    ELC 347

    project management

    Week 5

  • 8/2/2019 ELC 347 day 6

    2/26

    Agenda

    Assignment 2 re-graded Missing case 2.3 found and graded

    Assignment 3 Graded

    Could have used more effort case 3.1.xls

    First Quiz Will be graded by next class

    Integrative Project

    Outline of deliverables (posted in WebCT)

    Scope Management Using MS project

    http://case%203.1.xls/http://elc347_ip.htm/http://elc347_ip.htm/http://case%203.1.xls/
  • 8/2/2019 ELC 347 day 6

    3/26

    Scope Management

    Chapter 5

  • 8/2/2019 ELC 347 day 6

    4/26

  • 8/2/2019 ELC 347 day 6

    5/26

    Project Scope

    Project scopeiseverything about a projectwork content as well as expected outcomes.

    Scope managementis the function of

    controlling a projectin terms of its goalsand objectives and consists of:

    1) Conceptual development 4) Scope reporting

    2) Scope statement 5) Control systems

    3) Work authorization 6) Project closeout

  • 8/2/2019 ELC 347 day 6

    6/26

    Conceptual Development

    Theprocessthat addressesproject objectivesby

    finding the best ways to meet them.

    Key steps in information development:1. Problem/need statement2. Information gathering3. Constraints

    4. Alternative analysis5. Project objectives

  • 8/2/2019 ELC 347 day 6

    7/26

    Problem Statements

    Successful conceptual development requires:

    Reduction of overall project complexity

    Goals and objects are clearly stated Reference points are provided

    Complete understanding of the problem You cannot solve a problem till you UNDERSTANDthe problem

  • 8/2/2019 ELC 347 day 6

    8/26

    Statement of Work (SOW)

    A SOW is adetailed narrative descriptionof the workrequired for a project.

    Effective SOWs contain

    1. Introduction and background

    2. Technical description1. The more specific the better

    3. Timeline and milestones

    1. Anticipated (hoped-for)4. Client expectations

    1. What constitutes a project well done

  • 8/2/2019 ELC 347 day 6

    9/26

    The Scope Statement Process

    1. Establish the project goal criteria(deliverables)a) cost

    b) schedule

    c) performance

    d) deliverables

    e) review gates

    2. Develop the management plan for the project3. Establish a work breakdown structure

    4. Create a scope baseline

  • 8/2/2019 ELC 347 day 6

    10/26

    Work Breakdown Structure

    a process that sets a projects scope by breaking downits overall mission into a cohesive set of synchronous,increasingly specific tasks.

    What does WBS accomplish? Echoes project objectives

    Offers a logical structure

    Establishes a method of control

    Communicates project status Improved communication

    Demonstrates control structure

  • 8/2/2019 ELC 347 day 6

    11/26

    WBS and goals

  • 8/2/2019 ELC 347 day 6

    12/26

    Example WBS

  • 8/2/2019 ELC 347 day 6

    13/26

    Work Breakdown Structure and Codes

    Work Packages areindividual project activities

    1.0

    1.2 1.3 1.4

    1.2.1

    1.2.2

    1.2.3

    1.3.1

    1.3.2

    1.2.3.1

    1.2.3.2

    Deliverables are

    major projectcomponents

    Subdeliverables are

    supporting deliverables

    The project is theoverall project underdevelopment

  • 8/2/2019 ELC 347 day 6

    14/26

    Examples

  • 8/2/2019 ELC 347 day 6

    15/26

    Sample WBS in MS Project

  • 8/2/2019 ELC 347 day 6

    16/26

    Work Packages

    Lowest level in WBS X.X.X.X

    Deliverable result

    One owner

    Miniature projects

    Milestones

    Fits organization

    Trackable

  • 8/2/2019 ELC 347 day 6

    17/26

    Organizational Breakdown Structure

    Organizational Breakdown Structure (OBS) allows

    Work definition

    Owner assignment of work packages

    Budget assignment to departments

    OBS links cost, activity & responsibility

  • 8/2/2019 ELC 347 day 6

    18/26

    Intersection of WBS and OBS

  • 8/2/2019 ELC 347 day 6

    19/26

    Responsibility Assignment Matrix

    Notification Responsible SupportApproval

    LEAD PROJECT PERSONNEL

    BobIS

    Dave SueHR

    AnnR&D

    JimR&D

    Task& CodeDeliverable IS

    Match IT toOrg. Tasks

    proposalPrepare

    1.3

    1.1

    Identify ISuser needs

    1.2

    ProblemAnalysis

    Develop

    infoInterview

    users

    showDevelop

    Gain userbuy in

    Find cost/benefit info

    1.1.1

    1.1.2

    1.2.1

    1.2.2

    1.2.3

    1.3.1

  • 8/2/2019 ELC 347 day 6

    20/26

    Work Authorization

    The formal go ahead to begin work

    Follows the scope management steps of:

    1. scope definition

    2. planning documents

    3. management plans

    4. contractual documents

  • 8/2/2019 ELC 347 day 6

    21/26

    Contractual Documentation

    Most contracts contain:

    Requirements

    Valid consideration

    Contracted terms

    Contracts range from:

    Lump Sum Cost Plusalso calledTurnkey

  • 8/2/2019 ELC 347 day 6

    22/26

    Scope Reporting

    determineswhattypes of information reported,whoreceives copies, when, andhowinformation is acquired and disseminated.

    Typical project reports may contain

    1. Cost status

    2. Schedule status3. Technical performance

  • 8/2/2019 ELC 347 day 6

    23/26

    Types of Control Systems

    o Configuration

    o Design

    o Trend monitoring

    o Document

    o Acquisitiono Specification

  • 8/2/2019 ELC 347 day 6

    24/26

  • 8/2/2019 ELC 347 day 6

    25/26

  • 8/2/2019 ELC 347 day 6

    26/26

    Using MS project 2003

    Many of the required functions/reports in Projectmanagement are part of MS project 2003 Industry wide acceptance

    Do not use Wizard till you are comfortable with MSproject

    File ->New Enter Project and all

    Deliverables Sub deliverables Work packages

    Indent using arrows to show decomposition Template Actual project

    http://template.mpp/http://template.mpp/http://template.mpp/http://template.mpp/