for verification and to customer for reportingMonitor loads continuously and adjust enrollments accordinglyReconcile data with ERCOT monthly and collect and disburse program paymentsManage any program disputes and changes for customer
Notify customers in advance of potential eventsNotify customers during day of event of event “window” and requirementsCurtail load/initiate backup generator operation as requiredMonitor, meter, and adjust performance according to enrolled loadNotify customers of event completion and restore normal operationsProvide event and load reports accordinglyContinually ensure operational integrity of technical solution
Design technical solutionProcure required technology (e.g., metering, relays, controls)Install (or integrate with existing) metering, controls, and communicationTest and troubleshoot technical solutionInitiate monitoring and begin metering loadsApply for, administer, and secure eligible cost reimbursementsRegister as customer’s Responsible Interface Party (RIP)Aggregate customer loads as applicableEnroll assets into each DR program
EnerNOC’s offering is a tailored outsourced solution designed to maximize participation while minimizing end user and utility/ISO effort.
EnerNOC Approach
© 2006 EnerNOC, Inc. All Rights Reserved – Strictly Confidential, Permission Required for Distribution44
A modified BUL Market could increase demand response resources in ERCOT market
Three hurdles to consider removing:
ERCOT should enable payments to go directly to the demand response aggregator instead of the retail energy provider (REP)
Each end-user should have its own baseline; QSEs should be allowed to represent each end-user individually.
Demand response resources should be allowed to participate in both the BUL and the LaaR markets