    Network Life Cycle

    Created by Michael Law

  • 8/13/2019 CCDA Exam Quick-Study - Network Life Cycle

    2/11

    Citations Teare, Diane, 2008. Authorized Self-Study Guide:

    Designing for Cisco Internetwork Solutions (DESIGN),Second Edition. 800 East 96thStreet, Indianapolis,Indiana 46240 USA: Cisco Press

    Cisco Systems, Inc

  • 8/13/2019 CCDA Exam Quick-Study - Network Life Cycle

    3/11

    Network Life CyclePrepare

    Plan

    Design

    Implement

    Operate

    Optimize

  • 8/13/2019 CCDA Exam Quick-Study - Network Life Cycle

    4/11

    Prepare Phase Identify customerrequirements.

    Develop network strategy.

    Propose high-level conceptual architecture. Identify technologies that will be implemented.

    Assess the scope of the network design project.

    Identifying required information.

    Understanding organizational goals/constraints andtechnical goals/constraints.

  • 8/13/2019 CCDA Exam Quick-Study - Network Life Cycle

    5/11

    Prepare Phase - ExtensionIdentification Hierarchy

    Organizational Goals

    Add NewCustomerServices

    ImproveCustomerSupport

    Reduce Costs

    IncreaseCompetiveness

    OrganizationalConstraints

    Budget

    Personnel

    Policies

    Schedule

    Technical Goals

    ImproveNetwork

    Performance

    ImproveSecurity andReliability

    DecreaseExpected

    Downtime

    ModernizeOutdated

    Technology

    Technical Constraints

    ExistingEquipment

    BandwidthAvailability

    ApplicationAvailability

    Lack ofQualifiedPersonnel

  • 8/13/2019 CCDA Exam Quick-Study - Network Life Cycle

    6/11

    Plan Phase Identifying networkrequirements.

    Assess locations and existing network information.

    Perform gap analysis to determine if existinginfrastructure can support proposed system.

    This will manage tasks, responsibilities, criticalmilestones and resources required to implement.

    The output of this phase is a set of networkrequirements.

  • 8/13/2019 CCDA Exam Quick-Study - Network Life Cycle

    7/11

    Design Phase Design will be based on the requirements identified in

    the plan phase.

    Gather information from customer input, networkaudit, traffic analysis and network health checklist.

    A detailed design of the network is createsdocumentation for infrastructure, services and

    applications to be used. Create topological maps

  • 8/13/2019 CCDA Exam Quick-Study - Network Life Cycle

    8/11

    Design Phase - Extension Reviewing existing documentation including hardware,

    software, configuration and location of devices and cabling. Obtain verbal input about network to determine impression

    of network.

    CustomerInput

    Perform audit to judge against customer input of network. Reveals information about network including hardware,

    configuration and verification of existing documentation.

    NetworkAudit

    Verifies set of applications currently on the network. Alsomay reveal additional traffic unknown from the first twosteps.

    Reveal importance of traffic, priority and security.

    TrafficAnalysis

  • 8/13/2019 CCDA Exam Quick-Study - Network Life Cycle

    9/11

    Implement Phase The network is built according to the design

    specifications.

    Integrate devices without disruption or creating apoint of vulnerability.

    Sub-phases of the implementation phase are listed inorder: description of step, reference to design,

    implementation guidelines, rollback guidelines,estimated time needed for implementation.

    Verification of design is found in the implementationphase.

  • 8/13/2019 CCDA Exam Quick-Study - Network Life Cycle

    10/11

    Operate Phase Maintain the networks health on a day-to-day basis.

    Fault detection-and-correction and performance

    monitoring occurs in the operate phase. Monitor the network for errors and problems.

  • 8/13/2019 CCDA Exam Quick-Study - Network Life Cycle

    11/11

    Optimize Phase Proactive network management. Identify and resolve

    problems before they occur.

    Reactive fault correction occurs when proactivemanagement cannot predict and mitigate failures.

    The optimize phase may lead to network re-design iftoo many errors occur.