Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities...

17
Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity ~ 100,000 MW Fifth largest in the world 1,500 MW in 1947 95% of villages electrified 40% of households have access Per Capita Consumption : 350 kWh World Average: 2000 kWh Need to add 10,000 – 15,000 MW annually Actually added 4000 – 5000 MW p.a.

Transcript of Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities...

Page 1: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Decentralized Power Generation: Opportunities in Rural India

Anshu Bharadwaj

India’s Electricity ScenarioInstalled Capacity ~ 100,000 MW

Fifth largest in the world1,500 MW in 1947

95% of villages electrified40% of households have access

Per Capita Consumption : 350 kWhWorld Average: 2000 kWh

Need to add 10,000 – 15,000 MW annuallyActually added 4000 – 5000 MW p.a.

Page 2: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Regulatory Framework & Structure

Central State IPPGeneration

Transmission State Utilities

Distribution State/Private Utilities

SERC

MNES

CEA

CERC

MoP

Mismatch in Tariff & Consumption

Agriculture supply subsidizedFree in some states Not metered

Average cost of supply: Rs 3.04/kWh

Average Revenue: Rs 2.12/kWh

Rs 4.70/kWh5%Commercial

Rs 4.50/kWh35%Industrial

Rs 0.22/kWh31%Agriculture

17%

Consumption

Rs 1.20/kWhDomestic

TariffRs/kWh

Category

1 US $ = Rs 48Source: Karnataka Electricity Regulatory Commission

Page 3: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Uncovered Subsidies are Growing

0

50

100

150

200

250

300

350

400

1991 1997 1998 1999

Rs

Bill

ion

UncoveredSubsidy

Cross Subsidy

Covered by StateGovernment

Rural Electricity SupplyIntermittent

Voltage and frequency fluctuationsEquipment damage

Vicious circle: (World Bank, 2001)Subsidized TariffsLow InvestmentsPoor quality

T&D Losses > 30% (I2R + Theft)

Page 4: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Advantages of DG

Generate close to rural load centers (NRECA, US Department of Energy, FERC, California Energy Commission)

Reliability of supply Lower distribution lossesImprove voltage profilesPeak shaving Local supply of reactive power

Create incentives for increasing agricultural tariffWillingness to pay for good quality power (World Bank, 2001)

Biomass for Decentralized Generation

Biomass power potential 17,000 MWGasifier-reciprocating engine+ 5,000 MW from sugarcane bagasse and rice husk cogeneration

Sugar Mills (> 2500 Tons per Day)Export 5 – 30 MW

Page 5: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Enormous Potential of Power From Sugar Mills

Bagasse75 MT

Cane275 MT

Process Electricity@ 30 kWh/Ton~ 8 Billion kWh

Process Steam@ 500 kg/Ton~ 50 Billion kWh

Potential Export 25 - 40 Billion kWh4000 – 6500 MW

~

Annual Production (Million Tons)

Each Plant: 5 – 30 MW

SEB Policy for Renewable (DG):Buy-Back: Rs. 3.01/kWh

ExpensiveInterconnect at 66/33 kVDelay of months in paymentsNo reduction in SEB’s losses

Wheeling: up to 20% chargesSEBs view DG as a threat

Reactive power not valued

Present policies overlook potential benefits of DG

Cost of Power in Karnataka 2001-02

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

Hydel Thermal Central Other States IPP Cogeneration Others

Rs

/kW

h

(Karnataka Electricity Regulatory Commission, Bangalore)

Page 6: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Research Objectives

Techno-Economic Analysis of Rural Micro-Grids

Break the vicious circle

Options for Pricing Reactive Power

Rational basis for assessing wheeling charges

DG

Region

Third Party

Utility

ElectricityCash

Rural Distribution Feeder in Tumkur, Karnataka128 buses Sub-Station 66/11 kVPeak demand 3 MW

Page 7: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Present Tariffs & Consumption

7,831,400TOTAL

?Losses (Commercial)

?Losses (Technical)

13,3204.75Industrial

?0.20Irrigation Pumps

9004.50Commercial

183,9401.20Domestic

Units ConsumedTariffRs/kWh

Consumer

Load Flow Studies (3 Phase AC)

We know:Total kWh at the sub-stationsSanctioned load at each bus (kW)Length and impedances of conductors between buses

We don’t know:kWh at each busPower factor (hence kVAR at each bus)Unauthorized connections (theft)Sub-Station Voltage

Page 8: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Load Flow Studies (3 Phase AC)

Assumptions (Unknown Variables):On-Line Load (40% - 75%)Power Factor (0.7 – 0.9)Theft (15%)

POWERWORLD Simulation

Gauss - Seidel MethodAdmittance Matrix (128 X 128)

Voltage at each node:

Iterate till convergence

P Real PowerQ Reactive PowerV VoltageY Admittance MatrixR ResistanceL Inductive Resistanceω Angular Frequency

∑=

−−

=N

iiki

k

kkkkk VY

VjQP

YV1

])(

[

LjRYij ω+

=1

Results: Voltage Profiles:Load 75%, Theft 15%

0.70

0.75

0.80

0.85

0.90

0.95

1.00

0 20 40 60 80 100 120Bus No

Vo

ltag

e (p

u)

Power Factor: 0.90

Power Factor: 0.80

Power Factor: 0.70

Page 9: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Technical Distribution LossesLoad 60%, Theft 15%

4

6

8

10

12

14

0.65 0.7 0.75 0.8 0.85 0.9 0.95Power Factor

Lo

sses (

%)

Impact of Sub-Station Voltage

0.6

0.7

0.8

0.9

1

25% 35% 45% 55% 65% 75% 85% 95%Load

Vo

lta

ge

at

Bu

s #

89

(p

u)

Sub-Station Voltage = 11 kV

Sub-Station Voltage = 10 kV

Page 10: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Impact of DG on VoltagesLoad 60%, Theft 15%, Power Factor 0.8

0.8

0.85

0.9

0.95

1

1.05

1.1

0 20 40 60 80 100 120Bus #

Vo

ltag

e (p

u)

0 MW

0.5 MW

1 MW

2 MW

3 MW

2 MVAR

Impact of DG on LossesLoad 60%, Theft 15%, Power Factor 0.6

0

2

4

6

8

10

12

0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 Generator Rating (MVA)

Te

ch

nic

al

Lo

ss

es

(%

)

Generator Power Factor = 0.95

Generator Power Factor = 0.80

Page 11: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Capacitors in GridCAPACITOR[MVAR] IN THE GRID

SOURCE: KPTCL ADMIN REPORTS

YEAR 110KV 66KV 33KV 11KV TOTAL MVAR

96-97 640 871 170 559.12 2240.12

97-98 800 1051 170 559.12 2580.12

98-99 840 1091 170 559.12 2660.12

99-00 840 1091 170 559.12 2660.12

Power Transactions with Grid

-0.4

0.0

0.4

0.8

1.2

1.6

0.85 0.9 0.95 1Generator Power Factor

MW

, MV

AR

Reactive Power

Real Power

Page 12: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Economic Analysis: SEB’s Present Losses

SEB Consumers

Units Sold : 7.8 Million kWh

Cost of Supply: Rs 22 Million

Tariff Levied : Rs 1.2 Million

Tariff Collected : Rs 0.6 Million

Methodology

1. Estimate Generation Potential of IPP (2.5 MVA)PLF: 70%Auxiliary Power: 5%Power Factor of Generator: 0.95

2. Estimate consumption under unconstrained supplyForecast for domestic, commercial, industrial consumersForecast for IP Set consumptionTechnical Losses

3. Surplus available for Export to Grid/Third Party

Page 13: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Consumption Forecast Under Increased Supply

0

2

4

6

8

10

Domestic Commercial IP Sets Industrial Theft TechnicalLoss

Millio

n U

nit

s

Present

Forecast

Present 7.8 MUForecast 11.0 MU

Elasticity of Demand not applicable

Obtain Upper Limit of consumption

Increase hours of supply to ~ 12 – 14

Can’t flood the fields !!

Technical Losses: 2%

Commercial Losses: 15%

Scenario I – No Tariff ChangesDG’s Perspective

SEB Consumers

DG2.5 MVA

11.0 MU

2.8 MU

Third Party

Rs 2.2 Million

Rs 10.1 Million

Rs 29.3 Million

Revenues Expected : Rs 41.6 Million@ Rs. 3.01/kWh

Page 14: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Scenario I – No Tariff ChangesSEB’s Perspective

- Rs 8.8 MillionNet

Rs 34.0 Million7.8 MUSavings of Power from the Micro-grid & Potential Sale to HT Consumer

- Rs 29.3 MillionDisbursement to IPP

- Rs 13.5 Million2.82 MULoss of HT Consumer to IPP

Scenario II: Increase in Irrigation Tariff

-10

-8

-6

-4

-2

0

2

4

6

0 0.5 1 1.5 2 2.5

IP Set Tariff (Rs/kWh)

Ne

t C

ha

ng

e fo

r U

tility

(R

s M

illio

n

Pricing of biomass

Income to Farmers: Rs 11.5 Million @ Rs 0.5/kg

New IP Tariff : Rs 11.1 Million @ Rs 1.50/kWh

Restrictions on water usage

Depending on farm size, land, crop, pump etc.

Policy Options

Page 15: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Reactive Power Pricing Options

Ancillary service in deregulated world (FERC Order # 888)Most rural buses have low power factorDG Can supply reactive powerBUT, at the cost of real power

Classical economic definition (Baughman 1997, Chattopadhyaya 1995, Dai2001)

Optimal Power Flow: Marginal cost of reactive power at a busProblem: Intermittent supply & lack of data in rural India.

Avoided cost of synchronous condensers (Silva 2001)

Cost of not producing real power (Generator Capability Curve)

Reactive Power Pricing: Generator Capability Curve

0.00

0.20

0.40

0.60

0.80

1.00

1.20

0.80 0.85 0.90 0.95 1.00Desired Power Factor (Lagging)

Pri

ce o

f R

eacti

ve P

ow

er

(R

s p

er

kV

AR

h)

Make the generator indifferent to producing reactive power.

Page 16: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Wheeling of PowerCurrent policy:

Wheeling rates ~ 20%Not allowed in some states.

Rationale:Threat to SEB’s cash cow.Impose the T&D Losses (20%) as wheeling charges.

But, wheeling benefits the utility also.

More scientific basis needed for estimating wheeling charges.

Estimating Wheeling Charges

Strict Economic Definition: (Schweppe 1988, Caramanis 1986)

Solve Optimal Power Flow and obtain the marginal costs from Lagrangian Dual.Wheeling Rate between bus i & j = Difference of marginal cost of power at the two buses.Wheeling rates can be negative if it results in lower T&D Losses.

Load Flow StudiesLower Distribution Losses ~ 2%Voltage Support to SEB.Wheeling rates should be low, if not negative.

Page 17: Decentralized Power Generation: Opportunities in …...Decentralized Power Generation: Opportunities in Rural India Anshu Bharadwaj India’s Electricity Scenario Installed Capacity

Conclusions

Rural micro-grids can benefit SEB & consumersLower lossesImproved quality of supply

Reactive power pricing useful

Rational basis for assessing wheeling charges