ELC 347
project management
Week 5
-
8/2/2019 ELC 347 day 6
2/26
Agenda
Assignment 2 re-graded Missing case 2.3 found and graded
Assignment 3 Graded
Could have used more effort case 3.1.xls
First Quiz Will be graded by next class
Integrative Project
Outline of deliverables (posted in WebCT)
Scope Management Using MS project
http://case%203.1.xls/http://elc347_ip.htm/http://elc347_ip.htm/http://case%203.1.xls/ -
8/2/2019 ELC 347 day 6
3/26
Scope Management
Chapter 5
-
8/2/2019 ELC 347 day 6
4/26
-
8/2/2019 ELC 347 day 6
5/26
Project Scope
Project scopeiseverything about a projectwork content as well as expected outcomes.
Scope managementis the function of
controlling a projectin terms of its goalsand objectives and consists of:
1) Conceptual development 4) Scope reporting
2) Scope statement 5) Control systems
3) Work authorization 6) Project closeout
-
8/2/2019 ELC 347 day 6
6/26
Conceptual Development
Theprocessthat addressesproject objectivesby
finding the best ways to meet them.
Key steps in information development:1. Problem/need statement2. Information gathering3. Constraints
4. Alternative analysis5. Project objectives
-
8/2/2019 ELC 347 day 6
7/26
Problem Statements
Successful conceptual development requires:
Reduction of overall project complexity
Goals and objects are clearly stated Reference points are provided
Complete understanding of the problem You cannot solve a problem till you UNDERSTANDthe problem
-
8/2/2019 ELC 347 day 6
8/26
Statement of Work (SOW)
A SOW is adetailed narrative descriptionof the workrequired for a project.
Effective SOWs contain
1. Introduction and background
2. Technical description1. The more specific the better
3. Timeline and milestones
1. Anticipated (hoped-for)4. Client expectations
1. What constitutes a project well done
-
8/2/2019 ELC 347 day 6
9/26
The Scope Statement Process
1. Establish the project goal criteria(deliverables)a) cost
b) schedule
c) performance
d) deliverables
e) review gates
2. Develop the management plan for the project3. Establish a work breakdown structure
4. Create a scope baseline
-
8/2/2019 ELC 347 day 6
10/26
Work Breakdown Structure
a process that sets a projects scope by breaking downits overall mission into a cohesive set of synchronous,increasingly specific tasks.
What does WBS accomplish? Echoes project objectives
Offers a logical structure
Establishes a method of control
Communicates project status Improved communication
Demonstrates control structure
-
8/2/2019 ELC 347 day 6
11/26
WBS and goals
-
8/2/2019 ELC 347 day 6
12/26
Example WBS
-
8/2/2019 ELC 347 day 6
13/26
Work Breakdown Structure and Codes
Work Packages areindividual project activities
1.0
1.2 1.3 1.4
1.2.1
1.2.2
1.2.3
1.3.1
1.3.2
1.2.3.1
1.2.3.2
Deliverables are
major projectcomponents
Subdeliverables are
supporting deliverables
The project is theoverall project underdevelopment
-
8/2/2019 ELC 347 day 6
14/26
Examples
-
8/2/2019 ELC 347 day 6
15/26
Sample WBS in MS Project
-
8/2/2019 ELC 347 day 6
16/26
Work Packages
Lowest level in WBS X.X.X.X
Deliverable result
One owner
Miniature projects
Milestones
Fits organization
Trackable
-
8/2/2019 ELC 347 day 6
17/26
Organizational Breakdown Structure
Organizational Breakdown Structure (OBS) allows
Work definition
Owner assignment of work packages
Budget assignment to departments
OBS links cost, activity & responsibility
-
8/2/2019 ELC 347 day 6
18/26
Intersection of WBS and OBS
-
8/2/2019 ELC 347 day 6
19/26
Responsibility Assignment Matrix
Notification Responsible SupportApproval
LEAD PROJECT PERSONNEL
BobIS
Dave SueHR
AnnR&D
JimR&D
Task& CodeDeliverable IS
Match IT toOrg. Tasks
proposalPrepare
1.3
1.1
Identify ISuser needs
1.2
ProblemAnalysis
Develop
infoInterview
users
showDevelop
Gain userbuy in
Find cost/benefit info
1.1.1
1.1.2
1.2.1
1.2.2
1.2.3
1.3.1
-
8/2/2019 ELC 347 day 6
20/26
Work Authorization
The formal go ahead to begin work
Follows the scope management steps of:
1. scope definition
2. planning documents
3. management plans
4. contractual documents
-
8/2/2019 ELC 347 day 6
21/26
Contractual Documentation
Most contracts contain:
Requirements
Valid consideration
Contracted terms
Contracts range from:
Lump Sum Cost Plusalso calledTurnkey
-
8/2/2019 ELC 347 day 6
22/26
Scope Reporting
determineswhattypes of information reported,whoreceives copies, when, andhowinformation is acquired and disseminated.
Typical project reports may contain
1. Cost status
2. Schedule status3. Technical performance
-
8/2/2019 ELC 347 day 6
23/26
Types of Control Systems
o Configuration
o Design
o Trend monitoring
o Document
o Acquisitiono Specification
-
8/2/2019 ELC 347 day 6
24/26
-
8/2/2019 ELC 347 day 6
25/26
-
8/2/2019 ELC 347 day 6
26/26
Using MS project 2003
Many of the required functions/reports in Projectmanagement are part of MS project 2003 Industry wide acceptance
Do not use Wizard till you are comfortable with MSproject
File ->New Enter Project and all
Deliverables Sub deliverables Work packages
Indent using arrows to show decomposition Template Actual project
http://template.mpp/http://template.mpp/http://template.mpp/http://template.mpp/