Construction Update of Our
Projects for The Month of
November, 2018
Keshav Nagar, Pune
Florida Watercolor – November’18
‘A’ BUILDING:
RCC work completed for 1st, 2nd & 3rd slab
Block work completed for 1st floor
Internal plaster completed for 1st floor
50% external plaster work completed for 1st floor
Toilet - Internal concealed plumbing & internal floor plumbing work completed for 1st floor
90% work complete of 1st floor toilet & terrace waterproofing
Toilet granite door framing work completed for 1st floor
Concealed electrical work completed for 1st floor
70% work in progress for 1st floor wall & ceiling gypsum
Tiling Work–
1st floor mosaic flooring completed
1st floor toilet dado completed
1st floor toilet flooring completed
1st floor kitchen platform with dado completed
50% work completed for double height terrace external plaster
Construction Update – November’18
‘B’ BUILDING:
RCC completed up to terrace slab & lift shaft top slab. Over head water tank bottom slab work-in-progress
Block work completed up to 12th, 13th & 14th floor. Parapet block work-in-progress
Internal plaster completed up to 12th floor. 13th & 14th floor internal plaster work-in-progress
External plaster completed for North side. 70% work complete for flat terrace external plaster, 50% work
complete for West side & 10% work complete for South side external plaster
Toilet internal concealed plumbing completed up to 12th floor
Toilet internal floor plumbing completed up to 12th floor
Toilet waterproofing work completed up to 9th floor. 70% work complete for 10th floor, 50% work complete for
11th floor & 30% work complete for 12th floor
Toilet granite door & window framing work completed up to 8th floor & 50% work complete for 7th floor
Concealed electrical work completed up to 10th floor & 50% work complete for 11th floor
Wall & ceiling gypsum work completed up to 9th floor, 90% work complete for 10th floor & 15% work-in-progress
for 11th floor
Toilet tiling dado work completed up to 6th floor & 50% work complete for 7th floor
Kitchen platform making work completed up to 6th floor.
Keshav Nagar, Pune
Florida Riverwalk– November’18
‘A’ BUILDING:
RCC work -
Completed for 1st, 2nd, 3rd & 4th slab
5th slab work-in-progress
‘A’ Building
Sus, Pune
Oxford Paradise – November’ 18• RCC work completed
• Block work completed
• Gypsum work completed
• Waterproofing work completed
• 90% internal building & 80% external electrical work complete
• Tiling work completed
• Internal & external plaster work complete
• Internal & down-take line plumbing work completed
• 50% work complete for sanitary fittings
• 95% work complete for wooden doors
• Fabrication work completed
• Sliding door work completed
• Fire fighting system installed
• 75% work complete for solar system
• External painting completed & 75% work complete of internal painting
• 90% work complete for STP
• 99% work done for lift elevators & landscape area
THANK YOU!