Western Light Rail Transit Corridor Planning and ...

45
Western Light Rail Transit Corridor Planning and Environmental Assessment Study 1 May 2013 1

Transcript of Western Light Rail Transit Corridor Planning and ...

Page 1: Western Light Rail Transit Corridor Planning and ...

Western Light Rail Transit CorridorPlanning and Environmental 

Assessment Study

1 May 2013

1

Page 2: Western Light Rail Transit Corridor Planning and ...

Presentation Overview

1. Where We Began• Background and Study Area 

2. Understanding the Carling Options• Transportation Network Perspective• City‐Building Perspective• Transportation Performance Perspective

2

2

Page 3: Western Light Rail Transit Corridor Planning and ...

Presentation Overviewctd…

3. Proposed Rapid Transit Network

4. What We Heard (so far)• Community and NCC Concerns

5. Where We Are Headed

5. Summary and Next Steps

3

3

Page 4: Western Light Rail Transit Corridor Planning and ...

Council Direction:June 27, 2012

• The City presented details and preliminary analysis of 15 corridors 

• Council was not satisfied • Identified that clear interests of the community must be considered and reflected

• Directed to align with City, NCC planning initiatives

4

Page 5: Western Light Rail Transit Corridor Planning and ...

Study Context(2008 TMP)

5

5

Page 6: Western Light Rail Transit Corridor Planning and ...

Study Area

Bayview Station Operational 2018

Tunney’s Pasture Station operational 2018

Baseline Station / Algonquin Campus

6

6

O-Train

Queensway

Page 7: Western Light Rail Transit Corridor Planning and ...

Corridors Considered Initially (15)7

O‐Train

Holland

Island Park

Kirkwood

Tweedsmuir/HydroBroadview

Churchill

Woodroffe

Richmond

Rochester Field

Cleary

Page 8: Western Light Rail Transit Corridor Planning and ...

Understanding the Carling Options

• Compromises the network and operations 

• Would require continued bus service in the north, including using the Parkway for the foreseeable future

• 2 – 3 times the cost of other options

• Potentially very visually intrusive

• 7.1 km underground is impractical

8

Page 9: Western Light Rail Transit Corridor Planning and ...

Carling via O‐Train

Not Recommended for Further Analysis

Page 10: Western Light Rail Transit Corridor Planning and ...

Transportation Network Perspective: Fractured Network

O-Train (and service from the airport) terminates at Carling and requires a transfer

O-Train cannot connect to Gatineau

10

Reduced transit service to Tunney’s, Westboro, and Dominion

10

Page 11: Western Light Rail Transit Corridor Planning and ...

Transportation Network Perspective: Connection to Tunney’s Pasture

From East:Every 3-4 train to Tunney’s

11

From South West:Transfer at Baseline(replacing Tunney’s)ORMaintain BRT connection

11

T

T

Page 12: Western Light Rail Transit Corridor Planning and ...

Transportation Network Perspective: Connection to Tunney’s Pasture

From East:Every 3-4 train to Tunney’s

12

12

T

TFrom West:Transfer at Lincoln Fields(replacing Tunney’s)

T

Page 13: Western Light Rail Transit Corridor Planning and ...

Transportation Network Perspective: Connection to Tunney’s Pasture

13

13

T

T

T

T

From South:Transfer at Carling and LeBreton

From East:Every 3-4 train to Tunney’s

Reduced transit service to Tunney’s, Westboro, and Dominion

O-Train cannot connect to Gatineau

Page 14: Western Light Rail Transit Corridor Planning and ...

Transportation Network Perspective: Capacity Implications 

14

30 trains/hr.(2 min. service)

6 trains/hr.(10 min. service)

10-minute service inadequatefor employment at Tunney’s

24 trains/hr.(2.5 min. service)

Inadequate for demand fromthe west and southwest

14

Page 15: Western Light Rail Transit Corridor Planning and ...

www.ottawa.ca/westernLRT

City‐Building Perspective

• Elevated Guideway• Lincoln Fields• Experimental Farm• Over Queensway (along the Capital Arrival Route)

• Negative impact of infrastructure on view corridors

15

15

Page 16: Western Light Rail Transit Corridor Planning and ...

Transportation Performance Perspective 

16

16

Travel Time = Ridership 

Baseline to Tunney’s Pasture

• Choosing Carling Avenue adds between 3 – 13 minutes to a passengers’ trip

Page 17: Western Light Rail Transit Corridor Planning and ...

Transportation Performance Perspective: “Hybrid” Primary

17

?

17

Transfer Points

Supplementary Corridor (TBD)

Primary Corridor

Tunn

ey’s

Bay

view

Lincoln FieldsCarling/O-Train

Less efficient Primary line (longer)

Supplementary line that would focus on local needs is problematic -fractured

Page 18: Western Light Rail Transit Corridor Planning and ...

Population and Employment:18

Tunney’s Pasture

Ottawa Hospital Civic CampusCarlingwood Mall

Page 19: Western Light Rail Transit Corridor Planning and ...

Proposed Rapid Transit Network19

19

Page 20: Western Light Rail Transit Corridor Planning and ...

Lincoln Fields‐Baseline Connection

20

• Portion south of Lincoln Fields is common to all as it generally follows the current Southwest Transitway

• BRT and LRT in corridor between Lincoln Fields and Queensway

• New BRT connection to Queensway

• Iris Station will be modified to suit LRT

Page 21: Western Light Rail Transit Corridor Planning and ...

21

Lincoln Fields‐Baseline ConnectionStage 1

Page 22: Western Light Rail Transit Corridor Planning and ...

22

Lincoln Fields‐Baseline Connection –Stage 2

Page 23: Western Light Rail Transit Corridor Planning and ...

Iris Station  

23

Option C – Deep Trench

Option B – Shallow Trench

Option A – Cul-de-sac

Page 24: Western Light Rail Transit Corridor Planning and ...

What We Heard (so far)

Community Concerns

• Should protect – not ruin – Byron Linear Park

• Should connect – not physically divide – community 

• Should encourage – not restrict – access to greenspace, waterfront and pathway network

• Should avoid – not make use of – the Parkway

24

24

Page 25: Western Light Rail Transit Corridor Planning and ...

www.ottawa.ca/westernLRT

Parkway (Magenta)Where it fell short:

• Restricts access to greenspace, waterfront and pathway network

• Relies on using the Parkway

25

25

Page 26: Western Light Rail Transit Corridor Planning and ...

www.ottawa.ca/westernLRT

Richmond via Churchill (Blue)Where it fell short:

• Ruins Byron Linear Park• Physically divides community• Does little to encourage/improve access to waterfront pathways and parkland

26

26

Page 27: Western Light Rail Transit Corridor Planning and ...

www.ottawa.ca/westernLRT

Richmond via Rochester Field (Yellow)

Where it fell short:• Ruins Byron Linear Park• Physically divides community

27

27

Page 28: Western Light Rail Transit Corridor Planning and ...

www.ottawa.ca/westernLRT

CPR‐Richmond (Red)Where it fell short:

• Does little to protect Byron Linear Park west of Woodroffe

• Does little to encourage/improve access to waterfront pathways and parkland

28

28

Page 29: Western Light Rail Transit Corridor Planning and ...

Where We Are Headed

• Challenged ourselves to find options that respond to what we heard, while:

• Maintaining the integrity of transit long range financial plan

• Meeting transit ridership goals• Allowing for continued citywide network investments

• Solutions

29

29

Page 30: Western Light Rail Transit Corridor Planning and ...

www.ottawa.ca/westernLRT

Richmond Underground• Protects Byron Linear Park and keeps LRT off the Ottawa River Parkway

• Maintains community connectivity• Encourages access to greenspace, waterfront and pathway network

30

30

Page 31: Western Light Rail Transit Corridor Planning and ...

www.ottawa.ca/westernLRT

Richmond Underground ‐ North 

• Protects Byron Linear Park• Maintains community connectivity• Encourages access to greenspace, waterfront and pathway network

31

31

Page 32: Western Light Rail Transit Corridor Planning and ...

Estimated Costs

• Class D planning estimates• based on conceptual plans• 40 per cent contingencies• +/‐ 25 per cent• consistent with City policy

• In 2013 dollars

• Not including inflation to construction year and variable elements (fleet and maintenance facility)

32

Page 33: Western Light Rail Transit Corridor Planning and ...

Estimated Costs2013   +/‐ 25%

Carling via O‐Train:   $2.3 B

Richmond via Churchill:  $2.2 B

CPR Richmond:  $1.1 B

Richmond via Rochester Field: $960 M

Richmond Underground: $900 M

Richmond Underground‐North:  $880 M

Parkway:  $630 M

33

Page 34: Western Light Rail Transit Corridor Planning and ...

Summary

• Richmond Underground is preferred option

• Responds to clear community and NCC concerns• Most cost‐effective investment• Improves community and network transit service• Promotes transit ridership and City growth • Allows for citywide network expansions further 

east and south

34

34

Page 35: Western Light Rail Transit Corridor Planning and ...

Use of Former CPR Rail Bed ‐Skead Street (view North from Westminster)

35

Page 36: Western Light Rail Transit Corridor Planning and ...

Use of Former CPR Rail Bed ‐Skead Street

36

Page 37: Western Light Rail Transit Corridor Planning and ...

Cleary  Station – open air

37

Page 38: Western Light Rail Transit Corridor Planning and ...

Cleary  Station – view from the River

38

Page 39: Western Light Rail Transit Corridor Planning and ...

Cleary  Station – view from the pathway network

39

Page 40: Western Light Rail Transit Corridor Planning and ...

Cleary  Station – aerial view

40

Page 41: Western Light Rail Transit Corridor Planning and ...

New Orchard Station  

41

Page 42: Western Light Rail Transit Corridor Planning and ...

Richmond Underground (cross section)

42

Richmond Byron Linear Park

Page 43: Western Light Rail Transit Corridor Planning and ...

New Orchard Station

43

Page 44: Western Light Rail Transit Corridor Planning and ...

Next Steps

• Your input needed ‐ [email protected]• Transportation Committee and Council in June 2013

• Functional Design and EA Documentation• Decision included in 2013 TMP (late June)

44

44

Page 45: Western Light Rail Transit Corridor Planning and ...

Questions?

45