Corridor Management Planning in California

22
Corridor Management Planning in California Jeff X. Ban CCIT, UC-Berkeley Rensselaer Polytechnic Institute (RPI)

description

Corridor Management Planning in California. Jeff X. Ban CCIT, UC-Berkeley Rensselaer Polytechnic Institute (RPI). Overview. Motivation for CMP Demo Studies in California Challenging Issues Percentile-based Methods for Performance Assessment and Bottleneck Calibration - PowerPoint PPT Presentation

Transcript of Corridor Management Planning in California

Page 1: Corridor Management Planning in California

Corridor Management Planning in California

Jeff X. BanCCIT, UC-Berkeley

Rensselaer Polytechnic Institute (RPI)

Page 2: Corridor Management Planning in California

Overview

• Motivation for CMP

• Demo Studies in California

• Challenging Issues

• Percentile-based Methods for Performance Assessment and Bottleneck Calibration

• Current Progress and Expected Outcome

Page 3: Corridor Management Planning in California

The corridor system management plan is an evolving effort that is consistent with a maturing transportation system

Page 4: Corridor Management Planning in California

Motivation

• Problems of existing four-step planning process– Static– Can not evaluate various ITS strategies and some of

the operational improvements

• Proposed corridor management plan– A method that integrates detailed operational

analysis into traditional four-step planning process– Can capture detailed dynamics of the system by

using microscopic traffic simulation– Can evaluate both ITS strategies and operational

improvements

Page 5: Corridor Management Planning in California

Project Overview

• Goal: – To incorporate detailed performance measurement

and operational analysis into the traditional corridor planning efforts.

• Outcome: – A template for Caltrans to use in corridor planning

efforts that will integrate both planning and operations

– To help recommend the most effective improvement strategies.

• Major Tool:– PeMS (http://pems.eecs.berkeley.edu/Public/)– Microscopic Traffic Simulation (Paramics)

Page 6: Corridor Management Planning in California

Role of Micro-Simulation in CMP

Corridor Selection Data Collection

Corridor Performance Assessment

Base-Year Simulation Model Development

Evaluation of Future-Year Improvement Strategies

Final Recommendations

Paramics

Page 7: Corridor Management Planning in California

Demo Project – I880

37 miles

157 actuated signals

25 fixed-time signals

56 ramp meters (143 metered lanes)

Page 8: Corridor Management Planning in California

Demo Projects – SR41 & I5

SR41

16 miles

99 traffic signals

15 ramp meters

I5

30 miles

96 ramp meters

120 signals (actuated)

Page 9: Corridor Management Planning in California

Simulation Framework Development

I880 I5 (on-going)

Page 10: Corridor Management Planning in California

SR41 Paramics Network

Page 11: Corridor Management Planning in California

Technical Challenges

• Data Collection– Highway: PeMS– Arterials: Field Data Collection

• Data Consistency• Representative Day• Bottleneck Calibration in Simulation• Percentile-Based Methods for Performance

Assessment and Bottleneck Calibration

Page 12: Corridor Management Planning in California

Bottleneck Calibration in Simulation

• Why Percentile-Based Method?– Need an intelligent way to utilize available data (for

multiple days) in the near future– No typical or representative day for many

congested urban corridors

• Probability of BN OccurrenceTtNiptivtivP p ,,1,,,1,)),(),(( p-th percentile speed

Page 13: Corridor Management Planning in California

13

Speed Contour Map

IncidentAverage

No-Incident 15%

50% 85%

Page 14: Corridor Management Planning in California

Binary Speed Contour Maps

Vth = 35mph

Observed Data Simulation Data

N

iii

T

trs

N

iii

T

trs

xxtiBStiBS

xxtiBStiBSC

1 1

1 11

)}())],(),([{(

)}())],(),([{(

C1 = 90.5%

Vth = 35mph

Overlapping Area Union Area

Page 15: Corridor Management Planning in California

15

I-880 NB Speed Contour Maps

Observed Data

Simulation Data

Page 16: Corridor Management Planning in California

16

I-880 NB Binary Speed Contour Maps

• C1= 24.2%

Observed Data

Simulation Data

Page 17: Corridor Management Planning in California

Current Progress (The Three studies)

• I-880– The base year micro-simulation model

development is completed; Improvement scenario evaluation is near completion.

• SR-41– The study was completed in June of 2007; A final

report was submitted and under review.

• I-5– The development of the base year model is

completed; Future year evaluation is underway.

Page 18: Corridor Management Planning in California

Future Year Improvements for SR-41

• Short-term (2005)• Medium-term (2010)• Long-term (2025)• Long-term with HOV (2025)

Page 19: Corridor Management Planning in California

Results of Future Year Improvements

Average Freeway Speed (PM)

Page 20: Corridor Management Planning in California

Current Progress (Guideline Development)

• The project has been aligned with the statewide Corridor System Management Planning (CSMP) activities.– Development of guideline template for

conducting CSMP in general– Development of “Cookbook” on what steps

need to be performed to conduct CSMP by Caltrans Districts

Page 21: Corridor Management Planning in California

Acknowledgement

Page 22: Corridor Management Planning in California

Thank you

• Questions?

[email protected]