Case Study HS2

2
Registration No. 5839536 Removal of contaminated ground high in heavy metals and offsite treatment at Dunton soil treatment hub and installation and value engineered reduced thickness piling mat Client: Willmott Dixon Site: HS2 College, Birmingham Contract Value: £950,000.00 Duration: 2 Months Technology Used: Tensar TriAx TX190 Geogrid Bioaccelerator and Regener8 Treatment Products Dunton were appointed by Willmott Dixon to remove 3,500m3 of surplus contaminated made ground to the Wolverhampton hub site to treat and reduce waste classification prior to landfill. A pile matt was designed to reduce stone import by use of a Geo-Grid membrane. DEL were also asked to pre dig the drainage channels and backfill with clean 6F2 stone so that when the groundworks placed their drainage they would not encounter any contaminated materials DEL also managed pile and ground worker arisings via stockpiles and the hub site and/or direct to landfill. Registered Office: Unit 1, Tamebridge Industrial Estate, Aldridge Road, Perry Barr, Birmingham, B42 2TX www.duntonenvironmental.co.uk [email protected] Dunton were very professional and helpful in the approach to the specific site constraints Nick Gibb– Preconstruction Director Case Study

Transcript of Case Study HS2

Registration No. 5839536

Removal of contaminated ground high in heavy metals and offsite treatment at Dunton

soil treatment hub and installation and value engineered reduced thickness piling mat

Client: Willmott Dixon Site: HS2 College, Birmingham Contract Value: £950,000.00 Duration: 2 Months Technology Used: Tensar TriAx TX190 Geogrid Bioaccelerator and Regener8 Treatment Products

Dunton were appointed by Willmott Dixon to remove 3,500m3 of surplus contaminated made ground to the Wolverhampton hub site to treat and reduce waste classification prior to landfill. A pile matt was designed to reduce stone import by use of a Geo-Grid membrane. DEL were also asked to pre dig the drainage channels and backfill with clean 6F2 stone so that when the groundworks placed their drainage they would not encounter any contaminated materials

DEL also managed pile and ground worker arisings via stockpiles and the hub site and/or direct to landfill.

Registered Office: Unit 1, Tamebridge Industrial Estate, Aldridge Road, Perry Barr, Birmingham, B42 2TX www.duntonenvironmental.co.uk • [email protected]

‘Dunton were very professional and helpful in the approach to the specific site constraints

Nick Gibb– Preconstruction Director

Case Study

Hazardous soils present on site ● The site was historically used for industrial activity dated back to 1839, predominantly metals manufacture and glass works, and due to this, there were some hazardous and Non-hazardous waste class soils which required treatment and cart away. Hazard to workers and public residents ● The project comprised of excavation of contaminated materials and placing them in temporary stockpiles prior to treatment off site, which may cause environmental impacts, (dust, noise, odour). Excess waste soils also not geotechnically suitable for construction ● The structural properties of the existing soils were not suitable for construction of the proposed HS2 college.

Registered Office: Unit 1, Tamebridge Industrial Estate, Aldridge Road, Perry Barr, Birmingham, B42 2TX [email protected]

Challenges

Our Solution

A CEMP

(Construction

Environmental

Management

Plan) was put in

place prior to the

commencement

of the works, where

the procedures of

monitoring dust,

noise and odour

was undertaken on

site to ensure these

pollutants were

kept under control.

Results

A value engineering

exercise resulted in

an Interlock Tensar

TriAx TX 190 geogrid

placed to provide

additional tensile

strength to the

subgrade followed

by 300mm of 6F2

placed in layers and

compacted to

minimise any

settlement during

pile installation.

100% Recycled materials

recovered

• Project was completed on time

• Project was completed on budget

Asbestos and

heavy metals

containing

material was

identified within

the stockpiles,

which were

removed off site to

the DEL treatment

hub where the

material was

treated and

disposed of as

non-hazardous to

licensed facilities

at a reduced cost.