Crewkerne & Ilminster Strategic School Review Report (Stage 0) · the current locality system and...
Transcript of Crewkerne & Ilminster Strategic School Review Report (Stage 0) · the current locality system and...
Page 1 of 137
Futures for Somerset Limited
(The Somerset Local Education Partnership)
Crewkerne & Ilminster
Strategic School Review Report
(Stage 0)
Document Status: v1.0 FINAL
12th June 2019
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 2 of 137
Document Control
Document Properties
Document Owner Futures for Somerset
Organisation Futures for Somerset (FfS)
Title Crewkerne & Ilminster –
Strategic School Review Report
Abstract
This document contains the Report for the Crewkerne and Ilminster Area Strategic Education
Structure Review, developed by the Somerset Local Education Partnership (“the LEP”)
(Futures for Somerset Ltd. (“FfS”)) and commissioned by Somerset County Council.
The document outlines the findings from activities completed as part of the Stage 0 Strategic
Review, including the identification and assessment of site opportunities and constraints, site
capacity (BB103), review of potential alternative structural options and impact on a range of
key factors relating to the delivery of education within this area of Somerset.
Version History
Date
Editor Version Status Reason for change
07/05/2019 HW 0.1 Draft Draft Report Structure
04/06/2019 HW 0.2 Draft Formatted report for pre-issue review
12/06/2019 VS 0.3 Draft Draft Executive Summary
12/06/2019 HW 1.0 FINAL Final for issue
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 3 of 137
Contents:
Executive Summary ...................................................................................................................... 9
SCC Statement of Intent ..............................................................................................................15
1. Introduction and Background ................................................................................................17
1.1. Introduction ................................................................................................................................... 17
1.2. Background & Context .................................................................................................................. 17
1.3. FfS Assumptions ........................................................................................................................... 19
1.4. Overarching Objectives ................................................................................................................. 21
1.5. Opportunities ................................................................................................................................. 21
1.6. Constraints .................................................................................................................................... 22
2. Academy & MAT Landscape ................................................................................................23
2.1. Summary of Evolving Academy & MAT Landscape ..................................................................... 23
2.2. Potential Benefits of Evolving Academy & MAT Landscape ........................................................ 24
2.3. Potential Challenges of Evolving Academy & MAT Landscape ................................................... 25
3. Site & Buildings ....................................................................................................................25
3.1. First Schools in Scope .................................................................................................................. 25
3.2. Primary Schools in Scope ............................................................................................................. 32
3.3. Middle Schools in Scope ............................................................................................................... 34
3.4. Upper Schools in Scope ............................................................................................................... 36
3.5. Out of Scope Schools – Impact on Review .................................................................................. 37
4. Review Team .......................................................................................................................38
4.1. Futures for Somerset Ltd (the Somerset Local Education Partnership) – Strategic Review and
Project Management .................................................................................................................................. 38
4.2. Grainge Architects Ltd – Capacity Review and Masterplanning ................................................... 38
4.3. Randall Simmonds – Cost Advisors ............................................................................................. 39
4.4. Susan Fielden (Effervesce Ltd) – Specialist School Finance Advisor .......................................... 39
4.5. Jill Ewen – Education Consultant - Education Impact Review ..................................................... 40
5. Methodology ........................................................................................................................40
5.1. Area Wide Capacity Review ......................................................................................................... 40
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 4 of 137
5.2. Review of Basic Need & Growth Projection Data ......................................................................... 41
5.3. Masterplanning Scenarios ............................................................................................................ 41
5.4. Report Stage Consultation ............................................................................................................ 41
5.5. Future Consultation ....................................................................................................................... 42
5.6. Option & Scenario Scope .............................................................................................................. 43
6. Evaluation ............................................................................................................................44
6.1. Option & Scenario Scope .............................................................................................................. 44
6.2. Capital Cost Impact ....................................................................................................................... 46
6.3. Revenue Impact ............................................................................................................................ 47
6.4. Staffing .......................................................................................................................................... 47
6.5. Education ...................................................................................................................................... 47
6.6. Transport and Geography ............................................................................................................. 48
6.7. Equalities Impact ........................................................................................................................... 49
6.8. Community Impact ........................................................................................................................ 49
7. Scenario Testing – Option 1 (Baseline) ................................................................................50
7.1. Option 1 – Summary & Key Findings ............................................................................................ 50
7.2. Scenario 1A - Specifics: ................................................................................................................ 51
7.3. Capital Cost ................................................................................................................................... 52
7.4. Building Condition ......................................................................................................................... 52
7.5. Site rationalisation / disposal opportunities and condition improvement cost avoidance ............. 53
7.6. Revenue Impact ............................................................................................................................ 53
7.7. Education and Staffing Impact ...................................................................................................... 55
7.8. Transport / Geography .................................................................................................................. 56
7.9. Equality and Community Impacts ................................................................................................. 58
8. Scenario Testing – Option 2 .................................................................................................58
8.1. Option 2 – Summary & Key Findings ............................................................................................ 58
8.2. Revenue Impact ............................................................................................................................ 58
9. Scenario Testing – Option 3 .................................................................................................59
9.1. Two-tier education models ............................................................................................................ 59
9.2. Option 3 – Summary & Key Findings ............................................................................................ 61
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 5 of 137
9.3. Scenario 3B Specifics: .................................................................................................................. 62
9.4. Capital Cost ................................................................................................................................... 63
9.5. Building Condition ......................................................................................................................... 64
9.6. Revenue Impact ............................................................................................................................ 65
9.7. Education and Staffing Impact ...................................................................................................... 66
9.8. Sports / Extra-curricular / SEND and Wrap Around Care ............................................................. 68
9.9. Transitions ..................................................................................................................................... 69
9.10. Pre-school and Nursery ................................................................................................................ 69
9.11. Transport / Geography .................................................................................................................. 69
9.12. Equality and Community Impacts ................................................................................................. 70
10. Scenario Testing – Option 4 .............................................................................................72
10.1. Option 4 – Summary & Key Findings ............................................................................................ 72
10.2. Scenario 4A - Specifics: ................................................................................................................ 74
10.3. Scenario 4A - Capital Cost ............................................................................................................ 75
10.4. Scenario 4 - Building Condition ..................................................................................................... 76
10.5. Scenario 4A - Revenue Impact ..................................................................................................... 77
10.6. Scenario 4A - Education and Staffing Impact ............................................................................... 78
10.7. Scenario 4A - Sports / Extra-curricular / SEND and Wrap Around Care ...................................... 80
10.8. Scenario 4A - Transitions .............................................................................................................. 81
10.9. Scenario 4A - Pre-school and Nursery ......................................................................................... 81
10.10. Scenario 4A - Transport and Geography ................................................................................. 81
10.11. Scenario 4A - Equality and Community Impacts ...................................................................... 82
10.12. Scenario 4D - Specifics: ........................................................................................................... 85
10.13. Scenario 4D - Capital Cost ....................................................................................................... 86
10.14. Scenario 4D - Building Condition .............................................................................................. 86
10.15. Scenario 4D - Revenue Impact ................................................................................................ 87
10.16. Education and Staffing Impact .................................................................................................. 88
10.17. Sports / Extra-curricular / SEND and Wrap Around Care ......................................................... 89
10.18. Transitions ................................................................................................................................ 89
10.19. Pre-school and Nursery ............................................................................................................ 89
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 6 of 137
10.20. Transport and Geography ........................................................................................................ 89
10.21. Scenario 4D Equality and Community Impacts ........................................................................ 90
11. Scenario Testing – Option 5 .............................................................................................92
11.1. Option 5 – Summary & Key Findings ............................................................................................ 92
11.2. Scenario 5C specifics: .................................................................................................................. 95
11.3. Scenario 5C - Capital Cost ........................................................................................................... 95
11.4. Option 5C - Building Condition ...................................................................................................... 96
11.5. Scenario 5C - Revenue Impact ..................................................................................................... 97
11.6. Scenario 5C - Education and Staffing Impact ............................................................................... 98
11.7. Scenario 5C - Sports / Extra-curricular / SEND and Wrap Around Care .................................... 100
11.8. Scenario 5C - Transitions ........................................................................................................... 100
11.9. Scenario 5C - Pre-school and Nursery ....................................................................................... 101
11.10. Scenario 5C - Transport and Geography ............................................................................... 101
11.11. Scenario 5C - Equality and Community Impacts .................................................................... 102
11.12. Scenario 5D - Specifics: ......................................................................................................... 103
11.13. Scenario 5D - Capital Cost ..................................................................................................... 103
11.14. Scenario 5D - Building Condition ............................................................................................ 104
11.15. Scenario 5D - Revenue Impact .............................................................................................. 105
11.16. Scenario 5D - Education and Staffing Impact ........................................................................ 106
11.17. Scenario 5D - Sports / Extra-curricular / SEND and Wrap Around Care ............................... 107
11.18. Scenario 5D - Transitions ....................................................................................................... 107
11.19. Scenario 5D - Pre-school and Nursery ................................................................................... 107
11.20. Scenario 5D - Transport and Geography ............................................................................... 107
11.21. Scenario 5D - Equality and Community Impacts .................................................................... 108
12. Most Viable Options ....................................................................................................... 109
13. Project & Programme Management (Live Project) .......................................................... 112
13.1. Overview ..................................................................................................................................... 112
13.2. Governance ................................................................................................................................. 112
13.3. Change Management ................................................................................................................. 115
13.4. Programme ................................................................................................................................. 115
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 7 of 137
13.5. Key consultation stages (depending on preferred / viable options) ............................................ 118
13.6. Risk Management ....................................................................................................................... 118
13.7. Stakeholder Engagement ........................................................................................................... 119
14. Conclusions & Recommendations .................................................................................. 120
14.1. Conclusions ................................................................................................................................. 120
14.2. Recommendations ...................................................................................................................... 125
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 8 of 137
Appendices
1. Baseline Information
a. School site information
i. Site Plans
ii. General Arrangement Plans
iii. SoA Schedules
iv. Condition Information
2. Options Information
a. Geographical Plan
b. Pupil Number Comparison
c. Site Area Comparison
d. Building Area Comparison
e. Provision of Spaces Comparison
f. Under provision Solutions (as required) (Master planning)
3. Capital Cost Modelling
4. Revenue Budgets
5. Education Impact
6. Options Appraisal
7. Consultation
8. Programme
9. Risk Register
10. Catchment Map
Annex A - Supporting Design Information (by site)
i. Options Summary Data
ii. Space types - ESFA tool data
iii. Space types - Recommended v existing
iv. Site areas - ESFA tool data
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 9 of 137
Executive Summary
Futures for Somerset Ltd. were commissioned by Somerset County Council (SCC) to complete a
Strategic School Review exercise for the Crewkerne and Ilminster area. The purpose of the review
was to assess and test current and alternative education structures for viability and potential
sustainability into the future, in response to ongoing financial and demographic pressures.
This review is not intended to provide a definitive solution to the issues and challenges experienced
in the Crewkerne and Ilminster area, but is intended to provide a strategic overview to establish the
most viable alternative option(s) for consideration. These can then be taken forward as appropriate
for further, more detailed dialogue and consultation with stakeholders and more detailed stages of
work to establish the feasibility and deliverability of the preferred option(s) for change.
Somerset County Council requested that alternative options for the structure of education in the
Crewkerne and Ilminster area be explored, where possible utilising the existing school estate and
recognising the national presumption against the closure of small rural schools. Options considered
were to include both three-tier and alternative two-tier; primary and secondary structures, based on
the current locality system and wider national picture.
The educational system in Crewkerne and Ilminster is currently based on a three-tier system
comprising seven First Schools (Years R-4), two Middle Schools (Deemed secondary, Years 5-8)
and 1 Upper School (currently Years 9-13). It also includes two very small Primary Schools
operating within the system (Years R-6), accommodating just over 70 students between them.
The two towns of Crewkerne and Ilminster are small in scale and located in a relatively rural area
of South Somerset approximately 7.5 miles apart. The schools here serve the town populations and
a number of surrounding small rural villages and hamlets. Closure of small rural schools is an
important factor as the current educational system in Crewkerne and Ilminster comprises a network
of small first and primary schools with 6 schols based in rural communities outside of the main town
areas.
The first step of the review was to establish:
• The current position of the existing school estates, specifically what opportunities and
constraints there were for potential expansion and re-structuring.
• What capacity the system needs to be able to cater for to ensure sufficient educational
places in the future – i.e. growth projections for the locality for the next 10+ years.
The review has been designed to take account of growth and test the structure of education within
the area over the next 13-year period based on school population forecast and housing projection
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 10 of 137
data to 2032 as provided by the Local Authority. The projected additional housing demand is based
on submitted and approved new housing developments within the education locality in accordance
with SCC methodologies. The projected maximum demand is 2902 student places and this is the
same within all options and scenarios, whether delivered through two or three-tier structures.
A strategic review of all 12 of the education estates within the Crewkerne and Ilminster locality was
completed, assessing existing buildings and sites against Building Bulleting guidance (BB103) for
both current and projected numbers (projected demand to 2032 in accordance with SCC data).
Accommodation and site footprints were then also assessed utilising ESFA Building Bulletin
Schedule of Areas (SoA) tools for potential alternative educational delivery models (first, primary,
infant, junior, secondary) as required under the relevant options, to ascertain opportunities and
constraints for future site utilisation under different phases of education. This allowed the review to
conduct an objective analysis of possible viable scenarios, ascertaining which expansion and re-
structure options and combinations were viable at both individual site levels and as part of an
overarching system for the locality. It also allowed consideration of potential scope of changes and
associated works costs.
Viable options were then able to be identified and scenarios modelled to allow a wider evaluation
team to assess how these fit with key agreed criteria, such as optimal use of the existing school
estate, minimisation of development and cost implications and impact on other key factors such as
education delivery and outcomes, revenue budget implications, transport, geography and equality,
access and community needs.
Presented scenarios were developed within the framework of five agreed Option parameters:
Option 1 – The do nothing or minimum requirement option focused on retaining the existing three-
tier education structure but taking into account growth and future capacity needs. This option
demonstrates that ‘doing nothing’ is not an option – development is required to provide sufficient
places long term with growth exceeding existing capacity in both first and middle school areas.
Existing upper school numbers continue to exceed demand. This requirement and associated
Capital cost was established as the baseline for comparison of all alternative options and scenarios.
Option 2 – making no changes to the baseline structure but exploring the financial options and
implications relating to formula funding changes.
Options 3 and 4 – looking at viable alternative two-tier Primary and Secondary Structures. Option
3 utilising consolidated primary and secondary schools only, and Option 4 utilising split site Infant
and Junior or mixed Primary and Infant / Junior models, with secondary provision.
Option 5 – a hybrid three-tier system model focused on retaining the existing first school structure
but consolidating middle and upper year into combined ‘all through 9 – 16’ school provision.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 11 of 137
Potentially viable structures were established against these options, resulting in six scenarios
deemed to represent the most viable models for further assessment and discussion. Scenarios are
identified based on their viability and deliverability and as such many alternatives have been
discounted on the basis of not being deliverable within the assumptions and constraints of the
review scope (e.g. where sites are too small to practically deliver a scenario, physically or in terms
of viability of the resultant educational model, the scenario is not carried forwards as it would not
be viable / deliverable / recommended as a structure). Resultant scenarios vary in numbers of
schools in the system (and converse potential school closures) and the complexity of associated
changes.
These scenarios are not recommendations but an assessment of viable models for future
consultation and feasibility study, and as such no single scenario or hybrid scenario is proposed as
the best solution. The scenarios show ways required capacity and alternative educational structures
could be delivered within the constraints of existing and potential future expanded site
developments; but this needs to be reviewed in the wider context of community and Diocese impact,
Academisation, estate ownership and the changing MAT landscape etc. No one option can be
progressed without critical decisions being taken by stakeholders to agree a way forward.
It is important to understand not just the physical opportunities and constraints of the sites but the
regional context and ownership and control position in which they sit.
All schools within the Ilminster and Crewkerne area remain as maintained schools with the
exception of Maiden Beech which is an Academy (and therefore no longer a maintained school).
However, 8 of the 9 first / primary schools are designated as Voluntary Controlled (VC) Schools
along with the Upper School at Wadham. These school sites are typically owned by the Diocese
of Bath and Wells and therefore the Diocese holds significant influence over the future of the schools
and their sites. Only two schools (Swanmead Middle and Merriott First) remain as maintained
community schools under ownership of the Local Authority at the date of this report.
The above split in control of the Ilminster and Crewkerne Schools presents the Local Authority with
a significant challenge. Any implementation of structural change within the Ilminster and Crewkerne
area will require numerous stakeholders to work together to achieve an area wide structural change.
The review has reinforced the complexity of the issue that Somerset County Council are currently
contending with in the Crewkerne and Ilminster area. Somerset County Council currently hold the
financial burden of the deficit budget at Wadham school but have very limited ability to effect change
to alter this situation. Whilst there are potentially viable alternative options for consideration the
current education landscape and breadth of stakeholders within the education structure results in a
lack of strategic control to shape the structure for the future.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 12 of 137
Throughout the review several key themes and decision points have established themselves due
to the intrinsic nature of their relationship to all proposals - these are considered to be key for
discussion and agreement by stakeholders and form the core conclusions of the review.
There is a strong relationship between the size of schools and efficiency of education delivery and
progress, with optimal sizing of schools or groups of schools enabling an efficiency in the delivery
of education, sport, extra-curricular and wrap around care against set budgets whilst crucially
offering an appropriate breadth of education. This appears to support the potential benefit of
consolidating the school estate either physically or structurally.
The consolidation of schools within a new education structure has the ability to result in greater
efficiency of curriculum delivery, however there is a considerable degree of uncertainty over who
would benefit from such consolidation in the medium to longer term future. It remains unclear as to
whether the Local Authority & Schools or the Department for Education would see the greater
benefit of such improvements. If the latter, then this may lead towards a false benefit in that the
overarching budget would be resized to reflect any amalgamation and consolidation and therefore
counter any realisation of financial benefits. It is similarly unclear should any options containing land
disposals (consequential from school closures) be considered. With most schools in scope being
VC Church of England Schools, it is understood that any capital receipt would revert to the Diocese
of Bath & Wells and therefore would not necessarily benefit the overall project unless an alternative
agreement could be reached.
The introduction of a MAT(s) needs to be recognised as bringing a potentially significant opportunity
for improving the efficiency of revenue costs through the centralisation of core school functions (e.g.
HR, Procurement, IT, Estates, Finance etc). The central management, scale of economy and wider
buying power of a MAT model could add significant benefits to the structure of schools if developed
alongside the structural change.
Overall the review has identified a number of scenarios that could provide improved viability and
sustainability for the Crewkerne and Ilminster area schools, but none are viable without the need
for critical decisions to be taken by stakeholders. Consideration needs to be given to:
• The preferred solution for Secondary / combined Middle & Upper provision within the area
and the geographical impact that such a decision could have, particularly on Year 5 & 6
pupils.
• The education phase of the Middle School sites and potential conversion to Primary or
Secondary places. Any change to a viable two-tier Primary / Secondary model is contingent
upon the Middle school estate providing Primary capacity. This offers the greatest
opportunity to consolidate and rationalise the wider school system within the Crewkerne and
Ilminster area.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 13 of 137
• Implications of any potential closures to small rural schools, proposed in order to seek
greater efficiency in the school estate and therefore greater consolidation of places in fewer
sites (impact on community to enable optimisation of school sizes).
• The importance of Church of England VC schools within the Crewkerne and Ilminster area
and whether there is any scope for change to Governance arrangements in order to facilitate
alternative solutions.
The outcome of the above decisions will undoubtedly impact on the ability to carry forward any of
the solutions, and without the support of key stakeholders, progression of any option other than
‘baseline – as is’ will likely not prove deliverable. A detailed cost / benefit analysis of baseline
Scenario 1A against other options is recommended so the limitations and constraints of proceeding
with changes for natural growth only are fully understood, in terms of continued impact on education
provision (and potential future performance) and finances. All proposed improvement scenarios
require increased levels of Capital expenditure and have potential revenue cost associated with
factors such as travel; this needs to be better understood in relation to likely ongoing financial
deficits and baseline capital funding requirements.
Ultimately to move any other change forwards all Stakeholders need to be committed to achieving
a step change in the education structure for the Crewkerne and Ilminster area.
In order to progress the development of any viable option it is critical that all key stakeholders work
together to establish an agreed solution, recommended next steps are as follows:
• Establish appropriate review and feedback groups with all schools and governing bodies to
specifically review and consult on options, with the intention of moving towards an agreed
way forward and identifying which option(s) will be taken forward to a strategic level forum
for further work, review and consultation.
• Enter into detailed dialogue with the Diocese of Bath and Wells in relation to the Voluntary
Controlled Schools within the scope of this review. The willingness of the Diocese to work
with the Local Authority on the exploration of viable options will be critical to the deliverability
of a solution.
• Given the national education agenda and increasing move towards academisation within
the Crewkerne & Ilminster area it would be prudent develop a strategic working relationship
with an incoming MAT(s) to help shape the area review in greater detail. This could enable
added financial benefits to be gained for schools within the area.
A further stage of detailed feasibility work will be required on the Preferred Option(s) once identified
and agreed with the wider stakeholder group. That stage of work would seek to establish a
deliverable programme structure and add more detail to key workstreams including capital and
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 14 of 137
revenue budgets, estates surveys and reference scheme designs and required consultation and
change management processes, to clarify and support the agreed scope of change.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 15 of 137
SCC Statement of Intent
The market towns of Crewkerne and Ilminster, together with surrounding villages, are served by a
three-tier school system, consisting of first, middle and upper schools. There are 12 schools in total
with 2,120 pupils on roll from Reception to Year 11 (October 2018 census).
The future financial viability of the upper school (Wadham), and the two middle schools (Maiden
Beech and Swanmead) requires a re-evaluation of the suitability of the education system in this
area of Somerset.
The upper school (Wadham) currently has a significant budget deficit which, despite school leaders’
best efforts, is growing year on year. The cumulative deficit at the end of 2017/18 was £393,686,
giving a combined deficit at the end of 2018/19 of £646,301 and by the end of 2019/20 this is
anticipated to be in the region of £1m. This accumulated and growing deficit has placed the school
into a position where it will not be able to repay the Local Authority. The Local Authority has worked
hard with the school to support them in attempting to balance the budget; but has got to the position
where any further reductions in staffing will mean that standards at the school will risk significant
decline, which will result in less pupils attending the school and therefore less funding – the school
is then in a declining cycle.
The school currently caters for years 9-13; but the Sixth Form offering is no longer viable with the
money it receives from the ESFA. The Sixth Form currently has 40 students on role across years
12 & 13. The accepted view is that for a Sixth Form to be viable and offer a broad and balanced
curriculum, it needs a minimum level of 100 students per year group. However, closure of the Sixth
Form provision will not leave the school viable as an educational establishment with only 3 year
groups (Years 9-11). Around 30% of pupils who take GCSEs at Wadham remain in the Sixth Form
and this has been the case for a number of years. Those that leave tend to either attend Richard
Huish College in Taunton or Yeovil College.
The Local Authority is also aware that the two middle schools are facing increasing financial
pressure and have had to make staff redundant in order to balance their individual budgets.
It is understood that a number of First schools within the area are also under significant budget and
performance pressures with two schools having recently been judged as Inadequate by Ofsted.
The smaller schools are potentially vulnerable to fluctuations in pupil numbers and the financial
challenge that this brings in an already challenging financial climate.
A review of pupil numbers shows that there are around 800 11-16 year old pupils in the area with
no significant increase expected in the foreseeable future. This is the size of a medium sized
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 16 of 137
secondary school. At present these pupils are spread between three schools. Financially this is
not an effective use of resources, but it also means that at a time of difficulty in recruiting specialist
subject teachers, there are three schools competing to attract the best candidates.
From an academic perspective, all the schools in the area are currently judged as Good or better.
The middle and upper schools were subject to short inspections in the last academic year. All
retained their Good judgements with Wadham and Maiden Beech Academy being told they will be
subject to full inspections in the near future.
The 2016 area review (instigated by the local Headteachers) recommended closer working
relationships between schools and a move to federation / Multi-Academy Trust arrangement(s).
Some progress has been made but no tangible proposal for structural change have been
forthcoming. An initial approach to the Regional Schools Commissioner’s Office to form a Multi-
Academy Trust (MAT) in the area did not progress after the schools were informed that they would
not be able to form a new MAT but would have to join an existing one.
It is the view of Local Authority officers that the current system is not sustainable, and that the Local
Authority (working with the schools) should look to move to a different structure in the area where
possible utilising the existing estate of schools and recognising the national presumption against
the closure of small rural schools. If no action is taken the deficit at Wadham will continue to
accumulate and it is likely that in time the two middle schools could follow suit. Academic standards
are likely to slip with a real risk of Inadequate Ofsted judgements in the future.
It should be noted that the surrounding areas both within Somerset and across the border in Dorset
are all two- tier education structures.
To achieve this review, it is proposed that alternative options for the structure of education in the
Crewkerne and Ilminster area are explored. The Local Authority have commissioned Futures for
Somerset Ltd. to complete this review on their behalf in order to establish and test a series of
alternative options with a view to consulting of the most viable options that ensure best use of pupil
funding in the area over the next 10-year period.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 17 of 137
1. Introduction and Background
1.1. Introduction
1.1.1. FfS have been appointed by Somerset County Council to complete a review of current and
alternative education structures for the Crewkerne & Ilminster area in response to ongoing
financial and demographic pressures. The review focuses on the structure of education
from Reception stage to and including Year 11.
1.1.2. This review seeks to analyse the current education structure and compare against potential
alternative solutions in order to assess whether more financially viable structures are
possible, whilst remaining cognisant of the impact that alternative structures could
potentially have on a host of other important factors (e.g. education outcomes, transport
impact etc).
1.1.3. It is important to note from the outset that this review is not intended to provide a definitive
solution to the issues and challenges experienced in the Crewkerne and Ilminster area.
The exercise is designed to establish the most viable alternative options for consideration
and if appropriate further, more detailed dialogue and consultation with stakeholders.
1.1.4. The importance of taking time to ensure the right outcome from this exercise cannot be
over-stated. This report serves as a strategic overview and will need to be followed by
detailed stages of work to look at feasibility and deliverability of preferred options. With
such a significant number of stakeholders potentially impacted upon by this review it will
be critical to ensure shared Governance, objectives and outcomes before moving forwards
to a live programme of work.
1.2. Background & Context
1.2.1. The Crewkerne and Ilminster area are located within the South Somerset District of
Somerset. The two towns are approximately 7.5 miles apart, connected by a series of A
and B roads. Both towns are small in scale and located within a more rural area of
Somerset they also serve a number of surrounding small rural villages and hamlets.
1.2.2. Crewkerne is a historic town with significant history recorded back to 899 and the main
town along with many outlying villages is designated as a conservation area. The town
and surrounding area is served by a number of First Schools, a Middle School and an
Upper School. Crewkerne has a recorded population of c. 7000 (2011 census).
1.2.3. Ilminster is also an historic town with a history recorded back to 725. The main town and
many outlying villages are also designated as conservation areas. The town is served by
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 18 of 137
a number of Primary and First Schools, and a Middle School (Swanmead). Ilminster has
a population of c. 5088 (2011 census).
1.2.4. Both towns are surrounded by a number of larger towns with Yeovil located to the East
(9.5 miles from Crewkerne and 15 miles from Ilminster) and Chard located to the West (8
miles from Crewkerne and 5.5 miles from Ilminster). Langport is located to the North (15
miles from Crewkerne and 10 miles from Ilminster). Bridport (Dorset) is located to the
South (13 miles from Crewkerne and 18 miles from Ilminster). All these towns are
reachable by car or bus within a 45-minute travel period in average traffic.
1.2.5. The school system in Crewkerne and Ilminster is primarily based on a three-tier structure
comprising First Schools (Years R-4), Middle Schools (Deemed Secondary) (Years 5-8)
and an Upper School (currently Years 9-13). In addition there are two small Primary
Schools operating within the system (Years R-6).
1.2.6. Schools within wider Somerset mainly operate on a two-tier structure based on Primary
(Years R-6) and Secondary (Years 7-11). There are however a number of areas within
the County that continue to operate on a three-tier system including West Somerset and
Frome.
1.2.7. For context there has been a significant move away from three-tier school systems over
the last 30+ years (since the early-mid 1980’s). Data suggests that whilst there were c.
2,000 middle and combined schools in England and Wales in the early 1980’s there are
now less than 150 such schools, a reduction of more than 90% which appears to be
primarily down to adjustments in the National Curriculum and Key Stages, resulting in the
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 19 of 137
majority of these schools re-designating / reverting to Primary school status1. Those
remaining middle schools tend to be classified as Middle (Deemed Secondary) due to the
age range and teaching approach implemented.
1.2.8. All schools within the Ilminster and Crewkerne area remain as maintained schools with the
exception of Maiden Beech which is an Academy. There are a total of 12 schools within
the scope of this review, made up of 9 First / Primary Schools, 2 Middle Schools and 1
Upper School.
1.2.9. 5 schools have established early years pre-school / nursery facilities on site which are in
most cases instrumental in acting as feeders into foundation stages within the First /
Primary Schools.
1.2.10. A number of the First and Primary Schools have entered into Federation arrangements in
order to establish joint working relationships.
1.2.11. 8 of the 9 First / Primary Schools and the Upper School (Wadham) are designated as
Voluntary Controlled Schools. These school sites are typically owned by the Diocese of
Bath and Wells and therefore the Diocese holds significant influence over the future of the
schools and their sites.
1.2.12. 1 of the 2 Middle Schools (Maiden Beech) has become an Academy and therefore is no
longer a maintained school.
1.2.13. Only two schools (Swanmead and Merriott First) remain as maintained community schools
at the date of this report.
1.2.14. The above split in control of the Ilminster and Crewkerne Schools presents the Local
Authority with a significant challenge. Any implementation of structural change within the
Ilminster and Crewkerne are will require numerous stakeholders to work together to
achieve an area wide structural change.
1.3. FfS Assumptions
1.3.1. The following assumptions have been applied throughout the review in order to ensure a
consistent approach, clear boundaries and scope:
1.3.2. The core purpose of this review is to remain focused on the structure of education within
the Crewkerne and Ilminster area. Whilst Academy and MAT developments may occur
during or subsequently to the review they should not unduly influence the process or
1 Baseline information on Middle School numbers taken from https://en.wikipedia.org/wiki/Middle_school
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 20 of 137
outcomes. At this stage the review needs to lead developments in the Crewkerne and
Ilminster area to establish firm foundations for future developments.
1.3.3. It is noted that the geography within this rural area of Somerset is a significant factor
impacting on access to education and parental choice. It has been assumed that the
review needs to be cognisant of the impact that structural changes could have on travel
distances to school sites.
1.3.4. The review has been designed to test the structure of education within the area over the
next 13-year period based on housing projection data to 2032 as provided by SCC, thus
taking account of growth projections provided by the Local Authority.
1.3.5. For purposes of this review it has been assumed that the current revenue funding model
for schools remains broadly as the 2018-19 funding arrangements (i.e. no significant
change to National Funding Formula or current grant arrangements).
1.3.6. For purposes of this review it has been assumed that the current curriculum requirements
for schools remains as the 2018-19 curriculum requirements.
1.3.7. The Local Authority have advised that analysis is to assume that the Sixth Form (Years 12
& 13) at Wadham School is no longer viable.
1.3.8. Local Authority growth projections show significant growth to both the Yeovil and Chard
secondary phase over the next 5 years taking these schools to capacity. It is therefore
assumed that migration of pupils from Crewkerne and Ilminster into these neighbouring
schools will be reduced in the short-medium term due to capacity constraints.
1.3.9. The review is required to seek the optimal use of the existing school estate for the projected
numbers whilst minimising cost implications and balancing other impacted factors (e.g.
education delivery and outcomes, revenue budget implications, transport etc).
1.3.10. It has been assumed that Greenfylde School will relocate to a new 15-classroom (3 Form-
Entry) site as part of wider development of Ilminster town, with scope for further expansion
to a 20-classroom (4 Form Entry) site. The Local Authority have provided feasibility stage
information for this project which has been incorporated into analysis of the school estate.
1.3.11. It has been assumed that the existing Greenfylde School site will be disposed of by the
Local Authority and is therefore outside of the scope of this review.
1.3.12. The review has based all analysis of school sites and buildings on the Government Building
Bulletins (those current in May 2019) in order to assess facility and area requirements,
surplus areas and shortfalls within the existing sites and scenarios tested. It should be
noted that the ESFA do not provide specific area guidelines for middle schools (years 5-
8). Area assumptions for these facilities have been based on best practice utilising primary
and secondary models applied proportionately to the year group splits.
1.3.13. The review was based on use of the current ESFA Schedule of Areas tool available at the
point of the review taking place (May 2019).
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 21 of 137
1.3.14. The review has focused on trying to implement / maximise best practice from current
Building Bulletin standards using optimal class sizes and dedicated separate year group
structures.
1.3.15. It is noted that a number of schools have well established Early years, Pre-schools or
Nursery facilities on site. The review has wherever practical assumed that these facilities
are retained to serve the respective schools.
1.3.16. All schools have been treated as separate organisations unless already in a formal
relationship with another school – e.g. through federation or where Academy transfers
have already completed.
1.3.17. The Local Authority has provided condition survey information for each of the school sites.
This information has been used to inform the development of options, enabling current
condition issues to be considered across the school estate.
1.3.18. All Architect design work is indicative only at this stage and subject to further feasibility
work.
1.3.19. Assumed that rented and leased land is not in scope, only core school sites under
consideration.
1.3.20. The review does not aim to address inherent issues with school sites or buildings unless
there is a proposed change to the function of the site / buildings or expansion of the site
due to growth where it would need to be recognised.
1.4. Overarching Objectives
1.4.1. This strategic review focuses on the following overarching objectives:
1.4.2. The strategic review of education estates within the Crewkerne and Ilminster locality
against Building Bulletin guidance for current and projected numbers running through to
2032;
1.4.3. The strategic review of education delivery models / options for Crewkerne and Ilminster
schools and phases of education;
1.4.4. The assessment of options against evaluation criteria, covering Operational, Physical and
Financial criteria to establish viable and preferred alternative education structures.
1.5. Opportunities
1.5.1. The following opportunities have been established for this project:
1.5.2. The opportunity to ensure the implementation of a financially viable and sustainable
education structure capable of responding to growth and need over the next decade.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 22 of 137
1.5.3. The opportunity to enable a strategic and pro-active response to demographic and housing
growth within the area rather than reliance on reactive and ad-hoc responses.
1.5.4. The opportunity to ensure an efficient and effective area wide school estate.
1.5.5. The opportunity to ensure appropriate breadth of curriculum offer through education
phases, with appropriate staffing and resource to maintain and improve standards.
1.5.6. There may be an opportunity for some rationalisation of the education estate across the
area in order to reduce financial overhead, whilst maintaining suitable and sufficient
education provision within the area.
1.5.7. There may be an opportunity for the disposal of whole or parts of sites within the area
where facilities or land is identified as surplus to requirements, enabling capital receipts to
be used as funding for any wider adjustment of education facilities or expansion.
1.6. Constraints
1.6.1. The following constraints have been identified for this project:
1.6.2. The Local Authority have limited control over the school estate and therefore are restricted
in their ability to implement recommendations from this review without key stakeholders
with interests in the area coming on board (e.g. office of the Regional School
Commissioner, Diocese of Bath & Wells, Academies and potential Multi-Academy Trusts).
1.6.3. The Academy and Multi-Academy Trust (MAT) landscape within the Crewkerne & Ilminster
area was been slow to develop with only one school having converted to Academy status.
For a number of reasons there is now a higher level of activity developing with potential
Academy transfers and the establishment of a MAT hub (see section 2). This activity has
potential to act as a significant constraint on the Local Authority’s ability to pursue
recommendations or preferred options from this report.
1.6.4. The school estate within the Crewkerne and Ilminster area is one of multiple ownership.
The ability to develop or dispose of assets in part or whole is therefore more constrained
than other areas of Somerset.
1.6.5. Pupil numbers within the area are projected to grow with a requirement for expansion of
school places, however this growth is happening over a significant period of time (10+
years). With demand not expected to fill existing capacity under the current structure for
some time, or never in the case of upper school places this leave significant periods of
time with lower pupil numbers. These projections impact on the ability to consider swifter
changes over a shorter timescale and have potential to result in significant surplus floor
area across the estate over the short-medium term with related financial implications.
1.6.6. A number of the schools within the area have sites that are constrained or protected by
Conservation Area status and / or listed buildings on or adjacent to the sites.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 23 of 137
1.6.7. A number of the schools within the area are severely constrained by building and site
areas, resulting in compromised accommodation and facilities.
1.6.8. The majority of smaller schools within the scope of this review are classed as ‘Rural
Schools’ within the 2018 DfE List of Designate Rural Primary Schools. This is the latest
list of local authority-maintained primary schools in England that the Secretary of State has
designated as rural under the Designation of Rural Primary Schools (England) Order 2018.
Section 15 of the Education and Inspections Act 2006 requires that when either a local
authority or governing body of certain schools formulates proposals for the discontinuance
of a designated rural primary school it has regard to specific factors. These factors include
the likely effect of discontinuance on the local community and any alternatives to the
discontinuance of the school. Before publishing proposals for discontinuance, the local
authority or governing body must consult certain persons, including parents and, where
the local authority is a county council, any district and parish councils.
2. Academy & MAT Landscape
2.1. Summary of Evolving Academy & MAT Landscape
2.1.1. The Crewkerne and Ilminster area schools have to date only seen one Academy
conversion (Maiden Beech Academy), with all other sites remaining as Local Authority
Maintained schools. The majority of the school sites are Voluntary Controlled schools
linked to the Diocese of Bath & Wells.
2.1.2. The 2016 area review (instigated by the local Headteachers) recommended closer working
relationships between schools and a move to federation / Multi-Academy Trust
arrangement(s). Some progress has been made but no tangible proposal for structural
change have been forthcoming. An initial approach to the Regional Schools
Commissioner’s Office to form a Multi-Academy Trust (MAT) in the area did not progress
after the schools were informed that they would not be able to form a new MAT but would
have to join an existing one.
2.1.3. During 2019 the Local Authority has been made aware of a proposal for the Bridgwater
College Trust (BCT) to establish a Multi-Academy Trust MAT Hub model within the South
Somerset area. It is understood that BCT are currently in well-developed discussions with
both Maiden Beech Academy (regarding transfer) and Swanmead Middle School
(regarding conversion), with the intention of both schools joining the proposed BCT MAT
Hub.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 24 of 137
2.1.4. The Bridgwater College MAT was established in 2012 and have developed to be a very
successful Multi-Academy Trust of 5 schools within the Bridgwater, Sedgemoor and West
Somerset areas of Somerset.
2.1.5. It is understood that BCT have also held some initial discussions with Wadham School
about the potential of joining the BCTMAT Hub, but these discussions have not been
progressed further due to a number of complicated factors that potentially act as barriers
to such a transfer. It is also worth noting that:
▪ Wadham School is Voluntary Controlled and would potentially require 50% diocese
representation on the Trust board. BCT is not a Church MAT and therefore would
be unwilling to agree to such representation.
▪ Wadham school is currently operating with a significant budget deficit and it is
therefore unlikely that BCT would want to accept this liability without clear line of
recourse or remedial action to resolve the problem.
2.1.6. The Regional Schools Commissioner (RSC) have been asked to consider supporting
approval for the transfer and conversion of Maiden Beech Academy and Swanmead
Middle School respectively at the June 2019 Head Teachers Board.
2.1.7. It is understood that BCT may seek a change to the age range of the two middle schools
in order to enable education of Years 5-11 (where the middle schools currently operate
and deliver education to Years 5-8 only).
2.2. Potential Benefits of Evolving Academy & MAT Landscape
2.2.1. The establishment of a hub by a successful MAT in the South Somerset area has the
potential to offer significant benefits to the group of schools that it serves. Such an
arrangement would enable core functions within the group of schools to be centralised in
order to gain increased efficiency and deliver more effective and streamlined systems.
However, it should also be noted that this change alone would not be seen as sufficient to
resolve the scale of challenges faced within the Crewkerne and Ilminster area. If not
carefully managed the introduction of a successful MAT for a small proportion of the
schools in this area could have a detrimental impact on the stability of the wider structure
through an increased migration of students (due to surplus places), resulting in a
decreasing cycle of reduced pupil numbers, worsening of financial challenges and
consequently potential reduction in outcomes and standards.
2.2.2. A MAT has the potential to enable an increased breadth of curriculum offer, improved
continuity of resources and career progression across its schools, something that
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 25 of 137
individual schools, standalone academies and small federations cannot offer to the same
degree.
2.3. Potential Challenges of Evolving Academy & MAT Landscape
2.3.1. Any MAT entering the Crewkerne and Ilminster area at this current date will be operating
within an Education Structure and Funding Arrangement that is not viable or sustainable
into the future. This has the potential of resulting in a number of risks:
▪ The introduction of a MAT to a small proportion of schools in the area will potentially
make structural change harder to achieve if the basis of the change is not pre-agreed
with the MAT, or implemented prior to the MAT moving into the area.
▪ Academisation of maintained schools in this area will make any structural change
more complicated with an increased number of stakeholder and competing
aspirations potentially increasing the chance of the current challenges remaining
unresolved into the future.
▪ A reduced chance of achieving an area wide change that can respond to future
needs Crewkerne and Ilminster communities and projected growth.
2.3.2. If not managed with great care the introduction of a MAT could result in short-medium term
stabilisation of some schools, but significant worsening of others in the area due to student
migration and potential of age range changes.
2.3.3. Without carefully considered adjustment to the education structure in the short-medium
term, the ability to accommodation longer term (5 years plus) growth and expansion of
places within the area could provide difficult to achieve in a viable way.
3. Site & Buildings
3.1. First Schools in Scope
3.1.1. Greenfylde Church of England First School, Ilminster
(Note: SCC have provided a feasibility study which shows the proposed move of Greenfylde C of E
First School to a new site. For the purposes of this review, the details of the existing site are listed
below for information, but the modelling within the options appraisal has been based on the new
site as detailed within the feasibility study).
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 26 of 137
Type of Establishment Voluntary Controlled
Establishment Type Group LA Maintained
Diocese Bath and Wells
Federation N/A
Pre-School Provision Governor-led Pre-School
Pre-School Age Range 2-4
Pre-School NOR 60 (March 2019)
Land ownership Ilminster Educational Trust
School Age Range 4-9
NOR 341 (March 2019)
Ofsted Outstanding (March 2009)
Eligible FSM % 9.9% (April 2019)2
Number of Year Groups 5 (excluding Pre-School)
Number of Classrooms 16 Classrooms:
• 1 Pre-School Classroom
• 3 Reception Classrooms
• 6 Shared Yr1/2 Classrooms
• 4 Shared Yr3/4 Classrooms
• 2 Yr4 Classrooms
Recipient Schools Generally Swanmead
Catchment Area See Appendix 10 for details
Description of Site Centrally located Ilminster school surrounded by shops and housing.
The site comprises three permanent blocks supported by a number of temporary units, located around a central play area. No on-site playing fields, but the school has a swimming pool and has use of the local recreational ground
Block TF houses the Pre-School which is integral to the site.
Note – it is anticipated that the school will be moving to a new site, as per the SCC proposed Feasibility Study.
Third Party / Community Use Block D – used at weekends by Methodist Church
School Kitchen Small kitchen used for receiving and serving meals.
No production kitchen
Site Development Proposed move to new site as per SCC Feasibility Study.
No information available on proposals for existing site, but noted that the site is in the ownership of the Ilminster Education Trust
Site Constraints No dedicated parking on existing site, no on-site playing field
2 FSM Data taken from ‘get-information-schools.service.gov.uk’
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 27 of 137
Condition Required condition improvement works include refurbishment of heating, cooling and water systems, plus works to refurbish WCs and repair external wall
3.1.2. Hinton St George Church of England First School, Hinton St George
Type of Establishment Voluntary Controlled
Establishment Type Group LA Maintained
Diocese Bath and Wells
Federation N/A
Pre-School Provision Pre-School (run independently from school but located within school grounds)
Pre-School Age Range 2-4
Pre-School NOR 23 (March 2019)
Land ownership Diocese / Trustees
Somerset County Council (Playing Field)
School Age Range 4-9
NOR 54 (March 2019)
Ofsted Good (May 2018)
Eligible FSM % 7.7% (September 2018)2
Number of Year Groups 5
Number of Classrooms 3 Classrooms:
• 1 Pre-School
• 1 Shared YrR/1 Classroom
• 1 Shared Yr2/3/4 Classroom
Recipient Schools Generally Maiden Beech
Catchment Area See Appendix 10 for details
Description of Site Victorian village school located between Crewkerne and Ilminster, comprising one main block. School is surrounded by village housing, with a detached playing field a five-minute walk away and no dedicated parking. The school also have use of the church as required, and the village hall (for PE)
Third Party / Community Use First Floor Block A hired out to independent Pre-School
School Kitchen No production kitchen, very limited space for preparing serving school meals
Site Development N/A
Site Constraints Extremely constrained site, limited options for development.
Condition Required condition improvement works include refurbishment of playground surfaces, electrical wiring and lighting and repair of external walls
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 28 of 137
3.1.3. St Bartholomew’s Church of England First School, Kithill, Crewkerne
Type of Establishment Voluntary Controlled
Establishment Type Group LA Maintained
Diocese Bath & Wells
Federation N/A
Pre-School Provision N/A
Land ownership Somerset County Council
School Age Range 4-9
NOR 181 (March 2019)
Ofsted Good (November 2017)
Eligible FSM % 11.9% (May 2019)2
Number of Year Groups 5
Number of Classrooms 7 Classrooms:
• 2 Reception
• 2 Shared Yr1/2
• 1 Shared Yr 2/3
• 2 Shared Yr3/4
Recipient Schools Generally Maiden Beech
Catchment Area See Appendix 10 for details
Description of Site Site comprises one main masonry block (purpose built in 1994) with one temporary unit with ample hard play area and a generous sloped playing field area.
The school is located to the eastern side of Crewkerne, is surrounded by housing and has dedicated parking.
A public footpath crosses inside the school boundary adjacent to the playing field area.
Third Party / Community Use N/A
School Kitchen Small kitchen used for receiving and serving meals.
No production kitchen
Site Development Potential opportunities to develop the site are currently being considered – including possible extension of the main block
Site Constraints Extremely narrow site bordered by retaining walls and steeply sloping ground.
Condition Required condition improvement works include electrical fixed wiring.
3.1.4. Merriott First School, Merriott
Type of Establishment Community
Establishment Type Group LA Maintained
Diocese N/A
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 29 of 137
Federation Merriott and Haselbury Plucknett Schools Federation
Pre-School Provision Voluntary Charity-run Pre-School (run independently from school but located within school grounds)
Pre-School Age Range 2-4
Pre-School NOR 48 (April 2015)
Land ownership Somerset County Council
School Age Range 4-9
NOR 116 (March 2019)
Ofsted Good (March 2016)
Eligible FSM % 8.9% (April 2019)2
Number of Year Groups 5
Number of Classrooms 5 Classrooms:
• Dedicated classroom for each year group (but note that Yr 4 Classroom is not suitably sized for larger pupil numbers)
Recipient Schools Generally Maiden Beech
Catchment Area See Appendix 10 for details
Description of Site Village school (including Grade 2 listed elements) sited in a rural location approximately 3 miles north of Crewkerne, within a Conservation Area.
The site comprises the main Victorian block (previously extended) with the addition of two temporary units and a log cabin.
The school has a generous provision of grass and hard play areas to the rear of the site.
Merriott Pre-School (run independently to the school) is situated within the school grounds but is accessed separately.
Third Party / Community Use No formal third-party use
School Kitchen No school meal production
Site Development Possibility of developing grass area adjacent to Block TD
Site Constraints • Located within Conservation Area
• Grade 2 listed elements
• No dedicated parking available (but local agreement in place with Church for use of car park)
Condition Required condition improvement works include refurbishment of external hard play area, external decorations, replacement of rainwater goods, doors and windows
3.1.5. Haselbury Plucknett First School, Haselbury Plucknett, Crewkerne
Type of Establishment Voluntary Controlled
Establishment Type Group LA Maintained
Diocese Bath and Wells
Federation Merriott and Haselbury Plucknett Schools Federation
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 30 of 137
Pre-School Provision Governor-led Pre-School
Pre-School Age Range 2-4
Pre-School NOR 21 (March 2019)
Land ownership Part Trustees / Somerset County Council
School field leased from private owner
School Age Range 4-9
NOR 50 (March 2019)
Ofsted Good (July 2018)
Eligible FSM % 8.7% (April 2019)2
Number of Year Groups 5
Number of Classrooms 4 Classrooms:
• 1 Pre-School
• 2 Shared YrR/1 and occasionally Yr2
• 1 Shared Yr3/4 and Yr2 (mornings)
Recipient Schools Generally Maiden Beech
Catchment Area See Appendix 10 for details
Description of Site Village school sited in a rural location approximately 3 miles north-east of Crewkerne and located within a Conservation Area. Victorian school building with temporary unit accommodating Nursery / Pre-School and dining area, with access to leased field at the rear of the site.
Third Party / Community Use No formal third-party use
School Kitchen Small kitchen used for receiving and serving meals.
No production kitchen
Site Development Possibility of developing site in area of Block TA.
Site Constraints • Leased Playing Field, narrow / constrained site
• Conservation Area.
• No dedicated parking available
Condition No major condition issues noted
3.1.6. Ashlands Church of England First School, Crewkerne
Type of Establishment Voluntary Controlled
Establishment Type Group LA Maintained
Diocese Bath and Wells
Federation Ashlands and Misterton Schools Federation
Pre-School Provision N/A
Land ownership Somerset County Council
School Age Range 4-9
NOR 130 (March 2019)
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 31 of 137
Ofsted Good (March 2017)
Eligible FSM % 19.2% (December 2018)2
Number of Year Groups 5
Number of Classrooms 5 Classrooms
• Dedicated classroom for each year group
Recipient Schools Generally Maiden Beech
Catchment Area See Appendix 10 for details
Description of Site The school is located not far from the centre of Crewkerne on a busy through-road (A356).
A Victorian school (with Grade 2 listed elements) split over two levels which is sited on a constrained, steeply sloping site and located within a Conservation Area.
MUGA facility and large forest school area (available to other schools and organisations) are located on the lower level / to the rear of the site.
Third Party / Community Use School hall hired out once per week for community use
School Kitchen Small kitchen used for receiving and serving meals (meals received from Wadham).
No production kitchen
Site Development The school have recently acquired the Children’s Centre. The school is currently undergoing development of a number of areas in agreement with adjacent housing development.
Site Constraints • Conservation Area
• Possible listed built elements (fireplace)
• Steeply sloping site
• Possible issues ground water levels in some areas of the site
Condition Majority of built elements are condition C/D, requiring refurbishment works to Heating, decorations, roofing, fencing, doors, windows and ceilings / floors
3.1.7. Misterton Church of England First School, Crewkerne
Type of Establishment Voluntary Controlled
Establishment Type Group LA Maintained
Diocese Bath and Wells
Federation Ashlands and Misterton Schools Federation
Pre-School Provision N/A
Land ownership Trustees / Diocese
Private Landowner (field)
School Age Range 4-9
NOR 46 (March 2019)
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 32 of 137
Ofsted Good (March 2016)
Eligible FSM % 4.3% (February 2019)2
Number of Year Groups 5
Number of Classrooms 2 Classrooms:
• 1 Shared YrR/1
• 1 Shared Yr2/3/4
Recipient Schools Generally Maiden Beech
Catchment Area See Appendix 10 for details
Description of Site Located on a busy through road (the A356) approximately 2 miles south-east of Crewkerne, in a rural village location. The school comprises a single Victorian school building on a constrained site, with play areas to the rear including access to a privately-owned, leased field.
Third Party / Community Use N/A
School Kitchen Small kitchen used for receiving and serving meals (meals received from Wadham).
No production kitchen
Site Development N/A – but possibility of sharing accommodation across the federation (Ashlands School)
Site Constraints Leased playing field
Constrained site
No parking, adjacent to a busy through road
Condition Majority of built elements are condition C/D requiring refurbishment to electrical / heating systems, playground surfaces, roofing, windows and doors
3.2. Primary Schools in Scope
3.2.1. Shepton Beauchamp Primary School, Shepton Beauchamp, Ilminster
Type of Establishment Voluntary Controlled
Establishment Type Group LA Maintained
Diocese Bath and Wells
Federation The Three Saints Federation
Pre-School Provision N/A
Land ownership • Trustees / Diocese
• Shepton Beauchamp Parish Council (War memorial site)
• Lethbridge Memorial Recreational Field Committee (field)
School Age Range 4-11
NOR 40 (March 2019)
Ofsted Good (January 2018)
Eligible FSM % 11.1%2
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 33 of 137
Number of Year Groups 7
Number of Classrooms 3 Classrooms:
• 1 Reception
• 1 Shared Yr 1/2
• 1 Shared Yr 3/4/5/6
Recipient Schools Generally Swanmead
Catchment Area See Appendix 10 for details
Description of Site Village school located to the North East of Ilminster, comprising one main block with adjacent hard play area and informal grass area (unsuitable for formal use due to uneven ground). The school use the off-site Rectory Garden for recreational activities and have use of the church, village hall and recreational field on a regular basis. There is no dedicated parking.
Third Party / Community Use N/A
School Kitchen No school meal production
Site Development N/A
Site Constraints • No dedicated parking on existing site
• No on-site school playing field
• Victorian building on constrained site
Condition Required condition improvement works include footpath surface, roof lights and external window glazing.
3.2.2. St Mary & St Peter’s Church of England VC Primary School, Ilton, Ilminster
Type of Establishment Voluntary Controlled
Establishment Type Group LA Maintained
Diocese Bath and Wells
Federation The Three Saints Federation
Pre-School Provision Pre-School (run independently from school but located within school grounds)
Pre-School Age Range 2-4
Pre-School NOR 11 (March 2019)
Land ownership Somerset County Council
School Age Range 4-11
NOR 34 (March 2019)
Ofsted Special Measures (January 2019)
Eligible FSM % 17.1%2
Number of Year Groups 7
Number of Classrooms 3 Classrooms:
• 1 Pre-School
• 1 Shared Reception, Yr 1/2
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 34 of 137
• 1 Shared Yr 3/4/5/6
Recipient Schools Generally Swanmead
Catchment Area See Appendix 10 for details
Description of Site Village school located to the North of Ilminster, comprising two temporary blocks and an attached playing field. The school site is situated on the edge of Ilton village in a rural area. There is no dedicated parking. The school also have use of the church and the village hall on a regular basis.
Third Party / Community Use N/A
School Kitchen No school meal production
Site Development N/A
Site Constraints • No dedicated parking on existing site
• Constrained site comprising numerous temporary unit
Condition Required condition improvement works include footpath surface, roof lights and external window glazing.
3.3. Middle Schools in Scope
3.3.1. Maiden Beech Academy, Crewkerne
Type of Establishment Academy Converter
Establishment Type Group Academy
Diocese N/A
Federation N/A
Pre-School Provision N/A
Land ownership Somerset County Council
School Age Range 9-13
NOR 391 (March 2019)
Ofsted Good (June 2018)
Eligible FSM % 7.8%2
Number of Year Groups 4
Number of Classrooms Approximately 20 classrooms used by all year groups.
Feeder / Recipient Schools Feeder Schools:
• Generally Crewkerne First Schools including Ashlands, St Bartholomew’s, Misterton, Haselbury Plucknett, Merriott, Hinton St George
Current Recipient School:
• Wadham
Catchment Area See Appendix 10 for details
Crewkerne-centric, bordering Swanmead catchment area to the west, with no other adjacent Middle School Catchment areas.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 35 of 137
Description of Site Site comprises five masonry blocks and five temporary units with generous playing field on a large site.
The school is located to the southern side of Crewkerne, is surrounded by housing and has limited dedicated parking.
Third Party / Community Use Extended school use as required
School Kitchen Production kitchen supplies meals to other schools
Site Development No known site development plans.
Site Constraints Site suitable for redevelopment if required.
Condition Required condition improvement works include:
• Mechanical Heat Source (Block A and D)
• Electrical Automatic Control System (Block A)
3.3.2. Swanmead Community School, Ilminster
Type of Establishment Community School
Establishment Type Group LA Maintained
Diocese N/A
Federation N/A
Pre-School Provision Pre-School (run independently from school but located within school grounds)
Pre-School Age Range 2-4
Pre-School NOR 44 (June 2017)
Land ownership Somerset County Council
School Age Range 9-13
NOR 270 (March 2019)
Ofsted Good (February 2018)
Eligible FSM % 10.9%2
Number of Year Groups 5
Number of Classrooms Pre-School (Block TF)
Approximately 12 classrooms used by all year groups.
Feeder / Recipient Schools Feeder Schools:
• Generally Ilminster First Schools including Greenfylde, Shepton Beauchamp, St Mary & St Peter’s
Current Recipient School: Wadham
Catchment Area See Appendix 10 for details
Ilminster is located to the mid-west of the catchment area and borders Maiden Beech catchment area to the east, with no other adjacent Middle School Catchment areas.
Description of Site Site situated on the edge of Ilminster opposite a residential area. The site comprises one main permanent block, one temporary building, MUGA, hard pitch and a large level playing field.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 36 of 137
Third Party / Community Use
Hall, Gym and MUGA used by Community on regular basis
School Kitchen School production kitchen
Site Development Possibility that Swanmead may purchase the adjacent Ilminster Skills and Learning Centre
Site Constraints Site suitable for redevelopment if required.
Condition Required condition improvement works include roofing, windows, external decorations, water systems, electrical elements, boilers and WC refurbishment
3.4. Upper Schools in Scope
3.4.1. Wadham School, Crewkerne
Type of Establishment Voluntary Controlled
Establishment Type Group LA Maintained School
Diocese Diocese of Bath and Wells
Federation N/A
Pre-School Provision N/A
Land ownership The Crewkerne Education Foundation
Age Range Currently 13-18 years
(Noted that due to the non-viability of the 6th Form it is proposed that Years 12 & 13 will be closed)
NOR 467 (March 2018)
Ofsted Good (May 2018)
Eligible FSM % 8.7%2
Number of Year Groups 19 Tutor Groups across 3 year groups (excluding sixth form)
Number of Classrooms Approximately 30
Feeder Feeder Schools – Maiden Beech, Swanmead
Catchment Area See Appendix 10 for details
Possible impact on neighbouring secondary schools (e.g. Stanchester, Beaminster, Preston, Holyrood etc) if catchment area altered
Description of Site • Purpose-built secondary on a generous site footprint, located within a large housing development to the north east of Crewkerne.
• Substantially permanent 1970s construction (steel frame with external precast artificial stone envelope) designed around linked departmental blocks. In addition, the site accommodates one temporary unit, a caretaker’s bungalow plus the Community Leisure Centre and a derelict Cricket Pavilion (of historical interest)
• Two large playing field areas (one of which is currently out of use due to badger undermining) plus areas of sloping, wooded land that are unsuitable for sports use.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 37 of 137
A public footpath separates the larger playing field from the main site which generally includes a large number of mature trees and informal green spaces throughout.
Third Party / Community Use • Leisure Centre (Block J) - The school has recently taken-on the management of the Lottery-funded leisure centre on the site, with services to be developed for September 2019
• Sports Block (Block E) – used every evening for community sports
• Sports pitches - regular evening / weekend community use of football pitches
• Playing fields - current negotiations underway with the Town Council and Football Association re possible installation of 3G pitch to address shortfall of provision in the area
• Temporary Unit on field leased to Air Cadets
• Tennis Courts - Current negotiations underway with Town Council re provision of tennis courts for community use
School Kitchen Currently produces meals for Wadham, Ashlands and Misterton Schools
Site Development Possible requirement to improve road junction adjacent to school entrance if numbers significantly increase
Site constraints Site suitable for redevelopment if required, aside from sloping wooded areas of school field
Condition Required condition improvement works include window, door and boiler replacement. WCs require refurbishing throughout and a number of areas require improved thermal comfort / control.
External surfaces (including Redgra pitch) require refurbishment, alongside areas of structural improvement
3.5. Out of Scope Schools – Impact on Review
3.5.1. The neighbouring school systems in Chard, Yeovil across the County border into Dorset
remain outside of the scope of this review. It is noted that a number of pupils in catchment
for Crewkerne and Ilminster schools opt to attend schools in these areas and that due to
parental choice and capacity in the system this situation will continue. However, within the
Chard and Yeovil Schools (where Somerset County Council is the Local Authority) the
spare capacity in the system is fast being eroded by growth. SCC projections currently
predict that these schools will be operating at capacity by c. 2022 and therefore migration
from Crewkerne and Ilminster will be minimised.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 38 of 137
4. Review Team
4.1. Futures for Somerset Ltd (the Somerset Local Education Partnership) –
Strategic Review and Project Management
4.1.1. The Futures for Somerset team is comprised of a number of experienced Project and
Programme Managers who have a wealth of experience of working with schools,
academies, MATs and FE colleges on both capital and revenue projects – ranging from
the creation of new multi-million-pound secondary schools (as part of the Building Schools
for the Future Programme), to procuring and managing school improvement fund works.
The team has delivered projects in close collaboration with the Local Authority, the
Department for Education and the Education and Skills Funding Agency and works
regularly on behalf of education establishments and Multi Academy Trusts to provide
strategic advice, property consultancy, capacity reviews and site master planning services.
4.1.2. Alongside strategic-level work, Futures have experience of procuring and managing a
range of education / community service contracts including IT, Facilities Management, and
Community Leisure services – giving the team a broad insight and understanding of
operational and financial requirements in both education and community environments.
4.1.3. The team recognises the value of effective stakeholder engagement and strong
partnership working, and has utilised this to good effect across private, public and
community sectors in order to effectively deliver projects on time and to budget.
4.1.4. The team applies Prince 2 and Managing Successful Programmes (MSP) methodologies
in order to effectively manage a broad range of projects and programmes across the
education and community sector.
4.2. Grainge Architects Ltd – Capacity Review and Masterplanning
4.2.1. Grainge Architects have built up a strong reputation as being one of the leading
Architectural practices in the South West, with particular expertise in the education sector.
Grainge have successfully delivered projects across the entire range of educational
buildings, from Early Years accommodation, primary and secondary school new builds and
expansions, through to specialist, FE and university facilities. Futures and Grainge have
worked collaboratively to successfully deliver a number of projects in Somerset, involving
feasibility studies, capacity reviews, site masterplanning and Architectural design services.
4.2.2. The Grainge team comprises architects, designers and technicians who are highly
experienced at calculating education accommodation requirements in accordance with the
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 39 of 137
ESFA Building Bulletin documents, whilst applying a sensitivity and understanding of client
needs in order to deliver creative design solutions
4.3. Randall Simmonds – Cost Advisors
4.3.1. Randall Simmonds are a professional construction consultancy providing construction
development and cost advice services to Local Authorities, Housing Associations and
private developers across multiple industry sectors (including education). They provide
advice on projects and programmes ranging from high level strategic planning
programmes through to individual construction projects; providing cost plans,
benchmarking and assessment tools alongside procurement and delivery advice.
4.3.2. Randall Simmonds have worked with Futures on a number of education projects in
Somerset in a cost consultancy role. They understand the specific needs, standards and
legislation / regulation involved in constructing educational buildings and are familiar with
local market conditions in terms of construction materials and labour costs. Their multi-
skilled team of Quantity Surveyors, Project Managers, CDM Advisors and construction
professionals are experienced in providing early, informed views on feasibility and
affordability.
4.4. Susan Fielden (Effervesce Ltd) – Specialist School Finance Advisor
4.4.1. Susan has developed a wealth of experience in the school funding sector, working across
a range of strategic-level roles for Somerset County Council (SCC) and the Department
for Education since 1991. Previous SCC roles include the Strategic Project Manager for
School Funding and Services, and the Executive Officer for the Children and Young
People’s Compact (a strategic joint commissioning partnership between schools,
academies, early years providers and SCC). More recently, Susan has worked as the DfE
School Funding Policy Lead and is now Director of Effervesce Ltd – a specialist
consultancy working with school and education leaders to connect vision with strategic
financial planning.
4.4.2. Susan has been appointed to carry out the financial review of the options appraisal due to
her in-depth knowledge and understanding of the school finance sector, combined with her
drive to secure outstanding and sustainable provision for children and young people.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 40 of 137
4.5. Jill Ewen – Education Consultant - Education Impact Review
4.5.1. Jill has thirty-two years of education experience with over twenty-two years in schools
(including roles ranging from maths teacher - to over ten years in senior leadership roles
as Deputy, Vice-Principal and Acting Principal,) and ten years as the SCC School
Improvement Advisor. This role incorporated various responsibilities including maths
adviser, lead adviser for Special Schools, responsibility for the NQT Appropriate Body
service, managing Governor Services and Headteacher recruitment.
4.5.2. Jill now works as an independent consultant providing support for leaders in schools,
including Headteacher recruitment, school reviews, improvement planning,
coaching/mentoring and Ofsted preparation, and is also a Somerset Education Partner
(SEP) for SCC.
4.5.3. Jill has been appointed to carry out the ‘Education Impact Review’ of the options appraisal
due to her breadth of knowledge and experience, particularly in relation to Somerset
schools.
5. Methodology
5.1. Area Wide Capacity Review
5.1.1. Within the brief for this work package, Grainge Architects have completed a detailed
capacity review to assess the current and future accommodation needs at each of the 9
First / Primary Schools, 2 Middle Schools and 1 Upper School against the current Building
Bulletin 103 Recommended Minimum Areas for Basic Teaching, Large Spaces (Hall,
Dining, PE), Learning Resources, Staff & Admin, Storage, Non-Net and Supplementary &
Community, to identify any shortfalls in areas based on current pupil numbers and future
potential requirements. This exercise was based on the following methodology;
5.1.1.1. Review of the existing accommodation (“baseline”) to identify current layout and
usage of building (to ensure accuracy of information, Futures for Somerset
engaged with the schools, as required, to verify current room usage and the ESFA
space reference type i.e. Basic Teaching, Large Space etc), including (where
appropriate)
▪ Identification of any life-expired building stock and removal of this
accommodation from the assessment.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 41 of 137
5.1.1.2. Production of formalised coloured plans for each site to reflect the BB103 criteria.
5.1.1.3. Development of BB103 area schedule for potential future requirements and
comparison back to baseline schedule to identify accommodation surpluses and
/ or shortfalls.
5.1.1.4. Development of Functional SoA covering accommodation required for potential
future requirements.
5.2. Review of Basic Need & Growth Projection Data
5.2.1. Somerset County Council current population numbers and forecasts and recently updated
Pupil Product Ratios (the number of pupils that new housing developments will yield) have
been utilised in conjunction with housing data to assess future potential growth
requirements for the area. The projected numbers are the same under all tested Options.
The projected additional housing demand is based on submitted and approved new
housing developments identified within the education locality in accordance with instructed
SCC data and methodologies.
5.3. Masterplanning Scenarios
5.3.1. Grainge Architects have completed an initial master plan review of each school site. This
exercise looked at the potential areas within each school site for possible expansion /
development based on current shortfalls and future potential requirements (depending on
the preferred / viable options) as well as identifying any current site constraints. The
potential expansion / development has been shown as sqm blocks based on the findings
of the shortfall analysis with no internal details at this stage.
5.4. Report Stage Consultation
5.4.1. Futures for Somerset attended a series of meetings with Somerset County Council in the
initial stages of our appointment in order to understand the full scope / brief of the proposed
review. Further update progress meetings have been held with the County Council
throughout the development of the report.
5.4.2. Two consultation / update events, attended by both Somerset County Council and Futures
for Somerset, were held on 12th March 2019 and 3rd April 2019 with the Headteachers
and Chairs of Governors of the 12 identified schools. The events were an opportunity to
report on the progress of the review and to seek comments on the proposed contents /
details.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 42 of 137
5.4.3. Somerset County Council have separately engaged with the Regional Schools
Commissioner in order to promote the importance of the review and its timing in relation to
ongoing Multi-Academy Trust developments within the area. The Local Authority and
Regional Schools Commissioner have responded to acknowledge the importance of the
review and to confirm that the outcomes will be considered ahead of key decisions being
taken on Academy Transfers within the Crewkerne and Ilminster area.
5.5. Future Consultation
5.5.1. The review proposes a two-phase informal consultation prior to any formal consultation
that may be required as part of a statutory process for making a prescribed alteration
change (depending on the preferred / viable options). The suggested phasing and
timescale for the informal consultation has been developed with due regard to the DFE’s
“Consultation Principles Guidance 2018” and following research into recent reviews of
current and alternative education structures undertaken by other Local Authorities.
5.5.2. To ensure best practice, consultations should;
▪ Be clear and concise
▪ Have a purpose
▪ Be informative
▪ Last for a proportionate amount of time
▪ Be targeted
▪ Be agreed before publication; seek collective agreement before publishing a written
consultation.
▪ Take account of all relevant considerations
▪ Consult about proposals / plans when the development of those proposals / plans
are at a formative stage.
5.5.3. The proposed overall timescale for the informal consultation allows a period of time for the
collective agreement of the scope of the proposed consultation, the preparation of the
consultation documents and the prior advertising of the consultation itself including any
proposed events and details of where to find / how to respond to the consultation
document.
5.5.4. Phase 1 of the informal consultation allows for further engagement with the Headteachers
and Chairs of Governors of the 12 identified schools in advance of the wider consultation
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 43 of 137
proposed under Phase 2. It allows for a number of meetings to be arranged with the
schools, as required, and includes a period of time to review feedback and comments and
to incorporate any agreed changes into the Phase 2 consultation. It is suggested that the
Regional School Commissioner and the Diocese of Bath and Wells are invited to these
meetings.
5.5.5. Phase 2 is the wider consultation and will include the publication (hard copy and electronic)
of the consultation and response form documents. Suggested key consultees could
include, but are not limited to, governors, staff, parents and pupils of the 12 schools, the
Diocese of Bath and Wells, local Parish, County and District Councillors, Headteachers
and Chairs of Governors of schools in nearby / adjacent areas, Headteachers and Chairs
of Governors of schools in neighbouring local authorities, Directors of Education /
Children’s Services in neighbouring local authorities, Early Years care / education
providers, the local MP, staff union representatives, local community groups.
5.5.6. The proposed timescale for Phase 2 allows for a number of consultation events including
wider public engagement. It also allows for a period of time to collect, review and
incorporate relevant considerations from the various events and the completed response
forms into the final documentation for the formal (statutory) consultation required as part
of any prescribed alteration change. A period of eight weeks has been allowed for the
formal consultation period.
5.6. Option & Scenario Scope
5.6.1. Option 1 – Current Scenario (baseline Option)
5.6.1.1. This is the “do nothing” or minimum option. It serves as a baseline for the other
tested Options retaining the existing structure but incorporating required growth.
5.6.2. Option 2 – Adjusted Formula Funding
5.6.2.1. This option retains the current first, middle and upper three-tier structure but with
the potential for adjustments to the current formula funding arrangements.
5.6.3. Option 3 – Primary & Secondary
5.6.3.1. This is the first of two Options which look at a two-tier model of education (primary;
secondary) focusing on the potential for consolidated primary schools across the
review area. It is assumed under this Option that Secondary (11-16) places will
come from within the existing middle and upper schools.
5.6.4. Option 4 – Primary (split) & Secondary
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 44 of 137
5.6.4.1. Under this Option, split site Infant and Junior, and hybrid split site and
consolidated Options are considered. It is assumed, as per Option 3, that
Secondary places will come from within the existing middle and upper schools.
5.6.5. Option 5 – First Schools & Secondary (extended age range)
5.6.5.1. Option 5 specifically looks at Options to retain the existing First School structure
but amalgamates middle and upper years into one consolidated education
provision.
5.6.6. Sixth Form – Wadham School currently operates a Sixth Form (Years 12-13) alongside
the main Secondary provision (Years 9-11). The sixth form is currently operating with c.
40 students on role which sits significantly below the recognised minimum of 180-200
students across years 12 & 13 required to ensure a financially viable Sixth Form Centre.
The Local Authority have advised that their projections have demonstrated that the local
need is not sufficient for continuation of a Sixth Form offer and therefore, for purposes of
this review, it is to be assumed that the sixth form provision is to be wound-up. Students
would therefore seek to enter Further Education in Taunton, Chard, Yeovil or Huish
Episcopi. The floor area currently reserved for Sixth Form would therefore become
available as free space and can be factored into the review accordingly.
5.6.7. All-through (single site) – consideration has also been given the whether a greatly
simplified all-through (single site) provision could be provided within each of the Crewkerne
and Ilminster town areas - this has the potential to offer the most cost-effective delivery
model in terms of revenue budgets due to a scale of economy. Following initial
investigation this option was discounted on the basis that:
▪ no individual site is of a suitable size to offer such a large-scale development / co-
location of schools.
▪ The capital cost for such a development would prove cost prohibitive and
implementation would not be possible.
6. Evaluation
6.1. Option & Scenario Scope
6.1.1. Prior to starting the review process and development of options the structure, methodology
and evaluation process were carefully developed to ensure a fair evaluation process that
would not sway outcomes too greatly from any one factor, whilst still recognising that some
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 45 of 137
factors need to hold greater importance than others by the very nature and importance of
their role on day-to-day business. The table below summarises the evaluation categories
identified and the percentage weighting (relative importance) to be applied to these
categories during the evaluation of options.
6.1.2. It is recognised that a number of these categories overlap, but on closer inspection it is felt
that the overlaps cannot be avoided and that they actually prove useful in identifying where
a decision impacts on a number of functions of a school or set of schools. As a simplistic
example there is a very close link between the Revenue Budget, Staffing and Education –
where increased staffing is required this may potentially have a positive impact on
Education, but consequently is likely to have a more negative impact on the revenue
budget.
6.1.3. Evaluation of options will be completed by the appointed review team in order to establish
well considered analysis of each element of each option enabling an appropriate score to
be developed.
6.1.4. Option 1 (baseline) has been developed as the baseline option for reviewing alternatives
to the structure of education in the Crewkerne & Ilminster area. The option focuses on the
current structure of education and considers growth required to satisfy basis need running
through to 2032 based on Somerset County Council projections. This option serves as the
foundation against which other scenarios are reviewed and tested to ascertain whether
they could offer and improvement or worsen the existing situation in part of whole.
6.1.5. Within the scope of Option 2 to Option 5 set out within the Methodology Section of this
report (Section 5), a number of scenarios are developed and tested to establish their
Evaluation Category Weighting
1 Capital Cost 20%
2 Revenue Cost 25%
3 Education (Curriculum, SEN, Sport, Early Years)
25%
4 Staffing 15%
5 Transport 5%
6 Equalities 5%
7 Community 5%
Total 100%
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 46 of 137
viability and relative scoring to the baseline option. Under each option heading one or two
of the most viable scenarios are carried forward for evaluation against the Baseline Option
(Option 1). Scenarios are identified based on their viability and deliverability and as such
many alternatives have been discounted on the basis of not being deliverable within the
assumptions and constraints of the review scope (e.g. where sites are too small to
practically deliver a scenario, physically or in terms of viability of the resultant educational
model, the scenario is not carried forwards as it would not be viable / deliverable /
recommended as a structure).
6.1.6. The evaluation of options and related scenarios has been based upon a consistent review
principle that has aimed to establish degrees of positive or negative impact that each
scenario creates against the review criteria. The scoring system therefore seeks to
understand whether aspects of each scenario improve, worsen or remain the same when
compared to the Baseline Option (Option 1). This also enables the ranking of scenarios
relative to one another and the Baseline Option. The scoring system applied has been
outlined below:
Score Summary
-3 Significant negative impact compared to baseline proposal
-2 Considerable negative impact compared to baseline proposal
-1 Moderate negative impact compared to baseline proposal
0 No notable change when compared to baseline solution
1 Moderate positive impact compared to baseline proposal
2 Considerable positive impact compared to baseline proposal
3 Significant Positive impact compared to baseline proposal
6.2. Capital Cost Impact
6.2.1. The review will aim to assess the estimated capital cost of delivering options through the
development of high-level cost models based on the level of intervention required within
the school estate. Cost models will aim to establish levels of new build, remodelling and
refurbishment within options and will model costs against these categories of work
accordingly.
6.2.2. Cost modelling will be completed by Randall Simmonds based on estate options
developed by Grainge Architects. Modelling will use BCIS rates for work categories – all
costs are at baseline only with no inflation index applied as final works timeframes not
currently known. Inflation will therefore need to be applied to all project costs to establish
appropriate project budgets.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 47 of 137
6.2.3. In addition to the development of a capital cost model consideration will also be given to
the opportunity cost of disposing site elements (if deemed surplus to requirements in any
developed options). Any such capital receipts from the disposal of land or buildings would
be seen as beneficial in helping to balance capital costs.
6.3. Revenue Impact
6.3.1. The need to try and establish a viable and sustainable school structure in Crewkerne and
Ilminster has been instrumental to the establishment of this review. Therefore, it will be
critical to understand and assess the implications of each option on school revenue
budgets. At this stage, given the breadth of options it is not practical to model them all in
detail, but it is possible to complete an assessment of whether an option is likely to worsen
or improve key elements of a school budget (e.g. implications for revenue lump sum
funding, staffing costs, site maintenance costs etc).
6.3.2. The evaluation will take account of a high-level analysis for the likely impact that options
would have on school revenue budgets, establishing whether a negative, positive or no
change position would exist in each scenario.
6.4. Staffing
6.4.1. This section of the evaluation focuses on the impact each option may have on staffing
arrangements and whether the tested scenarios for improve, worsen or maintain current
staffing provision.
6.4.2. The staffing element does not take into account staff costs for each scenario, which are
considered under the revenue impact section of the evaluation.
6.4.3. The level and appropriateness of staff resource is considered along with the quality and
breadth of resource that each scenario would be likely to result in. Scenarios are reviewed
on the basis of whether they would be most likely to result in maintained, improved or
worsened staffing to support the required breadth of curriculum activity.
6.5. Education
6.5.1. Each scenario is reviewed to ascertain the level of impact that it is likely to have on the
delivery of Education. The Education workstream has been split down into a number of
sub-categories to facilitate the review, covering the following areas:
6.5.2. Curriculum – alternative scenarios are considered in terms of their potential impact on the
efficiency, viability and sustainability of curriculum delivery. Scenarios are reviewed using
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 48 of 137
a set of principles establish with the Education Consultant in order to understand whether
they are likely to result in a positive, neutral or negative impact on the breadth, quality,
consistency and continuity of curriculum delivery.
6.5.3. SEND – consideration is given the ability of each scenario to support SEND within
mainstream school settings, establishing the likelihood of positive, neutral or negative
effects for each scenario when compared to the current Baseline Option.
6.5.4. Sport & Extra-Curricular Activity – the varying impact that scenarios have on the ability to
deliver Sport & Extracurricular activity from school sites is specifically considered within
the review. This is again scored by reference to the current Baseline Option, establishing
where options improve, offer a status quo or worsen current arrangements and delivery.
6.5.5. Early Years – consideration is given throughout the review to the potential impact on Early
Years arrangements through tested scenarios. Whilst assessment of places is outside of
the scope of the review, the importance of existing Nursery and Pre-school arrangements
is recognised and reflected within the evaluation of scenarios, identifying if the existing
Baseline is impacted, remains the same or worsens due to alternative proposals.
6.5.6. Church Schools – the review is cognisant of the fact that the majority of schools in the
Crewkerne and Ilminster area are established as Church of England Voluntary Controlled
schools. Consideration has therefore been given to the impact that scenarios could have
on this current arrangement, in terms of the education offer in the area.
6.6. Transport and Geography
6.6.1. This section of the review aims to consider the geography and transport implications and
challenges for each option / scenario tested in order to establish whether an option results
in a positive, neutral or negative impact on the following factors:
6.6.2. Infant and Primary Schools are currently provided within local communities and therefore
travel distances for many families are typically short. Developed options will be reviewed
to establish their likely impact on the current position, establishing whether the position is
improved of worsened. The Local Authority have advised that no Primary age student
should be forced to have a travel time of more than 45 minutes to their local school.
6.6.3. Consideration will be given each options impact on the ability of parents and pupils to walk
to school. In rural village schools this is an important part of the village and community
and therefore options will be reviewed to reflect adjustments based on geography of the
various options.
6.6.4. The evaluation of options will also consider the high-level impact on parents dropping
pupils to school on route to work. Whilst individual travel routes cannot be taken account
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 49 of 137
of, proposed options will be reviewed in terms of the level of impact they are likely to have
on current arrangements based on geography.
6.7. Equalities Impact
6.7.1. This section of the review aims to consider the equalities implications and challenges for
each option / scenario tested in order to establish whether an option results in a positive,
neutral or negative impact.
6.7.2. Consideration will be given to the potential impact that structural changes to the school
system and estate could have on the ability to gain fair and equal access to public services
and premises and the scale of impact any identified changes could have (either positive or
negative). Consideration will also be given to the current baseline position presented by
the current school structure and estate (including current compromises where compliance
cannot be fully achieved due to the constraints of the facilities).
6.7.3. A full Equalities Impact Assessment will be required for any Preferred Option that is taken
forward, but as part of this Strategic Review, an initial view has been taken on the potential
positive, neutral or negative impact of each option on the relevant protected characteristics,
to include (but not be limited to) age, disability, race (including ethnicity, nationality,
Gypsies and Travellers), religion and belief, rurality and low income.
6.8. Community Impact
6.8.1. This section of the review aims to consider the implications and challenges of each option
/ scenario tested on the local Community in order to establish whether an option results in
a positive, neutral or negative impact.
6.8.2. It is recognised that most of the first schools are designated as Rural Schools under the
Designation of Rural Primary Schools (England) Order 2018. On this basis the testing and
evaluation of options need to ensure that any proposed changes to schools take account
of potential impacts on local community character and the function that schools play within
their communities (i.e. community use, polling stations, community hubs etc).
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 50 of 137
7. Scenario Testing – Option 1 (Baseline)
7.1. Option 1 – Summary & Key Findings
7.1.1. Option 1 comprises the ‘do nothing’ or minimum requirement position. It serves as a
baseline for other options under review and outlines what needs to be done to retain an
‘as is’ existing three-tier first, middle and upper school system; when taking into account
projected requirements for growth to meet school population forecast and additional
housing development demands. The table below summarises the current student numbers
(as at SPF population baseline 2018), the assessed existing capacity with the 12
Crewkerne & Ilminster schools (based on SCC SCAP data and existing school site
accommodation analysis), and the projected required student numbers for the area by tier
type:
Current NoR Existing
Capacity Projected Required Number
Uplift beyond current capacity
First Schools 998 1044 1317 Uplift of 273
Middle Schools 683 840 924 Uplift of 84
Upper School 450 775 661 Excess of 114
Total 2131 2659 2902
7.1.2. It is important to note that whilst several of the existing schools are currently under-utilised
with pupil numbers below site capacity (particularly across middle and upper schools –
consistent with the outlined associated financial pressures), the projected growth of pupil
numbers across the Crewkerne and Ilminster area over time is expected to exceed existing
capacity; with additional school places needed across first and middle year groups to meet
educational needs. This option does therefore represent a ‘minimum requirement’ position,
on the basis that do nothing is not feasible if sufficient educational places are to be realised.
7.1.3. Scenario 1A therefore illustrates the position ‘As is, taking into account growth’.
7.1.4. The main area of projected growth is within the first school tier / year groups where there
is currently very little spare existing capacity. A small number of places have been identified
across Ashlands and Greenfylde, but the majority of the small first / primary school sites
(particularly those of less than 100 pupils) are struggling to comply with building & site
BB103 SoA (Government template - Schedule of Accommodation) requirements for their
existing pupil numbers, let alone suggested increased SCAP numbers - meaning additional
expansion capacity needs to be found to serve future pupils under this model.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 51 of 137
7.1.5. The middle schools of Swanmead and Maiden Beech have existing capacity in place and
will see growth of student numbers over time to take them to full occupancy, plus a small
level of increased demand requiring additional accommodation to support.
7.1.6. Analysis shows that whilst Upper year student numbers are expected to grow from the
current position it will not be significant and is not expected to exceed the capacity that
currently exists within the Wadham site. The gap between max. Site capacity and NoR will
reduce slowly over time but will not close. Excessive or redundant upper student capacity
will continue to exist at Wadham under this model; which leaves residual risk regarding
ongoing financial sustainability. If this option were to be adopted as the preferred strategy
going forward knowing this to be the case, further risk mitigation actions or financial support
/formula funding changes may need to be considered (that is explored further under Option
2)
7.2. Scenario 1A - Specifics:
7.2.1. Scenario 1A summarises the following actions anticipated to be required under the ‘do
minimum’ option – to maintain existing structure whilst incorporating projected growth:
▪ Expand First numbers at Ashlands school site utilising existing vacated
accommodation. A block has been identified on site, following closure of the former
Children’s Centre – with the potential to be reconfigured to house 2 additional
classrooms.
▪ Expand First numbers at Greenfylde’s school, based on the relocation and
expansion to alternative SCC site – as outlined in existing feasibility study provided
by the Local Authority. With expansion options very limited on smaller sites this
relocation and expansion is critical to realising the required numbers.
▪ Plan for small expansion of Middle student accommodation at Maiden Beech as
existing capacity nears exhaustion – there is scope for limited expansion on both
Swanmead and Maiden Beech sites, but Maiden Beech has the greater site area
and flexibility of options to incorporate so increased capacity has been indicated
there.
▪ Consider excess area to remain unutilised at Wadham and review and consider short
term and longer-term options to close / decommission / mothball areas of redundant
estate. Practical application will likely be limited but should be reviewed alongside
potential options for funding support, long term or to bridge until growth reaches
suitable position.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 52 of 137
7.3. Capital Cost
7.3.1. Expansion works will be required to ensure continued provision of student places under
the existing three-tier system and this will have an associated Capital cost. We have looked
to assess this cost as part of the review; on the basis of the works remit outline above, to
establish a Baseline of potential cost against which we can compare alternative options.
There is effectively no capital cost neutral option to cater for the future, so assessment of
capital cost will be relative to this ‘do minimum’ level of funding.
7.3.2. Each site (with the exception of Greenfylde where there is an existing costed feasibility
study) has been analysed using the relevant BB103 SoA tools to identify area shortfalls
and accommodation types that will be required to support additional numbers and establish
calculated estimates of additional area. These areas have then been fed into a high-level
cost model to establish appropriate works rates and provide an outturn Order of Magnitude
capital cost. A copy of the feasibility cost model completed by cost advisors Randall
Simmonds can be found within Appendix 3. The table below summarises the calculated
development areas, works type and Order of Magnitude Capital Cost:
Site Area Works Type OoM Capital Cost
Ashlands 170m2 Refurb / Reconfiguration £379,000
Greenfylde 2700m2 New Build £7,300.000
Maiden Beech ~500m2 New Build £1,538,000
Total Baseline Cost: £9,197,000
7.4. Building Condition
7.4.1. All buildings will need to be retained under this model meaning that any remedial and repair
works associated with the age and condition of the buildings will need to be addressed as
they arise going forward (through LA maintenance funds or CIF / Academy based grants
as appropriate). We have reviewed and presented known building condition data relating
to each site to establish a RAG rating, but as ‘retain all’ is the default or Baseline position
we limited the focus at this stage of the review on assessing and highlighting any potential
opportunities for improvement upon that position under the alternative options. The only
exception to this could be where reviewing the excess capacity at Wadham to see if any
areas that could be decommissioned / mothballed temporarily or permanently could be tied
in with known areas of poor condition. This may be limited in practical application.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 53 of 137
7.5. Site rationalisation / disposal opportunities and condition improvement cost
avoidance
7.5.1. As outlined above this scenario has limited scope for site rationalisation and disposal
opportunities, beyond the assumed change of Greenfylde site, as all buildings are required
to be retained and utilised to sustain the existing three-tier education system. The table
below captures a high-level summary of the current building condition status for each of
the 12 sites within the relevant Crewkerne and Ilminster area to give an indication of
potential future maintenance needs – potential site rationalisation / disposal opportunities
and condition improvement cost avoidance under other options will reference back to this:
Site Rationalisation / Disposal Opportunity
Building Condition
RAG rating
Notes / Comments
Haselbury Plucknett None – All sites proposed to be retained under this option
Amber / Green Any remedial / repair / replacement works associated with the age and condition of the buildings will need to be addressed as they arise going forward. No cost avoidance opportunity with all sites in operation.
Hinton St George Amber
Misterton Amber / Red
Shepton Beauchamp Red / Amber
St Mary and St Peter’s Unknown**
Merriott Amber
St Bartholomew’s Amber / Green
Ashlands Amber
Greenfylde* New Site Green
Swanmead Amber / Red
Maiden Beech Amber / Green
Wadham Potential for excess area rationalisation
Amber May be limited in practical application – applying to very limited area
*Greenfylde is modelled above on basis of new replacement site. The disposal opportunity arising from old site (Red / Amber condition
status) is assumed to be available to the Local Authority / relevant Education Trust as part of proposal.
**Unknown building condition status (not captured ESFA Property Data Survey) - site comprised entirely of temporary buildings.
7.6. Revenue Impact
7.6.1. This option essentially shows the position as it is now, but after the required levels of
expansion and growth have been applied. A calculation of formula cost, derived from basic
lump sum funding (and any other relevant factors in terms of split site or scarcity funding)
has been completed to estimate the new baseline revenue cost position in the expanded
state. The table below indicates the calculated baseline against which other options have
been assessed, in terms of variation and potential savings / improved financial position:
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 54 of 137
Option Estimate of Lump Sum Costs
Variation from Baseline (Potential saving)
Year 1 saving Grant Lump sum (PE / Sports premium etc)
Variation from Baseline (potential saving)
Overall Revenue Saving to Public Purse
1A Baseline
£1,320,000 N/A N/A £192,000 N/A N/A
7.6.2. A detailed summary of the Financial impact assessment can be found within in Appendix
4; the information below is a summary of the scope of the financial assessment completed
for this initial options appraisal stage review.
7.6.3. The financial assessment has focused on delegated budgets or ISB (ISB being the
Individual School Budget and term used to describe the budget allocated to schools
through the funding formula). However, the assessment also includes comment on non-
ISB financial implications, financial risks, the revenue costs associated with implementing
change and overall cost-effectiveness.
7.6.4. Judgements were made on the basis of the following assessments:
▪ The cost to the public purse – recognising that some options present considerable
revenue savings but that the benefit would accrue to the DfE not Somerset
▪ Other financial implications, in terms of the loss of funding to the area and the scope
for further savings
▪ Financial risk, including where the responsibility for bearing costs was uncertain or
the risk of financial failure
▪ Curriculum efficiency – a measure of the likely proportion of revenue spend that
would be for class teaching, educational support and resources rather than
leadership and management, administration and premises costs, based on
benchmark data.
7.6.5. The equivalent sections following within this report (under other options headings) will
contain an extract of the key comments and factors identified relevant to the specific
Scenario under review, as has been used to contribute to the options appraisal evaluation,
based around those four key headings:
7.6.6. Funding Implications
7.6.6.1. The figure outlined in the table above represents the baseline position.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 55 of 137
7.6.7. Other Financial Implications
7.6.7.1. Six of the twelve schools are already collaborating within three federations, each
of two schools. Each federation has a single headteacher, realising beneficial
leadership cost savings.
7.6.7.2. Further integration of these federations, leading potentially to an area-based
multi-academy trust would provide further opportunities for efficiencies and cost-
effective collaboration.
7.6.8. Financial Risks
7.6.8.1. Wadham is at serious risk of financial failure, with premises costs and minimum
staffing levels exerting a disproportionate demand on the budget.
7.6.8.2. Three schools reported a cumulative deficit at the end of 2017/18 with five more
showing an in-year deficit. The in-year deficit at Maiden Beech academy
considerably exceeds the residual balances indicating a risk of financial failure in
the current financial year.
7.6.8.3. Retaining this configuration risks irrecoverable deficits which could be, in the
event of educational failure, be left for the LA to write off, from the LA budget not
DSG. A deficit in an academy could lead to withdrawal of the funding agreement.
7.6.9. Curriculum Efficiency
7.6.9.1. The results found under this assessment form the baseline position against which
other options are compared. It is noted that the small schools are likely to
experience lower proportion of spend attributed to classroom teaching and
educational support/ resources due to fixed costs.
7.7. Education and Staffing Impact
7.7.1. As per other areas of analysis this option serves as a baseline for comparison and
effectively looks at the anticipated size and education phase of the encompassing schools
after growth, to allow factors such as relevant factors (such as pupil to teacher ratios,
numbers per year groups, current mixed age year classes, numbers of school transition
points and at what age they occur, potential disadvantages and opportunities of alternative
sizes and models to staffing skills and recruitment and retention) to be considered to
assess if changes under Scenarios are anticipated to largely; maintain the status quo,
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 56 of 137
provide opportunity for improvement to deliver a position better than the current status or
potentially have a detrimental or worsening impact.
7.7.2. As expected for option 1A under retained existing three-tier first, middle and upper school
model, the baseline system comprises the following:
▪ 9 existing first and primary schools - 5 very small with less than 100 pupils, 3 small
between 100 and 200 and 1 of medium / larger size at 346.
▪ 2 middle schools of medium primary or small / very small secondary size, and
▪ 1 upper school of equivalent size to medium size secondary.
7.7.3. A detailed review of considerations and findings relating to Educational Impact and Staffing
can be found within Appendix 5 of this report, the following is a summary of the structure
of the review and key points of note:
7.7.4. The review was centred around assessment of implications for each of the following
scenarios / model types; Primary, Secondary, Infant and Junior and First and all through 9
– 16 years. The principles and key consideration of these and how they link with student
numbers / sizes and education phases was established and then applied to each scenario
based on the new proposed structure. Each alterative / option under consideration is
therefore structured against these key headings with factors relating to Sport and Extra-
curricular activities, SEND and Wrap around care following.
7.7.5. The current three-tier system has 5 school sites with nursery provisions and (with the
potential exception of ~ 74 students at existing primary schools) requires all students to
make 2 transitions within their educational pathway, from first to middle and then from
middle to upper. All alternative scenarios are measured in terms of impact on these
measures, I.e. any potential loss to nursery places or potential benefit to continuity of
education through reduction in transitions.
7.7.6. The key conclusion within the assessment was that the staffing and educational
opportunities that a school can offer depends far more on the size of the school than the
age phases or tier system it operates within, and that the older the pupils within the school
the more important that becomes in terms of being able to offer a diverse range of options
with access to staff that can specialise in that subject – how this translates under each
scenario is summarised within the option heading but there is a clear correlation between
optimal school sizes and positive educational impact.
7.8. Transport / Geography
7.8.1. An overview map illustrating the geographical locations of current existing capacity across
the relevant Crewkerne and Ilminster sites is included within Appendix 2 of this report titled
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 57 of 137
‘Existing Schools Overview’ – it shows the current spread of educational places across the
three-tier year groups as in the current baseline on which commentary on transport and
geography is based.
7.8.2. The key points of note are:
▪ 6 of the small existing first / primary school sites are within rural village / community
settings, with the remaining three spread between Ilminster and Crewkerne.
▪ The 2 existing middle schools are split between Crewkerne and Ilminster with
provision in both areas.
▪ Upper school places are only available in Crewkerne with all pupils attending
travelling there from across the region.
7.8.3. As outlined within the summary of Educational Impact assessment (see Appendix 5) the
greatest distance between existing schools (St Mary and St Peter’s and Haselbury
Plucknett) equates to 12 miles. On the basis that it is possible to travel this within the
stipulated 45-minute time limit any proposed change in school site for pupils and their
families will be within a permissible distance. It is assumed however that most moves will
be to next nearest school cutting down the potential distances considerably from that
worst-case scenario. As illustrated within the appendix table over one third of all the
schools are located at a proximity of 5 miles of less from each other.
7.8.4. Each potential alternative option will consider the equivalent overview in terms of
implications for split of student places and year groups over the geography, the potential
travel distances of proposed changes and numbers affected, and implications on
opportunity to walk to school.
7.8.5. Option 1A is illustrated on an overview map included within Appendix 2 of this report titled
‘Option 1A Overview’ – it effectively shows the current spread of educational places across
the three-tier year groups but with the relevant sites shown at their expanded student
numbers.
7.8.6. The key points of note are:
▪ As expected there are no changes to transport considerations or geographical split.
▪ The required uplift in first school numbers is based on area need – with the vast
majority of additional first school places delivered via the Greenfylde expansion there
may be families in new housing areas having to travel from further afield as local
provision will be full.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 58 of 137
7.9. Equality and Community Impacts
7.9.1. Option 1A is illustrated on an overview map included within Appendix 2 of this report titled
‘Option 1A Overview’ – it effectively shows the current spread of educational places across
the three-tier year groups but with the relevant sites shown at their expanded student
numbers.
7.9.2. Option 1A is anticipated to have neutral equalities impact on any of the protected
characteristics as there is no change to the existing educational structure or geographical
spread of provision. Planned future expansions to Greenfylde, Ashlands and Maiden
Beech sites will also have neutral impact as they are designed to deliver growth and
demand needs for the area based on existing locations / sites. Likewise, there is likely to
be no foreseeable community impact directly due to planned site expansions.
8. Scenario Testing – Option 2
8.1. Option 2 – Summary & Key Findings
8.1.1. Option 2 is focused on retaining the existing first, middle and upper three-tier structure but
with assessment of potentially viable adjustments to formula funding. The required pupil
numbers and site constraints remain the same, so the model in terms of required
developments (capital cost, and impacts on transport, equality and community etc) is
essentially the same as outlined above under Scenario 1A. The section below therefore
captures any relevant aspects of change relating to revenue that could provide
improvement to financial sustainability of this model.
8.1.2. A detailed analysis of the potential considerations, tools, options and discussions that
might be utilised to target formula funding and strengthen areas of identified financial risk
and weakness within the existing system (‘As is’ scenario) is included within the
accompanying Financial impact assessment report which can be found within in Appendix
4; the information below is a summary of the key elements broken down across the four
assessment headings:
8.2. Revenue Impact
8.2.1. Funding Implications
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 59 of 137
8.2.1.1. Any divergence from the National Funding Formula will be at a cost to the
Somerset DSG and therefore affect all schools. The most targeted approach
would be to seek support from the DfE to vary sparsity thresholds and minimum
funding levels to fairly reflect the three-tier system. This, combined with the use
of a lump sum rather than tapered sparsity value for secondary/upper schools
could provide relief for Wadham until pupil numbers increase. A similar approach
could be considered for the first and middle schools.
8.2.2. Other Financial Implications
8.2.2.1. The most significant financial risk to an individual school is year on year loss of
pupils, leading to a level of operation that is significantly under capacity.
8.2.2.2. Implementing a formula change to support the three-tier system would encourage
community confidence in the schools and reduce pupil drift.
8.2.3. Financial Risks
8.2.3.1. The process of seeking these sorts of changes to the local formula requires local
consultation and an application to the DfE to disapply the Regulations. Failure to
carry the support of the Schools Forum places other aspects of the Schools
Budget at risk, particularly strategies to address High Needs demands.
8.2.3.2. Changes to formula funding for Wadham in particular may increase in-year
viability but will not address cumulative deficits.
8.2.3.3. Formula change has the effect of reducing financial risk to LA funds through
adding a planned additional charge to the DSG. This shifts from uncertain to
known, and from LA funds to DSG.
8.2.4. Curriculum Efficiency
8.2.4.1. In Option 2 the basic configuration of educational provision is as for Option 1.
There is no change in predicted curriculum efficiency as any beneficial change in
the formula for Wadham school in particular would reduce the deficit rather than
allow for increased curriculum spend.
9. Scenario Testing – Option 3
9.1. Two-tier education models
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 60 of 137
9.1.1. Options 3 and 4 consider alternative two tier primary and secondary education models; in
order to assess this in the same way as the baseline model both existing and potential
future capacity needs to be mapped against the relevant equivalent primary and secondary
years – as previously this needs to take into account projected requirements for growth to
meet school population forecast and additional housing development demands. The table
below summarises the current student numbers (as at SPF population baseline 2018), the
assessed existing capacity with the 12 Crewkerne & Ilminster schools (based on SCC
SCAP data and existing school site accommodation analysis), and the projected required
student numbers for the area, this time by two-tier primary and secondary types:
Current NoR Existing
Capacity Projected Required Number
Uplift beyond current capacity
Primary Places (split over existing first and middle school sites)
1340 1464 1799 Uplift of 335
Infant 568 641 787 Uplift of 146
Junior 753 823 1012 Uplift of 189
Secondary (split over existing middle and upper school sites)
792 1195 1103 Excess of 93
Total 2131 2659 2902
9.1.2. The projected growth of primary pupil numbers across the Crewkerne and Ilminster area
over time is expected to exceed existing capacity; with additional school places needed
across both infant and junior primary year groups to meet educational needs. Secondary
provision however shows a different story; indicating that even with anticipated growth
there is excess capacity across the region once existing under-utilised sites are filled. As
outlined previously; several of the existing middle and upper schools which contribute to
secondary year group capacity are currently significantly under-utilised (with pupil numbers
well below site capacity), providing ample / excess capacity even for future numbers.
9.1.3. It is however important to recognise that:
▪ The current illustrated excess capacity in secondary places is accumulated across
three existing sites, with two of the schools also currently delivering ‘junior’ primary
equivalent places – that capacity will not necessarily translate neatly into alternative
configurations.
▪ The projected number of secondary pupils requiring school places in the region after
growth is only 1103, equating effectively to one medium / large secondary school.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 61 of 137
▪ With year groups mapped across from three-tier to two-tier systems (with the
exception of 2 very small primary schools; Shepton Beauchamp and St Mary and St
Peter’s, totalling 74 students) all current primary equivalent capacity is split – with
infant years delivered under ‘first’ and junior years split between ‘first and middle’
schools.
▪ Cumulative capacity across multiple locations, as opposed to planned re-structuring
across educational phases can give rise to unusual pupil class numbers / teaching
configurations and increased class groups, as opposed to optimal 30 to a class
model as specified under BB guidance. Though with student numbers growing into
capacity organically over time this can be true for periods within re-structured models
as well.
9.2. Option 3 – Summary & Key Findings
9.2.1. Option 3 is the first of two alternative two-tier primary and secondary options under review,
focusing on the potential for consolidated primary schools across the region. Consolidated
in this instance meaning that every viable site must be able to support the full 7 primary
year groups (Reception – Yr. 6) in one location. Option 4, covered later in this document
considers alternative split site Infant (R – Yr. 2) and Junior (Yr. 3 – Yr. 6) and hybrid split
site and consolidated options.
9.2.2. It was assumed prior to analysis that under each two-tier option, Secondary (11 – 16)
places would come from within the existing middle and upper schools only (namely
Swanmead, Maiden Beech and Wadham) and that all possible combinations for provision
of secondary education could apply equally to either primary model. Whilst this is true in
principle it was evident on analysis of consolidated primary options under Option 3 that not
all secondary options were feasible if the primary model was to be achieved with a number
of secondary options having to be discounted to support a switch of existing capacity to
primary.
9.2.3. Fundamental to understanding this is understanding how the existing first schools translate
in terms of potential consolidated primaries. The vast majority of the existing first /primary
school sites are very small in size and unable to accommodate the required 7 classrooms
or 210 students (for a 1 form entry school). The majority of sites (particularly those of less
than 100 pupils) are struggling to comply with building & site BB103 SoA requirements for
their existing pupil numbers let alone expanded NoRs. Development options on those
small sites are extremely limited if possible at all, meaning they cannot realise the
additional teaching areas to meet the SoA requirements and cannot function as
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 62 of 137
consolidated primaries without compromising efficiency of class sizes and/or promoting
heavy use of mixed age group teaching across multiple age range and key stages – to a
greater degree than is happening in practice within the existing 5 year groups. Only 2 of
the larger existing first sites were identified as potentially viable to support a consolidated
primary model (with a query around potential 3rd at St Bartholomew’s), and taking into
account growth and required numbers, even at maximum thresholds these schools alone
would leave a massive shortfall in primary numbers of at best ~750+ primary places.
9.2.4. Sufficient capacity utilising consolidated primaries can therefore only be achieved if
development of the larger first sites is supplemented with capacity from the current middle
school provision. I.e. for this option to work both middle school sites would be required to
change to primary schools (and take expanded numbers) to meet the area demand,
meaning there would be no capacity there to support secondary provision. Wadham having
the capacity to expand and deliver a sole site secondary option - and release the middle
school capacity for primary education - is intrinsic to this model having a viable scenario
and being able to deliver appropriate capacity in the appropriate age brackets.
9.2.5. Assessment of the viability of other secondary options is therefore detailed below under
Option 4, where greater flexibility in ways to deliver primary places opened-up additional
options. For completeness it is worth noting that the analysis found Wadham as a sole
site secondary to be the recommended secondary model, meaning the preferred Option 3
scenario summarised below correlates with the optimal secondary provision anyway and
is directly comparable against the other two-tier options in terms of evaluation of this
aspect.
9.3. Scenario 3B Specifics:
9.3.1. Scenario 3B summarises the following actions anticipated to be required to deliver a
solution utilising consolidated primary schools (all sites to cater for 7 year groups)
▪ The majority of existing small first sites are unable to accommodate 7 classroom
arrangements and are not viable as consolidated primary schools – under this option
there would be potential opportunity for closure of 7 existing school sites.
▪ Expand numbers at Ashlands school site utilising existing vacated accommodation.
A block has been identified on site, following closure of the former Children’s Centre
– with the potential to be reconfigured to house 2 additional classrooms and take
total to 7 to support 1FE Primary structure.
▪ Expand numbers at Greenfylde’s school, based on the relocation and expansion to
alternative SCC site and a change of provision to a 3FE Primary School. The current
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 63 of 137
feasibility study as provided by the Local Authority shows plans to support a 4FE first
school of 20 classrooms. It is considered viable that this could be revised to a 21-
classroom arrangement to support an alternative 3FE primary school.
▪ Expand numbers at Swanmead to accommodate a 420 pupil 2FE primary school –
this is in line with the maximum number that Swanmead site can hold while meeting
BB standards and fits well against the required provisions. The school building area
is of sufficient size currently and has an overprovision of each space type required
for primary education, requiring internal reconfiguration and refurbishment only to
ensure the correct functions and facilities appropriate to revised age range.
▪ Expand numbers at Maiden Beech to accommodate a 630 pupil 3FE primary school
– this is comfortably feasible within the site constraints. The school building area is
of sufficient size currently, requiring internal reconfiguration and refurbishment only
to ensure the correct functions and facilities appropriate to revised age range.
▪ Expand numbers at Wadham through delivery of a new accommodation block to
accommodate the full requirement of 1103 secondary students as a sole site facility
– this is comfortably feasible within the site constraints with potential identified site
areas. Wadham also has an overprovision of accommodation in some areas
meaning it may be feasible to realise some, or all, of the additional places through
internal reconfiguration.
9.4. Capital Cost
9.4.1. Each site (with the exception of Greenfylde where there is an existing costed feasibility
study) has been analysed using the relevant BB103 SoA tools to identify area shortfalls
and accommodation types that will be required to support additional numbers and establish
calculated estimates of additional area. These areas have then been fed into a high-level
cost model to establish appropriate works rates and provide an outturn Order of Magnitude
capital cost. A copy of the feasibility cost model completed by cost advisors Randall
Simmonds can be found within Appendix 3. The table below summarises the calculated
development areas, works type, ‘Order of Magnitude’ capital cost and comparative position
against the baseline ‘do minimum’ option:
Site Area Works Type OoM Capital Cost
Ashlands 170m2 Refurb / Reconfiguration £379,000
Greenfylde 2700m2 New Build £7,300.000
Swanmead 506m2 Refurb / Reconfiguration £1,284,000
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 64 of 137
Maiden Beech 865m2 Refurb / Reconfiguration £2,109,000
Wadham* 1000m2 New Build £3,180,000
Total Scenario Cost Total Scenario Cost £14,232,000
Total Baseline Cost Total Baseline Cost: £9,197,000
*Costed based on New Build Option due to risks associated with condition of potential identified reconfiguration area
9.4.2. This option requires development across 5 sites as opposed to 3 under the ‘do minimum’
baseline taking into account the internal reconfiguration works associated with age change
requirements at Swanmead and Maiden Beech sites.
9.5. Building Condition
9.5.1. There is potential scope for the closure of 7 existing school sites under this scenario
meaning a significant opportunity to improve upon the baseline position; where all buildings
will need to be retained and any remedial and repair works associated with the age and
condition of the buildings addressed as they arise going forward.
9.5.2. Site rationalisation / disposal opportunities and condition improvement cost avoidance
9.5.3. As outlined above this scenario has significant scope for site rationalisation and disposal
opportunities, beyond the assumed change of Greenfylde site, with 7 additional existing
first/ primary sites identified for potential closure. The table below indicates the current
known building condition status for each of the identified opportunity sites to give an
indication of the potential scale of benefits (in terms of future maintenance needs):
Site Rationalisation / Disposal Opportunity
Building Condition
RAG rating
Notes / Comments
Haselbury Plucknett Potential Closure Amber / Green
Hinton St George Potential Closure Amber
Misterton Potential Closure Amber / Red
Shepton Beauchamp Potential Closure Red / Amber
St Mary and St Peter’s Potential Closure Unknown** Temporary Buildings
Merriott Potential Closure Amber
St Bartholomew’s Potential Closure Amber / Green
Ashlands Sites to be retained Amber
Greenfylde* New Site Green
Swanmead Amber / Red
Maiden Beech Amber / Green
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 65 of 137
Wadham Amber
*Greenfylde is modelled above on basis of new replacement site. The disposal opportunity arising from old site (Red / Amber condition
status) is assumed to be available to the Local Authority / relevant Education Trust as part of proposal.
**Unknown building condition status (not captured ESFA Property Data Survey) - site comprised entirely of temporary buildings.
9.6. Revenue Impact
9.6.1. A detailed summary of Financial impact assessment is included within in Appendix 4, the
information below is an extract of the key comments and differentiating factors identified
relevant to the specific Scenario under review, as has contributed to the options appraisal
evaluation:
Option Estimate of Lump Sum Costs
Variation from Baseline (Potential saving)
Year One Saving
Grant Lump sum (PE / Sports premium etc)
Variation from Baseline (potential saving)
Overall Revenue Saving to Public Purse
1A Baseline
£1,320,000 N/A N/A £192,000 N/A N/A
Option 3B £550,000 (£770,000) (£115,500) £80,000 (£112,000) (£882,000)
9.6.2. Funding Implications
9.6.2.1. This option represents the greatest saving overall, but it will be for the DfE -
funding into Somerset will reduce in line with formula and grant saving.
9.6.2.2. The additional lump sum payment in the year following amalgamation would
contribute to the cost of change.
9.6.2.3. Use of a split site primary option rather than using an existing middle school site
would add cost through the split site factor.
9.6.3. Other Financial Implications
9.6.3.1. This option represents the largest reduction in DSG and grant funding coming
into Somerset and the Crewkerne and Ilminster area. Assuming that significant
savings could be realised through reductions in premises and administrative
costs, the saving is still likely to translate to a reduction in the number of teachers.
Whilst this will mainly affect leadership posts, if the saving is broadly proportionate
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 66 of 137
to school spending generally, it could be assumed that this would translate to a
reduction of 6 to 8 teachers.
9.6.3.2. This option also reflects a significant reduction in specific grant for PE and Sports,
which may be mitigated by more efficient provision in larger schools.
9.6.4. Financial Risks
9.6.4.1. It is not clear if the expectation of 85% of lumpsum saving passing to the newly
amalgamated schools in year one would be at a cost to the DfE or Somerset
DSG.
9.6.4.2. It is not clear if any additional split site costs would be funded by the DfE, and if
funded there may be a lag of one year and/or an application process.
9.6.4.3. The larger schools in this option bring increased resilience and viability.
9.6.5. Curriculum Efficiency
9.6.5.1. Whilst there is evidence that very large schools demonstrate a decline in
curriculum spending as a proportion of total spend, this may be as a result of
financial efficiency, with educational support staff and resources shared efficiency
across multiple classes in each year group. Despite the drop off in the curriculum
efficiency metric for larger schools, this option has close to the top weighted
metric.
9.7. Education and Staffing Impact
9.7.1. A detailed Education and Staffing Impact review is included within Appendix 5, the
information below is an extract of the key comments and factors identified as relevant to
the specific Scenario under review, as has contributed to the options appraisal evaluation.
9.7.2. For this option the relevant assessment models were Primary and Secondary, and the
summary is split between the two areas accordingly.
9.7.3. Key findings of Primary assessment:
▪ The advantages / disadvantages of a primary model are different and more directly
correlated with the size of school rather than comparison of first or infant / junior
models however there can be greater consistency of approach to teaching and
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 67 of 137
learning, curriculum planning and behaviour management, and reduced potential for
repetition /misalignment of approaches when continuing from ages 4 to 11 in one
phase.
▪ Primary schools of small student numbers (particularly where retaining schools with
less than 100 students) with multi-age classes is considered challenging, in terms of
being able to stretch and challenge students when covering multiple curriculum
elements in class and with difficulties associated with staff recruitment and retention
and limitations on career progression.
▪ Larger primary schools with a larger staff body will benefit from greater access to
and retention of specialist staff and expertise with more opportunities for wider
curriculum and associated enrichment opportunities. Increased opportunities for
school leaders to focus on leadership and strategic improvement.
9.7.4. Key findings of Secondary assessment:
▪ Research indicates that the optimal size for a secondary school, where performance
is optimised is evidenced to be in the order of ~1000 pupils.
▪ Small / smaller secondary will not be able to offer the breadth of choice in KS4 that
a larger one can, as seen in review of comparable sized secondary sized schools in
Somerset. The smaller the school the less likely students are to have access to
specialist staff with increased challenges in recruiting and retaining staff and
covering all subjects with specialists, more part time staff may be needed or teachers
having to teach more than 1 subject.
▪ A review of recent Government Capacity UD1 data (covering 3376 schools across
the country designated with secondary pupils) showed that less than 1% of
secondaries existed of very small size (less than 350 pupils). It would be considered
highly unusual to create one and it is not recommended to be used for secondary
(11 – 16) provision.
▪ Increased size in secondary provision can provide greater support and opportunities
for both students and staff, with a larger staff body allowing a full and balanced
curriculum supported by the appropriate specialist staff / subject expertise to stretch
and challenge all pupils. Larger school sizes provide greater resilience and flexibility
in how staff are deployed.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 68 of 137
9.7.5. This scenario proposes to have 4 consolidated primary schools ranging from smaller 1FE
entry 210 pupil size to 3 FE 640 pupil size, and one single site secondary school providing
all the required capacity at 1103 pupils and is considered the optimal model in terms of
educational and staffing impact, maximising the opportunities and advantages of
economies of scale with all school sites within optimal size ranges. Whilst secondary
provision was required to be a sole solution in order to have viable capacity at primary
level, the single site solution proposed is considered to be the optimal model and would
have been recommended anyway (as illustrated in more detail under option 4).
9.8. Sports / Extra-curricular / SEND and Wrap Around Care
9.8.1. Impact or opportunities for improvement in these areas were found to also largely correlate
with size of schools proposed under the scenario, on the following basis:
▪ There are more opportunities in larger schools for team sports and for participating
in tournaments and competitive games. Training and specialist knowledge is also
more likely to be apparent in larger schools.
▪ There is likely to be increased range of additional other extracurricular activities,
such as music and drama in larger schools, where staffing time and expertise are
available.
▪ A larger school has the opportunity to deploy TAs in more creative way and can
support more pupils – they also have an advantage in training opportunities as TAs
can specialise in certain approaches I.e. ELSA. Smaller schools probably have more
limited opportunities in how they use Pupil Premium funding because they have
fewer staff to utilise.
▪ Wrap around care provision (before and after school clubs etc) is largely generated
by the school and parent demand and not confined to a particular type of school or
model – it could therefore be offered to equivalent standard in any provision, but with
greater opportunity to expand or increase financial sustainability at a larger school
where there is increased numbers and potential increased demand.
9.8.2. This scenario proposes to have 4 consolidated primary schools ranging from smaller 1FE
entry 210 pupil size to 3 FE 640 pupil size, and one single site secondary school providing
all the required capacity at 1103 pupils and is considered the optimal model in terms of
maximising the opportunities and advantages of economies of scale in these areas.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 69 of 137
9.9. Transitions
9.9.1. This scenario proposes that all pupils will transition directly from primary to secondary
education after Year 6, this means a reduction to optimal position of only one transition,
which could provide greater continuity for the more vulnerable (reducing anxiety for some
students) and minimise impact associated with poor transition.
9.10. Pre-school and Nursery
9.10.1. This option has the most risk of potentially detrimental impact upon pre-school nursery
provision with 3 of the existing 5 nurseries on sites that are indicated for potential closure.
This would need careful consideration and mitigation planning if this option were to
progress.
9.11. Transport / Geography
9.11.1. Option 3B is illustrated on an overview map included within Appendix 2 of this report titled
‘Option 3B Overview’ – it shows the proposed spread of educational places delivered under
a two-tier structure using consolidated primary schools and a single secondary school site.
9.11.2. With a reduction from 12 to 5 schools and changes in year groups patterns there will be
transport implications for a large number of pupils and families.
9.11.3. The key points of note are:
▪ There remains a good split of capacity across both Crewkerne and Iminster areas
with 2 primary schools sited in each location.
▪ All moves resulting from the closure of the smaller existing first / primary school sites
require moves of under 5 miles.
▪ There will no longer be provision for the older middle year (Years 7 and 8) within the
Ilminster area as these become part of the secondary provision delivered from
Crewkerne – however this affects non-primary children. The longest travel distance
from primary to secondary will be 9 miles, which is equivalent to the current move
from Swanmead middle to Wadham Upper, the transition is just happening earlier in
line with primary / secondary model.
▪ The equivalent Yr. 7 and 8 pupils will move 1 mile from Maiden Beech to Wadham.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 70 of 137
▪ With closure of smaller more rural schools there will be lost opportunity to walk to
school from village locations, however with increased capacity for lower age ranges
within Crewkerne and Ilminster hubs there may be increased opportunity there in
both denser populated areas.
9.12. Equality and Community Impacts
9.12.1. Significantly this option could see the closure of seven existing rurally-located first / primary
schools, with consolidated Primary provision now concentrated in four primary schools –
two in Ilminster and two in Crewkerne, plus a single Secondary School in Crewkerne. This
option sees a negative impact in relation to the existing status quo, largely due to the
number of planned school closures across the region, in particular leading to impact on the
following protected characteristics:
9.12.2. In particular, equalities impact assessments will need to ensure that impacts on the
following protected characteristics are understood and mitigated:
9.12.3. Religion and Belief - Proportion of church schools
9.12.3.1. Due to the high proportion of existing Diocese Schools in the area (8 of the 9
existing First / Primary Schools are Diocese Schools), option 3B would see a
reduction in the number of Diocese schools across the region and a reduced
geographical spread. However, the proposals see consolidated Diocesan Primary
provision available in Ilminster (Greenfylde) and Crewkerne (Ashlands), alongside
a non-denominational Primary in each town, offering greater parental choice across
the region.
9.12.4. Rurality - Rural and Village Schools and Communities
9.12.4.1. The majority of proposed schools for closure are considered to be designated as
‘rural schools’ and as such, a detailed impact assessment would need to ensure
that any significant impact on the community is understood and mitigated where
possible. The removal of schools from these areas could impact on community
facilities and cohesion, although currently there is no significant community use
noted for these schools.
9.12.4.2. Travel times for pupils and families (for those with an onward journey to works) are
likely to be increased and therefore proposals would need to consider the
availability of transport links etc in order to mitigate any impact.
9.12.4.3. A number of the schools have associated Pre-School / Nursery provision which
may be impacted should the school sites close. A lack of Early Years provision can
impact on the ability of rural families to work and can also have a negative impact
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 71 of 137
on a child’s Early Years development. A proportion of this Early Years provision is
delivered from school premises with the majority being run independently from the
school, although a small number are under school control. Future Early Years
growth, demand and provision is outside of the scope of this Feasibility Study, but
further assessment will be required in order to ensure that sufficient alternative
provision is available and that any negative impact on rural families is mitigated.
9.12.5. Race - Minority Communities
9.12.5.1. St Mary and St Peter’s school is proposed for closure under this option. It has been
noted that a number of children from the Travelling Community attend the school
and therefore further assessment will be required in order to understand and
mitigate any negative impact on this community.
9.12.5.2. At this stage, no other negative impact on race has been noted in relation to the
other schools proposed for closure, but further assessment will be required at
feasibility stage
9.12.6. Disability – Accessibility
9.12.6.1. A number of schools proposed for closure under this option are Victorian village
schools which are limited in terms of possible disability adaptations. A move to a
more consolidated Primary model in a smaller number of refurbished buildings, may
positively impact on the ability of schools across the region to accommodate pupils
and staff with disabilities, but it should be noted that the refurbishment of existing
building stock may limit accessibility in some cases.
9.12.7. Low income
9.12.7.1. Utilising the percentage of children eligible for Free School Meals as a deprivation
indicator (see Part 3 for details for each school), the majority of schools earmarked
for potential closure under this proposal demonstrate a level of deprivation below
the national average, with the exception of St Mary and St Peter’s (17.1%)2.
9.12.7.2. Ashlands (19.2%)2 site is proposed to be developed under this option and therefore
the investment in the site may impact positively on low income families within this
area. However further assessment will be required to ensure that any impact on
low income families attending St Mary and St Peter’s is recognised and mitigated.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 72 of 137
10. Scenario Testing – Option 4
10.1. Option 4 – Summary & Key Findings
10.1.1. Option 4 is the second of the two-tier primary and secondary options under review, with
the greatest number of sub-options as it looks at both split site Infant and Junior
combinations and hybrid split infant / junior and consolidated primary options. As
summarised under the previous option it is assumed that Secondary (11 – 16) places will
come from within the existing middle and upper schools (namely Swanmead, Maiden
Beech and Wadham) and that all possible combinations for provision of secondary
education could apply in conjunction with this primary model.
10.1.2. As site options for secondary places are more limited, and existing middle schools
(spanning both primary and secondary age ranges) could feasibly contribute to either
primary or secondary school solutions (as demonstrated under Option 3), assessment of
secondary capacity and requirement numbers was considered crucial. Determining the
most viable model for secondary provision helped establish what existing / future middle
school capacity could be considered under this option for incorporation into primary
models.
10.1.3. Analysis of secondary provision and site options can be summarised as follows:
10.1.4. All three potential middle and upper sites were assessed against government guidance
BB103 building and site standards to establish their potential for expansion and any
limitations on growth arising from site constraints. Analysis (summarised below) shows that
whilst all sites have the potential for some viable expansion, both Swanmead and Maiden
Beech have student number limits that would preclude them from delivering places for all
1103 students and being sole secondary school sites. Wadham is the only site with
sufficient expansion space to support that model. If existing middle schools are to
contribute to secondary capacity then this would need to be via a shared or split secondary
model.
▪ Analysis of Swanmead estate shows that whilst there is scope to accommodate
limited building expansion on site, with a site area of 30,764m2 ~420 students is the
maximum that the site can hold before breaching BB guidance on site space
standards per pupil (in terms of external learning, play and sports spaces etc).
▪ Maiden Beech has more development space and a larger site area of 52,352m2 with
~840 students being the calculated maximum that the site can hold before breaching
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 73 of 137
BB guidance on site space standards per pupil (in terms of external learning, play
and sports spaces etc).
▪ Wadham has a very large site at 119,000m2 and considerable scope for expansion
with viable BB101 compliant building and site solutions demonstrated for up to
~1600 students.
10.1.5. With all three schools potentially required to change the number of year groups they would
teach (from 3 or 4 to 5 secondary) it is also important to consider how capacity numbers
(existing and future) benchmark against optimal increments of 30 students to ensure that
proposals are efficient and workable without necessitating additional classes / teachers or
mixed groups etc.
Site Constraints Swanmead
Max 420
Maiden Beech
Max 840
Wadham
Max ~1600
Expansion Increments - based on 5 year groups (7 - 11) and optimal classes of 30 students where possible
150 300 450 600 750 900 1050 1103
Required Secondary Number: 1103
10.1.6. With Swanmead’s estate constraints (and calculated maximum of 420 students) the site
cannot expand to 450 to support a full 3FE secondary school and would likely either have
to function with efficiency limitations at existing 348 capacity or reduce further to 300
students to support a 2FE entry model. There are various concerns regarding educational
implications for a such a small secondary site even at 3FE entry size, as captured under
the educational impact assessment and it is not considered a recommended viable option.
A review of recent Government Capacity UD1 data (covering 3376 schools across the
country designated with secondary pupils) showed that less than 1% of secondaries
existed of that range of pupil size. It would be considered highly unusual to create one and
it is not recommended to be used for secondary (11 – 16) provision.
10.1.7. With Swanmead unable to support a viable full secondary provision even as a multi-site
option, this leaves two alternatives, Maiden Beech and Wadham as a split two secondary
school provision or Wadham as a sole secondary school.
10.1.8. There are anticipated to be limited pupil numbers of secondary age, with 1103 students
equivalent to one medium / large secondary school required after growth. The existing
capacity across Maiden Beech and Wadham sites exceeds that required at maximum
student growth levels (even if Maiden Beech was capped at optimal 450 student size);
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 74 of 137
meaning one site would likely be left in a position of increased financial pressure as an
under-utilised facility. Assessment indicates that Secondary provision would be most
efficiently delivered and derive the most educational and financial benefits as a single /
sole site solution. Based on site constraints that would need to be based at Wadham.
10.1.9. On this basis a sole secondary site at Wadham was identified as the preferred position
(representing the optimal / most viable option for secondary places 11 – 16); and carried
through under both presented Option 4 scenarios.
10.1.10. We have included both a viable split site infant and junior and a hybrid split infant / junior
and consolidated primary option within the presented scenarios to represent the best of
the range of possibilities within this option.
10.2. Scenario 4A - Specifics:
10.2.1. Scenario 4A summarises the following actions anticipated to be required to deliver a
solution utilising a hybrid mixture of consolidated primary schools (catering for 7 year
groups) and split site infant and junior schools (catering for 3 and 4 Year groups
respectively).
▪ Expand numbers at Ashlands school site utilising existing vacated accommodation
to deliver a consolidated primary school. A block has been identified on site,
following closure of the former Children’s Centre – with the potential to be
reconfigured to house 2 additional classrooms and take total to 7 to support 1FE
Primary structure.
▪ Expand numbers at Greenfylde school, based on the relocation and expansion to
alternative SCC site and a change of provision to a 3FE consolidated primary school.
The current feasibility study as provided by the Local Authority shows plans to
support a 4FE first school of 20 classrooms. It is considered viable that this could be
revised to a 21 classroom arrangement to support an alternative 3FE primary school.
▪ Expand numbers at Maiden Beech to accommodate a 630 pupil 3FE consolidated
primary school – this is comfortably feasible within the site constraints. The school
building area is of sufficient size currently, requiring internal reconfiguration and
refurbishment only to ensure the correct functions and facilities appropriate to
revised age range.
▪ Utilise the larger remaining first sites of Merriott and St Bartholomew’s as Junior
Schools with the remaining smaller first / primary sites catering for Infants only. The
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 75 of 137
combined capacity from the smaller schools would deliver infant capacity in excess
of the required numbers and there would be options to close potentially 2 of those
sites – identification of those could be determined by a number of considerations
from existing challenges / performance to numbers of classrooms, geographical
locations or condition / finance factors.
▪ With existing first schools providing capacity as split site infant and junior schools
the existing capacity at Swanmead is surplus to requirement. Under this option there
would be the potential for closure of that site.
▪ Expand numbers at Wadham through delivery of a new accommodation block to
accommodate the full requirement of 1103 secondary students as a sole site facility
– this is comfortably feasible within the site constraints with potential identified site
areas. Wadham also has an overprovision of accommodation in some areas
meaning it may be feasible to realise some, or all, of the additional places through
internal reconfiguration.
10.3. Scenario 4A - Capital Cost
10.3.1. Each site (with the exception of Greenfylde where there is an existing costed feasibility
study) has been analysed using the relevant BB103 SoA tools to identify area shortfalls
and accommodation types that will be required to support additional numbers and establish
calculated estimates of additional area. These areas have then been fed into a high-level
cost model to establish appropriate works rates and provide an outturn Order of Magnitude
capital cost. A copy of the feasibility cost model completed by cost advisors Randall
Simmonds can be found within Appendix 3. The table below summarises the calculated
development areas, works type, ‘Order of Magnitude’ capital cost and comparative position
against the baseline ‘do minimum’ option:
Site Area Works Type OoM Capital Cost
Ashlands 170m2 Refurb / Reconfiguration £379,000
Greenfylde 2700m2 New Build £7,300.000
Maiden Beech 865m2 Refurb / Reconfiguration £2,109,000
Wadham* 1000m2 New Build £3,180,000
Junior Schools Additional Age Range Changes £37,000
Total Scenario Cost £12,985,000
Total Baseline Cost: £9,197,000
*Costed based on New Build Option due to risks associated with condition of potential identified reconfiguration area
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 76 of 137
10.3.2. This option requires development across 4 sites as opposed to 3 under the ‘do minimum’
baseline taking into account the internal reconfiguration works associated with age change
requirements at Maiden Beech.
10.4. Scenario 4 - Building Condition
10.4.1. There is potential scope for the closure of up to 3 existing school sites under this scenario
meaning an opportunity to improve upon the baseline position; where all buildings will need
to be retained and any remedial and repair works associated with the age and condition of
the buildings addressed as they arise going forward.
10.4.2. Site rationalisation / disposal opportunities and condition improvement cost avoidance
10.4.3. As outlined above this scenario has scope for site rationalisation and disposal
opportunities, beyond the assumed change of Greenfylde site, with 2 additional existing
first/ primary sites and 1 middle school site identified for potential closure. The table below
indicates the current known building condition status for each of the identified opportunity
sites to give an indication of the potential scale of benefits (in terms of future maintenance
needs):
Site Rationalisation / Disposal Opportunity
Building Condition
RAG rating
Notes / Comments
Haselbury Plucknett Potential Closure of 2 sites – as over required numbers for Infant provision.
Amber / Green
Hinton St George Amber
Misterton Amber / Red
Shepton Beauchamp Red / Amber
St Mary and St Peter’s Unknown** Temporary Buildings
Merriott
Sites to be retained
Amber
St Bartholomew’s Amber / Green
Ashlands Amber
Greenfylde* New Site Green
Swanmead Potential Closure Amber / Red Poorest condition of existing middle/upper sites
Maiden Beech Sites to be retained Amber / Green
Wadham Sites to be retained Amber
*Greenfylde is modelled above on basis of new replacement site. The disposal opportunity arising from old site (Red / Amber condition
status) is assumed to be available to the Local Authority / relevant Education Trust as part of proposal.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 77 of 137
**Unknown building condition status (not captured ESFA Property Data Survey) - site comprised entirely of temporary buildings.
10.5. Scenario 4A - Revenue Impact
10.5.1. A detailed summary of Financial impact assessment is included within in Appendix 4, the
information below is an extract of the key comments and differentiating factors identified
relevant to the specific Scenario under review, as has contributed to the options appraisal
evaluation:
Option Estimate of Lump Sum Costs
Variation from Baseline (Potential saving)
Year One Saving
Grant Lump sum (PE / Sports premium etc)
Variation from Baseline (potential saving)
Overall Revenue Saving to Public Purse
1A Baseline
£1,320,000 N/A N/A £192,000 N/A N/A
Option 4A £1,210,000 (£110,000) (£16,500) £176,000 (£16,000) (£126,000)
10.5.2. Funding Implications
10.5.2.1. This option would deliver a saving on lumpsum costs, but it will be for the DfE -
funding into Somerset will reduce in line with formula saving.
10.5.2.2. The additional lump sum payment in the year following amalgamation would
contribute to the cost of change.
10.5.2.3. Further net savings could be achieved through amalgamation of primary schools
with multiple site provision retained. The saving on the lump sum would fall to
the DfE, with some doubt over whether any increased costs for a split site
payment would be funded.
10.5.3. Other Financial Implications
10.5.3.1. Development of an area-based multi-academy trust would build on existing
federations and allow for further improvements in cost-effectiveness and
efficiency without the loss of funding associated with school closure or the extra
cost associated with split-site provision.
10.5.4. Financial Risks
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 78 of 137
10.5.4.1. It is not clear if the expectation of 85% of lumpsum saving passing to the newly
amalgamated schools in year one would be at a cost to the DfE or Somerset
DSG.
10.5.4.2. It is not clear if any additional split site costs would be funded by the DfE, and if
funded there may be a lag of one year and/or an application process.
10.5.4.3. The larger secondary school in this option brings increased resilience and
viability.
10.5.5. Curriculum Efficiency
10.5.5.1. This option achieves a better score than the baseline position due to the improved
curriculum efficiency in secondary provision.
10.6. Scenario 4A - Education and Staffing Impact
10.6.1. A detailed Education and Staffing Impact review is included within Appendix 5, the
information below is an extract of the key comments and factors identified as relevant to
the specific Scenario under review, as has contributed to the options appraisal evaluation.
10.6.2. For this option, the relevant assessment models were Primary, Infant and Junior and
Secondary and the summary is split between the three areas accordingly.
10.6.3. Key findings of Primary assessment:
▪ The advantages / disadvantages of a primary model are different and more directly
correlated with the size of school rather than comparison of first or infant / junior
models however there can be greater consistency of approach to teaching and
learning, curriculum planning and behaviour management, and reduced potential for
repetition /misalignment of approaches when continuing from ages 4 to 11 in one
phase.
▪ Primary schools of small student numbers (particularly where retaining schools with
less than 100 students) with multi-age classes is considered challenging, in terms of
being able to stretch and challenge students when covering multiple curriculum
elements in class and with difficulties associated with staff recruitment and retention
and limitations on career progression.
▪ Larger primary schools with a larger staff body will benefit from greater access to
and retention of specialist staff and expertise with more opportunities for wider
curriculum and associated enrichment opportunities. Increased opportunities for
school leaders to focus on leadership and strategic improvement.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 79 of 137
10.6.4. Key findings of Infant / Junior assessment:
▪ Overall size of school is the predominant factor with many of the key considerations
and arguments very similar or the same as those outlined above under Primary
model.
▪ Splitting the year groups into infant and junior and reducing the years in any one
school to 3 or 4 gives increased opportunity in the smallest retained schools to
separate year groups to dedicated classrooms and reduce the probability of mixed
age classes.
▪ Reduced opportunity with separation of younger and older pupils for observing /
example setting between age ranges.
▪ Dedicated infant schools could benefit from increased age specific resources,
elements like outdoor play can be particularly focused, and younger pupils have the
opportunity for taking on responsibilities.
▪ Dedicated junior schools again could benefit from set up specifically for age group,
different ways of organising may be possible. Staff have increased opportunity to
discuss teaching approaches peer to peer and workload can be better spread with
headteacher having other to support them. TAs can be shared and used more
effectively.
10.6.5. Key findings of Secondary assessment:
▪ Research indicates that the optimal size for a secondary school, where performance
is optimised is evidenced to be in the order of ~1000 pupils.
▪ Small / smaller secondary will not be able to offer the breadth of choice in KS4 that
a larger one can, as seen in review of comparable sized secondary sized schools in
Somerset. The smaller the school the less likely students are to have access to
specialist staff with increased challenges in recruiting and retaining staff and
covering all subjects with specialists, more part time staff may be needed or teachers
having to teach more than 1 subject.
▪ A review of recent Government Capacity UD1 data (covering 3376 schools across
the country designated with secondary pupils) showed that less than 1% of
secondaries existed of very small size (less than 350 pupils). It would be considered
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 80 of 137
highly unusual to create one and it is not recommended to be used for secondary
(11 – 16) provision.
▪ Increased size in secondary provision can provide greater support and opportunities
for both students and staff, with a larger staff body allowing a full and balanced
curriculum supported by the appropriate specialist staff / subject expertise to stretch
and challenge all pupils. Larger school sizes provide greater resilience and flexibility
in how staff are deployed.
10.6.6. Scenario 4A as a hybrid model proposes to have 3 consolidated primary schools ranging
from smaller 1FE entry 210 pupil size to 3 FE 640 pupil size, and a split of infant and junior
schools across the existing first school sites (3 larger junior schools at over 100 pupils and
in the order of 5 infant schools with less than 100 pupils). This option is considered to
increase educational benefit from the current system, but with limitations on application at
a primary level through the retention of multiple small school sites.
10.6.7. With one single site secondary school providing all the required capacity at 1103 pupils
secondary provision is considered to be optimised.
10.7. Scenario 4A - Sports / Extra-curricular / SEND and Wrap Around Care
10.7.1. Impact or opportunities for improvement in these areas were found to also largely correlate
with size of schools proposed under the scenario, on the following basis:
▪ There are more opportunities in larger schools for team sports and for participating
in tournaments and competitive games. Training and specialist knowledge is also
more likely to be apparent in larger schools.
▪ There is likely to be increased range of additional other extra-curricular activities,
such as music and drama in larger schools, where staffing time and expertise are
available.
▪ A larger school has the opportunity to deploy TAs in more creative way and can
support more pupils – they also have an advantage in training opportunities as TAs
can specialise in certain approaches, i.e. ELSA. Smaller schools probably have
more limited opportunities in how they use Pupil Premium funding because they
have fewer staff to utilise.
▪ Wrap around care provision (before and after school clubs etc) is largely generated
by the school and parent demand and not confined to a particular type of school or
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 81 of 137
model – it could therefore be offered to equivalent standard in any provision, but with
greater opportunity to expand or increase financial sustainability at a larger school
where there is increased numbers and potential increased demand.
10.7.2. Option 4A with the hybrid implementation is considered to have scope to increase
opportunities and advantages of economies of scale in these areas but with heavy
limitations on application at a primary level through the retention of multiple small school
sites.
10.8. Scenario 4A - Transitions
10.8.1. The hybrid implementation under Option 4A means that pupils within the area will have
different pathways and different numbers of transition points. The majority will transition
directly from primary to secondary education after Year 6, meaning a change to optimal
position of only move, however a proportion will retain a 2 transition need from infant to
junior to secondary (effectively the same as the current status quo but undertaken at a
different age).
10.9. Scenario 4A - Pre-school and Nursery
10.9.1. This option carries risk of potential detrimental impact upon pre-school nursery provision
with the potential for loss of up to 2 nursery sites. 1 is definitely affected by the potential
closure of Swanmead; with the potential for another arising from small school closures.
This would need careful consideration and mitigation planning if this option were to
progress.
10.10. Scenario 4A - Transport and Geography
10.10.1. Option 4A is illustrated on an overview map included within Appendix 2 of this report titled
‘Option 4A Overview’ – it shows the proposed spread of educational places delivered under
a two-tier structure using a mixture of consolidated primary schools and split site infant and
junior schools. Secondary education is from a single secondary school site.
10.10.2. With a reduction from 12 to potentially 9 schools and changes in year groups patterns there
will be transport implications for some pupils and families, but this is more limited in scope
than under the previous Option 3.
10.10.3. The key points of note are:
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 82 of 137
▪ There remains a good split of primary capacity across both Crewkerne and lIminster
with consolidated primaries in both locations, however with the closure of Swanmead
under this option there will be less primary capacity in Ilminster and more students
and families travelling to locations nearer Crewkerne.
▪ With the majority of small existing first schools retained the position for many
families in infant years (Reception and Yrs. 1 and 2) will be the same as now with
local provision in place; there will however be a requirement to make an earlier
transition across to Junior school site under this split site model. These moves would
all be 5 miles or less with the exception of St Mary and St Peter’s (~8 miles from
nearest Junior site).
▪ There is opportunity to potentially close two of the smaller sites (incorporating
students into the consolidated primaries) and travel distances and geographic
locations could be a consideration factor.
▪ As previously described there will no longer be provision for Years 7 and 8 within the
Ilminster area as these become part of the secondary provision delivered from
Crewkerne. The longest travel distance from primary to secondary will be 9 miles,
which is equivalent to the current move from Swanmead Middle to Wadham Upper,
the transition is just happening earlier in line with primary / secondary model. Travel
distances at this transition point will be less overall under this option with the split
site junior schools already nearer to Crewkerne.
▪ The equivalent Yr. 7 and 8 pupils will move 1 mile from Maiden Beech to Wadham.
▪ With closure of smaller more rural schools there will be lost opportunity to walk to
school from village locations, but this will affect only 2 potential sites in this instance.
With the closure of Swanmead there will be a reduction in numbers of students that
can potentially access on foot within the Ilminster area. There will be increased
opportunity within the Crewkerne Hub.
10.11. Scenario 4A - Equality and Community Impacts
10.11.1. Significantly, this option could see the closure of two existing rurally-located first / primary
schools (not identified at this point in time), with a slight geographical shift towards
Crewkerne. However, the opportunity within this option to further review which primary /
first schools to retain / close means that Option 4A could offer reduced negative equalities
impact in relation to Options 3B and 4D and generally sees a slightly increased negative
impact in relation to the status quo.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 83 of 137
10.11.2. In particular, equalities impact assessments will need to ensure that impacts on the
following protected characteristics are understood and mitigated:
10.11.3. Religion and Belief - Proportion of Church Schools
10.11.3.1. Due to the high proportion of existing Diocese Schools in the area (8 of the 9
existing First / Primary Schools are Diocese Schools), option 4A is likely to see a
slight reduction in the number of Diocese schools across the region and a reduced
geographical spread. However, the proposals see consolidated Diocesan Primary
provision available in Ilminster (Greenfylde) alongside a range of Diocese Infants,
Junior and Primary Schools in Crewkerne, supported by a Diocese Secondary
School.
10.11.4. Rurality - Rural and Village Schools and Communities
10.11.4.1. This option proposes the closure of two First / Primary Schools across the region.
As the majority of the outlying smaller schools are considered to be designated as
‘rural schools’, a detailed impact assessment would need to ensure that any
significant impact on the community is understood and mitigated where possible.,
and that the schools selected for closure lead to increased benefits and reduced
negative equalities impact. The removal of schools from any of these village areas
could impact on community facilities and cohesion, although currently there is no
significant community use noted for these schools.
10.11.4.2. This option offers a better Equalities outcome than that of Options 3B and 4D due
to the fact that less school closures are proposed and there is some flexibility within
the proposals.
10.11.4.3. The closure of 2 Primary / First Schools means that travel times for pupils and
families (for those with an onward journey to works) in these areas are likely to be
increased and therefore proposals would need to consider the availability of
transport links etc in order to mitigate any impact. However, in comparison to
Options 3B and 4D, the reduced number of closures will lead to reduced negative
impact.
10.11.4.4. Likewise, the impact on nursery provision (which can impact on a family’s ability to
work and child development) in rural areas would be reduced in relation to Options
3B and 4D due to the reduced number of site closures associated with Early Years
provision. Future Early Years growth, demand and provision is outside of the scope
of this Feasibility Study, but further assessment will be required in order to ensure
that sufficient alternative provision is available as required and that any negative
impact on rural families is mitigated.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 84 of 137
10.11.5. Race - Minority Communities
10.11.5.1. Should St Mary and St Peter’s school be identified for closure under this option,
further assessment would be required in order to mitigate any impact on the
Travelling Community. However, this option provides the opportunity to review
provision in the area to ensure that there is still a school within an acceptable travel
distance for Travelling Communities and as such, offers a reduced negative impact
in relation to Options 3B and 4D
10.11.5.2. At this stage, no other negative impact on race has been noted in relation to the
other schools proposed for closure, but further assessment will be required at
feasibility stage
10.11.6. Disability – Accessibility
10.11.6.1. The closure of two small village schools and the associated refurbishment of other
existing sites, may positively impact on the ability of schools across the region to
accommodate pupils and staff with disabilities, but it should be noted that the
refurbishment of existing building stock may limit accessibility in some cases.
10.11.7. Low income
10.11.7.1. Utilising the percentage of children eligible for Free School Meals as a deprivation
indicator (see Part 3 for details for each school), the majority of schools impacted
on by this option demonstrate a level of deprivation below the national average,
with the exception of St Mary and St Peter’s (17.1%)2 and Ashlands (19.2%)2.
10.11.7.2. The impact on low income families should be considered when selecting which of
the two First / Primary schools to close and as such, there is opportunity to mitigate
negative impact.
10.11.7.3. Ashlands (19.2%)2 site is proposed to be developed under this option and therefore
the investment in the site may impact positively on low income families within this
area.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 85 of 137
10.12. Scenario 4D - Specifics:
10.12.1. Scenario 4D summarises the following actions anticipated to be required to deliver a
solution utilising separate split site infant and junior schools (catering for 3 and 4 Year
groups respectively) across all of primary provision:
▪ Expand numbers at Ashlands school site to cater for 180 pupils at Infant Years
utilising existing vacated accommodation. A block has been identified on site,
following closure of the former Children’s Centre – with the potential to be
reconfigured to house the additional classroom required to take total to 6 and deliver
optimal 30 pupil classes.
▪ Expand numbers at Greenfylde’s school, based on the relocation and expansion to
alternative SCC site and a change of provision to a 5FE Junior School. The required
classroom total is 20, equivalent to the 4FE First school as outlined in existing
feasibility study provided by the Local Authority.
▪ Utilise the existing capacity at Swanmead to accommodate Infant age pupils. The
school building area is of sufficient size requiring an element of internal
reconfiguration and refurbishment only to ensure the facilities appropriate to younger
pupils.
▪ Utilise the existing capacity at Maiden Beech to accommodate Junior age pupils.
The school building area is of sufficient size requiring an element of internal
reconfiguration and refurbishment only to ensure the correct functions and facilities
appropriate to revised age range.
▪ Utilise the larger remaining first sites of Merriott and St Bartholomew’s to provide the
remaining required infant provision.
▪ Capacity at the smaller existing first sites is not required – there is the potential to
close 5 existing first /primary school sites under this option.
▪ Expand numbers at Wadham through delivery of a new accommodation block to
accommodate the full requirement of 1103 secondary students as a sole site facility
– this is comfortably feasible within the site constraints with potential identified site
areas. Wadham also has an overprovision of accommodation in some areas
meaning it may be feasible to realise some, or all, of the additional places through
internal reconfiguration.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 86 of 137
10.13. Scenario 4D - Capital Cost
10.13.1. Each site (with the exception of Greenfylde where there is an existing costed feasibility
study) has been analysed using the relevant BB103 SoA tools to identify area shortfalls
and accommodation types that will be required to support additional numbers and establish
calculated estimates of additional area. These areas have then been fed into a high-level
cost model to establish appropriate works rates and provide an outturn Order of Magnitude
capital cost. A copy of the feasibility cost model completed by cost advisors Randall
Simmonds can be found within Appendix 3. The table below summarises the calculated
development areas, works type, ‘Order of Magnitude’ capital cost and comparative position
against the baseline ‘do minimum’ option:
Site Area Works Type OoM Capital Cost
Ashlands 170m2 Refurb / Reconfiguration £379,000
Greenfylde 2700m2 New Build £7,300.000
Swanmead 158m2 Refurb / Reconfiguration £505,000
Maiden Beech 221m2 Refurb / Reconfiguration £691,000
Wadham* 1000m2 New Build £3,180,000
Infant Schools Age Range SoA Changes £26,000
Total Scenario Cost £12,061,000
Total Baseline Cost: £9,197,000
*Costed based on New Build Option due to risks associated with condition of potential identified reconfiguration area
10.13.2. This option requires development across 5 sites as opposed to 3 under the ‘do minimum’
baseline taking into account the internal reconfiguration works associated with age change
requirements at Swanmead and Maiden Beech sites.
10.14. Scenario 4D - Building Condition
10.14.1. There is potential scope for the closure of 5 existing school sites under this scenario
meaning a sizable opportunity to improve upon the baseline position; where all buildings
will need to be retained and any remedial and repair works associated with the age and
condition of the buildings addressed as they arise going forward.
10.14.2. Site rationalisation / disposal opportunities and condition improvement cost avoidance
10.14.3. As outlined above this scenario has scope for site rationalisation and disposal
opportunities, beyond the assumed change of Greenfylde site, with 5 additional existing
first/ primary sites identified for potential closure. The table below indicates the current
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 87 of 137
known building condition status for each of the identified opportunity sites to give an
indication of the potential scale of benefits (in terms of future maintenance needs):
Site Rationalisation / Disposal Opportunity
Building Condition
RAG rating
Notes / Comments
Haselbury Plucknett Potential Closure Amber / Green
Hinton St George Potential Closure Amber
Misterton Potential Closure Amber / Red
Shepton Beauchamp Potential Closure Red / Amber
St Mary and St Peter’s Potential Closure Unknown** Temporary Buildings
Merriott
Sites to be retained
Amber
St Bartholomew’s Amber / Green
Ashlands Amber
Greenfylde* New Site Green
Swanmead Amber / Red
Maiden Beech Amber / Green
Wadham Amber
*Greenfylde is modelled above on basis of new replacement site. The disposal opportunity arising from old site (Red / Amber condition
status) is assumed to be available to the Local Authority / relevant Education Trust as part of proposal.
**Unknown building condition status (not captured ESFA Property Data Survey) - site comprised entirely of temporary buildings.
10.15. Scenario 4D - Revenue Impact
10.15.1. A detailed summary of Financial impact assessment is included within in Appendix 4, the
information below is an extract of the key comments and differentiating factors identified
relevant to the specific Scenario under review, as has contributed to the options appraisal
evaluation:
Option Estimate of Lump Sum Costs
Variation from Baseline (Potential saving)
Year One Saving
Grant Lump sum (PE / Sports premium etc)
Variation from Baseline (potential saving)
Overall Revenue Saving to Public Purse
1A Baseline
£1,320,000 N/A N/A £192,000 N/A N/A
Option 4D £770,000 (£550,000) (£82,500) £112,000 (£80,000) (£630,000)
10.15.2. Funding Implications
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 88 of 137
10.15.2.1. This option would deliver a significant saving on lumpsum costs, but it will be for
the DfE - funding into Somerset will reduce in line with formula saving.
10.15.2.2. The additional lump sum payment in the year following amalgamation would
contribute to the cost of change.
10.15.3. Other Financial Implications
10.15.3.1. This option represents a large reduction in DSG and grant funding coming into
Somerset and the Crewkerne and Ilminster area. Assuming that significant
savings could be realised through reductions in premises and administrative
costs, the saving is still likely to translate to a reduction in the number of teachers.
Whilst this will mainly affect leadership posts, if the saving is broadly proportionate
to school spending generally, it could be assumed that this would translate to a
reduction of 4 to 6 teachers.
10.15.3.2. This option also reflects a large reduction in specific grant for PE and Sports,
which may be mitigated by more efficient provision in larger schools.
10.15.4. Financial Risks
10.15.4.1. It is not clear if the expectation of 85% of lumpsum saving passing to the newly
amalgamated schools in year one would be at a cost to the DfE or Somerset
DSG.
10.15.4.2. The larger schools in this option bring increased resilience and viability.
10.15.5. Curriculum Efficiency
10.15.5.1. This option achieves the highest weighted curriculum efficiency metric due to the
medium to large primary provision and cost-effective secondary provision size.
10.16. Education and Staffing Impact
10.16.1. A detailed Education and Staffing Impact review is included within Appendix 5, the
information below is an extract of the key comments and factors identified as relevant to
the specific Scenario under review, as has contributed to the options appraisal evaluation.
10.16.2. For this scenario, the relevant assessment models were Infant and Junior and Secondary
– the key findings and considerations are the same as captured under 4A above and can
be found in sections 10.6.4 and 10.6.5.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 89 of 137
10.16.3. Scenario 4D as an Infant and Junior model proposes to have 6 schools provide all of the
required primary capacity, split between 2 medium / large junior schools (600 and 420)
and 4 infant schools ranging from smaller 1FE entry 90 pupil size to larger 4 FE 360 pupil
size. This option is considered to increase educational benefit from the current system and
represent a mid-point between current first and consolidated primary systems.
10.16.4. With one single site secondary school providing all the required capacity at 1103 pupils,
secondary provision is considered to be optimised.
10.17. Sports / Extra-curricular / SEND and Wrap Around Care
10.17.1. The key considerations re Impact or opportunities are the same as captured under 4A
above and can be found in section 10.7.1.
10.17.2. Option 4D with proposed infant and junior structure is considered to have greater scope to
increase opportunities and advantages of economies of scale in these areas and represent
a mid-point between current first and consolidated primary systems.
10.18. Transitions
10.18.1. Option 4D proposes that all pupils will transition from infant to junior to secondary school
requiring two transitions. The transition points would be at different years to the current
three-tier structure but would be the same in number as under the current provision.
10.19. Pre-school and Nursery
10.19.1. This option carries risk of potential detrimental impact upon pre-school nursery provision
with potentially 2 of the existing 5 nurseries on existing small school sites that are indicated
for potential closure. This would need careful consideration and mitigation planning if this
option were to progress.
10.20. Transport and Geography
10.20.1. Option 4D is illustrated on an overview map included within Appendix 2 of this report titled
‘Option 4D Overview’ – it shows the proposed spread of educational places delivered
under a two-tier structure using a split site infant and junior schools across the region.
Secondary education is from a single secondary school site.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 90 of 137
10.20.2. With a reduction from 12 to potentially 7 schools and changes in year groups patterns there
will be transport implications for some pupils and families, this is more limited in scope than
under the Option 3 as affects the very smallest school sites only.
10.20.3. The key points of note are:
▪ There remains a good split of primary capacity across both Crewkerne and lIminster
with infant and junior provisions in both locations, with overall primary capacity in the
Ilminster area increased from that proposed under option 4A.
▪ All moves resulting from the closure of the 5 smallest existing first / primary school
sites require moves of under 5 miles.
▪ There will however be a requirement to make an earlier transition across to Junior
school sites under this split site model. These moves would all be 5 miles or less
with the majority transferring within a distance of a mile or less.
▪ As under the previously described two-tier options there will no longer be provision
for Years 7 and 8 within the Ilminster area as these become part of the secondary
provision delivered from Crewkerne. The longest travel distance from primary to
secondary will be 9 miles, which is equivalent to the current move from Swanmead
Middle to Wadham Upper, with the split very similar to how it works currently under
middle school system, just happening earlier in line with primary / secondary
transition model.
▪ The equivalent Yr. 7 and 8 pupils will move 1 mile from Maiden Beech to Wadham.
▪ With closure of smaller more rural schools (5 in this instance) there will be lost
opportunity to walk to school from village locations. Opportunity to walk to school
within Ilminster hub will be very similar to the baseline model with overall student
places largely the same just in a different age configuration. There will be increased
opportunity within the Crewkerne Hub.
10.21. Scenario 4D Equality and Community Impacts
10.21.1. Due to the proposed level of closure of Primary / First Schools under this option, the
negative impact is similar to that of Option 3B and sees a negative impact in relation to the
existing status quo, largely due to the number of planned school closures across the
region. In particular leading to impact on the following protected characteristics:
10.21.2. Religion and Belief - Proportion of Church Schools
10.21.3. Due to the high proportion of existing Diocese Schools in the area (8 of the
9 existing First / Primary Schools are Diocese Schools), option 4D would see a reduction
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 91 of 137
in the number of Diocese schools across the region and a reduced geographical spread.
The proposals include the provision of a Diocese Junior School (Greenfylde) in Ilminster,
with the remainder of the Infants and Junior and Secondary Diocese provision shifting
geographically towards Crewkerne. This may negatively impact on parental choice due to
the reduced availability and spread of Diocesan provision in the Ilminster area, although
Crewkerne would remain largely unaffected.
10.21.4. Rurality - Rural and Village Schools and Communities
10.21.4.1. The majority of proposed schools for closure are considered to be designated as
‘rural schools’ and as such, a detailed impact assessment would need to ensure
that any significant impact on the community is understood and mitigated where
possible. The removal of schools from these areas could impact on community
facilities and cohesion, although currently there is no significant community use
noted for these schools.
10.21.4.2. Travel times for pupils and families (for those with an onward journey to works) are
likely to be increased and therefore proposals would need to consider the
availability of transport links etc in order to mitigate any impact.
10.21.4.3. A number of the schools have associated Pre-School / Nursery provision which
may be impacted should the school sites close. A lack of Early Years provision can
impact on the ability of rural families to work and can also have a negative impact
on a child’s Early Years development. A proportion of this Early Years provision is
delivered from school premises with the majority being run independently from the
school, although a small number are under school control. Future Early Years
growth, demand and provision is outside of the scope of this Feasibility Study, but
further assessment will be required in order to ensure that sufficient alternative
provision is available and that any negative impact on rural families is mitigated.
10.21.5. Race - Minority Communities
10.21.5.1. St Mary and St Peter’s School is proposed for closure under this option. It has been
noted that a number of children from the Travelling Community attend the school
and therefore further assessment will be required in order to understand and
mitigate any negative impact on this community.
10.21.5.2. At this stage, no other negative impact on race has been noted in relation to the
other schools proposed for closure, but further assessment will be required at
feasibility stage.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 92 of 137
10.21.6. Disability – Accessibility
10.21.6.1. A number of schools proposed for closure under this option are Victorian village
schools which are limited in terms of possible disability adaptations. A move to a
more centralised two-tier provision in a smaller number of refurbished buildings,
may positively impact on the ability of schools across the region to accommodate
pupils and staff with disabilities, but it should be noted that the refurbishment of
existing building stock may limit accessibility in some cases.
10.21.7. Low income
10.21.7.1. Utilising the percentage of children eligible for Free School Meals as a deprivation
indicator (see Part 3 for details for each school), the majority of schools earmarked
for closure under this proposal demonstrate a level of deprivation lower than the
national average, with the exception of St Mary and St Peter’s (17.1%)2 and
Ashlands (19.2%)2.
10.21.7.2. Ashlands site is proposed to be developed under this option and therefore the
investment in the site may impact positively on low income families within this area.
However further assessment will be required to ensure that any impact on low
income families attending St Mary and St Peter’s is recognised and mitigated.
11. Scenario Testing – Option 5
11.1. Option 5 – Summary & Key Findings
11.1.1. Option 5 represents a hybrid 2/ three-tier system looking specifically at options to retain
the existing first school structure but amalgamate middle and upper years into one
consolidated educational phase; taking into account projected requirements for growth to
meet school population forecast and additional housing development demands.
Consolidated in this instance meaning that every viable ‘combined middle and upper site’
must be able to support the full 7 middle and upper year groups (Yr. 5 to Yr. 11) in one
location; separation of those year groups across sites would default the position back to
the existing separate middle and upper structure as covered under the 1A do minimum
scenario.
11.1.2. The overall pupil numbers required and splits across first, middle and upper phases are
the same as outlined previously under Option 1A and the proposal to deal with the
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 93 of 137
additional places required in first schools remains the same. The key change is a new
target number to be delivered from combined middle and upper pupil totals. The table
below summarises the current student numbers (as at SPF population baseline 2018), the
assessed existing capacity with the 12 Crewkerne & Ilminster schools (based on SCC
SCAP data and existing school site accommodation analysis), and the projected required
student numbers for the area mapped against hybrid combined two / three-tier splits:
Current NoR Existing
Capacity Projected Required Number
Uplift beyond current capacity
First Schools 998 1044 1317 Uplift of 273
Middle Schools 683 840 1585 Overall uplift of 30 pupils
(Middle yrs + 84, Upper yrs –114)
Upper School 450 775
Total 2131 2659 2902
11.1.3. Analysis of combined middle/ upper school provision and site options can be summarised
as follows:
11.1.4. All three potential middle/ upper sites were assessed against government guidance BB103
building and site standards to establish their potential for expansion and any limitations on
growth arising from site constraints. Analysis (summarised below) shows that whilst all
sites have the potential for some viable expansion, both Swanmead and Maiden Beech
have student number limits that would preclude them from delivering places for all 1585
students and being a sole combined middle/ upper school site. Wadham was found to have
sufficient expansion space to potentially support that model. If existing middle schools are
to contribute to combined middle/upper capacity then that would need to be under a multi-
site model.
11.1.5. Analysis of Swanmead estate shows that whilst there is scope to accommodate limited
building expansion on site, with a site area of 30,764m2 ~420 students is the maximum
that the site can hold before breaching BB guidance on site space standards per pupil (in
terms of external learning, play and sports spaces etc).
▪ Maiden Beech has more development space and a larger site area of 52,352m2 with
~ 840 students being the calculated maximum that the site can hold before breaching
BB guidance on site space standards per pupil (in terms of external learning, play
and sports spaces etc).
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 94 of 137
▪ Wadham has a very large site at 119,000m2 and considerable scope for expansion
with viable BB101 compliant building and site solutions demonstrated for up to ~
1600 students.
11.1.6. With all three schools potentially required to change the number of year groups they would
teach (from 3 or 4 to 7 for combined middle and upper years) it is also important to consider
how capacity numbers (existing and future) benchmark against optimal increments of 30
students to ensure that proposals are efficient and workable without necessitating
additional classes / teachers or mixed groups etc and that movements of existing student
numbers can be accommodated as part of any potential transition.
Site Constraints Swanmead
Max 420
Maiden Beech
Max 840
Wadham
Max ~1600
Expansion Increments - based on 7 year groups (5 - 11) and optimal classes of 30 students where possible
210 420 630 840 1050 1260 1470 1585
Required combined Middle/ Upper Number: 1585
11.1.7. This position with regard to site constraints mirrors very closely the considerations and
analysis outlined previously in relation to secondary education (see section 10.1.6 under
Option 4) and leads to essentially the same conclusions – the key differences / nuances
are highlighted below.
11.1.8. Swanmead is still limited to maximum of 420 students by the identified site constraints – in
this instance with the capacity split over 7 year groups and the number of students in each
year, particularly KS4 reduced, the concerns with regards to educational impact are further
heightened and it is not considered a recommended viable option.
11.1.9. With Swanmead unable to support a viable combined middle/ upper provision even as a
multi-site (2 or 3 site option), this leaves two alternatives: Maiden Beech and Wadham as
a two site combined middle / upper school arrangement or Wadham as a sole combined
middle/ upper school. These options are both feasible and are presented accordingly as
the best representation of viable scenarios under this option – summarised below as
Scenarios 5C and 5D.
11.1.10. The total number of combined middle/upper students is anticipated to be 1585 equivalent
to one large ‘secondary / school’ facility. Assessment indicates that a combined middle/
upper provision would be most efficiently delivered and likely derive the most educational
and financial benefits as a single / sole site solution – and it should be noted that the two
sites feasible as a multi-site option are located geographically within 1 mile of each other
in Crewkerne, which means there is potentially negligible benefit to multi locations in terms
of catchments and travel distances across the wider region.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 95 of 137
11.2. Scenario 5C specifics:
11.2.1. Scenario 5C summarises the following actions anticipated to be required to retain the
existing first school structure accommodating growth, and amalgamate middle and upper
years into one consolidated educational phase through 2 combined middle/upper schools;
▪ Expand First numbers at Ashlands school site utilising existing vacated
accommodation. A block has been identified on site, following closure of the former
Children’s Centre – with the potential to be reconfigured to house 2 additional
classrooms.
▪ Expand First numbers at Greenfylde’s school, based on the relocation and
expansion to alternative SCC site – as outlined in existing feasibility study provided
by the Local Authority. With expansion options very limited on smaller sites this
relocation and expansion is critical to realising the required numbers.
▪ Utilise existing capacity at Wadham to accommodate combined middle and upper
year groups.
▪ Expand Maiden Beech to ~810 places to accommodate the remaining required
numbers of middle and upper year students – this is comfortably feasible within the
site constraints.
▪ Existing capacity at Swanmead is surplus to requirement. Under this option there
would be the potential for closure of that site.
11.3. Scenario 5C - Capital Cost
11.3.1. Each site (with the exception of Greenfylde where there is an existing costed feasibility
study) has been analysed using the relevant BB103 SoA tools to identify area shortfalls
and accommodation types that will be required to support additional numbers and establish
calculated estimates of additional area. These areas have then been fed into a high-level
cost model to establish appropriate works rates and provide an outturn Order of Magnitude
capital cost. A copy of the feasibility cost model completed by cost advisors Randall
Simmonds can be found within Appendix 3. The table below summarises the calculated
development areas, works type, ‘Order of Magnitude’ capital cost and comparative position
against the baseline ‘do minimum’ option:
Site Area Works Type OoM Capital Cost
Ashlands 170m2 Refurb / Reconfiguration £379,000
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 96 of 137
Greenfylde 2700m2 New Build £7,300.000
Maiden Beech 2000m2 New Build £5,938,000
Wadham 180m2 Reconfiguration – Age change works
£288,000
Total Scenario Cost £13,885,000
Total Baseline Cost: £9,197,000
11.3.2. This option requires development across 4 sites as opposed to 3 under the ‘do minimum’
baseline taking into account the internal reconfiguration works associated with age change
requirements at Wadham to convert excess specialist rooms for general Year 5 and 6
teaching.
11.4. Option 5C - Building Condition
11.4.1. There is potential scope for the closure of 1 existing school site under this scenario
meaning an opportunity to improve upon the baseline position; where all buildings will need
to be retained and any remedial and repair works associated with the age and condition of
the buildings addressed as they arise going forward.
11.4.2. Site rationalisation / disposal opportunities and condition improvement cost avoidance
11.4.3. As outlined above this scenario has scope for site rationalisation and disposal
opportunities, beyond the assumed change of Greenfylde site, with 1 additional existing
middle school site identified for potential closure. The table below indicates the current
known building condition status for each of the identified opportunity sites to give an
indication of the potential scale of benefits (in terms of future maintenance needs):
Site Rationalisation / Disposal Opportunity
Building Condition
RAG rating
Notes / Comments
Haselbury Plucknett Sites to be retained Amber / Green
Hinton St George Amber
Misterton Amber / Red
Shepton Beauchamp Red / Amber
St Mary and St Peter’s Unknown** Temporary Buildings
Merriott Amber
St Bartholomew’s Amber / Green
Ashlands Amber
Greenfylde* New Site Green
Swanmead Potential Closure Amber / Red Poorest condition of existing middle/upper sites
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 97 of 137
Maiden Beech Sites to be retained Amber / Green
Wadham Sites to be retained Amber
*Greenfylde is modelled above on basis of new replacement site. The disposal opportunity arising from old site (Red / Amber condition
status) is assumed to be available to the Local Authority / relevant Education Trust as part of proposal.
**Unknown building condition status (not captured ESFA Property Data Survey) - site comprised entirely of temporary buildings.
11.5. Scenario 5C - Revenue Impact
11.5.1. A detailed summary of Financial impact assessment is included within in Appendix 4, the
information below is an extract of the key comments and differentiating factors identified
relevant to the specific Scenario under review, as has contributed to the options appraisal
evaluation:
Option Estimate of Lump Sum Costs
Variation from Baseline (Potential saving)
Year One Saving
Grant Lump sum (PE / Sports premium etc)
Variation from Baseline (potential saving)
Overall Revenue Saving to Public Purse
1A Baseline
£1,320,000 N/A N/A £192,000 N/A N/A
Option 5C £1,210,000 (£110,000) (£16,500) £176,000 (£16,000) (£126,000)
11.5.2. Funding Implications
11.5.2.1. This option would deliver a saving on lumpsum costs, but it will be for the DfE -
funding into Somerset will reduce in line with formula saving.
11.5.2.2. The additional lump sum payment in the year following amalgamation would
contribute to the cost of change.
11.5.2.3. Further net savings could be achieved through amalgamation of first schools with
multiple site provision retained. The saving on the lump sum would fall to the
DfE, with some doubt over whether any increased costs for a split site payment
would be funded.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 98 of 137
11.5.3. Other Financial Implications
11.5.3.1. Development of an area-based multi-academy trust would build on existing
federations and allow for further improvements in cost-effectiveness and
efficiency without the loss of funding associated with school closure or the extra
cost associated with split-site provision.
11.5.4. Financial Risks
11.5.4.1. It is not clear if the expectation of 85% of lumpsum saving passing to the newly
amalgamated schools in year one would be at a cost to the DfE or Somerset
DSG.
11.5.4.2. It is not clear if any additional split site costs would be funded by the DfE, and if
funded there may be a lag of one year and/or an application process.
11.5.5. Curriculum Efficiency
11.5.5.1. Benchmark data for 9-16 schools is not available and so the combined
middle/upper combination is treated as a secondary school for this assessment.
11.5.5.2. Two modest sized middle/upper schools contribute to a reduced curriculum
efficiency score, but this could be enhanced through combining the schools and
delivering provision across two sites, facilitating sharing of leadership, support
staff and specialist teachers.
11.6. Scenario 5C - Education and Staffing Impact
11.6.1. A detailed Education and Staffing Impact review is included within Appendix 5, the
information below is an extract of the key comments and factors identified as relevant to
the specific Scenario under review, as has contributed to the options appraisal evaluation.
11.6.2. For this option, the relevant assessment model was All through 9 – 16 schools (with first
school structure to be retained as is).
11.6.3. This option shares many similarities with Secondary assessment, but has additional
distinct features and considerations:
▪ Research indicates that the optimal size for a secondary school, where performance
is optimised, is evidenced to be in the order of ~1000 pupils and that small / smaller
sized schools will not be able to offer the breadth of choice in KS4 that a larger one
can. Under the all through 9 – 16 model where 7 year groups are being taught within
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 99 of 137
one school, school sizes need to be larger in order to retain the same / equivalent
size year groups.
▪ The smaller the school teaching KS4 and the smaller the year group(s) the less likely
students are to have access to specialist staff with increased challenges in recruiting
and retaining staff and covering all subjects with specialists, more part time staff may
be needed or teachers having to teach more than 1 subject. Small school sizes are
not recommended for secondary provision and the reservations that would apply
equally here would be even more exaggerated / critical with increased age ranges.
▪ Increased school sizes for all through 9 - 16 models (in addition to ensuring year
group sizes are not detrimentally impacted) can provide greater support and
opportunities for both students and staff, with a larger staff body allowing a full and
balanced curriculum supported by the appropriate specialist staff / subject expertise
to stretch and challenge all pupils. Larger school sizes provide greater resilience and
flexibility in how staff are deployed, and potentially provides more career progression
opportunities without having to move school.
▪ There would be greater opportunities for staff to collaborate to ensure the curriculum
progresses logically, for development of an all-through pedagogy, and to plan
together for cross phase learning.
▪ Such an all through system could present challenges in terms of how to split the
curriculum plan between primary and secondary and the need for collaborative
working to ensure senior leaders understand and give appropriate credit and
recognition to all aspects of both primary and secondary expertise.
11.6.4. This hybrid two / three-tier scenario proposes to retain first schools as modelled under 1A
with no change, it is the change from existing separate middle and upper schools to
combined all through 9 – 16 only that is being assessed. This option proposes that this
combined middle / upper provision will be from 2 school sites each of medium size (~800
pupils).
11.6.5. This option is considered to increase educational benefit from the current system, through
the consolidation of the middle and upper years and associated benefits but is seen as
limited by the associated reservations about the size of proposed schools. As the first
school position remains the same as baseline position and it is effectively only the middle/
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 100 of 137
upper student element that can derive improvement this option scores less for educational
benefit than the optimal two-tier system.
11.7. Scenario 5C - Sports / Extra-curricular / SEND and Wrap Around Care
11.7.1. Impact or opportunities for improvement in these areas are still seen to correlate with size
of schools proposed under the scenario, on the following basis:
▪ There are more opportunities in larger schools for team sports and for participating
in tournaments and competitive games. Training and specialist knowledge is also
more likely to be apparent in larger schools.
▪ There is likely to be increased range of additional other extra-curricular activities,
such as music and drama in larger schools, where staffing time and expertise are
available.
▪ A larger school has the opportunity to deploy TAs in more creative way and can
support more pupils – they also have an advantage in training opportunities as TAs
can specialise in certain approaches, i.e. ELSA. Smaller schools probably have more
limited opportunities in how they use Pupil Premium funding because they have
fewer staff to utilise.
▪ Wrap around care provision (before and after school clubs etc) is largely generated
by the school and parent demand and not confined to a particular type of school or
model – it could therefore be offered to equivalent standard in any provision, but with
greater opportunity to expand or increase financial sustainability at a larger school
where there is increased numbers and potential increased demand.
11.7.2. This option is considered to have scope to increase opportunities and advantages of
economies of scale in these areas within the middle/ upper age ranges but with heavy
limitations on application at a first level through the retention of multiple small school sites.
11.8. Scenario 5C - Transitions
11.8.1. This scenario proposes that all pupils will transition directly from first to combined middle /
upper or all though 9 – 16 education after Year 4, this means a reduction to optimal position
of only one transition, which could provide greater continuity for the more vulnerable
(reducing anxiety for some students) and minimise impact associated with poor transition.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 101 of 137
This is effectively the same as the optimal scenario under the two-tier system, but with
transitions happening at a younger age during ‘primary’ years.
11.9. Scenario 5C - Pre-school and Nursery
11.9.1. This option carries risk of potential detrimental impact upon pre-school nursery provision
with the potential closure of Swanmead. This would be the only nursery location potentially
affected with all the smaller sites with nurseries effectively to be retained. This would need
careful consideration and mitigation planning if this option were to progress.
11.10. Scenario 5C - Transport and Geography
11.10.1. Option 5C is illustrated on an overview map included within Appendix 2 of this report titled
‘Option 5C Overview’ – it shows the proposed spread of educational places delivered
under the hybrid two / three tier system, with existing first schools retained and middle and
upper year combined into one consolidated education phase. In this scenario this
combined middle/upper capacity is over 2 site locations.
11.10.2. This option shows a reduction from 12 to potentially 11 schools with the closure of 1 middle
school site to support consolidated upper/middle model – with all first schools retained
impacts on geography and travel are limited to middle year (Yr. 5 – Yr. 8) students only.
11.10.3. The key points of note are:
▪ Provision of first year education remains the same with no change from 1A
▪ The required uplift in first school numbers is based on area need – with the vast
majority of additional first school places delivered via the Greenfylde expansion there
may be families in new housing areas having to travel from further afield as local
provision will be full.
▪ With the combined upper/ middle site locations both located in Crewkerne there will
no longer be provision for middle year students (Yrs. 5 – 8) within the Ilminster area.
This is a fairly significant change meaning increased travel distances for pupils at St
Mary and St Peter’s*, Shepton Beauchamp*, Greenfylde – and those transferring
from Swanmead prior to closure (*Primary sites may transition later at Yr. 7, if remain
as primaries). The longest travel distance from first / primary* to combined middle/
upper will be 10, with the majority in the region of 8 /9 miles. That is equivalent to
the current move from Swanmead Middle to Wadham Upper but would now be
happening earlier within primary years. All distances are within specified travel times
for Primary age students.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 102 of 137
▪ With the closure of Swanmead there will be a reduction in numbers of students that
can potentially access on foot within the Ilminster area. There will be increased
opportunity within the Crewkerne Hub.
11.11. Scenario 5C - Equality and Community Impacts
11.11.1. Due to the limited changes of this option in terms of school closures / adjustments to
educational structure, the negative equality impact is reduced in relation to Options 3B, 4A
and 4D, and remain more or less neutral in relation to the current status quo.
11.11.2. Religion and Belief - Proportion of Church Schools
11.11.2.1. There are no planned closures to Diocese schools within this option, and
therefore no impact on the proportion or geographical spread of church schools
across the region.
11.11.3. Rurality - Rural and Village Schools and Communities
11.11.3.1. The only closure proposed under this option is to Swanmead School, which is not
one of the more rurally isolated village schools, and as such – it is considered that
there would be no significant impact on rural schools and communities.
11.11.4. Race - Minority Communities
11.11.4.1. As above, as the only closure proposed is to Swanmead School, it is considered
that there would be no significant negative impact on minority communities under
this proposal, although further assessment will be required to ensure that travel
distances to middle and upper school provision is acceptable for the Travelling
Community.
11.11.5. Disability – Accessibility
11.11.5.1. The planned refurbishments under this option are likely to positively impact on
the ability of schools across the region to accommodate pupils and staff with
disabilities, but it should be noted that the refurbishment of existing building stock
may limit accessibility in some cases.
11.11.6. Low income
11.11.6.1. There is no expected impact on low income families under this option
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 103 of 137
11.12. Scenario 5D - Specifics:
11.12.1. Scenario 5D summarises the following actions anticipated to be required to retain the
existing first school structure accommodating growth, and amalgamate middle and upper
years into one consolidated educational phase at one sole middle/upper school site;
▪ Expand First numbers at Ashlands school site utilising existing vacated
accommodation. A block has been identified on site, following closure of the former
Children’s Centre – with the potential to be reconfigured to house 2 additional
classrooms.
▪ Expand First numbers at Greenfylde’s school, based on the relocation and
expansion to alternative SCC site – as outlined in existing feasibility study provided
by the Local Authority. With expansion options very limited on smaller sites this
relocation and expansion is critical to realising the required numbers.
▪ Expand numbers at Wadham through delivery of new accommodation to meet the
full requirement of 1585 combined middle/ upper year students as a sole site facility
– this is feasible within the site constraints with potential identified site areas.
▪ Existing capacity at Swanmead is surplus to requirement. Under this option there
would be the potential for closure of that site.
▪ Existing capacity at Maiden Beech is surplus to requirement. Under this option there
would be the potential for closure of that site.
11.13. Scenario 5D - Capital Cost
11.13.1. Each site (with the exception of Greenfylde where there is an existing costed feasibility
study) has been analysed using the relevant BB103 SoA tools to identify area shortfalls
and accommodation types that will be required to support additional numbers and establish
calculated estimates of additional area. These areas have then been fed into a high-level
cost model to establish appropriate works rates and provide an outturn Order of Magnitude
capital cost. A copy of the feasibility cost model completed by cost advisors Randall
Simmonds can be found within Appendix 3. The table below summarises the calculated
development areas, works type, ‘Order of Magnitude’ capital cost and comparative position
against the baseline ‘do minimum’ option:
Site Area Works Type OoM Capital Cost
Ashlands 170m2 Refurb / Reconfiguration £379,000
Greenfylde 2700m2 New Build £7,300.000
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 104 of 137
Wadham 2700m2 New Build £8,544,000
Total Scenario Cost £16,203,000
Total Baseline Cost £9,197,000
11.13.2. This option requires development across 3 sites the same as proposed under the ‘do
minimum’ baseline.
11.14. Scenario 5D - Building Condition
11.14.1. There is potential scope for the closure of 2 existing school sites under this scenario
meaning an opportunity to improve upon the baseline position; where all buildings will need
to be retained and any remedial and repair works associated with the age and condition of
the buildings addressed as they arise going forward.
11.14.2. Site rationalisation / disposal opportunities and condition improvement cost avoidance
11.14.3. As outlined above this scenario has scope for site rationalisation and disposal
opportunities, beyond the assumed change of Greenfylde site, with 2 additional existing
middle school sites identified for potential closure. The table below indicates the current
known building condition status for each of the identified opportunity sites to give an
indication of the potential scale of benefits (in terms of future maintenance needs):
Site Rationalisation / Disposal Opportunity
Building Condition
RAG rating
Notes / Comments
Haselbury Plucknett Sites to be retained Amber / Green
Hinton St George Amber
Misterton Amber / Red
Shepton Beauchamp Red / Amber
St Mary and St Peter’s Unknown** Temporary Buildings
Merriott Amber
St Bartholomew’s Amber / Green
Ashlands Amber
Greenfylde* New Site Green
Swanmead Potential Closure Amber / Red Poorest condition of existing middle/upper sites
Maiden Beech Potential Closure Amber / Green
Wadham Sites to be retained Amber
*Greenfylde is modelled above on basis of new replacement site. The disposal opportunity arising from old site (Red / Amber condition
status) is assumed to be available to the Local Authority / relevant Education Trust as part of proposal.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 105 of 137
**Unknown building condition status (not captured ESFA Property Data Survey) - site comprised entirely of temporary buildings.
11.15. Scenario 5D - Revenue Impact
11.15.1. A detailed summary of Financial impact assessment is included within in Appendix 4, the
information below is an extract of the key comments and differentiating factors identified
relevant to the specific Scenario under review, as has contributed to the options appraisal
evaluation:
Option Estimate of Lump Sum Costs
Variation from Baseline (Potential saving)
Year One Saving
Grant Lump sum (PE / Sports premium etc)
Variation from Baseline (potential saving)
Overall Revenue Saving to Public Purse
1A Baseline
£1,320,000 N/A N/A £192,000 N/A N/A
Option 5D £1,110,000 (£220,000) (£33,000) £160,000 (£32,000) (£252,000)
11.15.2. Funding Implications
11.15.2.1. This option would deliver a saving on lumpsum costs, but it will be for the DfE -
funding into Somerset will reduce in line with formula saving.
11.15.2.2. The additional lump sum payment in the year following amalgamation would
contribute to the cost of change.
11.15.2.3. Further net savings could be achieved through amalgamation of first school
provision with multiple site provision retained. The saving on the lump sum would
fall to the DfE, with some doubt over whether any increased costs for a split site
payment would be funded.
11.15.3. Other Financial Implications
11.15.3.1. Development of an area-based multi-academy trust would build on existing
federations and allow for further improvements in cost-effectiveness and
efficiency without the loss of funding associated with school closure or the extra
cost associated with split-site provision.
11.15.3.2. A multi-academy trust with a large middle/upper school and feeder first schools
provides a configuration that easily allows for centralised administrative functions
and specialist support for additional and high needs as well as wider early
intervention and family support. The benefits also accrue in the case of a hub
within a larger MAT.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 106 of 137
11.15.3.3. These potential financial benefits are offset by the reduction of funding into the
area, with resultant loss of educational staff and funding for PE, though there may
be some mitigation by more efficient provision in larger schools.
11.15.4. Financial Risks
11.15.4.1. It is not clear if the expectation of 85% of lumpsum saving passing to the newly
amalgamated schools in year one would be at a cost to the DfE or Somerset
DSG.
11.15.4.2. It is not clear if any additional split site costs would be funded by the DfE, and if
funded there may be a lag of one year and/or an application process.
11.15.4.3. The large middle/upper school in this option brings increased resilience and
viability.
11.15.5. Curriculum Efficiency
11.15.5.1. Benchmark data for 9-16 schools is not available and so the combined
middle/upper combination is treated as a secondary school for this assessment.
11.15.5.2. The single large middle/upper school delivers the prospect of enhanced
curriculum efficiency.
11.16. Scenario 5D - Education and Staffing Impact
11.16.1. A detailed Education and Staffing Impact review is included within Appendix 5, the
information below is an extract of the key comments and factors identified as relevant to
the specific Scenario under review, as has contributed to the options appraisal evaluation.
11.16.2. For this option, the relevant assessment model was All through 9 – 16 schools (with first
school structure to be retained as is) – the key findings and considerations are the same
as captured under 5C above and can be found in section 11.6.3.
11.16.3. This hybrid two / three-tier scenario proposes to retain first schools as modelled under 1A
with no change, it is the change from existing separate middle and upper schools to
combined all through 9 – 16 only that is being assessed. This option proposes that this
combined middle / upper provision will be delivered from one sole site, a large combined
school of ~ 1585 pupils.
11.16.4. This option is considered to increase educational benefit from the current system and
optimise the educational benefits across the middle and upper years by optimising school
size. As the first school position remains the same as baseline position and it is effectively
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 107 of 137
only the middle/ upper student element that can derive improvement this option scores
less for educational benefit than the optimal two tier system, but is the highest scoring
option under hybrid two / three-tier systems where the first school structure is maintained.
11.17. Scenario 5D - Sports / Extra-curricular / SEND and Wrap Around Care
11.17.1. The key considerations re Impact or opportunities are the same as captured under 5C
above and can be found in section 11.7.
11.17.2. Option 5D is considered to have the greater scope to increase opportunities and
advantages of economies of scale in these areas by further consolidating associated staff
and funding through one larger combined middle/ upper school.
11.18. Scenario 5D - Transitions
11.18.1. This scenario is effectively the same as 5C in terms of transitions and proposes that all
pupils will transition directly from first to combined middle / upper or all though 9 – 16
education after Year 4. This means a reduction to optimal position of only one transition,
which could provide greater continuity for the more vulnerable (reducing anxiety for some
students) and minimise impact associated with poor transition. This is effectively the same
as the optimal scenario under the two-tier system, but with transitions happening at a
younger age during ‘primary’ years.
11.19. Scenario 5D - Pre-school and Nursery
11.19.1. This option carries risk of potential detrimental impact upon pre-school nursery provision
with the potential closure of Swanmead. This would be the only nursery location potentially
affected with all the smaller sites with nurseries effectively to be retained. This would need
careful consideration and mitigation planning if this option were to progress.
11.20. Scenario 5D - Transport and Geography
11.20.1. Scenario 5D is illustrated on an overview map included within Appendix 2 of this report
titled ‘Option 5D Overview’ – it shows the proposed spread of educational places delivered
under the hybrid two / three-tier system, with existing first schools retained and middle and
upper year combined into one consolidated education phase. In this scenario this
combined middle/upper capacity is on one sole site location at Wadham.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 108 of 137
11.20.2. The options show a reduction from 12 to potentially 10 schools with the closure of 2 middle
school site to support consolidated upper/middle model – with all first schools retained
impacts on geography and travel are limited to middle year (Yr. 5 – Yr. 8) students only.
11.20.3. With Maiden Beech and Wadham sites only 1 mile away from each other Option 5D is
essentially exactly the same as summarised under Option 5C above – see section 11.10.
There will still be increased opportunity overall to walk to school within the Crewkerne Hub,
but that arrangement will change slightly with all the capacity centred in one location within
the town.
11.21. Scenario 5D - Equality and Community Impacts
11.21.1. Due to the limited changes of this option in terms of school closures, the negative equality
impact is reduced in relation to Options 3B, 4A and 4D, and remain more or less neutral in
relation to the current status quo. However, further assessment will be required in terms of
travel distances to the consolidated Middle / Upper School provision.
11.21.2. Religion and Belief - Proportion of Church Schools]
11.21.2.1. There are no planned closures to Diocese schools within this option, and
therefore no impact on the proportion or geographical spread of church schools
across the region.
11.21.3. Rurality - Rural and Village Schools and Communities
11.21.3.1. The only closure proposed under this option is to Swanmead School, which is not
one of the more rurally isolated village schools, and as such – it is considered that
there would be no significant impact on rural schools and communities.
11.21.4. Race - Minority Communities
11.21.4.1. As above, as the only closure proposed is to Swanmead School, it is considered
that there would be no significant negative impact on minority communities under
this proposal, although further assessment will be required to ensure that travel
distances to middle and upper school provision is acceptable for the Travelling
Community
11.21.5. Disability – Accessibility
11.21.5.1. The planned refurbishments under this option are likely to positively impact on
the ability of schools across the region to accommodate pupils and staff with
disabilities, but it should be noted that the refurbishment of existing building stock
may limit accessibility in some cases.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 109 of 137
11.21.6. Low Income
11.21.6.1. There is no expected impact on low income families under this option.
12. Most Viable Options
12.1.1. A detailed options appraisal has been completed in accordance with the evaluation
methodology and weighting outlined in Section 6 of this report and can be found within
Appendix 6.
12.1.2. The appraisal document includes assessment notes and associated score sheets for each
of the agreed criterion and an overarching summary sheet indicating both the raw and
weighted scores for each of the presented scenarios. The table below provides a summary
of the outturn scores for each scenario against the 7 key measures:
12.1.3. The scores indicate that Scenario 3B, proposing a consolidated system of 5 larger primary
and secondary schools, is the strongest or most beneficial viable option ahead of Scenario
4D, the later again constituting a two-tier system model but split into consolidated infant,
junior and secondary schools. It was the strongest scoring option for positive improvement
across both revenue finance and educational and staffing impact assessment, scoring a
mid-range position in terms of required Capital expenditure.
12.1.4. It should be noted that Capital or Project Cost is presented as a negative in all instances
as all alternative models have cost estimates above the £9.17m outlined at baseline,
requiring varying degrees of additional Capital to expedite the proposed expansion,
restructure and age range changes required.
12.1.5. Transport, Equalities and Community also all present as neutral or negative positions. The
current educational model is very ‘localised’ with schools spread widely across the region,
within village settings as well as larger population hubs - all options to consolidate or
produce improved educational and / or financial benefit from optimal school sizes and
economies of scale therefore have the potential to worsen these measures.
Scenario 1A Scenario 2 Scenario 3B Scenario 4A Scenario 4D Scenario 5C Scenario 5D
Project Cost 0.000 0.000 -0.400 -0.200 -0.200 -0.400 -0.600
Finance Revenue 0.000 0.063 0.375 0.313 0.375 0.188 0.313
Education 0.000 0.000 0.458 0.167 0.208 0.250 0.375
Staffing 0.000 0.000 0.450 0.150 0.300 0.150 0.300
Transport 0.000 0.000 -0.075 -0.050 -0.075 -0.150 -0.150
Equalities 0.000 0.000 -0.100 -0.050 -0.100 0.000 0.000
Community 0.000 0.000 -0.125 -0.100 -0.100 -0.100 -0.125
Total 0.000 0.063 0.583 0.229 0.408 -0.063 0.113
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 110 of 137
12.1.6. Whilst Option 3B is the highest scoring under the agreed all round evaluation, it is important
to look at the strongest options against each of the key weighted criteria. Options 3B and
4D as highlighted above were tied as the strongest in terms of revenue assessment but
were closely followed by both options 4A and 5D; hybrid two-tier and three-tier models
respectively.
12.1.7. In terms of educational and staffing impact, Option 3B was the optimal model with Option
5D to retain existing first schools and move to one consolidate upper / middle all through
9 – 16 school in a strong second position. The key conclusion within this area of
assessment was that the staffing and educational opportunities that a school can offer
depends far more on the size of the school than the age phases or tier system it operates
within, and that the older the pupils within the school the more important that becomes in
terms of being able to offer a diverse range of options with access to staff that can
specialise in that subject. This is reflected within the scoring pattern, with education and
staffing showing the most potential for positive improvement where there are larger school
sizes, particularly as secondary or all through 9 – 16 phases.
12.1.8. A graphical summary is included below which illustrates the positive and negative aspects
of the scoring process and strongest and weakest scenarios under each of the key areas.
You can see within each option how the strengths are offset by the potential costs and
detrimental impacts on factors such as travel and equality and community.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 111 of 137
12.1.9. This synopsis of most viable options is illustrating the findings of the scored evaluation
against the presented options, however, as highlighted through-out this report we
understand there are many additional complexities and considerations that may impact
upon both appetite and ability to pursue these presented courses of action.
12.1.10. We have taken the key findings through into the summary of conclusion and
recommendations (see section 14) and overlaid these wider factors, such as MAT
landscape, Academisation, LA and Diocese control of the estate to try and distil the key
decisions that need to be made to ascertain the preferred option(s) to progress for further
feasibility study.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 112 of 137
13. Project & Programme Management (Live Project)
13.1. Overview
13.1.1. The scale and scope of programme / project management and the required governance
structure will be determined by the scale and scope of required activities identified through
the outcome of the Strategic Review. The following recommendations are appropriate for
a complex programme of work involving multiple users, stakeholders and projects.
However, this approach can be scaled down appropriately to suit the recommended
programme of activities.
13.1.2. Recognising the complexities involved in implementing any recommended change to the
Crewkerne and Ilminster education structure, it is imperative that robust programme and
project management structures are wrapped around any identified programme of activities,
irrespective of the scale of proposed activities.
13.1.3. Progress against the objectives and benefits of the programme / projects will need to be
closely monitored whilst balancing the interests of multiple stakeholders within tightly
constrained financial and programming requirements.
13.1.4. In order to streamline activity and utilise existing expertise and specialisms, the programme
will be developed around a number of defined programme workstreams including
Governance, Legal (including HR and Recruitment), Finance, Education Change
Management, ICT, Communications and Estates.
13.1.5. The use of accepted industry standard Prince / MSP methodologies will allow progress to
be monitored against cost, quality, scope, timescale, risk and benefit realisation, whilst
ensuring communications and decision-making processes are clear and well-defined.
13.2. Governance
13.2.1. Working on the assumption that the outcome of the Strategic Review is for a number of
projects to be taken forward, a strong Governance structure will be required to maintain
focus on the delivery of programme objectives and to ensure that there is a clear and
transparent governance and decision-making process which acknowledges the interests
of the multiple stakeholder groups. It is important that from the outset, the sensitivity around
any conflicting stakeholder interests and the changing Trust landscape, is recognised and
addressed within the governance model.
13.2.2. ‘Terms of Reference’ should be agreed which clearly define roles and responsibilities,
accountabilities, management and reporting arrangements and the scheme of delegation
for each tier of the governance model.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 113 of 137
13.2.3. Working on the assumption that the Strategic Review will outline a number of projects to
take forward, it is recommended that the Programme be managed under the following
indicative Governance structure, with details to be defined once programme activities and
key roles and responsibilities are agreed:
13.2.4. The Terms of Reference for each tier of the Governance model will clearly define the roles,
responsibilities and accountability of individuals and of the group as a whole. Whilst the
detail will be determined once the outcome of the review and therefore the scope and scale
of activities is known, a typical programme management model is recommended as
follows:
Strategic Programme Board
Programme Steering Group
Project Board 1
Project 1
(e.g. School 1 redevelopment)
Project Board 2
Project 2
(e.g. Schools 2 & 3 organisational
change)
LAB Chairs Group
School 1 School 2 School 3 etc...
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 114 of 137
• Responsible For
• Overall alignment of programme with strategic direction
• Overarching programme authority
• Financial decisions
• Assurance Reviews
• Members
• Senior Responsible Owner
• Executive Leadership Team
• Executive Stakeholders
Strategic Programme
Board
•Responsible For:
• Driving programme activity forwards to deliver outcomes and benefits
•Members:
• Senior Responsible Owner
• Programme Manager
• Business Change manager
• Project Executives (LAB, school, community, Diocese & Diocese representatives)
• Workstream leads (Finance, HR, Risk, Corporate Property etc)
Programme Steering Group
• Responsible For:
• Driving project activity forwards to deliver outcomes and benefits, aligned to programme requirements
• Members:
• Chair
• Project Manager
• Stakeholder Representatives
• School Representatives
Project Boards
(As required)
• Responsible For:
• Representing interests of Local Advisory Boards and liaising with Project Board / Steering Group as required
•Members
• Nominated Chair
•LAB Chairs
Local Advisory Board Chairs
Group
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 115 of 137
13.3. Change Management
13.3.1. Alongside robust programme and project management, recognised frameworks (such as
MSP, Prince etc) recommend that ‘Business Change’ management is embedded within
the Programme Management function for any programme that involves ‘Transformational
Change’ to an existing business / structure. The role of the Business Change Manager is
to work both at Programme level and with each affected organisation throughout
development and delivery of programme of activities, acting as the link between the
Programme and the operational / business element of the schools. This ensures that the
proposed changes are deliverable in terms of operational and business requirements.
13.3.2. The Business Change Manager’s role is to work closely with schools / stakeholders to
ensure that any required changes to operational delivery (triggered by the programme) are
understood, supported and embedded by all parties, enabling multiple schools and
stakeholders to adapt business models, operational models, behaviours etc as required in
order to deliver the desired Programme objectives.
13.4. Programme
13.4.1. An indicative programme has been developed based on initial discussions and guidance
from the Local Authority (see Appendix 8).
13.4.2. The scale of any transformational change and capital works required could range vastly
depending on the Preferred option chosen, ranging from some minor refurbishments to a
rolling programme of site adjustments across the area. This would lead to a programme of
co-dependent but individual projects across various sites and organisations, that sit under
an overarching programme structure. Therefore, the programme will need to be further
developed and refined once a Preferred option has been identified.
13.4.3. At this stage, the indicative programme has been developed on the following staged basis:
▪ Stage 0 – Desktop Review and Masterplanning:
Stage 0 dates are reflective of the current programme position and estimated dates
for the SCC decision making process.
This Stage is designed to provide SCC with the sufficient information to decide
whether to move forwards to more detailed feasibility studies for any Preferred
Option/s, incorporating:
▪ Desktop reviews of individual school and area-wide capacity, basic need and
growth projection figures and estates condition information, in order to
establish feasible Masterplan options.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 116 of 137
▪ Scenario testing and evaluation of various Masterplan options including
impact on capital cost, staffing, school revenue, education, transport,
equalities and community.
▪ Production of Strategic Review for submission to SCC and Regional Schools
Commissioner.
▪ Decision to proceed to Feasibility
▪ Stage 1 – Feasibility
Stage 1 dates are reflective of the current programme position, plus estimated
timescales for the SCC decision making process and recommended timescales for
consultation periods, incorporating:
▪ Detailed revenue and capital costing exercises for any preferred option/s –
including production of Business Case/s and final budget approval for each
project within the agreed programme funding envelope
▪ Consultation period
▪ Preferred Option Decision
▪ Statutory Notices – as required for any identified ‘Significant Change’
including (but not limited to) significant expansion or reduction of places and
or premises, change of age range, transfer to a new site or closure of a site.
▪ Stage 2 – Tender (Capital Projects)
Stage 2 reflects the required tender period for required capital projects required as
per the Preferred Option. It should be noted that timescales included in this stage
are indicative of a typical programme plan but may be reduced or lengthened
depending on the complexity of the Preferred Option.
This stage incorporates:
• Development of tender documentation for any required capital works
• Tender release and evaluation
• Planning consultation, fine tuning of design and cost plans
• Contract award.
▪ Stage 3 – Implementation
As a preferred option is not known, the implementation phases of the programme
have been developed on an indicative programme of rolling transformational change
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 117 of 137
and capital works, that can be scaled up or down depending on the outcome of the
Strategic Review and the chosen option to take forward to implementation.
Educational transformational change activities will be dependent on the scale of
organisational change, and may include (but not be limited to) TUPE, recruitment,
training, HR adjustments, transport requirements, changes to governance structure
13.4.4. The key programme stages are currently anticipated as follows:
Task Start Complete Notes
Stage 0 - Masterplanning
Masterplanning 01/04/19 17/05/19 Including estates, capital, revenue, education impact
Options Appraisal 20/05/19 31/05/19 Scoring, Report
SCC Sign off (Options Appraisal)
03/06/19 28/06/19
Stage 1 – Preferred Option(s) – Detailed Feasibility
Phase 1 Consultation 01/07/19 09/08/19 Schools, Key Education Stakeholders
Phase 2 Consultation 26/08/19 01/11/19 Schools, community, wider stakeholders
Consultation Feedback / Fine Tuning
04/11/19 08/11/19
Detailed Revenue Feasibility
01/07/19 27/09/19 To include TUPE, training, recruitment, transport, governance etc
Detailed Capital Feasibility 01/07/19 27/09/19 Detailed Affordability Review, Business Case Review etc
SCC Review / Approval 18/11/19 07/02/20
Statutory Notices 10/02/20 03/04/20 As required
Stage 2 – Invitation to Tender (for Construction – as Required)
Develop Tender Documentation
06/04/20 03/07/20 Appointments, tender documentation development
Tender Period (Part 1 & 2) 06/07/20 19/03/20 Design development, Preferred Contractor selection, planning consultation etc
Detailed Design to Contract Close
22/02/21 30/04/21 Inc contract signing
Stage 3 – Implementation - Indicative Rolling Programme of Works
Phase 1 Education Change Management
03/05/21 20/08/21 TUPE, training, recruitment, transport, governance etc
Phase 1 Construction 31/05/21 20/08/21 Indicative refurbishment works
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 118 of 137
Phase 2 Education Change Management
03/05/21 15/10/21 TUPE, training, recruitment, transport, governance etc
Phase 2 Construction 31/05/21 18/03/22 Indicative Greenfylde Project construction dates
Phase 3 Education Change Management
23/08/21 07/01/22 TUPE, training, recruitment, transport, governance etc
Phase 3 Construction 20/09/21 07/01/22 Indicative refurbishment works
13.5. Key consultation stages (depending on preferred / viable options)
13.5.1. Consultation
13.5.1.1. It is likely that a period of consultation will be required – the scale and scope of
which will be dependent on the preferred options identified as a result of the
Options appraisal
13.5.1.2. As such, the indicative programme currently includes the following allowances for
required consultations which have been split into 2 phases (see 5.5.1 – Future
Consultation for further detail on phasing and scope):
▪ Phase 1 - Informal Consultation, 1st July 2019 – 23rd August 2019
To include Headteachers and Chairs of Governors of 12 schools, Regional
School Commissioner and Representative of Dioceses of Bath and Wells
8 weeks allocated to incorporate meetings, feedback, review etc.
▪ Phase 2 – Formal Consultation, 26th August 2019 – 8th November 2019
To include (but not be limited to) Phase 1 Consultees, plus wider
educational and stakeholder groups, parents, communities, unions, local
MP etc.
11 weeks allocated to incorporate meetings, feedback, review, fine-tuning
and SCC sign-off
13.6. Risk Management
13.6.1. Working on the assumption that the outcome of this review will identify a number of
recommended Programme activities that will involve multiple stakeholders, it is imperative
that Risk and Issue Management is embedded within the Programme Management
function. This applies no matter what the scale and scope of works but becomes
increasingly important with the possible complexities of working with multiple organisations
and stakeholders. A clear strategy will need to be set out to determine roles and
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 119 of 137
responsibilities, reporting requirements and the agreed process of communicating risks
and issues that span between programme and project activities.
13.6.2. Risk and Issue management procedures should therefore be applied at programme and
project level by the respective Programme / Project Manager, in accordance with the
agreed strategy. A typical model sees Risks and Issues being reported within regular
Project Board and monthly Steering Group meetings. Each Risk or Issue is rated to
establish its severity and priority level. Risks and Issues are allocated an individual owner
and management plan to ensure that appropriate mitigation is put in place.
13.6.3. Top risks identified for the project following this early stage review are summarised below
with further detail provided within Appendix 9. The risk log focuses on residual risks for
consideration and mitigation as the programme moves forwards through next stages
(rather than risks associated with each individual options / scenario).
13.6.4. The highest level risks identified at programme level generally relate to the potential
imbalance of individual stakeholder priorities, regional requirements and the potential
inability of the Local Authority to take forward any preferred options due to the existing
complex multi-stakeholder landscape. The options appraisal highlights that whilst a
number of options appear to be more preferable in terms of sustainability across the region,
there will be a recognised impact on existing school / MAT structures and communities for
any of the options taken forward.
13.6.5. Due to the sensitivities around any proposed changes, there is a high risk that stakeholders
may feel disengaged or unfairly treated and that there will be a negative impact on cross-
organisation relationships and possible reputational damage, unless there is an extremely
strong communications strategy and governance structure embedded at the earliest
opportunity within the programme. Early stakeholder communication and consultation is
therefore imperative in order to reduce some of the identified high-level risks.
13.6.6. A robust Equalities Impact Assessment will be required in order to recognise and mitigate
against the equalities impact of any preferred option.
13.6.7. A number of the high-level risks identified at this stage will need to be explored further
during the feasibility stage, once SCC have identified either an option, or a number of
options to take forward. This will enable a clearer understanding of the possible impact of
the associated risks and required mitigation measures of each option, which will
subsequently feed into the final decision as to which option to take forward to
Implementation.
13.7. Stakeholder Engagement
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 120 of 137
13.7.1. A recognised theme of effective Project and Programme Management, is the requirement
for a strong Stakeholder Engagement Strategy and a clearly defined Communications Plan
which recognises multiple stakeholder needs. As the recommended outcome of this review
is likely to impact on multiple stakeholders, it is absolutely critical that key project
information flows between all parties at both Project and Programme levels (as required).
13.7.2. Whilst the Governance Structure will provide defined Schemes of Delegation and decision-
making processes / responsibilities, the Communications Plan and Stakeholder
Engagement Strategy will provide the template and structure for sharing information
between all parties.
13.7.3. Communications will be designed to keep Stakeholders informed, manage expectations,
set out clear timeframes for activities / decisions etc and provide continual updates on the
Programme rationale and expected outcomes.
14. Conclusions & Recommendations
14.1. Conclusions
14.1.1. This basis of this review has been that of a reasonably clinical, high-level appraisal of
strategic options for the delivery of an effective, efficient, viable and sustainable education
structure for the future within the Crewkerne and Ilminster area. The review will need to
be followed by more detailed stages of work to complete more detailed feasibility stage
assessments of Preferred Options to establish the scope of any change programme and
related projects.
14.1.2. During the process of this review it has been established that there has been a strong
national trend since the mid-1980’s for 3-tier school systems to move back towards 2-tier
structures (in varying forms). In the main this theme appears to have been largely driven
by changes to the National Curriculum and a drive for increased efficiency in curriculum
delivery. However, the 3-tier system continues to offer benefits and in particular within
rural areas. This said, it is important to note that the Department for Education and
Education & Skills Funding Agency offer little to no guidance for 3-tier school systems in
terms of estates and building or revenue funding. Building Bulletin and DfE National
Funding guidance is based on standardised two-tier and all-through school systems due
to the drive to maximise efficiency and effectiveness within the school system.
14.1.3. In addition, National Guidance does not encourage the development of new small schools
on the basis that these are less viable. For example, the Free School programme tends
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 121 of 137
to focus on a minimum school size of 80-100 (albeit recognising that the management of
such a school would present financial challenges from day one).
14.1.4. The DfE do however recognise the importance of existing small rural schools through the
Designation of Rural Primary Schools (England) Order 2018. This order recognises the
importance of rural primary schools (which are often small schools) within their local
communities, however does not go so far as offering any financial subsidy or protection to
such schools.
14.1.5. The review has also reinforced the complexity of the issue that Somerset County Council
are currently contending with in the Crewkerne and Ilminster area. Somerset County
Council currently hold the financial burden of the deficit budget at Wadham school but have
very limited ability to effect change to alter this situation. The current education landscape
and breadth of stakeholders within the education structure results in a lack of strategic
control to shape the structure for the future.
14.1.6. Throughout the review a number of key themes have established themselves due to the
intrinsic nature of their relationship to all proposals and the evaluation process. In
particular the following themes are important to note:
14.1.7. There is a strong relationship between the size of schools, efficiency of education delivery
and progress. In Somerset the available data appear to demonstrate an optimal school
size of c. 420 for Primary and 1,200 for Secondary phase of education. This information
appears to support the potential benefit of consolidating the school estate either physically
or structurally.
14.1.8. The optimum sizing of schools or groups of schools enables an efficiency in the delivery
of education against set budgets whilst offering an appropriate breadth of education. This
becomes increasingly important during the Secondary phase of education and especially
during Key Stage 4 where smaller schools typically offer significantly reduced options.
Optimally sized school can enable improved breadth and quality of staff, improved
continuity of curriculum and teaching and stronger contingency planning and staff
coverage. They also have the ability to better support wrap around care, sport and extra-
curricular activities.
14.1.9. In Crewkerne and Ilminster the Middle School capacity is also critical to the ability to meet
the overall demand for places. With these sites and buildings sitting literally in the ‘Middle’
of the education structure for the area the facilities are critical to the development of all
alternative scenarios. A key decision in all scenarios has been whether to retain these
schools or to invest in their use as part of a revised consolidated estate and education
structure. In the scenarios where their use is retained (and potentially extended) there are
insufficient pupils to then sustain a small (non-optimal) upper school serving only years 9-
11. In scenarios where the Middle School estate is put to alternative use in either
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 122 of 137
supporting the consolidation of Primary or Secondary schools’ significant cost is incurred
and due to the location of the sites, a displacement of pupil places also typically occurs.
As such there are some key decisions that arise for the Local Authority and other key
stakeholders to contemplate before moving forwards – these are outlined in more detail
later in this section of the report.
14.1.10. In assessing the relative impacts of each scenario on revenue funding it has been
important to note that the above statement of optimal school sizes also hold true. Whilst
the option of a change to formula funding initially appeared as a potential quick fix, it soon
became clear that this would in effect only result in a temporary relaxation of the increasing
deficit and would not have any impact on the quality or sustainability of education going
forwards.
14.1.11. Other scenarios identified a similar theme to the Education workstream, demonstrating that
optimal school sizing results in positive impacts on revenue budgets. The consolidation of
schools within a new education structure has the ability to result in greater efficiency of
curriculum delivery, however there is a considerable degree of uncertainty over who would
benefit from such consolidation in the medium to longer term future. It remains unclear as
to whether the Local Authority & Schools or the Department for Education would see the
greater benefit of such improvements. If the latter, then this may lead towards a false
benefit in that the overarching budget would be resized to reflect any amalgamation and
consolidation and therefore counter any realisation of financial benefits.
14.1.12. Similarly, should any options containing land disposals (consequential from school
closures) be considered, it is unclear as to which parties would benefit. With most schools
in scope being Voluntary Controlled Church of England Schools, it is understood that any
capital receipt would revert to the Diocese of Bath & Wells and therefore would not
necessarily benefit the overall project unless an alternative agreement could be reached.
14.1.13. The introduction of a MAT needs to be recognised as bringing a potentially significant
opportunity for improving the efficiency of revenue costs through the centralisation of core
school functions (e.g. HR, Procurement, IT, Estates, Finance etc). The central
management, scale of economy and wider buying power of a MAT model could add
significant benefits to the structure of schools if developed alongside the structural change.
14.1.14. It should be noted that this review focuses on a given set of assumptions that recognise
the potential of an incoming MAT, but do not factor it into the alternative education
structures at this stage. This overlaying of the MAT developments within this area of
Somerset add a further layer of complication to an already complicated picture. However,
if co-ordinated well between all key stakeholders there is the potential to overlay a positive
change that can bring increased efficiency and effectiveness to education delivery in the
area. It is important however that the structural design of education leads first and that the
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 123 of 137
benefits of a MAT are overlaid to complement this. There is a significant risk in a MAT
establishing a part-presence within the area should their strategic direction differ from
preferred alternative structures for the area. This difference of direction could serve to
further fracture education and compound challenges, making a long-term solution harder
to achieve. However, there could be a positive opportunity in working closely with a MAT
and wider stakeholders to enable an area-wide structure that serves all parties well.
Ultimately there has to be a careful balance here as the eventual structure has to remain
attractive to the MAT landscape moving forwards as otherwise the Crewkerne and
Ilminster area could become disenfranchised from the National education agenda.
14.1.15. Overall the review has identified a number of scenarios that could provide improved
viability and sustainability for the Crewkerne and Ilminster area schools, but no single
scenario or hybrid of scenarios is without the need for critical decisions to be taken by
stakeholders. Consideration needs to be given to the following:
i. The preferred solution for Secondary / combined Middle & Upper provision within the
area and the geographical impact that such a decision could have on Year 5 & 6
pupils (and proximity of their nearest school). As things currently stand projections
do not demonstrate the need for three Middle and Upper School sites across the
Crewkerne and Ilminster area.
ii. The preferred use of Middle School sites and whether these should continue to
provide Middle (deemed secondary) places or revert to provide Primary or
Secondary phase places under an alternative model. Any change to a viable two-tier
Primary / Secondary model is contingent upon the Middle school estate providing
Primary capacity. The Middle school estate offers the greatest opportunity to
consolidate and rationalise the wider school system within the Crewkerne and
Ilminster area.
iii. Potential implications of any closures of small rural schools in order to seek greater
efficiency in the school estate and therefore greater consolidation of places in fewer
sites (enabling optimisation of school sizes). Many of the First Schools sit below
current Free School viability guidelines and therefore add to the challenge of keeping
the school structure financially viable.
iv. The importance of Church and Voluntary Controlled schools within the Crewkerne
and Ilminster area and whether there is any scope for change to Governance
arrangements in order to facilitate alternative solutions. There is a risk that the
Voluntary Controlled estate and Church School status will limit the ability any
restructure of education within the Crewkerne and Ilminster area.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 124 of 137
14.1.16. The outcome of the above decisions will undoubtedly impact on the ability to carry forward
highest scoring scenarios or other hybrid solutions. Until there is clarity on whether parties
can work together to agree priorities the closest that this report can get is the presentation
of a range of viable solutions on a scale where some that have greater impact on the
existing school system (and potentially result in greater efficiency in delivery) and other
have a lesser impact on the existing system (with potentially lesser efficiency in delivery).
For example, the most controversial Scenario (3B&4D) proposes significant change to the
First and Middle School structure in order to achieve a vastly consolidated structure across
the area. This option demonstrates a reasonably clinical business driven approach that
reconciles the estate to the clinical need for places, resulting in a more negative impact on
various other factors such as Transport, Community, Equalities etc. However, without the
support of key stakeholders the option would not prove deliverable.
14.1.17. By contrast a debatably less disruptive scenario (4A) would also require key decisions on
the willingness to remove a Middle School from the system, resulting in a split-site Primary
model that keeps the majority of school sites open. Consequently, there is an impact on
community provision in Ilminster and the need to transport middle school students to
alternative sites in the area.
14.1.18. Without the support of key stakeholders progression of any option other than ‘baseline –
as is’ will most likely prove non-deliverable. A detailed cost / benefit analysis of ‘baseline
Scenario 1A’ against other options is recommended so the limitations and constraints of
proceeding with changes for natural growth only are fully understood, in terms of continued
impact on education provision (and potential future performance) and finances. All
proposed improvement scenarios require increased levels of capital expenditure and have
potential revenue cost associated with factors such as travel; this needs to be better
understood in relation to likely ongoing financial deficits and ‘do minimum’ capital funding
requirements.
14.1.19. Ultimately to move any proposed change forwards all Stakeholders need to be committed
to achieving a step change in the education structure for the Crewkerne and Ilminster area.
Due to the current structure no single party is able to act alone in instigating such a change.
Whilst the Local Authority is keen to drive change to achieve a sustainable and viable
structure for the future, it can only do so with the commitment of the schools, any incoming
MAT, the Diocese, the DfE and the RSC. In the event that any one of these parties were
to object or block such a change it would be extremely difficult to bring about a wholistic
longer term solution that can more effectively and efficiently serve the needs of the
Crewkerne and Ilminster are over and beyond the next decade.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 125 of 137
14.2. Recommendations
14.2.1. In order to progress the development of any viable option it is critical that all key
stakeholders work together to establish an agreed solution. At present there are significant
divisions within the area that will not facilitate a sustainable solution for the future of the
area. Appropriate review and feedback groups need to be established with all schools and
governing bodies to specifically review and consult on options, with the intention of moving
towards an agreed way forward and identifying which option(s) will be taken forward to a
strategic level group forum for further work, review and consultation. This group should
include representative(s) from each of the key stakeholder groups with delegated authority
to enter into dialogue on behalf of their stakeholder group.
14.2.2. Detailed dialogue should be entered into with the Diocese of Bath and Wells in relation to
the Voluntary Controlled Schools within the scope of this review. The Diocese control the
majority of the school estate in the area and therefore any proposals would require their
commitment and ownership. The willingness of the Diocese to work with the Local
Authority on the exploration of viable options will be critical to the deliverability of a solution.
14.2.3. Given the national education agenda and increasing move towards academisation within
the Crewkerne & Ilminster area it would be prudent to work with an incoming MAT to help
shape the area review in greater detail. A close strategic working relationship with A MAT
could enable added financial benefits to be gained for schools within the area. Overall it
would be beneficial to have a greater number of schools working closely with or placed
within a MAT to help gain added budget efficiencies and ensure continuity of working
across the area.
14.2.4. A further stage of detailed feasibility work is required on the Preferred Option(s) once
identified and agreed with the wider stakeholder group. This stage of work would seek to
add more detail to the following workstreams in order to establish a deliverable programme
structure with clear mandate and scope:
▪ Consultation with wider stakeholder group;
▪ Education and Estate Structure – development of reference scheme design(s);
▪ Capital Cost Plan – development of cost plan;
▪ Revenue budget – development of revenue budget plan;
▪ Change Management – development of change management plan that provides
route map and workstreams for moving from current to new solution;
▪ Related surveys and investigations to inform feasibility and consultation work;
▪ Formal consultation – preparation for formal consultation process.
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 126 of 137
Appendices
1. Baseline Information
2. Options Information
3. Capital Cost Modelling
4. Revenue Budgets
5. Education Impact
6. Options Appraisal
7. Consultation
8. Programme
9. Risk Register
10. Catchment Area Map
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 127 of 137
Appendix 1
Baseline Information
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 128 of 137
Appendix 2
Options Information
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 129 of 137
Appendix 3
Capital Cost Modelling
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 130 of 137
Appendix 4
Revenue Budgets
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 131 of 137
Appendix 5
Education Impact
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 132 of 137
Appendix 6
Options Appraisal
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 133 of 137
Appendix 7
Consultation
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 134 of 137
Appendix 8
Programme
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 135 of 137
Appendix 9
Risk Register
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 136 of 137
Appendix 10
Catchment Area Map
Futures for Somerset Ltd
Crewkerne & Ilminster Strategic School Review
Page 137 of 137