Construction Update of Our Projects for The Month of November, 2018

Transcript of CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18...

Page 1: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water

Construction Update of Our

Projects for The Month of

November, 2018

Page 2: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water

Keshav Nagar, Pune

Page 3: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water

Florida Watercolor – November’18

‘A’ BUILDING:

RCC work completed for 1st, 2nd & 3rd slab

Block work completed for 1st floor

Internal plaster completed for 1st floor

50% external plaster work completed for 1st floor

Toilet - Internal concealed plumbing & internal floor plumbing work completed for 1st floor

90% work complete of 1st floor toilet & terrace waterproofing

Toilet granite door framing work completed for 1st floor

Concealed electrical work completed for 1st floor

70% work in progress for 1st floor wall & ceiling gypsum

Tiling Work–

1st floor mosaic flooring completed

1st floor toilet dado completed

1st floor toilet flooring completed

1st floor kitchen platform with dado completed

50% work completed for double height terrace external plaster

Page 4: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water

Construction Update – November’18

‘B’ BUILDING:

RCC completed up to terrace slab & lift shaft top slab. Over head water tank bottom slab work-in-progress

Block work completed up to 12th, 13th & 14th floor. Parapet block work-in-progress

Internal plaster completed up to 12th floor. 13th & 14th floor internal plaster work-in-progress

External plaster completed for North side. 70% work complete for flat terrace external plaster, 50% work

complete for West side & 10% work complete for South side external plaster

Toilet internal concealed plumbing completed up to 12th floor

Toilet internal floor plumbing completed up to 12th floor

Toilet waterproofing work completed up to 9th floor. 70% work complete for 10th floor, 50% work complete for

11th floor & 30% work complete for 12th floor

Toilet granite door & window framing work completed up to 8th floor & 50% work complete for 7th floor

Concealed electrical work completed up to 10th floor & 50% work complete for 11th floor

Wall & ceiling gypsum work completed up to 9th floor, 90% work complete for 10th floor & 15% work-in-progress

for 11th floor

Toilet tiling dado work completed up to 6th floor & 50% work complete for 7th floor

Kitchen platform making work completed up to 6th floor.

Page 5: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water
Page 6: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water

Keshav Nagar, Pune

Page 7: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water

Florida Riverwalk– November’18

‘A’ BUILDING:

RCC work -

Completed for 1st, 2nd, 3rd & 4th slab

5th slab work-in-progress

Page 8: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water

‘A’ Building

Page 9: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water

Sus, Pune

Page 10: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water

Oxford Paradise – November’ 18• RCC work completed

• Block work completed

• Gypsum work completed

• Waterproofing work completed

• 90% internal building & 80% external electrical work complete

• Tiling work completed

• Internal & external plaster work complete

• Internal & down-take line plumbing work completed

• 50% work complete for sanitary fittings

• 95% work complete for wooden doors

• Fabrication work completed

• Sliding door work completed

• Fire fighting system installed

• 75% work complete for solar system

• External painting completed & 75% work complete of internal painting

• 90% work complete for STP

• 99% work done for lift elevators & landscape area

Page 11: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water
Page 12: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water
Page 13: CONSTRUCTION UPDATE OF OUR PROJECTS FOR THE MONTH … · Construction Update –November’18 ‘B’ BUILDING: RCC completed up to terrace slab & lift shaft top slab. Over head water