Cerner Lab Upgrade with 2Hour Order Entry Downtime September 28 th 10-12noon Simultaneous implementation of two projects: Cerner Laboratory Information System (LIS) will replace the current GE (LIS) Abbott Diagnostics automated chemistry line will replace the current Beckman instruments

description

Cerner Lab Upgrade with 2Hour Order Entry Downtime September 28 th 10-12noon. Simultaneous implementation of two projects: Cerner Laboratory Information System (LIS) will replace the current GE (LIS) Abbott Diagnostics automated chemistry line will replace the current Beckman instruments. - PowerPoint PPT Presentation

Transcript of Cerner Lab Upgrade with 2Hour Order Entry Downtime September 28 th 10-12noon

Page 1: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

Cerner Lab Upgradewith 2Hour Order Entry Downtime

September 28th 10-12noonSimultaneous implementation of two projects:

Cerner Laboratory Information System (LIS) will replace the current GE (LIS)

Abbott Diagnostics automated chemistry line will replace the current Beckman instruments

Page 2: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

ACTIONS NURSING UNIT TO TAKE NOW TO PREPARE

●Staff unit appropriately: (higher than a normal Saturday)●Schedule an MR and ●Schedule one extra nurse

●Make sure Downtime Kits are fully stocked for all types of Downtime documents before September 28th ●physician order (POS) sheets (remove all triplicate forms you

may still have)● lab requisitions

●Look for emails, articles and Nurse Alerts with the latest details prior to the day

Page 3: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

Order Ample Supply of DT Lab Requisitions and POS

E-docs link to order downtime requisitions:https://edocsprod.mc.vanderbilt.edu/EDocsView.aspx?EDocsId=3363

Page 4: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

PreDowntime – Day of● Providers encouraged to:

● Order routine lab tests prior to 10am● Avoid ordering serial labs prior to 12N

● Nurses to ● Sort Batch print of requisitions to remove those dated and

timed after 12 Noon 9/28/2013. Discard them● Dock Glucometers at midnight as usual then begin scanning

account # on armband instead of MRN● Send specimens prior to 10 am whenever possible

● MR ● Print extra HEO lab labels, have POS ready to stamp for

providers● Sort batch requisitions, shred those timed for after 12 noon

● SSS to round on units to remind about the downtime processes

Page 5: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

During Downtime-Provider and Nursing Instructions

● DT Orders entered on STAMPED/LABELED downtime physician order sheet

● New labs sent with STAMPED/LABELED DT paper requisitions● Labs ordered prior to DT will be sent with the HEO/Wiz requisition

printed at order time UNTIL 12NOON● Medications ordered during DT will be faxed to pharmacy per normal

HEO/WIZ DT procedures and will be entered by pharmacy then available in Admin-Rx

● Labs will be resulted as usual though possibly slower● Systems Support onsite for inpatient areas to assist with questions

related to downtime● Clinical Operations Engineers will be onsite to support outpatient areas

using VOOM

Page 6: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

During Downtime – MR● Be prepared to assist nurses and providers with stamped/labeled

DT POS, and lab requisitions as needed● Fax medications orders to pharmacy so they can enter into HMM

● Nurses will then be able to administer meds in Admin-Rx● Notify these services by phone of any new orders and a DT

requisition:●Radiology●Respiratory Therapy or Rehab Services ●Heart Diagnostic Test (Echo, EKG)●Lab:

● Labs will continue to be done during the downtime and results posted in StarPanel

● Critical Labs will be communicated to provider/unit per protocol● Questions during the DT can be called to the lab hotline:

Page 7: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

After Downtime- Nursing Nursing Instructions:●Charge RN will ensure that remaining HEO

requisitions timed after 12 NOON are thrown away

●SSS/DT Team -Active Lab orders in HEO will be dc’d and reentered starting at 12 noon ●New HEO requisitions will be printed as the

orders are re-entered in HEO/Wiz●Any lab that needs to be sent prior to receiving

the new HEO/Wiz requisition should be sent with a DT requisition

Page 8: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

After Downtime-Nursing, cont.Nurse Instructions:Verify labs carefully – the team dc’ing and re-entering the orders will not know what you sent, order changes etc. during the downtimeAsk: ●Was this lab sent during the downtime?●Do we still need this lab? Did it get dc’d on paper or

verbally during the DT●Which requisition should be used? – if you have 2

HEO requisitions, use the requisition with the most recent “request date/time” on the requisition

Page 9: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

After DT – MR and PharmacistsMRs (or designee): ●Enter “ongoing non-pharmacy” written orders

into HEO/Wiz●Written completed orders during Downtime will

NOT be back-entered into HEO/WizPharmacists:●enter “ongoing” written medication orders into

HEO/Wiz●Once processed in HMM, medication orders

display in Care Organizer to be verified

Page 10: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

After Downtime-ProvidersProvider Instructions:●All lab orders in HEO/Wiz will be dc’d and

reentered to allow HEO to communicate the order to Cerner lab

●Lab orders will be reentered as “written” to avoid multiple co-signatures needed but be prepared as some may occur

Page 11: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

After DT cont. Changes for Point of Care Blood Glucose,

GEM, & Hemoglobin A1C Testing

• Inpatient Nurses will now scan patient’s account number and not the MRN

• Outpatient nurses will scan/enter the Epic account number on the label or encounter form

Page 12: Cerner Lab Upgrade with 2Hour Order Entry  Downtime September 28 th  10-12noon

Reference Numbers & Resources for Lab Upgrade 9/28/13

• 3-HELP – HelpDesk will contact lab or support group to assist as needed

• VUMC Lab to see new reference ranges• www.lab.vu.com or click on this StarPanel icon:

• 5-LABS during the DT for lab questions• SSS website for DT Process questions:

• SSS Downtime webpage• Link to order DT Forms from E-docs:

• https://edocsprod.mc.vanderbilt.edu/EDocsView.aspx?EDocsId=3363