Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis...

56
Union Oasis Transit Oriented Development Public-Private Partnership Project Confidential Information Memorandum February 2016 Roads and Transport Authority is advised by:

Transcript of Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis...

Page 1: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Union Oasis Transit Oriented Development

Public-Private Partnership Project

Confidential

Information Memorandum

February 2016

Roads and Transport Authority is advised by:

Page 2: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

February 2016

Important Notice

This Information Memorandum (“Memorandum”) is provided as part of the evaluation materials to the

recipient solely for informational purposes in order to assist the recipient and its advisors in assessing

whether they wish to consider participating in the competitive tender for a Public-Private Partnership

(“PPP”) tender involving the design, financing, construction, operation and maintenance of a new mixed

use Transit Oriented Development (“TOD”), being the Union Oasis Project (the "Project").

The Memorandum is being issued by the Roads Transport Authority (“RTA”) solely for use by the

prospective developer (“Prospective Developer”) and their advisors in considering the Project.

The Memorandum has been prepared with the assistance of the RTA’s Transaction Advisor, Ernst & Young

(“EY” or “Transaction Advisor”), supported by Faithful+Gould (“F+G”) as Technical Consultant and

Trowers & Hamlins (“T&H”) as Legal Consultant. The Memorandum does not contain or purport to contain

all the information that a Prospective Developer may desire. In all cases, interested parties should conduct

their own investigation and analysis of the Project and of the data set forth in this Memorandum. Neither

the RTA, nor any of their advisors, other representatives or agents make any representation (expressed or

implied) or warranties as to the accuracy or completeness of this Memorandum and shall have no liability

for this Memorandum or for any other written or oral communication transmitted to the recipient in the

course of the recipient’s evaluation of the Project.

Neither the RTA nor any of their advisors will be liable to reimburse or compensate the recipient for any

costs or expenses incurred by the recipient in evaluating or acting upon this Memorandum or otherwise in

connection with competitive tender for the Project as contemplated herein. The Memorandum contains

certain interpretations, explanations and/or summaries of the Dubai PPP laws, and other governmental

authorizations which were prepared solely to acquaint the recipient with the matters described in a

general manner only and are not intended to constitute legal opinions, memoranda or interpretations or to

disclose or discuss any aspects of such laws or other governmental authorizations that may be important

to a recipient, and interested parties and their advisors (including legal counsels) must rely solely on their

own due diligence review and findings in connection with the same.

The RTA reserves the right: (i) to modify any of the rules or procedures set forth herein or any other rules

or procedures without giving prior notice or assigning any reason therefore and/or (ii) to take any action

which they deem necessary or prudent in their sole discretion in connection with the Project (including

cancelling the Project and/or the bidding process). The RTA may amend, supplement, or replace any

information contained in this Memorandum at any time, without giving prior notice or providing any

reason. The Memorandum does not constitute a solicitation to invest, or otherwise participate, in the

Project.

This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the

Project. The information contained herein is intended solely for selected bidders having the necessary

expertise to determine whether to accept the risks inherent in such an investment. This Memorandum is

not to be reproduced or redistributed without the prior written consent of the RTA and the Transaction

Advisor.

This Memorandum is intended solely for use on a confidential basis by those persons to whom it is

transmitted by the RTA and the Transaction Advisor in connection with the contemplated tender for the

appointment of a Developer for the Project. Recipients of this Memorandum by their acceptance and

retention of this Memorandum, acknowledge and agree to preserve the confidentiality of the contents of

this Memorandum and all accompanying documents and to return this Memorandum and all such

Page 3: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

February 2016

documents to the RTA or the Transaction Advisor if the recipient does not proceed with a bid for the

Project.

Page 4: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

February 2016

Contents

Glossary ................................................................................................................................... 5

Figures ...................................................................................................................................... 7

Tables ....................................................................................................................................... 8

1. Introduction ...................................................................................................................... 9 1.1 Executive Summary ................................................................................................................................ 9 1.2 Project background .............................................................................................................................. 10 1.3 Project objectives ................................................................................................................................. 16 1.4 Objectives of the Information Memorandum ........................................................................................ 18

2. Industry background ...................................................................................................... 19 2.1 Overview of Dubai ................................................................................................................................ 19 2.2 Dubai and Deira real estate market ...................................................................................................... 21

3. Project description ........................................................................................................ 27 3.1 Site analysis ......................................................................................................................................... 27 3.2 Project parameters .............................................................................................................................. 35 3.3 Architectural vision .............................................................................................................................. 37

4. Commercial principles ................................................................................................... 42 4.1 Transaction structure and contracts .................................................................................................... 42 4.2 Minimum Revenue Guarantee .............................................................................................................. 44 4.3 Payment mechanism ............................................................................................................................ 45

5. Tender process and timetable ....................................................................................... 47 5.1 Tender process ..................................................................................................................................... 47 5.2 Indicative timetable .............................................................................................................................. 49

6. Contact Details ............................................................................................................... 50

Appendix A – Affection Plan for the Site ............................................................................. 51

Appendix B – Area of the Site intended for the Project ...................................................... 52

Appendix C – Transaction Term Sheet .................................................................................. 53

Page 5: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Glossary

February 2016

Glossary

Term Definition

AED United Arab Emirates Dirham

Architectural Vision Term relating to architectural visioning options for the development, also referred to as

concept or visioning in this Memorandum

BUA Built-up Area, which is the total constructed area of the building

CAGR Compound Annual Growth Rate

CMA Concession and Musataha Agreement

Company A special purpose company established for the purpose of implementing the Project, and

which will enter into the CMA with the RTA

Developer Entity which arranges financing (as required, inter alia, equity and/or debt) to the

Company alongside providing management expertise to engage a contractor to complete

the construction and operators to manage the various real estate assets

D&B Design & Build

DM Dubai Municipality

EOI Expression of Interest

EY Ernst & Young (Dubai Branch), Transaction and Financial Advisor

FAR Floor Area Ratio, which equals total building area including all usages and staircases

(excluding car parking) divided by the area of the plot

F+G Faithful + Gould, Technical Consultant

GDP Gross Domestic Product

KPI Key Performance Indicators

IRR Internal Rate of Return

LEED Leadership in Energy and Environmental Design

Legal Consultant Trowers & Hamlins LLP

M Million

MRG Minimum Revenue Guarantee

O&M Operations & Maintenance

PPP Public-Private Partnership

Page 6: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Glossary

February 2016

Term Definition

RFQ Request for Qualification

RFT Request for Tender

RTA Roads and Transport Authority

RTPI Real Time Passenger Information

Technical Consultant Faithful+Gould

TIA Traffic Impact Assessment

TOD Transit Oriented Development

Transaction Advisor Ernst & Young

T&H Trowers & Hamlins, Legal Consultant

UAE United Arab Emirates

Union Oasis Name of the TOD, which will be built on Union Square; the Project

Union Square Refers to the site above Union metro station in Deira, which is planned for TOD

development named Union Oasis

Union Station Also known as Al Ittihad station; it is a rapid transit station on the Green and Red Lines of

the Dubai Metro in Dubai, located in Deira below Union Square, for which it is named

VP Variable Payments

WTO World Travel Organization

Page 7: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Figures

February 2016

Figures

Figure 1: Dubai Metro Ridership (in millions of passengers) .............................................. 10

Figure 2: Metro ridership at Red Line stations (2014) ....................................................... 11

Figure 3: Metro ridership at Green Line stations (2014) .................................................... 12

Figure 4: Union Station ridership vs. overall Dubai Metro, 2010 – 2014 .......................... 13

Figure 5: Union Station monthly ridership ........................................................................... 14

Figure 6: Dubai Metro ............................................................................................................ 15

Figure 7: Union Oasis Architectural Vision Perspective 1 .................................................. 17

Figure 8: Historic Union Square and Union Square’s current neighbourhood ................... 18

Figure 9: Deira residential properties analysis .................................................................... 22

Figure 10: Deira office building analysis .............................................................................. 23

Figure 11: Deira retail analysis ............................................................................................. 24

Figure 12: Deira hotels analysis ........................................................................................... 25

Figure 13: Deira hotel apartments analysis ......................................................................... 26

Figure 14: Project site location map .................................................................................... 27

Figure 15: Union Square site in 1966 .................................................................................. 28

Figure 16: Historic condition of the site in 2006 ................................................................ 28

Figure 17: View of the Project site from Al Reem Tower .................................................... 29

Figure 18: View of the Project site from Radisson Hotel .................................................... 29

Figure 19: Omar Bin Al Khattab proposed bridge ............................................................... 30

Figure 20: Transport plan...................................................................................................... 31

Figure 21: Existing conditions around the Project site - key roads and junctions ............ 32

Figure 22: Union Square utility connections ....................................................................... 33

Figure 23: Height of buildings in areas surrounding Union Square .................................... 34

Figure 24: Union Oasis Architectural Vision Perspective 2 ................................................ 37

Figure 25: Characteristics of the Union Square development ........................................... 38

Figure 26: Environmental considerations for Union Oasis development ........................... 41

Figure 27: Union Oasis development plan ........................................................................... 41

Figure 28: Potential contractual structure for the Project ................................................ 42

Figure 29: Tender process for the Project ........................................................................... 47

Figure 30: Indicative tender timetable................................................................................. 49

Page 8: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Tables

February 2016

Tables

Table 1: Union Oasis Project objectives ............................................................................... 16

Table 2: Summary of Traffic Impact Assessment ................................................................ 32

Table 3: Key parameters of Union Oasis development ........................................................ 35

Table 4: Uses for consideration of the Developer ................................................................ 35

Page 9: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Introduction

9

1. Introduction

1.1 Executive Summary

The Investment in Dubai Metro has seen a success with the numbers of trips increasing consistently since

its inauguration in 2009, with annual ridership experiencing 300% growth in ridership from almost 39

million in 2010 to 164 million trips in 2014. Union Station, is the second largest station along the Red Line

in terms of ridership, having seen over 6 million trips during 2014, accounting for 6.5% of total ridership

along the Red Line.

In continuation with the success of Dubai Metro, the Roads and Transport Authority of Dubai (“RTA”) is

embarking on a development of the land available above Union Station into a Transit Oriented

Development (“TOD”) named Union Oasis (the “Project”).

The TOD concept has many success stories in Europe, Asia, and America, bringing benefits to the

communities, regenerating areas and creating positive commercial impact; Union Oasis will be the first

TOD in the region and a landmark destination for the people and visitors of Dubai. The aim of Union Oasis

is to foster transit use and support other key goals relating to people movement, such as increased

walking and cycling.

Furthermore, the RTA believes this Project is attractive to Developers due to the following:

- Attractiveness of the Site location in the busy commercial hub and historic centre of Dubai;

- No requirement for upfront land contribution by the Developer;

- Flexibility for the Developer to innovate and determine the development mix and detailed design of

the Project to maximize revenues; and

- RTA’s collaborative approach to working with the Developer to ensure best value for money is

achieved for all stakeholders of the Project.

For making the project further attractive, the RTA Management has recently approved the following

enhancements to the project structure:

- Payments to RTA will be a percentage of the profits achieved by the Company with no

requirement for fixed base payments;

- Extended concession period to 50yrs (including construction); and

- Provision for Minimum Revenue Guarantee (MRG) for the first 15 years of operations for

covering O&M and debt service costs. The MRG is a biddable parameter and the maximum

revenues to be guaranteed by RTA correspond to revenues at 45% occupancy (see section 4.2).

In order to ensure a fair and competitive tendering process, the RTA foresee the Project to be delivered as

a PPP between the RTA and the Selected Developer.

The principles associated with the PPP form of contracting, in addition to the attractiveness of the Project,

will allow the private sector to use their development and operational expertise, and commercial acumen

to determine the optimal development mix and design for the Project, which is expected to encourage

innovation and efficiencies that can be achieved, thus maximizing profitability and commercial returns.

Following the first round of market sounding, the RTA has received feedback from the Private Sector with

regards to the features of the transaction, which it took into consideration and is now reissuing this

Information Memorandum (“IM”).The tender process will start with the issuance of the Request for

Qualification, which will include an invitation to one-to-one meetings between interested developers and

the RTA, to further discuss any aspect of the Project.

Page 10: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Introduction

10

1.2 Project background

Dubai Metro Success

The Dubai Metro was ceremonially inaugurated at 09:09:09 PM on 9 September 2009, by H.H. Sheikh

Mohammed bin Rashid Al Maktoum, the Ruler of Dubai. The Red Line and Green Line are operational, with

three further lines planned. These first two lines run underground in the city centre and on elevated

viaducts elsewhere. The currently operating system includes 74 km of track and 47 stations.

The investment in Dubai Metro has already brought positive effect on the property prices in the Emirate as

the Metro system provides:

Easy and efficient mobility;

Multimodal transport options;

Lower transportation costs; and

Travelling comfort in excellent quality facilities.

Metro ridership

Dubai Metro ridership has seen the numbers of trips increase consistently since its inauguration in 2009,

with annual ridership growing from almost 39 million trips in 2010 to 164 million trips in 2014 (Figure 1),

Figure 1: Dubai Metro Ridership (in millions of passengers)

0

20

40

60

80

100

120

140

160

180

2010 2011 2012 2013 2014

38.90

69.00

109.50

137.80

164.30

Page 11: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Introduction

11

Red Line ridership

Red Line ridership totalled 63% of total Metro ridership. The Deira City Center station registered the most trips in 2014 with 7.18 million, followed by Union (Red Line) with 6.77 million trips. Burj Khalifa/ Dubai Mall registered 6.69 million trips in 2014. The top 10 stations in terms of ridership constituted 56% of ridership at all Red Line stations in 2014. These figures are highlighted in Figure 2 below.

Figure 2: Metro ridership at Red Line stations (2014)

7.18 6.77 6.69 6.61 6.41 5.87 5.66

4.52 4.37 4.33 4.15 4.08 4.03 3.76 3.28 3.03 3.03 2.87 2.54 2.23 2.18 2.12 2.11

1.62 1.43 1.33 1.27 0.38 0.16

012345678

Red

Lin

e rid

ersh

ip ,

mill

ion

Ridership station by, 2014

Ridership station by, 2014

7%

7%

6%

6%

6%

6%

5% 4% 4% 4%

4%

4%

4%

4%

3%

3%

3%

3%

2%

2% 2%

2% 2% 2% 1% 1% 1% 0% 0%

Deira City Centre Union (Red Line)

Burj Khalifa / Dubai Mall Al Rigga

BurJuman (Red Line) Mall of the Emirates

ADCB Noor Bank

Rashidiya Dubai Internet City

Ibn Battuta Jumeirah Lakes Towers

Al Jafiliya Business Bay

DAMAC PROPERTIES World Trade Centre

Emirates Towers FGB

Financial Centre Sharaf DG

GGICO Airport Terminal 1

Emirates Nakheel

Jebel Ali Danube

Airport Terminal 3 Nakheel Harbour & Tower

Energy

Page 12: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Introduction

12

Green Line ridership Green Line ridership totalled 37% of total ridership. Al Fahidi station registered the most trips in 2014 with 6.92 million, followed by Baniyas Square station with 6.45 million trips. Ridership registered in 2014 at Union Station on the Green Line was over 2.5 million, which takes total Union Station ridership (both Red Line and Green Line) to 9.36 million. The top 10 stations in terms of ridership constituted 73% of ridership at all Green Line stations in 2014. These figures are highlighted in Figure 3.

Figure 3: Metro ridership at Green Line stations (2014)

6.92 6.45

4.87 4.20 4.20 4.01 3.93

3.41 3.33 2.77 2.73 2.60

2.16 2.16 1.97 1.66 1.43

1.04

0.27 0.17

0

1

2

3

4

5

6

7

8

Al Fahidi BaniyasSquare

AlGhubaiba

Oud Metha Salah AlDin

Stadium Abu BakerAl Siddique

BurJuman(GreenLine)

DubaiAirport

Free Zone

Palm Deira Abu Hail Union(GreenLine)

Al Nahda Al Ras Al Qusais Al Qiyadah DubaiHealthcare

City

Etisalat Creek Al Jadaf

Gre

en li

ne r

ider

ship

, mlli

on

Ridership by station, 2014

Ridership by station, 2014

11%

11%

8%

7%

7% 7% 7%

6%

6%

5%

5%

4%

4%

4% 3%

3% 2% 2% 0% 0%

Al Fahidi Baniyas Square Al GhubaibaOud Metha Salah Al Din StadiumAbu Baker Al Siddique BurJuman (Green Line) Dubai Airport Free ZonePalm Deira Abu Hail Union (Green Line)Al Nahda Al Ras Al Qusais

Page 13: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Introduction

13

Union Station Ridership

The growth in the number of passengers using the Union Station showed an upward trend over the years

2010-2014, growing by a Compound Annual Growth Rate (“CAGR”) of 16.4%, rising from 4.9 million

passengers in 2010 to 9.3 million passengers in 2014. Over the same period, the number of passengers

of Dubai Metro grew by CAGR of 52.4%.

The percentage of Union Station ridership in the overall Dubai Metro ridership dropped from 13% in 2010

to 6% in 2014. This is largely explained by the continuous addition of new metro stations, which increased

from 26 in 2010 to 47 in 2014. Figure 4 highlights the above mentioned statistics.

Figure 4: Union Station ridership vs. overall Dubai Metro, 2010 – 2014

Ridership detail 2010 2011 2012 2013 2014

All stations ridership (in million) 38.9 69 109.5 137.8 164.3

Union Station ridership (in million) 4.9 6.4 6.4 7.7 9.3

Union Station ridership % in all stations ridership 13% 9% 6% 6% 6%

The monthly ridership of Union Station depicts an increasing trend. The monthly data shows that Union

Station ridership picks up during the months of April and May, as well as the period from October to

January. In contrast, the data shows consistent drop in the number of passengers in the summer months,

particular from July to September, which is explained by the increasing temperatures, which in turn is

affecting the number of tourists in Dubai. This time of the year also often coincided with the Holy Month of

Ramadan, and the fact that many expatriate workers leave the city for their annual vacations.

Figure 5 shows the monthly ridership trend at Union Station, highlighting the summer months when traffic

at Union Station drops.

38.9

69

109.5

137.8

164.3

4.9 6.4 6.4 7.7 9.3

0

20

40

60

80

100

120

140

160

180

2010 2011 2012 2013 2014

Rid

ersh

ip, m

illio

n pa

ssen

gers

All stations ridership Union Station ridership

Page 14: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Introduction

14

Mar

14

June

14

Sep

14

Dec

14

2014

Figure 5: Union Station monthly ridership

Transit-Oriented Development and a Place for People

In continuation with the success of Dubai Metro, the RTA is embarking on a development of the land

available above Union Station into a TOD named Union Oasis. It will be the first TOD in the region and a

landmark destination for the people and visitors of Dubai. The intention is for a Developer to develop a

mixed-use complex including residential and commercial properties, designed to maximize access to the

public transport and incorporating features to encourage transit ridership. In addition to creating a

multimodal transport hub, the Project will be a catalyst for the regeneration of the Deira neighbourhood.

Implementation of the TOD concept echoes one of the key objectives included in the RTA Strategic Plan,

focusing on increasing the use of public transit means from 6% in 2009 to 30% in 2030, currently standing

at approximately 12%.The TOD concept has many success stories in Europe, Asia and America, bringing

benefits to the communities, regenerating areas and creating positive commercial impact. The RTA’s

aspiration is that the Union Oasis will take into consideration international best practices with regards to

design of transit-oriented communities and will enhance them in consideration of local and regional

context and requirements.

The vision for Union Oasis is to provide a place for people. This will be achieved through a strong focus on

good quality pedestrian-oriented streetscape, landscaping and buildings. The vibrant civic and community

facilities, retail and other amenities of this compact mixed-use development will not only support transit

ridership, but will also provide a comfortable and enjoyable place for local residents and visitors alike.

Transit-oriented communities lend themselves to cost-effective transportation networks and services,

which will allow Dubai to move people and goods more efficiently and to produce more value for each

transportation investment implemented by the Government.

The objective of Union Oasis is to uncover and deploy the best solutions for integrating community

development with transit investment, resulting in an improved quality of life for all who live and work in

the city of Dubai and the neighbourhood of Deira. In this context, the development around the Union

Square station will regenerate the area, create more affordable lifestyles and disposable income, provide

better job access and catalyse private investment.

Planning and designing communities has a profound impact on travel behaviour. The aim of Union Oasis is

to foster transit use and support other key goals relating to people movement, such as increased walking

and cycling.

0

100,000

200,000

300,000

400,000

500,000

600,000

700,000

800,000

900,000

Sep

-09

Dec

-09

Mar

-10

Jun-

10

Sep

-10

Dec

-10

Mar

-11

Jun-

11

Sep

-11

Dec

-11

Mar

-12

Jun-

12

Sep

-12

Dec

-12

Mar

-13

Jun-

13

Sep

-13

Dec

-13

Passengers

Union Station Ridership

2010 2011 2012 2013

Page 15: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Introduction

15

The RTA has performed a detailed feasibility study for the Union Oasis development, which indicates

healthy returns for the private sector in consideration of realistic revenue expectations from the RTA.

Figure 6: Dubai Metro

Procurement of Developer

The RTA wishes to invite Prospective Developers to undertake the Project on the basis of PPP concession

and musataha principles. The successful Developer will be selected via tender process, currently

envisaged to start with the issuance of pre-qualification documents to the market no later than February

2016 and to conclude with commercial and financial close in the fourth quarter of 2016.

Page 16: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Introduction

16

1.3 Project objectives

The RTA has set out the following objectives for the Union Oasis development:

Landmark development;

Public transport orientated;

Mixed use development;

Providing high quality services; and

Commercially feasible.

A detailed explanation of each objective for the Project is provided in Table 1 below.

Table 1: Union Oasis Project objectives

Objective Details

Mixed use development

Including a mix of various uses;

Attractive for local residents and visitors;

Contribute to the overall economic and environmental sustainability of the Deira community;

Allow for the aggregation of open space and amenity space to benefit the whole community;

Create opportunities to help retain and grow viable local small businesses;

Employ Deira’s existing strengths – ethnic diversity, eclectic small businesses and

“crossroads” location;

Provide public realm and green spaces for residents and visitors;

Landmark development

Maintain the character of neighbourhoods in Deira;

Capturing traditional architecture and heritage, and highlighting site importance;

Landmark and prominent building defined by its qualities relating to architecture, landscape

and transport connectivity;

High-quality project that significantly improves the physical realm of Union Square and Deira;

Public transport orientated

Create a TOD, a walkable, mixed-use community which enhances/promotes the use of public

mass transit services;

Provide high-pedestrian traffic and bicycle connectivity and emphasize street level activity

that is safe, secure and appealing;

Promote complimentary development that enhances connectivity and greater integration;

between Deira and Dubai;

Providing high quality

services

High quality of services to the residents and visitors and enhanced customer care will be

provided in the development;

Appropriate long-term asset management, operation and maintenance programme will be

implemented to incorporate whole life cycle considerations and preserve the assets in good

condition throughout the concession period and beyond;

Commercially feasible

Financially feasible and sustainable project through leveraging expertise of private sector

Developer and RTA contribution, harnessing the PPP concept;

Utilize a mixed-use development to achieve a better balance of residential and commercial

uses;

Revitalize economic drivers, including entertainment, a variety of boutique retail

establishments and restaurants;

Innovation brought by private sector; and

Balanced commercial terms to be achieved between the Developer and the RTA to achieve

best value for money.

Page 17: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Introduction

17

Architectural Vision

The Project will be a mixed use TOD, developed preferably with the Architectural Vision shown in figure 7

below. In order to provide Prospective Developers with more flexibility in the development of this iconic

Project, the RTA is allowing Prospective Developers to propose, alternative conceptual designs which must

contain a mix of modern buildings fused with a traditional architecture.

Figure 7: Union Oasis Architectural Vision Perspective 1

Project Attractiveness for Developers

The following factors contribute to the attractiveness of the Project for the Developer:

No requirement for upfront land contribution by the Developer;

Phasing of the Development is allowed, with the Operational Terms of the Musataha Agreement fixed

at 50 years inclusive of the period of construction;

No requirement for fixed base payments to RTA;

Provision for Minimum Revenue Guarantee (MRG) for the first 15 years of operations for covering

O&M and debt service costs. The MRG is a biddable parameter and the maximum revenues to be

guaranteed by RTA correspond to revenues at 45% occupancy (see section 4.2);

Attractive site location in the busy commercial hub and the historic centre of Dubai;

Benefit of 16 million footfall from the Union metro station;

Convenient access from the Union Oasis development to various public transport modes, including the

metro, buses, water transport and taxis; and

Flexibility for the Developer to innovate and determine the development mix and detailed design of the

Project to maximize revenues.

Page 18: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Introduction

18

1.4 Objectives of the Information Memorandum

The objective of this Memorandum is to provide basic information about the Project to Prospective

Developers to generate interest in the Union Oasis Project. By issuing this Memorandum, the RTA is

progressing toward the stage of qualification.

In addition, the RTA expects to organize one-on-one meetings with interested parties as part of the

Request for Qualifications (“RFQ”) process.

Figure 8: Historic Union Square and Union Square’s current neighbourhood

Page 19: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Industry background

19

2. Industry background

2.1 Overview of Dubai

Dubai is one of seven emirates in the United Arab Emirates federation. The main city of the Emirate is also

called Dubai. The current ruler, His Highness Sheikh Mohammed bin Rashid Al Maktoum, is also the Vice

President and Prime Minister of the United Arab Emirates and member of the Supreme Council of the

Union.

The Dubai Emirate is located on the southeast coast of the Arabian Gulf and it has the largest population in

the UAE at 2.17 million (2013, Dubai Statistics Centre) and the second-largest territory (4,114 sq. km)

after the capital Abu Dhabi.

Since the establishment of the UAE in 1971, Dubai has grown towards developing a distinct identity as a

modern and dynamic city. Today, the city enjoys a global reputation as a regional economic, financial and

tourism hub. The Emirate of Dubai, through the development of tourism, media, shipping, trading and

commercial services facilities, aims to accelerate the diversification process to compensate for its less

significant oil industry and build a prominent position for itself as a finance, trade and services centre

within the Gulf region.

►Dubai’s success can be primarily attributed to the bold visionary leadership and a flexible human capital

structure. In addition, the city’s mega projects and free trade zones have assisted in attracting the excess

liquidity in the region brought about by the high oil prices in the form of Foreign Direct Investment. Dubai is

allocating resources efficiently in providing infrastructure suitable for positioning itself as a regional

business hub.

►Over the last few years, economic growth in the Emirate has also been fuelled by private sector

participation in developing sectors where the Government has developed a platform by establishing a

conductive business environment, coupled in many instances with initial investments to boost private

sector confidence.

►Although the financial crisis has hampered this growth trend, market intelligence data reveals that the

economy has started rebounding in the middle of 2010 with overall business sentiment in positive territory

at present. In November 2013, it was announced that Dubai will host the World Expo 2020. As a result, a

significant amount of capital and resources are currently deployed in Dubai, which in turn is expected to

contribute to a considerable increase in GDP growth through to 2020 and beyond.

As part of the Government's strategy of diversifying Dubai's economy from its historic dependence on

labour intensive and oil–related industries, tourism has become a major focal sector for the Emirate.

Tourism is seen by the Government of Dubai as a major growth industry, and has been the focus of a series

of major infrastructure based investments aimed at establishing Dubai as a leading international

destination and consequently raising the profile and positioning of the Emirate around the world.

Dubai welcomed more than 10 million international visitors during 2012, according to the estimates from

Dubai Statistics Centre, representing an increase of over 9 percent compared to the year before. Not only

this, but Dubai’s hotels reaped a bumper AED18.82bn ($5.12bn) in revenues, a 17.9 percent year-on-year

hike. The CAGR in tourist arrivals to Dubai over the period 2007 to 2012 has been approximately 6.5%.

The World Travel Organization (“WTO”) estimates that the number of tourist arrivals worldwide grew by

4.6% in 2011. This indicates that despite the global slowdown, Dubai continues to enjoy higher than

average tourism trends.

The high season in Dubai for tourism occurs during the first and last quarters of the year when

temperatures are cooler. Additionally, European tourists visit Dubai during the same period in order to

Page 20: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Industry background

20

avoid the winter season in their home countries. Following the Emirate’s property market crash of 2008-

2009, which saw prices fall by up to 60 percent, Dubai’s real estate market has rallied in 2013 on the back

of strong economic fundamentals and a rising population.

Page 21: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Industry background

21

2.2 Dubai and Deira real estate market

Scope of initial market assessment

An initial market assessment for the site was performed during the Feasibility Study undertaken by the RTA

and it is summarized below. The Developer will have to perform their own analysis and due diligence to

determine the most appropriate property mix on the site, and for the decision-making purposes, in

consideration of market dynamics and commercial acumen.

Union Square is located in Deira, where a number of Government agencies and trading businesses are

based. The Deira area is becoming popular among families looking for affordable accommodation when

compared to other areas as newer parts of Dubai (e.g. Dubai Marina) have become increasingly expensive.

The following sectors were investigated during the market analysis:

Residential;

Offices;

Retail;

Hotels/convention space; and

Hotel apartments.

Properties comparable to potential uses within Union Oasis were used as competitive market area.

Page 22: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Industry background

22

Residential

The outlined yellow area on Figure 9 has been defined as the competitive market area for residential

use and is home to some of the oldest, but high quality residential buildings in Dubai. This is widely

considered to be the ‘original downtown’ of Dubai; and

The buildings in the selected competitive set are some of the best quality buildings in Deira and range

from 8 to 22 stories in height and 2 to 20 years in age. These buildings were primarily chosen for the

analysis based on the desirability from the tenant’s perspective which has been analysed through

discussions with property managers and real estate brokers. The catchment area of the considered

buildings included buildings as close as 200 m and as far as 3.3 km of driving distance from Union

Square.

Figure 9: Deira residential properties analysis

Zeenah Residence

Twin Tower

Falcon tower

Creekside Residence

Easa Saleh Al Gurg 3

Easa Saleh Al Gurg 2

Dar Al Buteen 2

Creek Tower

Legend Plaza

Al Ghurair Center apartments

Al Aman house

Union Square

Page 23: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Industry background

23

Offices

The competitive market area for office space was defined as two distinct office districts in Deira, as

identified in Figure 9. These buildings are expected to compete with the Project in terms of quality

office space;

On Figure 10, the area shaded and named in yellow is defined as Downtown Deira, while the area

shaded and named in blue is defined as Airport Area; and

The catchment area of the considered buildings included buildings as close as 200 m and as far as

3.2 km of driving distance from Union Square.

Figure 10: Deira office building analysis

► The Downtown area is occupied by manysingle tenanted buildings includinggovernment departments and large localinsurance companies and banks.

► Most other buildings in this area areoccupied by small trading firms.

► The Airport area is predominantly occupied bylarge private firms, many of which occupymultiple floors.

► Other tenants include small sized professionalservices firms and some small tradingcompanies.

Easa Saleh Al Gurg3

Easa Saleh Al Gurg1

Al GhurairOffices

Damas Tower

Al Reem Tower

Twin Towers

Creek Tower

Business Point

Business Avenue

ACICO Business Park

Al Masaood Tower 2

City Avenue

Al Fattan Plaza

NGI House

New Century City Tower

Union Square

Airport Area

Downtown Deira

Page 24: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Industry background

24

Retail

Retail space within the analysed area consists of ground floor retail within residential or commercial

buildings, community malls spread over 2 or 3 levels within larger buildings and fully fledged shopping

malls. The competitive market area for retail space includes ground floor retail within quality

buildings, as well as community and fully fledged shopping malls in Deira, all of which are expected to

compete with the Project. The catchment area includes buildings as close as 200 m and as far as

3.2 km of driving distance from Union Square;

The community malls within the competitive set include Galleria, Galadari Plaza and Twin Towers.

Galadari Plaza and Galleria are connected to hotels and therefore their primary business comes from

hotel guests. Twin towers is a residential and commercial complex with 2 storeys of retail area and a

food court on the third level which is frequented by people working in the locality; and

There are three major malls in Deira including:

Al Ghurair Centre, which was extended by approximately 75% and opened in 2013;

Deira City Centre which was once the most successful mall in Dubai and is still the most successful

mall in Deira with the highest lease and occupancy rates; and

Reef Mall which caters to mid-market clients.

Figure 11: Deira retail analysis

Union SquareGalleria (Hyatt) Reef Mall Deira City Center

Al Ghurair CenterTwin towers Galadari Plaza

Page 25: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Industry background

25

Hotels

The hotel market in Deira consists primarily of two and three star, unbranded properties; and

The competitive market area for hotels was defined as all 4 and 5 star branded properties which would

be expected to compete with a new branded hotel of similar rating. These have been highlighted in the

map in Figure 12 with a catchment area that is as close as 750 m and as far as 3.4 km of driving

distance from the Project;

Figure 12: Deira hotels analysis

Traders Hotel (4star)

Taj Palace Hotel (5star)

Metropolitan Palace Hotel Deira (5star)

Radisson BluDubai Creek (5star)

Hilton Dubai Creek (5star)

Sheraton Dubai Creek (5star)

MovenpickHotel (5star)

Holiday Inn Downtown (4star)

Hyatt RegencyHotel (5star)

Union Square

Page 26: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Industry background

26

Hotel apartments

The hotel apartment market in Deira bears similar characteristics to the hotels in this market, as

described above;

The competitive market area in Figure 13 is defined as all branded hotel apartment properties in

Deira, which would be expected to directly compete with a new branded hotel apartment building.

Areas as close as 1.2 km and as far as 3.2 km of driving distance from Union Square were found to be

within this catchment;

The branded properties are however relatively old and were established when Deira was the most

important commercial hub in Dubai;

In this asset class too, there are very few branded properties and most properties fall in the unbranded

‘standard’ segment as opposed to the ‘deluxe’ hotel apartment segment as defined by the Dubai

Tourism and Commerce Marketing Department; and

Most hotel guests in the Deira market are traders or budget travellers and therefore have a preference

for low to mid segment hotel apartments.

Figure 13: Deira hotel apartments analysis

Hyatt Regency Serviced Residences (Deluxe)

Rimal RotanaSuites (Standard)

Taj Palace Hotel Apartments (Deluxe)

Al SondosLe Meridien (Deluxe)

Marriott Executive Residences (Deluxe)

Clover Creek Hotel Apartments (Deluxe)

Union Square

Page 27: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

27

3. Project description

3.1 Site analysis

Size and Physical Layout

Union Square, formerly Al Nasr Square, is a large open space set in the busy commercial centre of Dubai,

on the boundary between the historic district of Deira to the west and the newer Al Rigga to the east.

The land above Union Station, intended for developing the Project, has an area of 37,855 m2.

The site is bounded to the south and east by heavily used main roads, both dual carriageways. To the north

the site is bounded by a small bus station and the Tabreed district cooling system which serves the Metro

stations on the site and in the surrounding districts. To the west is the memorial monument Jamal Abdul

Nasser (recently refurbished).

Set along the northern boundary, but extending well into the site, is the underground Union Station for the

Dubai Metro system. This is a major station on the system, serving both the Red and Green lines which

come together and run through Union Station along parallel axes but at different levels. At ground level all

that can be seen of the Metro are the two entrance pods at each end of the boundary, and six light tunnels

which extend some 3m above the surface. However, below ground the installation is extensive, and building

above it is not possible (although reasonable landscaping works certainly are).

Figure 14: Project site location map

Page 28: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

28

Historical and current condition of the site

The below Figure 15 illustrates the historic context of the site, dating to the middle of 1960’s.

Figure 15: Union Square site in 1966

The below Figure 16 shows the historic condition of the site, illustrating the Union Square before the Metro

station was added under the Oum al Reoul monument.

Figure 16: Historic condition of the site in 2006

Page 29: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

29

The current condition of the site is illustrated in the below Figure 17. This figure illustrates the iconic

Dubai Metro access pods, with the highest buildings on the site being the Tabreed water cooling facilities

of approximately six stories.

Figure 17: View of the Project site from Al Reem Tower

Figure 18 illustrates the current state of the plot from a vantage point of approximately 12 stories above

the site. In comparison to the site condition from year 2006 (Figure 13 above), there are porta cabins in

the south of the site and lack of recreational grounds on top of the metro box.

Figure 18: View of the Project site from Radisson Hotel

Page 30: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

30

Oum Al Reoul

Oum Al Reoul is the name given to the small defensives structure which used to stand at the heart of what

is now Union Square. It was a two-storey building, with a small room and adjacent walled terrace supported

on another small room and freestanding columns below. Access to the upper level was by ladder. It

provided a defensible lookout point overlooking the approaches to Deira in a double quadrant extending

from the creek in the south through the eastern approaches to Sharjah in the north. The tower was

demolished many years ago. A replica was constructed, but this has also been lost during the Metro

construction works. A new replica of Oum Al Reoul is required by the Dubai Municipality, however the RTA

will be responsible for reinstating the structure.

Access

Pedestrian access is eminently possible from anywhere along the south or east boundaries, and to a

slightly more limited extent from the west. A primary source of access to the site is of course the

underground station, and the abra stations, also providing a source of pedestrian traffic. A desire line

exists through the site from south west to north east, connecting both creek side and Deira commercial

districts to the Al Ghurair centre. Road access will be along the south and east boundaries, avoiding the

junction for obvious safety reasons.

Figure 19 illustrates the linkages of the site to other public transport modes with taxi and ferry stations.

Figure 19: Omar Bin Al Khattab proposed bridge

Page 31: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

31

The Transport plan in Figure 20 shows that the site is directly above the confluence of the two Metro lines

(Red and Green), and is surrounded by a network of major urban roads linking it directly to wider Dubai.

The commercial developments in Al Rigga, and the hotels on the creek side, the adjacent abra station and

Dubai Municipality headquarters attract significant pedestrian populations.

Figure 20: Transport plan

Traffic Impact Assessment

The Developer will have to perform a Traffic Impact Assessment (”TIA”) during the tendering stage. An

initial TIA was performed during the Feasibility Study for the Project to evaluate possible effects of the

Project’s traffic on the transportation network of the community. This TIA concluded that TOD is an

appropriate concept for the site in order to minimize additional traffic volumes on the neighbouring roads

and to increase public transport use by visitors and residents. The TIA recognised the unique nature of the

site in terms of its public transport provision, particularly as an interchange for the Metro red and green

lines. Therefore, enhancement of public transport integration, as well as improvements to signage and

pedestrian connectivity were identified as very important to the success of the development from a

transport perspective. Such improvements are envisaged to be provided by the RTA unless they form

integral part of the Project or are required by relevant authorities, in which case they will be delivered by

the Developer.

Figure 21 illustrates that the key routes on the site perimeter attract high traffic flows. Furthermore, the

traffic observations around the site show significant traffic volumes during the peak periods, particularly at

the Al Maktoum/Omar Bin Al Khattab Junction. The wider road network around the Project site is generally

congested, with key land uses such as Al Maktoum Hospital and Al Ghurair Mall generating significant trips.

Page 32: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

32

Figure 21: Existing conditions around the Project site - key roads and junctions

Source: Atkins understanding of traffic flows – traffic data from 2011 and 2012.

The TIA recognized a number of traffic-related issues around the Project site, which are summarized in

Table 2. As mentioned previously, the Developer will have to perform its own assessment to validate and

expand findings, and to draw relevant conclusions for the Project and its success as TOD.

Table 2: Summary of Traffic Impact Assessment

Subject TIA findings

Road traffic The road network and junctions surrounding the site experience high traffic volumes;

There is limited scope to adjust existing road junction layouts or access points to the development;

Careful consideration is required when planning and providing access and egress to/from the site;

The final impact of the proposed 777 Crossing of Dubai Creek is still unknown in terms of phasing and

final design, however initial analysis of the Dubai traffic model flows indicates that this crossing could

reduce at grade traffic flows around the site at most junctions;

Bus infrastructure Maintenance of the existing bus infrastructure requires additional attention, in particular bus stop air

conditioning and Real Time Passenger Information (“RTPI”);

Additional bus-related signage may be required around the development;

Pedestrian

connectivity

A number of pedestrian crossings require improvement to support pedestrian desire lines;

Pedestrian conflict with vehicular traffic was identified, notably in the bus interchange;

There is a need to improve pedestrian connectivity to key surrounding land uses, notably the Al Ghurair

Mall;

Page 33: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

33

Subject TIA findings

Cyclist access Cycle routes would be required to connect the site to wider Deira neighbourhood;

Ideally cycle routes should be segregated from the main traffic flows;

Parking Limited control and management of surrounding parking supply;

50% reduction in all trips and parking has been proposed and approved for the Project; and

Policies such as shared parking should be promoted in the development to improve peak parking demand

management.

*Based on analysis undertaken during the Feasibility Study by F+G. Prospective Developers will be responsible for performing their

own due diligence and gather information to be used for their decision-making purposes.

Utilities

Utilities as identified in Figure 22 are readily available in the immediate area as the site is ringed with a full

range of the basic services. It is for the Prospective Developers to ascertain during the tendering stage the

adequacy of capacity to support their proposed development. A large Tabreed Chilled Water Facility is

along the Northern Boundary of the site (to supply cooling to the Metro facility). The Tabreed facility has

spare capacity and Developer should discuss with Tabreed an option for the provision of cooling services

from this facility.

Figure 22: Union Square utility connections

Page 34: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

34

Adjacent land uses

The areas surrounding the site were assessed to provide an indication of the scale of adjacent

developments. As illustrated in Figure 23 the Union Oasis site has a cemetery directly adjacent to the west

with a high proportion of low rise buildings to the north and west of the site. The majority of buildings to

the east and south of the site are mid-rise buildings with a few high rise buildings close to the Creek.

The nature of the surrounding buildings is generally mid-rise (10 to 25 storeys) mixed-use

commercial/residential/office buildings, together with one or two hotels. These structures are generally

reasonably contemporary designs, in good condition, although the low-rise commercial buildings to the

north of the site are now tired and in need of maintenance. They are generally hidden from view by the

Tabreed buildings and bus station, so do not have a direct effect on the views or character of the site.

Union Station serves both Government and commercial districts, including the Dubai Municipality's Health

Centre, the Dubai Economic Department, the Dubai Chamber of Commerce and Industry and the Dubai

Land Department. It is also a convenient access point for commuters from the Northern Emirates and a

transfer point between the Red and Green Metro lines.

Figure 23: Height of buildings in areas surrounding Union Square

Union Square Site

Mid Rise buildings:7 to 12 storeys

High Rise buildings:15 to 25 storeys

Low Rise buildings:3 to 5 storeys

Page 35: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

35

3.2 Project parameters

Key parameters

The Developer will develop the Project within the site parameters, which are set out in the affection plan,

summarized in Table 3 below. A copy of affection plan is included in Appendix A.

Table 3: Key parameters of Union Oasis development

Detail Description

Setback Not mandatory

Max Height 4 basements + G + Mezzanine + 20 story

Usage Residential, commercial, offices

Parking Not mandatory

Plot Size 37,855 m2*

Allowable Footprint 30%

FAR 2.5

Additional requirements Provide a prayer room and green areas

The entire plot size is 37,855m2, however the area of the site planned for the development is 14,662 m2.

Appendix B highlights the site area intended for the Project.

Development mix

By definition, the TOD community should include a mix of various uses. Encouraging a vibrant mix of land

uses should help to create a complete, walkable and diverse neighbourhood around Union Station and to

support community growth. Major traffic reduction benefits of the TOD occur not only because of

increased transit ridership, but because of increased walking for the majority of household travel that is

not commute-related. In a community where most of the basic needs of daily life are available within

walking distance, owning and using a car can become an optional rather than a daily requirement.

The Developer will have the flexibility to select the development mix in accordance with its market

knowledge and commercial acumen, in consideration of the Project objectives and maximum trip

generation and parking numbers allowable for the site. A balanced approach will be required from the

Developer to combine achieving TOD objectives and maximizing revenues on the Project site.

The below Table 4 summarizes examples of uses (non-exhaustive), which can be included on the site.

Table 4: Uses for consideration of the Developer

# Use type Example

1 Residential Apartments for rental

2 Commercial Offices

3 Hospitality Hotel, hotel apartments, convention centre

4 Retail Convenient stores, grocery stores

5 Community facilities Nursery, fitness centre, medical centre (e.g. dentist, walk-in clinic), park

6 Personal services Bank, post office

7 Entertainment Amphitheatre, cinema

At the neighbourhood scale, a mix of land uses such as homes, offices, hospitality retail, parks and

entertainment in close proximity creates an environment where many needs of daily life can be met within

Page 36: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

36

a short walk from home, work or transit. The development should feel safe and lively because different

types of uses are active at different times of day. A built form that supports a mix of land uses can also

allow a community to be more resilient over time, adapting to changing economy and demographics.

Areas within 200 meters of transit facilities are particularly valuable to encourage a mix of attractive land

uses. People often like to combine tasks in one trip – such as picking up coffee on the way to work or

getting groceries on the way home – and, therefore, convenient access to goods and services makes

transit much more attractive. Providing retail and community services near transit can also promote local

business opportunities and can help to create lively street life, a pleasant pedestrian environment and safe

and secure public realm.

The following should be taken into consideration by the Developer when selecting the development mix:

Encourage retail and service uses in order to put the most common needs of daily life in convenient

locations for transit riders;

Promote the most active uses such as retail, cafes and restaurants in the way to promote safe and

lively pedestrian environment;

Encourage a diverse mix of land uses that are attractive at different times of the day to encourage a

vibrant pedestrian environment;

Promote the location of grocery shops (both large and small) to support combined transit-shopping

trips and walkability;

Discourage low-density and auto-oriented uses, such as gas station or drive-through facilities; and

Locating the following land uses near to stations tends to contribute positively to transit-oriented

communities:

Convenience stores and pharmacies;

Grocery stores;

Child-care facilities;

Fitness clubs;

Restaurants and fast food outlets;

Medical services; and

Personal services.

Page 37: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

37

3.3 Architectural vision

Having analysed the constraints, objectives and priorities for the Project site, an Architectural Vision for

Union Oasis was prepared during the feasibility study stage of the Project. This Architectural Vision has

been endorsed by His Highness Sheikh Mohammad bin Rashid Al Maktoum, the Ruler of Dubai.

Figure 24 below present the Union Oasis Architectural Vision.

Figure 24: Union Oasis Architectural Vision Perspective 2

The private sector are expected to use their development and operational expertise to determine the

detailed design and development brief, which will be constructed. The Prospective Developers will be

allowed to propose improvements and modifications to the vision in their tenders.

The Developer will provide the following to adhere to the Architectural Vision:

Green roof, which represent previously existing green park on the square;

Podium at the ground level of the development;

Water feature incorporated in the development;

Community space;

Connectivity to the Metro and other modes of transport; and

Appropriate quality materials to deliver the vision.

Considerations during development of Architectural Vision

The Architectural Vision developed for the Project addresses factors, which have been identified in

consideration of the Project objectives. These are captured in Figure 25 and description below.

Page 38: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

38

Figure 25: Characteristics of the Union Square development

Landmark development

Union Square has grown out of what was once the site of a watchtower, a defensive position to the east of

the old port of Deira and Bur Dubai. As the city has expanded and grown around it, the space has been

retained, and it now holds a pivotal position in the modern business district of Deira. This open area

between old and new is a physical expression of the change that has embraced the city. It requires a

landmark development to reflect this, with a suitable development to highlight the change.

Integration of transport modes

The site benefits from superior transport links, particularly for a city centre location, with Metro

connections in every direction below ground, and road connections likewise at surface level. It also forms

an important component on the pedestrian route connecting the abras of Dubai’s Creek to the newer

commercial ventures of Al Rigga and eastern Deira, and the site is directly adjacent to the Dubai

Municipality headquarters building, the administrative heart of the city.

The Project development will encourage intermodal passenger transport, involving a combination of

various public transportation options in one journey, namely metro, buses, taxis and water transport. The

major goal of the intermodal passenger transport will be to reduce dependence on cars as the major mode

of ground transportation and increase use of public transport.

Based on international benchmarks, a half-mile-radius circle is envisaged to be the catchment area for the

Project. This will include the areas of Riggat Al Bateen, Muraqabbat, Naif and Rigga. A half mile (800

meter) corresponds to the distance someone can walk in 10 minutes at 3 mph (4.8 km/h) and is a common

estimate for the distance people would walk to a transit station.

When deciding whether to use transit, one of the most important factors for people to consider is the

distance between their origin and a transit passenger facility, and again to their destination. What matters

for the traveller is not the straight line distance, but rather the actual walking distance using available

streets and paths. While cyclists are not as sensitive to distance as pedestrians because they move more

quickly, they are more sensitive than vehicle drivers, and therefore well connected cycling routes promote

cycling as means of access to the Metro.

The Project will be designed in a way to promote cycling and walking, including provision of long-term and

short-term bicycle parking, if possible.

Page 39: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

39

Transit and walkability are mutually supported by many of the same land use and built environment

factors, such as well-designed public realm, higher density homes located near commercial uses, a

diversity of land uses and well-connected streets that reduce walking distances.

Walkability is among the best predictors of demand for transit, while transit use is predictive of physical

activity levels – transit users are more than three times more likely than non-users to achieve

recommended levels of daily physical activity. This relationship between transit, walkability and active and

healthy lifestyles suggests that combining the benefits of walkable neighbourhood design and broader

focus on transit connection in Dubai will realize the most benefits for community and environment.

Regeneration of market space

Union Square has been dedicated to the construction of the Dubai Metro for the last seven years. While

undeniably worthwhile, the temporary loss of the square has left the surrounding districts somewhat

heartless, unconnected and unsupported. The new development will bring life back to the square by

providing a balanced mix of uses and re-establishing pedestrian and transport links, and in so doing,

providing a catalyst for the regeneration of the area and in tandem, act as a driver for economic growth.

Deira has the potential to be known as the original downtown or the old souk of Dubai with ongoing efforts

to promote the area and to attract increased tourism to the neighborhood, with the Union Metro Station

already inviting to the key surrounding attractions. Union Square is a landmark space and it requires an

exceptional development to highlight the heritage, the history and the significant changes contributing to

the importance of this location.

The vibrant and community-focused Union Oasis will enhance the significant position of the location at the

heart of the transition between the old and the new city, offering some striking views over the Dubai

Creek.

Heritage

Union Oasis should capture conceptually traditional architectural approach as well as history and heritage

of the site, with the aim of maximizing the public realm where the old green park is represented by a green

roof of the podium.

Community and green space

While Dubai’s soaring buildings and network of roads form a dynamic three-dimensional composition that

emphasises the thrust and vigour of a modern city, such a structure only has resonance when set in

counterpoint to the calm of parks and gardens, natural colours and shapes, serene lines and peaceful

acoustics. The proposed development uses the space above Union Station, at the heart of the site, as the

basis of a new park, sheltered by the buildings arranged around it. It provides the communities of Deira and

Al Rigga with a new space in which to relax, in safety and peace.

To support the transit-oriented community, the public realm will be both functional and attractive, and it

will be inviting for those walking, cycling or enjoying leisure time. High-quality public spaces are expected

to take on many different forms from small, intimate spaces between buildings, through niches or steps

that allow pedestrians to pause along a busy commercial corridor, to large open plazas that can

accommodate public gatherings and events and have convenient access to public transit.

Market dynamics

Current market dynamics are developing in new directions, away from towering skyscrapers and massive

monolithic structures. The move now is toward compact developments, sympathetic to their physical

context, and with a calmer, more supportive approach to their occupants and neighbours. This proposal is

Page 40: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

40

designed to reflect Dubai’s new more considered approach to development, while still creating an

outstanding work of contemporary architecture.

Sustainability considerations

Figure 26 below illustrates matters of sustainability which the Developer will have to consider to eventually

achieve LEED Silver Certificate, which will be required as a minimum. The Developer will have flexibility to

propose the relevant design aspects and ongoing operations and maintenance considerations in order to

achieve such certification. The difficulties of dealing with the underground station, occupying a diagonal

axis of the site, should be turned to advantage by using it as a major component in the underground part of

the development, which has significant functional and environmental advantages and leaves the ground

level free for the establishment of attractive, peaceful landscaped parks and gardens.

Page 41: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Project description

41

Figure 26: Environmental considerations for Union Oasis development

Development plan

Figure 27 below presents the plan of Union Oasis development.

Figure 27: Union Oasis development plan

Page 42: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Commercial principles

42

4. Commercial principles

4.1 Transaction structure and contracts

Transaction structure

The Project will be delivered as a PPP between the RTA and a Developer selected in a competitive

tendering process. The principles associated with the PPP form of contracting will allow the private sector

to use their development and operational expertise, and commercial acumen to determine the exact

development brief and detailed design, which will be constructed. This is expected to encourage

innovation and efficiencies that can be achieved by the Developer, thus maximizing commercial returns.

It is envisaged that the Developer will establish a Special Purpose Company (“Company”) to deliver the

Project. The Company will enter into a Concession and Musataha Agreement (“CMA”) with the RTA, the

owner of the Project site. Under the CMA, the Company will be granted a long-term musataha interest in

the Project site. The Company will be responsible for the design, construction, financing, management and

operation & maintenance of the mixed-use development on the Project site. The Company will take

advantage of the revenue streams from commercial operations of the various components of the Project,

and in return will offer the RTA a percent of the project profits (see section 4.3). The RTA will mitigate the

market demand risk of the Company by providing a minimum revenue guarantee to the Developer for the

first 15 years of operations for covering O&M and debt service costs (see section 4.2).

It is currently envisaged that the musataha interest will be granted for 50 years (including the

construction period), following which the development will be handed back to the RTA. As part of the

RTA’s commitment to support Developers achieve the objectives of this Project while maintaining an

acceptable return on investment, the RTA has approved an extension of the term of the Musataha

agreement to 50 years.

A potential contractual structure for the Project is presented in Figure 28 below.

Figure 28: Potential contractual structure for the Project

Roads and Transport Authority

Project Company

Concession

Musataha

Agreement

(CMA)

Finance

providers

(Equity and/or

Debt)

Subleases

and/or

Management

Contracts

D&B

Contractor

Design & Build

Contract

Debt and/or

Equity

Potential

Sub-lessors

O&M

Contractor

Operations &

Maintenance

Contract

Page 43: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Commercial principles

43

The Developer will have the flexibility to select the financing type (corporate, project/property finance and

or hybrid) provided that any financing documentation will be subject to RTA's approval and must contain,

among other things, RTA step-in rights (envisaged through a Direct Agreement) and further, ensure that

the Project debt is ring-fenced through the Company mechanism with a definable boundary from other

corporate funding.

The Company is likely to have multiple sub-leases and management contracts beneath it providing

operational experience of the real estate assets, e.g. providing a brand for the hotel, retail management or

residences management.

Key contracts

A summary of the key commercial relationships illustrated in Figure 28, which are anticipated to

document the Project arrangements, is set out below.

The CMA will be the key contract between RTA and the Company setting out the rights granted by RTA to

the Company for the development and operation of the Project and the Company's payment obligations to

the RTA. Amongst other things, the CMA will address the following:

Contract duration;

Grant of musataha rights over the project site;

Development of the Project in accordance with the agreed design and output specification;

Operation and management of the Project including grant of sub-leases;

Assignment and sub-contracting;

Procedure for agreeing changes to the Project;

Payment by the Company to the RTA;

Minimum Revenue Guarantee Mechanism;

Treatment of Refinancing Gains;

Insurance requirements;

Force majeure and political risk;

Early termination and the effects of early termination;

Step-in rights;

Expiry of the CMA term;

Hand-back obligations to return the site and the Project to the RTA;

Disputes settlement mechanism; and

Governing laws.

As a Government entity, RTA must comply with certain procedures and processes for the award of the

Project in accordance with applicable laws. The CMA will be drafted in a manner, which will comply with all

such applicable laws, as well as the latest PPP law.

The CMA has been structured as a concession and musataha agreement under which the RTA will grant the

Company a musataha interest in the land on the terms set out in the CMA. This will allow the Company to

register the CMA with the Department of Lands, thereby taking a real right in the Project site for the term

of the CMA. As musataha interests may be mortgaged, pledged or leased under the Civil Code, this should

Page 44: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Commercial principles

44

facilitate funding for the development of the Project. The RTA has obtained an exception from the

Department of Land to allow for foreign developers to participate in the Project, enter into the CMA and be

granted Musataha rights over the land for the Project.

Appendix C includes a high-level Transaction Term Sheet, which is intended to present the key commercial

aspects of the Project and the contractual relationship between RTA and the Company. The terms and

conditions will be detailed in the CMA, which will be issued with the RFT document.

A Construction Contract will be entered into between the Company and its selected construction

contractor. Under the Construction Contract the Company will subcontract its development obligations

under the CMA to the contractor. Construction will be completed in accordance with an agreed design

(based on the Architectural Vision) and within an agreed schedule. RTA will be responsible for site

clearance. All requisite approvals for the development of the Project in accordance with the CMA are to be

secured by the Company.

The Company is expected to enter into Operating Agreements/Facilities Management Contracts,

subcontracting its facilities management and operating obligations in respect of the Project. The extent to

which such obligations are subcontracted/fully delegated to a manager may vary between different aspects

of the Project and the Company’s approach. The Company will have a flexibility to select operations

specialists.

Lease Agreements in relation to any office, residential and retail units, the Company will need to grant

leases to end-users / tenants through which revenue will be generated.

Developer Guarantee: the RTA will require a guarantee or support undertaking from the Developer in

respect of certain of the Company's obligations under the CMA, especially to the extent the Project is

equity-financed and therefore reliant on the contribution of equity funding from the Developer. The

Developer would also need to undertake to maintain its shareholding in the Company (or to sell down its

equity stake in the Company only within agreed levels).

The CMA will make provision for Security to be provided in respect of the Company’s performance during

all of the design, construction, operational and hand-back phases of the CMA term.

4.2 Minimum Revenue Guarantee

The Minimum Revenue Guarantee (MRG) concept is a mechanism for mitigating the risk of demand in

infrastructure assets. According to the Minimum Revenue Guarantee concept, approved by RTA

Management, the RTA will guarantee the Developer a minimum level of revenues during the first 15 years

of operations for covering O&M and debt service costs. The annual revenues to be guaranteed by RTA is a

biddable parameter and the Developer will propose the “annual revenues guaranteed” in its response to the

RFT. In principle, the “annual revenues guaranteed” proposed by bidders cannot exceed the revenues (in

the baseline financial model) corresponding to 45% occupancy of the development mix. If in a given year

actual revenues fall below the “annual revenues guaranteed” set for that year, the RTA will pay the

Company the shortfall in revenues. Any amount paid to the Developer by RTA will be treated as a loan. The

repayment terms of the loan will be defined by the Company in its response to the RFT (further details will

be provided in the RFT).

Page 45: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Commercial principles

45

4.3 Payment mechanism

Definition and key principles

One of the main components of the CMA is the Payment Mechanism, which is a contractual

procedure/mechanism for calculating and executing the payment from the Company to the RTA.

The Developer will be able to select one of the following combinations of payment method and security for

the Project:

Bank transfer or direct debit, accompanied by Bank Guarantee; or

Annual renewable irrevocable Letter of Credit.

The following payment components are envisaged in the CMA:

Variable Payments (payments to RTA for granting of the Musataha agreement);

Repayment of liabilities under the MRG concept (if applicable); and

Penalties.

Payment components

Variable payments (payments to RTA for granting of the Musataha agreement)

Payments to RTA will be a percentage of the profits achieved by the Company (the percentage of

profits to be paid to RTA is a biddable parameter);

The payments will be calculated and paid in advance on a quarterly basis, based on annual cash flow

estimates; and

Amounts will be adjusted at year end, based on Company’s audited accounts and other relevant

financial information.

Repayment of liabilities under the MRG Concept

If, at any point in time, RTA make cash payments to the Company under the provisions of the MRG,

these amounts will be treated as liabilities of the Company to RTA. The repayment of these liabilities

will be defined by the Company in its response to the RFT (further details will be provided in the RFT).

Penalties

Penalties will be applicable in the event of reaching contractually agreed thresholds of penalty points

accrued by the Company in relation to non-compliance with contractually agreed Key Performance

Indicators (“KPIs”);

Quarterly caps on penalty points and penalty amounts applicable will be established, and penalty

points accrued in each quarter will be cancelled at the end of such quarter;

Key considerations in determining KPIs by the RTA include:

Meeting RTA’s project objectives;

Attractiveness of the Project to market; and

Value for money.

Four categories of KPIs will be included in the CMA, focusing on the key areas of importance for the

RTA. These include:

Adherence to TOD principles;

Page 46: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Commercial principles

46

Protection of asset condition;

High quality of services; and

Compliance with Health, Safety and Security requirements.

The CMA will be flexible on the general operations and maintenance plan, which will be prepared and

followed by the Company in accordance with good industry practices.

Page 47: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Tender process and timetable

47

5. Tender process and timetable

5.1 Tender process

The procurement process will commence with the issuance of the RFQ and it will follow the below

presented four main phases (Figure 29).

Figure 29: Tender process for the Project

Pre-qualification

The objective of this phase is to short-list the Prospective Developers and invite them to submit a tender

for the Project. Bidders having expressed interest as response to this Memorandum will be automatically

invited to submit a Pre-qualification document within the framework of the Request for Qualification

(“RFQ”) document, which will be issued by the RTA. During the Pre-qualification stage, Prospective

Developers will be invited to one-to-one meetings with the RTA to further discuss any aspect of the

Transaction. The RFQ responses will be evaluated on a pass/fail basis. The key considerations in short-

listing Developers will relate to the strength of the applying organization (or consortium, if applicable) with

regards to financial capacity, resources and previous experience in delivering similar schemes. Pre-

qualified bidders will be announced.

Tender

The purpose of this phase is to select the preferred bidder for the Project. The pre-qualified parties will be

invited to submit a response to the Request for Tender (“RFT”), which will be issued by the RTA. The RFT

document will include instructions to bidders, technical specifications and the draft CMA. During the RFT

response time, the bidders will have an opportunity to ask clarification questions in relation to the RFT

contents. Furthermore they will have to perform their own due diligence and submit a Technical Proposal

and Financial Proposal to the RTA. The Technical Proposals will be evaluated and scored against detailed

criteria. The bidder will have to meet certain minimum score threshold for the Technical Proposal in order

to have the Financial Proposal evaluated.

Following the evaluation and clarifications of bidder’s responses to the RFT, the RTA will announce the

preferred bidder for the Project.

Pre-qualification

Tender

Negotiations

Close

Short-list of

developers/investors and

invitation to tender

Preferred

developer/investor

selection

Final project

agreements and

funding packageFine-tuning of best

value for money and

alignment with

objectives

Page 48: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Tender process and timetable

48

Negotiations

The purpose of this phase is to refine the detailed conditions of the CMA (technical, commercial and legal)

included in the preferred bidder’s tenders. It should be noted that the purpose of this stage is not to

re-open the discussions about Project terms, but to finalize the CMA to progress to the close. The

negotiations will be performed in consideration of fine-tuning the best value for money for the private and

public sectors and ensuring that the RTA’s project objectives are appropriately reflected in the Project

contractual documentation. During this phase, the preferred bidder will also have to negotiate/agree the

relevant funding arrangements, subcontracts and/or other agreements for the Project.

Close

The purpose of this phase is to achieve commercial and financial close for the Project, which relate to

signing all the relevant agreements. Commercial close is coinciding with the date when the RTA and the

preferred bidder have reached agreement on all the contractual documents and the CMA is signed. The

financial close is the date on which all the Project contracts and financing documentation are signed and

condition precedent for initial drawing of the debt has been fulfilled.

Page 49: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Tender process and timetable

49

5.2 Indicative timetable

An indicative timetable for the Project is provided in below Figure 30. It should be noted that this

timetable is only provided as a reference and is subject to change, based on the progress of the

transaction.

Figure 30: Indicative tender timetable

Union Square Project - Procurement Programme

Jan Feb Mar Apr May Jun July Aug Sep

1 2 3 4 5 6 7 8 9

1. Issue Request for Qualification (RFQ) document -

2. RFQ response 4

3. One-to-One Meetings 1

4. RFQ responses evaluation 2

5. Announcement of Pre-Qualified Bidders -

6. Issue of the Request for Tender (RFT) document -

7. RFT response 12

8. RFT responses evaluation 6

9. Successful Bidder announcement -

10. Negotiations 4

11. Commercial Close -

Activity

Envisaged

duration

(weeks)

2016

Page 50: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Contact Details

50

6. Contact Details

For further information in relation to the Project and submission of feedback and formal Expression of

Interest in participating in the Project tendering, please contact:

Jawad Kamal Sajwani

Project Manager – Rail Agency

Roads & Transport Authority

Phone: +9714 2902233

Mobile: +971 55 965 6565

E-mail: [email protected]

Page 51: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Appendix A – Affection Plan for the Site

51

Appendix A – Affection Plan for the Site

Page 52: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Appendix B – Area of the Site intended for the Project

52

Appendix B – Area of the Site intended for the Project

Page 53: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Appendix C – Transaction Term Sheet

53

Appendix C – Transaction Term Sheet

This Transaction Term Sheet is intended to present the key commercial aspects of the Project and the

contractual relationship between RTA and the Company. The terms and conditions will be detailed in the

CMA, which will be issued with the RFT document.

Parties and purpose The parties to the CMA shall be RTA and the Company. The Company will be

responsible for the design, construction, financing, management and operation &

maintenance of the Project.

Ownership The RTA will retain ownership of the site and it will grant musataha interest for

the site to the Company for the duration of the CMA term. The Company will own

the Project facilities for the CMA term, following which the ownership of the

Project facilities will be transferred to the RTA.

Term The envisaged term of the CMA is 50 years including construction period.

Shared risks The CMA will allocate the risks between the parties involved and will define their

respective responsibilities in connection with the Project. Table A, which appears

at the end of this Transaction Term Sheet, provides an overview of the proposed

allocation of main risks and responsibilities.

Under the CMA, the Company will be responsible for designing, building and

financing all the works of the Project, including possible delays and cost overruns.

The Company shall thus be required to obtain the permits and certificates of

authorization required for carrying out the Project, to meet all the requirements

(including environmental or regulatory requirements), as well as the obligations

of result with regard to the Project. Once construction is complete, the Company

will be responsible for the Project’s management and operations, as well as the

facilities maintenance. The demand risk, will be mitigated by the provision of a

Minimum Revenue Guarantee (MRG) from RTA to the Company for the first 15

years of operations. The maximum level of revenue guarantee is defined at 45%

occupancy and is intended to cover O&M and debt service costs.

The Company will bear all risks related to inflation and financing of the Project

during construction and operation periods.

To the extent indicated in the CMA, the RTA will support the Company in

obtaining authorizations and permits necessary to carry out the Project .

Payments In exchange for granting the musataha rights RTA will receive a share of the

annual profits of the Company. The percent of profit sharing will be proposed in

the bids, submitted in response to the RFT.

Compliance with

service performance

standards

During the operation period of the CMA term, the Company shall comply with the

agreed service performance standards and relevant Key Performance Indicators.

In the event of non-compliance, the Company will be responsible for the cost of

Page 54: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Appendix C – Transaction Term Sheet

54

non-compliance rectification and it will accrue agreed level of penalty points in

relation to each non-compliance event. If the penalty points exceed a certain

agreed threshold in a fixed period of time (e.g. a quarter) and the Company does

not improve its performance to the agreed service levels, this may progressively

lead to (i) a request for performance recovery plan by the RTA (ii) serving

warning notices by the RTA, and (iii) the CMA termination by the RTA.

In addition to the above remedies, penalties will be applicable in the event of

reaching contractually agreed thresholds of penalty points accrued by the

Company. Quarterly caps on penalty points and penalty amounts applicable will be

established, and penalty points accrued in each quarter will be cancelled at the

end of such quarter.

Compensation on

termination

The CMA will include a compensation on termination (“comp on term”) regime

that will set out compensation payable by the RTA to the Company, if the CMA

terminates early. The following three scenarios will be contemplated in the CMA,

if the Project is financed using limited recourse project finance debt:

Company default

RTA default or RTA voluntary termination

Prolonged force majeure

Insurance and

guarantees

The CMA shall stipulate that appropriate insurance coverage guarantees, letters

of credit and bonds be obtained and maintained in force by the Company.

Page 55: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Appendix C – Transaction Term Sheet

55

Table A: Key risks and responsibilities allocation between the Company and RTA

Risk / Responsibility Responsible

Design and construction Developer RTA

Authorization and permits

Design

Construction

Legal liability and property insurance

Construction schedule and schedule overruns

Cost overruns

Operations phase

Management and operations

Facilities management

Legal liability and property insurance

Demand on Project facilities (MRG is provided for the first 15 years of

operations – MRG is capped at a level of 45% occupancy)

Inflation and financing

Risk of inflation fluctuations during the construction and operation phases

Financing terms and conditions

Legend

Bears full responsibility partial responsibility

Page 56: Confidential Information Memorandum - rt A...This Memorandum is furnished on a confidential basis for the purpose of evaluating an investment in the Project. The information contained

Appendix C – Transaction Term Sheet

56