    Work Planning & Control OverviewDefining Required

    Maintenance TasksExecuting Maintenance

    TasksCapturing

    MaintenanceHistory

    Impro

    Identify Ad-HocMaintenance Tasks

    PlanningInputs: Planned

    MaintenanceSchedules

    Unscheduled WorkOrders (from PM,

    PDM feedback) Outstanding Work

    Orders Backlog (of

    scheduled WorkOrders)

    Production Demand(Ops Plan)

    Outputs: Ops Plan 5 yr plan 1 yr plan 3 month plan Weekly plan

    Opportunity Planning Overhaul Planning Workload smoothing Resource planning Etc.

    TacticalMaintenance

    Non-tacticalMaintenance

    E

    M

    3Emergency

    RepairEmergency

    Maint. Procedure

    2Operator RepairFirst Line Maint.

    Procedure

    4Plan &

    Schedule JobsPlanning

    Procedure

    6Do PM

    MaintenancePreventative

    Maint. Procedure

    7

    Do PredictiveMaintenance

    Predictive Maint.Procedure

    11Do CorrectiveMaintenance

    Corrective Maint.Procedure

    8Repair by UHAR

    UHAR RepairProcedure

    9Repair by

    ContractorContractor Repair

    Procedure

    10Overhaul Unit

    (UHAR)Unit Overhaul.

    Procedure

    MOO

    MO

    Pr

    P

    K

    U

    Incident Log Observations

    1Report FaultsFault Reporting

    Procedure

    5Operator Checks

    Daily RoutineChecks

    12Close-OutWork OrderClose-outProcedure

  • 8/3/2019 ALUR WPC

    2/61

    enance

    snt

    t

    ens

    ening

    e

    g

    S

  • 8/3/2019 ALUR WPC

    3/61

    Any Person

    1.1

    If you see a fault,ID the equipmentno & report it the

    Operator

    Yes

    No

    Operator

    1.2Is the faultrecorded?

    MIMS

    Operator

    1.4

    Log fault on MIMSIncident Log

    MSO627:

    Complete as far aspossible:

    add production

    work group name

    Date

    operation shift,

    equipment

    number

    exact time offinding

    detailed problem

    description

    maintenance typerequired

    FLM Sup Name

    where applicable

    Operator

    1.3Notify Fault

    Reporter that faultis logged already.

    Yes

    No

    Ops Sup

    1.6Can it be

    rectified byFirst LineMainte-

    nance?

    MIMS

    Ops Sup

    1.9Raise a Work Orderon MIMS (MSO627

    action W)andassign to a work

    group.

    Ops Sup

    1.7Notify Operator to

    carry out therequired First Line

    Maintenance

    Yes

    No

    Ops Sup

    1.8

    Does itrequire

    Emergency

    Repair?

    Operator

    1.5Notify Sup Ops

    Yes

    No

    Ops Sup

    1.10Day Time?

    Ops Sup

    1.1Report to

    Mai

    Ops Sup

    1.11Report to

    Mai

    Emergency if:

    Serious

    Safety Risk

    Unit Trip

    20%+ Derated

    Will cause trip /

    20%+ derationif not repairedwithin 48 hrs

    1.0 Fault Reporting

  • 8/3/2019 ALUR WPC

    4/61

    2.1FLM

    3.1EM

    4.5.1P & S

    Sup Crt

    ech Crt

  • 8/3/2019 ALUR WPC

    5/61

    2.0 First Line Maintenance

    1.7FR

    Operator

    2.2

    Investigate job todetermine whattools and material

    are required

    O

    Mus

    Operator

    2.6Collect Tools &

    spares if required,then carry outmaintenance

    Opera

    Reco(fail

    corrematerWO /retur

    Yes

    No

    Operator

    2.3Materialrequired?

    Operator

    2.1Record Incident No

    in Operatorsworkbook

  • 8/3/2019 ALUR WPC

    6/61

    MIMS

    s Sup

    2.4Issue Generalaterial requisitioning standard WO

    per unitMSQ140 &

    SO62Q action I

    MIMS

    DM Prod

    2.5Authorise Materialrequisition usingstandard WO per

    unitMSQ140 &

    MSO62Q action I

    Operator

    2.8Return unusedparts to store

    tor

    2.7rd all findingsure, cause,ctive action,ial usage) onworkbook &to Ops Sup

    MIMS

    Ops Sup

    2.9Close Incident Log

    MSO627

    13.1

    13.2

  • 8/3/2019 ALUR WPC

    7/61

    3.0 Emergency Maintenance

    1.11

    FRTech Cr Maint

    3.1Do a FieldInspection

    Location Surrounding

    Area Equipment

    Status Facility

    Availability Other related

    equipment Safety Factors

    Yes

    No

    Sup Cr Maint

    3.3Can UP Fixproblem?

    Sup C

    RespGro

    Tech Cr Maint

    3.14Record all fin

    (failure, caucorrective ac

    material usagWO / workboreturn to Ops

    Sup Cr Maint

    Sup Cr Maint

    3.21

    Sup Cr Maint

    Fore

    MateR

    MS

    Tech Cr Maint

    3.2Notify / Report to

    Sup Cr Maint

    1.12FR

    Tech CR M

    3.18Stage & So

    Spares /Resource

    MIMS

    Tech CR Maint

    3.16Update Job Status -

    Awaiting Spares

    Tech Cr Maint

    3.13Perform required

    Maint. Job

    Yes

    No

    Tech CR Maint

    3.11Spares /

    ResourcesAvailable?

    Tech Cr Maint

    3.12Collect Tools,Spares, etc as

    required for Job

    Tech CR Maint

    3.17Notify Sup Ops &

    Sup CR Maint

    Tech CR Maint

    3.20Close work permit

    Tech / Sup CrMaint

    3.8Raise ManualRequisition for

    Material

    Printer

    Tech / Sup CrMaint

    3.6Print Job Card

    Tech CR Maint

    3.7Obtain a work

    permit

  • 8/3/2019 ALUR WPC

    8/61

    Sup Cr Maint

    3.19Notify Sup Prod

    that job iscompleted

    Yes

    No

    .Job

    Completed?

    job feedback onJob CardSign-off

    3.22Deliver Complete

    Card to Plann

  • 8/3/2019 ALUR WPC

    9/61

    Sup Cr Maint

    3.5Notify UHAR

    MIMS

    r Maint

    3.4Changeonsible Workup to UHAR

    8.2UHAR

    dingsse,tion,e) onok &Sup

    MIMS

    an Cr Maint

    3.9rial & Sparesequisition140 / MSQ

    Action I

    MIMS

    Sup Cr Maint

    3.10Approve

    Requisition

    aint

    rce

    s.

  • 8/3/2019 ALUR WPC

    10/61

    d Jober

    12.1CWO

  • 8/3/2019 ALUR WPC

    11/61

    6.0 Preventive Maintenance

    MIMS

    Sup PM

    6.3Raise RequisitionsGeneral Material

    MSO140 &

    MSO620 Action I

    MIMS

    DM Maint

    6.4Approve

    Requisitions forGeneral Material

    Sup Ops

    6.14Approve Job

    Feedback

    Tech PM

    6.15Return Tools

    Sup PM

    6.1Receive Job Cards

    Yes

    No

    Sup PM

    6.2Job Cardrequire general

    materila?

    D

    Foremen PM

    6.7Allocate Job Cardsto PM Technicians

    Tech PM

    6.9Obtain Permit to

    Work from Sup Ops

    Tech PM

    6.10Execute

    Tech PM

    6.12Record all findings

    on job cardincluding correctiveactions required &

    material usage.Return to Sup PM

    Tech PM

    6.8Collect Tools, GenMaterials, etc asrequired for Job

    Sup Ops

    6.13Close work

    permit

  • 8/3/2019 ALUR WPC

    12/61

    12.1CWO

    Yes

    No

    M Maint

    6.5RequisitionApproved?

    Sup PM

    6.6Distribute JobCards to applicable

    Foremen

    ork

    Sup PM

    6.16Evaluate and verifyjob feedback on

    Job CardSign-off

    Yes

    No

    Tech PM

    6.11Any other faults

    identified?1.1

  • 8/3/2019 ALUR WPC

    13/61

    4.0 Maintenance Planning

    4.1

    Develop 5 yearPlan

    4.2Develop Plan of the

    Year

    4.3Develop Plan of the

    Quarter

    4.4Develop Plan of t

    Week Detail Planning

    & Scheduling

    of individual

    Outages First Line

    MaintenanceWork Orders

    Monthly

    Schedule &LoadBalancing

    Work outsideOutages not urgent(required afterdays)

    Preventative

    Maintenance

    UHAR

    Contractor

    Corrective

    Yearly

    Quarterly

    Monthly

    Weekly

    Yearly PM &PdM Schedule

    & LoadBalancing

    Yearly

    MaintenanceBudget

    PlannedOutage

    Scheduling

  • 8/3/2019 ALUR WPC

    14/61

    he

    4.5Develop Plan of the

    Day

    7

    Daily

    Work outsideOutages urgent (requiredin less than 7 days)

    PreventativeMaintenance

    UHAR

    Corrective

  • 8/3/2019 ALUR WPC

    15/61

    4.5 Planning & Scheduling

    Plan the Jobsmake sure that all thematerial andresources (Spares,Support Equipment,People, Time requiredto complete a Job)are available,complete with thedetailed taskinstructions, BEFOREscheduling a job andissuing the jobcard.

    This will result in moreeffective use of limitedand valuablemaintenance man-hours by reducingwasted maintenanceman-hours throughpreventing starting ajob and then have towait for material andother resources.

    Pl

    Plann

    Uploin

    Do resourcesmoothing

    Job DescriptionCheck with

    Weekly Plan

    MIMS

    Planner

    4.5.3Extract list of workorders to be done

    in next 7 days(from Morning

    Meeting)

    4.5.6Repair by UHAR

    Planning

    WOs from reported faults

    WOs resulting from PMs and

    PdMs

    4.5.5Corrective

    MaintenancePlanning

    WOs from reported faults

    WOs resulting from PMs and

    PdMs

    Additional PMs

    required

    MIMS

    Planning Sup

    4.5.12Approve Work

    Orders

    Planner

    4.5.8ID additional task

    (planningcompleted) to be

    done during Force

    Outage

    Planner

    4.5.10Complete Planning& Schedule tasks

    for today

    Yes

    No

    Planner

    4.5.7Is a forced

    outage requiredto do a job?

    Daily

    Planner

    4.5.4From WOs raised,Identify additionalPM Tasks to be

    done today

    Morning Meeting

    4.5.1Discuss IncidentLog to identifymaintenance

    actions required

    DM Maint / Ops Ops Sups

    Ops Plan Sup Maint. Sups

    Maint Plan Sup UHAR Plan Sup Eng Coordinator Planners

    MIMS

    Planner UP

    4.5.2Raise a Work Orderon MIMS (MSO627action W)andassign to a work

    group.

    5.9OC

    4.4.1

    P&SWKL

    12.5WCO

  • 8/3/2019 ALUR WPC

    16/61

    Printer

    anner

    4.5.13

    Print Job Cards

    Planning Sup

    4.5.14Distribute Job

    Cards

    MIMS

    r

    4.5.11ad scheduleto MIMS

    Planner

    4.5.9Negotiate outage

    time & duration with

    Ops Planner &Dispatcher.

    d

    4.5.15Outage Planning

    Last week before outage

    Follow-up on Specific Materialorders

    Planner

    4.5.5.1From WOs raised,Identify CM Tasksto be done from

    next week onwardsYes

    No

    Planner

    4.5.5.2Field Inspection

    Required?

    Yes

    No

    Foreman CM

    4.5.5.4Material /services

    Required?

    Pl

    Comp

    R

    4.5.1

    Yes

    No

    Sup CM

    4.5.5.5Approve

    Quantities?

  • 8/3/2019 ALUR WPC

    17/61

    Foreman CM

    4.5.5.3Do Field inspection:ID Spares, SupportEquipment, People,

    Time requiredComplete Job/Task

    Instruction

    MIMS

    lanner

    4.5.5.6

    lete Material /Services

    equisition

    Yes

    No

    Planner

    4.5.5.9All requiredMaterial &services

    Available?

    Planner

    4.5.5.10Initiate

    ProcurementProcess

    MIMS

    DM Maint.

    4.5.5.7

    Approve

    Requisition

    4.5.7

    Yes

    No

    Planner

    4.5.5.8RequisitionApproved?

  • 8/3/2019 ALUR WPC

    18/61

    4.0 Planning & SchedulingPlanner (Ops &Maint)

    4.1.1Obtain planninginputs

    Current 5 yearplan

    PlannedOutages perunit

    OperationalPlan - 5 yearproductionplan(Dispatchers)

    History(Forced &Maint.

    Outages) Unit Capacities

    MajorModifications /Upgrades

    Other majorevents to beplanned for

    Fuel Supply

    Safety

    Insurance

    Environment

    Planner (Ops &Maint)

    4.1.2Prepare a draft5-year plan

    Ops Planner

    4.1.3Distribute draft Plan

    UP Planning Team

    4.1.4Yearly PlanningMeeting no 1

    PJB Planning Team

    4.1.7Yearly PlanningMeeting no 2:

    Approve 5-yearPlan

    UP Manager

    DMs

    Ops Planner

    Maint. Planner

    ROP PJB

    UP Manager

    DMs

    Ops Planner

    Maint. Planner

    PJB Corporate

    Planner Direktorat

    Niaga

    Draft Schedule

    ResourceRequirements

    Identify LongLead Items &Services

    ROP PJB

    UP Manager

    DMs

    PJB Budgeting,Financing &Corporate Planner

    Direktorat Niaga

    UP Manager

    4.1.9Distribute Approved

    Plan

    UP Manager

    4.1.6Distribute Plan

    Planner (Ops &Maint)

    4.1.8Update 5-year planas per minutes of

    meeting

  • 8/3/2019 ALUR WPC

    19/61

  • 8/3/2019 ALUR WPC

    20/61

    Planner (Ops &Maint)

    4.1.5

    Update 5-year planas per minutes of

    meeting

    Planner (Ops &Maint)

    4.1.10Place Schedule

    onto notice boardsin planning offices

    Maint. Planner

    4.1.11Place orders forlong lead items

    (Specific Material)

    Planner

    4.2.1

    Plot 52-weekCalender

    Planner

    4.2.2

    Indicate PlannedOutages / Projects(from 5-year plan)

    L

    Planner

    4.2.5Determi

    Available Lhours / Work

    skill level /

    Planner

    4.2.8Allocate EstimatedDuration /

    Workgroup / skilllevel / week

    Corrective

    Maintenance(CM, UHAR,Contractor)

    Planner

    4.2.10Compile

    Maintenance &Capital Budget

    Planner

    4.2.9Determine

    Required Spares &Tools

    Tea

    Re

    D S S S M

    fo M

    Pl O O

  • 8/3/2019 ALUR WPC

    21/61

  • 8/3/2019 ALUR WPC

    22/61

    lanner

    4.2.3

    ist ALL ScheduledTasks

    Planner

    4.2.4Allocate Estimated

    Duration /Workgroup / skill

    level / week

    nebour

    group /week

    Planner

    4.2.6Identify Imbalances

    Planner

    4.2.7Address

    Imbalances

    Maint. Planner

    4.2.14Place order for long

    lead items(3 months plus)

    ScheduledMaintenance

    (PM &Planned

    Outages)

    4.2.11view Meeting

    Planner

    4.2.12Update Plan of the

    Year

    MIMS

    Planner

    4.2.13Update MIMS

    M Maintenanceupervisors PM

    upervisor PdMupervisors CM

    aintenanceremenaintenancelannersps Supervisor

    ps Planner

    MIMS

    Planner

    4.3.20Upload to MIMS &

    Create WOs

    Parent, Sub,

    Standing

    UHAR

    4.3.Prepare

    sche

    UHAR

    4.3.16Plan all tasks (HR,

    Spares, tools,Support Eq)

    Planner

    4.3.7Identify ALL

    Specific Materialrequired.

    Planner

    4.3.11Prioritise tasks to

    be carried outduring outage.

    Outage Te

    4.3.Meeti

    Reviewscope / pSpecific

    Planner

    4.3.1Identify Outages tobe executed within

    next Quarter

    Planner

    4.3.2Identify MajorProjects to be

    executed withinext Quarter

    First LineMaintenance

    Planner

    4.3.25Get FeedbackCurrent StandiWork Order fo

    Closure

    2 Monthsoutage /

    MI

    DM Maint.

    4.3.Approv

    Ord

    Plann

    A

    To be complete

  • 8/3/2019 ALUR WPC

    23/61

  • 8/3/2019 ALUR WPC

    24/61

    Planner

    4.3.19Distribute scheduleto Ops Sup, Maint.Sups & Foreman &

    UHAR

    Outage Team

    4.3.18Meeting 3

    Approve OverhaulPlan & Schedule

    Printer

    Planner

    4.3.24Print Job Cards

    10

    Planner

    4.3.9Initiate Purchase

    Procedure

    17verhaulule

    Planner

    4.3.4

    Prepare StandardScope of Work

    Planner

    4.3.5Identify additional

    scope of work

    (From PdM, PM,Incident Logs,UHAR)

    am

    12ng 2/ refineriority &

    aterial

    Planner

    4.3.13Update scope ofwork & SpecificMaterial from

    meeting

    DM Maint. & UHAR

    4.3.14Approve minutes &final scope of work& Specific Material

    n

    Planner

    4.3.26Do Job Feedback

    on CurrentStanding Work

    Order

    Planner

    4.3.28Raise New

    Standing WorkOrder

    ngr

    Planner

    4.3.27Close CurrentStanding Work

    Order

    prior toProject

    1 Month prior to

    outage / Project

    S

    21Workrs

    Planner

    4.3.15Distribute Scope ofWork to Planner UP

    & UHAR

    Yes

    No

    er

    4.3.8pecificaterialailable?

    Planner

    4.3.10Identify tasks wherematerial will not be

    available forOutage / Project

    MIMS

    Planner

    4.3.22Issue requisitionsSpecific Spares

    MIMS

    DM Maint.

    4.3.23Approve

    Requisitions

    MIMS

    Planner

    4.3.6Create WOs where

    necessary

    Outage Team

    4.3.3Meeting 1

    Confirm Outages &Projects for nextQuarter

    3 Months prior tooutage / Project

    withinOne Weekafter Meeting 3

    PlanThe pmakethe mresouSuppEquipTimecompare acompdetailinstruBEFscheand ijobca

    Thismore

    of limivaluamainthourswastemainthoursprevea jobhavematerresou

    Plan

    Extrorde

    fro

    ridays

    Thursdays

    Mon

    daystoWednesdays

    Mondays

    12.5

    WCO

  • 8/3/2019 ALUR WPC

    25/61

  • 8/3/2019 ALUR WPC

    26/61

    the Jobsurpose is tosure that allaterial andrces (Spares,ortment, People,required tolete a Job)ailable,

    lete with theed taskctions,REuling a jobsuing the

    rd.

    ill result in

    effective useited andbleenance man-by reducingdenance man-

    throughnting startingand thento wait forial and otherrces.

    Weekly Review Team

    4.4.14Weekly Review

    Meeting Schedule Backlog

    Planner

    4.4.15Update & Finalise

    SchedulesPrinter

    Planner

    4.4.17Print Job CardsPdM Job List

    Planning Sup

    4.4.18Distribute Job

    MIMS

    Planner

    4.4.12Upload schedule

    into MIMS

    DM Maint

    Planning Sup

    Planners

    CM Sups

    PM Sups

    PdM Sups

    Ops Planning

    Supervisor

    Do resourcesmoothing

    Job Description

    MIMS

    ner

    4.4.1act list of workrs to be startedm next weekonwards

    4.4.19Outage Planning

    Follow-up on Specific Material

    orders

    4.4.5Repair by

    Contractor Planning

    WOs from reported faults

    WOs resulting from PMs and

    PdMs

    4.4.4Repair by UHARPlanning

    WOs from reported faults

    WOs resulting from PMs and

    PdMs

    4.4.3Corrective

    MaintenancePlanning

    WOs from reported faults

    WOs resulting from PMs and

    PdMs

    4.4.2

    PreventativeMaintenancePlanning

    Weekly list of standard PMs

    Additional PMs required

    MIMS

    Planning Sup

    4.4.16Approve Work

    Orders

    Yes

    No

    Planner

    4.4.7Can it be

    postponed tillnext planned

    outage?

    Planner

    4.4.9ID additional tasks

    (planningcompleted) to bedone during Maint.

    Outage

    Planner

    4.4.10

    Negotiate outagetime & duration withOps Planner &

    Dispatcher.

    Planner

    4.4.11Complete Planning& Schedule tasks

    for next week

    Yes

    No

    Planner

    4.4.6Is an outage

    (maint./ planned)required to do

    a job?

    Planner

    4.4.8Update task detail

    & Mark WO for nextPlanned Outage

    4.3.4

    Printer

    Planner

    4.4.13Print Job Lists for

    next week forreview meeting

    Maint. Outage

    Opportunity

  • 8/3/2019 ALUR WPC

    27/61

    List

  • 8/3/2019 ALUR WPC

    28/61

    Planner

    4.4.2.1From MIMS,Identify StandardPM Tasks for next

    week

    Planner

    4.4.2.3From WOs raised,Identify PM Tasksto be done during

    next week

    MIMS

    Planner

    4.4.2.2Run weekly

    Planning process

    4.4.64.4.1

  • 8/3/2019 ALUR WPC

    29/61

  • 8/3/2019 ALUR WPC

    30/61

    Planner

    4.4.3.1From WOs raised,Identify CM Tasksto be done from

    next week onwardsYes

    No

    Planner

    4.4.3.2Field Inspection

    Required?

    Foreman CM

    4.4.3.3Do Field inspection:ID Spares, SupportEquipment, People,

    Time requiredComplete Job/Task

    Instructions

    Yes

    No

    Foreman CM

    4.4.3.4Material /services

    Required?

    MIMS

    Planner

    4.4.3.6

    Complete Material /Services

    Requisition

    Yes

    No

    Planner

    4.4.3.9All requiredMaterial &services

    Available?

    Plann

    Pro

    MIMS

    DM Maint.

    4.4.3.7

    Approve

    Requisition

    4.4.1

    Yes

    No

    Sup CM

    4.4.3.5Approve

    Quantities?

    Yes

    Planner

    4.4.3.8RequisitioApproved

  • 8/3/2019 ALUR WPC

    31/61

  • 8/3/2019 ALUR WPC

    32/61

    10tementss

    4.4.6

    No

    Planner

    4.4.4.1From WOs raised,

    Identify UHARTasks to be donefrom next week

    onwards

    Yes

    No

    UHAR

    4.4.4.3Field

    InspectionRequired?

    UHAR

    4.4.4.4Do Field inspID Spares, SEquipment, P

    Time requComplete Job

    Instructio

    Yes

    No

    UHAR

    4.4.4.5Material /services

    Required?

    MIMS

    PlannerUP / UHAR

    4.4.4.7Complete General /

    Specific Material

    Requisition

    Plan

    MIMS

    DM Maint. UP /Man. UHAR

    4.4.4.8Approve

    Requisition

    Yes

    No

    UHAR

    4.4.4.6Approve

    Quantities?

    Planner

    4.4.4.2NotifyUHAR

    4.4.1

  • 8/3/2019 ALUR WPC

    33/61

  • 8/3/2019 ALUR WPC

    34/61

    No0l?

    Planner

    4.4.4.11Initiate

    ProcurementProcess

    UHAR

    4.4.4.12Prepare & Submit

    Quotation Scope, Schedule Time required

    Cost

    4.4.6

    Yes

    No

    Planner

    4.4.4.9RequisitionApproved?

    P

    I4.4.1

    Planner

    4.4.5.1From WOs raised,Identify ContractorTasks to be donefrom next week

    onwards

    Planner

    4.4.5.2Compile

    specification forwork to be done

  • 8/3/2019 ALUR WPC

    35/61

  • 8/3/2019 ALUR WPC

    36/61

    r

    .4.5.3procurementrocessl. service)

    Planner &Procurement

    4.4.5.4Review Offers from

    Contractors4.4.6

  • 8/3/2019 ALUR WPC

    37/61

    5.0 Operator Cheks for Maintenance

    Ops & MaintPlanner

    5.1Compile check listsfrom OEM Manuals,

    As Built & MaintRequirements

    Ops Planner

    5.2File Check Lists &

    copy 3-month stock

    Operator

    5.3Collect Check listfrom Ops Planner

    Operator

    5.4Perform check listinspections twice

    per shift

    Supervisor Ops

    5.6Check & approve

    Yes

    No

    Operator

    5.5Problem

    identified?

    1.1

    FR

    Supervisor Ops

    5.7Return Check List

    to Ops Planner

    Ops Planner

    5.8Prepare monthly

    report (plant /equipmentefficiency)

    Ops Planner

    5.10Archive Check Lists

    Yes

    No

    Ops Planner

    5.9Problemidentified

    from trend?

    1.13

    FR

    13.3

  • 8/3/2019 ALUR WPC

    38/61

    7.0 Predictive Maintenance

    Tech PDM

    7.4Prepare Tools for

    PDM

    Tech PDM

    7.6Obtain Permit to

    Work from Sup Ops

    Yes

    No

    Tech PDM

    7.5Require Permit

    to Work?

    Tech PD

    7.Execut

    Sup PDM

    7.9Evaluate DailyReports and

    compile weeklyreport

    Yes

    No

    Sup PDM

    7.10ID Problemsthat require

    furtherattention?

    Sup PDM

    7.11Inform Planner

    Sup PDM

    7.1Collects Weekly

    Schedule from Planning

    4

    Sup PDM

    7.2Plan and schedule

    daily tasks

    Sup PDM

    7.3Issue daily task lists

    to Technicians

    Da

    Daily DailyDaily

  • 8/3/2019 ALUR WPC

    39/61

    7e work

    Tech PDM

    7.8Download, Analyse

    & produce report

    4P&S

    End

    Sup PDM

    7.12File the analysis

    report

    ily Daily

  • 8/3/2019 ALUR WPC

    40/61

    8.0 Repair Uhar

    UHAR

    8.16

    UHAR

    8.15

    UHAR

    UHA

    ExReq

    Purch

    Yes

    No

    UHAR

    8.9Require

    additionalwork?

    U

    G

    UHAR

    8.8Sign-off Job Card

    4

    UHAR

    8.1Receive Job Cardfrom UP Planner

    UHAR

    8.2Plan & schedule

    work to be done

    Yes

    No

    UHAR

    8.7Work specified

    on job cardcompleted?

    Yes

    No

    UHAR

    8.10Must work bedone before

    return toservice?

    Sen.Sup QA

    8.11Notify UP Planner

    that additional work

    is required beforehanding back.

    To be authorised by HO

    UHAR to raise requisition for:

    Consumables

    General Material

    Specific spares (to be

    authorised by UP Planner

    4

    P&S

    UHAR

    8.4Obtain Permit to

    Work

    Yes

    No

    Planner

    8.3Repair Workto be done

    on-site?

    3.5

    EM

  • 8/3/2019 ALUR WPC

    41/61

    an ac oOperations

    ose erm oWork

    8.17Hand Job Card

    Planner

  • 8/3/2019 ALUR WPC

    42/61

    Planner / DM MaintUP

    8.18

    12.1

    8.5ecute Workuest materialase non-stock

    UHAR

    8.6Capture Job

    Feedback

    HAR

    8.12et UP Planner to

    Coordinatebetween Ops &UHAR for test

    Yes

    No

    Sup Ops

    8.13Test &Acceptwork?

    Sup Ops

    8.14Capture rework

    reason on job card

  • 8/3/2019 ALUR WPC

    43/61

    Acceptance Letter

    to

    CWO

  • 8/3/2019 ALUR WPC

    44/61

    9.0 Repair Contractor

    Requisition Process (inside 9.6)

    Contractor

    9.8Planner toCoordinate

    between Ops &Contractor for test

    YesNo

    Sup Ops

    9.9Test &Acceptwork?

    UP QC Team

    9.10Acceptance Letter

    Contractor

    9.12Hand back toOperations

    Contractor

    9.11Close Permit to

    Work

    Contr

    C

    Y

    No

    Contractor

    9.4Work to be

    done on site?4

    Planner UP

    9.6.5Notify Contractor

    that SparesRequisition is

    approved

    Contractor

    9.6.6Draw spares from

    UP store

    Yes

    No

    Sup Maint UHAR

    9.6.7Spares

    available?

    Contractor

    9.6.1Give Spares List to UPPlanner for requisition

    MIMS

    Planner UP

    9.6.2

    Raise Material

    Requisition

    Yes

    No

    DM Maint UP

    9.6.3Approve

    Requisition?

    Planner UP

    9.6.4Notify Contractor

    that SparesRequisition is not

    approved

    Contractor

    9.1Receive Purchase

    Order

    Contractor

    9.2Plan & Schedule

    work

    Contractor

    9.3Notify UP Plannerwhen you will start

  • 8/3/2019 ALUR WPC

    45/61

    Contractor

    9.5Obtain Permit to

    Work

    Contractor

    9.6Execute Work

    Request materialPurchase non-stock

    actor

    9.7apture Jobeedback

    Contractor

    9.13Hand Job Feedback to

    Planner

    12.1

    CWO

    es

    Contractor

    9.6.8Contractor to

    purchase spares

    9.6

  • 8/3/2019 ALUR WPC

    46/61

    10.0 Overhaul

    4

    Sup OH Maint

    10.1Received Job Card

    from Planner

    ELLIPSE

    Planner

    10.2Issue requisition

    General Material,

    Consumables

    ELLIPSE

    DM Maint

    10.3Approve requisition

    No

    Planner

    10.4

    MaterialAvailable?

    Supervisor Ops

    10.6Shutdown Unit/

    equipments

    Supervisor Ops

    10.7Handover to start

    up Team

    Tech OH Maint

    10.8Obtain Permit to

    Work

    Tech OH Maint

    10.9Prepares tools and

    get spares

    Sup OH Maint

    10.20

    Evaluate &Approved result of

    work

    No

    Start-up Team

    10.21Test

    Acceptance

    Tech OH Maint

    10.22Close Permit to

    Work with Start UpTeam

    Tech OH Maint/Contractor

    10.19

    Capture Jobfeedback on Job

    Cards

    No

    Planner

    10.11Additional

    work required

    Sup OH Maint

    10.12Identify & scope the

    additional workrequired

    No

    DM Maint

    10.13Get Approval

    No

    DM Maint

    10.14Required inshutdown

    Planner

    10.15Issue approval note

    ELLI

    Planner

    10.1Create

    Yes

    M

    Planner

    10.Creat

  • 8/3/2019 ALUR WPC

    47/61

    10.25Compile Overhaul

    report

  • 8/3/2019 ALUR WPC

    48/61

    Planner

    10.5

    Follow PurchaseProcedure

    Tech OH Maint/Contractor/ Eng

    10.10Execute Work

    Start-up Team

    10.23Start up plant

    up OH Maint

    Planner

    10.27

    SE

    O

    Printer

    Planner

    10.17Print Job Card

    IMS

    18e WO

    Start-up Team

    10.24Hand back to OPS

    Issue hand overcertificate

    4.0

  • 8/3/2019 ALUR WPC

    49/61

    10.26Return job card &report to Planner

    Report to identify

    improvementopportunities

    12.1CWO

  • 8/3/2019 ALUR WPC

    50/61

    11.0 Corrective Maintenance

    Sup CR

    11.1Collect Job Card

    Tech Cr Maint

    11.2Obtain Material /

    spares / tools

    Foreman

    Tech CrMaint

    Yes

    No

    Sup CR

    11.16Require

    additionalwork?

    Y

    Sup O

    11.2TestAccework

    4Yes

    No

    Sup CR

    11.17Must work bedone before

    return toservice?

    Sup CR

    11.18Notify UP Planner

    that additional workis required before

    handing back.

    Sup CR

    11.19Capture Additionalwork required on

    Job Card

    Yes

    NoTech CrMaint

    11.12AdditionalMaterial?

    Tech CrMaint

    Foreman

    Postpone

    MIMS

    Tech CR Maint

    11.4Update Job Status -

    Awaiting Spares

    Tech Cr

    11Perform

    Main

    Yes

    No

    Tech CR Maint

    11.3Spares /

    ResourcesAvailable?

    Tech

    NotifSu

    Tech Cr Maint

    11.8Get Permit to Work

    from SupervisorOps

    Yes

    No

    Tech Cr Maint

    11.7Permit to

    Work?

    MIMS

    Foreman

    11.13Material & SparesRequisition

    MSQ140 / MSQAction I

    Yes

    No

    Sup CR

    11.14Approve

    Quantitiesetc.?

    Yes

    No

    DM Maint

    11.15Approve

    Requisition?

  • 8/3/2019 ALUR WPC

    51/61

    11.2Hand baOperati

    11.23Close Permit to

    Work

    11.22Return unused

    material / spares

    11.24Sign-off Job Card

  • 8/3/2019 ALUR WPC

    52/61

    Sup CR

    es

    No

    ps

    0&pt?

    Yes

    No

    Sup CR

    11.11Work specified

    on job cardcompleted?

    Sup Ops

    11.21Capture rework

    reason on job card

    Tech Cr Maint

    11.10Record all findings

    (failure, cause,corrective action,

    material usage) onWO / workbook &return to Ops Sup

    Tech CR Maint

    11.6Stage & Source

    Spares /Resources.

    aint

    .9requiredt. Job

    CR Maint

    11.5y Sup Ops &p CR Maint

  • 8/3/2019 ALUR WPC

    53/61

    5ck toons

    11.26Hand Job Card to

    Planner

    12.1CWO

  • 8/3/2019 ALUR WPC

    54/61

    12.0 Close WO

    Planner

    12.1Receive completed

    Job Cards

    3.22

    EM

    6.16

    PM

    8.18

    UHAR

    9.13

    Contr

    10.27

    Ovrh

    11.26

    CR

    MIMS

    Planner

    12.2

    Capture Job

    Feedback on MIMS

    Plann

    Aany

    Prob

    MIMS

    Planner

    12.3

    Close Work Orders

    Standing

    Sub

    Main

  • 8/3/2019 ALUR WPC

    55/61

    Yes

    No

    r

    12.4re thereidentified

    lems to befixed?

    MIMS

    Planner

    12.5

    Create new Work

    Order Assign to

    applicable work

    group

    4.4.1

    P&S

    4.5.3P&S

    End

    13.2

  • 8/3/2019 ALUR WPC

    56/61

    13.0 Identify Maintenance Improvement O

    Same as 17.specific for M

    ImprovOpportu

    Same as 17.1, just in moredetail for Maintenance

    Improvement Opportunities

    Planner

    13.1Identify

    DeterioratingReliabilities

    Planner

    13.2Identify

    DeterioratingAvailabilities

    Ops Planner

    13.3Identify Low orDeterioratingEfficiencies

    Planner

    13.Raise MaiImprovem

    as per

    2.9

    FLM

    12.5

    WCO

    5.8

    OC

  • 8/3/2019 ALUR WPC

    57/61

    pportunities

    , just moreaintenancementnities

    4tenance

    ent ECP17.2

    17.3

  • 8/3/2019 ALUR WPC

    58/61

    17.0 Engineering Change Manage

    See 14.4 14.8forMaintenanceImprovementOpportunities

    See 14.1 14.3forMaintenanceImprovement

    Opportunities

    See 13 for Maintenance ImprovementOpportunities

    Originator

    17.1Identify need for

    change /modification

    Originator

    17.2Complete change

    proposal form(ECP)

    Originator

    17.3Submit change

    proposal to yourSupervisor

    ChangeManag

    Evalua

    c(Week

    Yes

    No

    Deputy ManagerEng

    17.6Accept needto change?

    Deputy Manager Eng

    17.7Notify Originator

    Deputy Manager Eng

    17.8Archive ECP

    Eng Team

    17.9Finalise / design

    the change /modification

    package

    Eng

    17.16Supply Updated

    Drawings

    Eng

    17.20Update PdMSchedules

    Eng

    17.21Update PMSchedules

    Eng

    17.22Update MIMS(Equipment)

    Eng

    17.17Ops Manual

    Eng

    17.19Maint Manual

    Planner (Ops /Maint)

    17.11Plan

    Implementation

    MIMS

    Planner Maint

    17.13Issue Work Order

    Ops / UHAR /Contractor / CM

    17.14ImplementChange /

    Modification

    Eng

    17.15Update package to

    As Built

    Yes

    No

    EngTeam

    17.12Require WO?

    Eng

    17.18SOP

    Eng Team

    17.10Indicate on ECP

    what docs. &systems needs to

    be updated

    DeEn

    Eng

    17.23Update ProcessControl System

    Eng

    17.24Update Business

    Process

    Supervisor

    17.4Evaluate proposed

    change(Approve)

  • 8/3/2019 ALUR WPC

    59/61

    ent

    ment Team

    17.5te proposed

    hangely Meeting)

    uty Manager

    17.25Sign Off ECP

    SafetyProcess

    ImprovementAvailabilityReliabilityetc

    Deputy Manager Eng

    17.26Archive ECP

  • 8/3/2019 ALUR WPC

    60/61

    14.0 Maintenance Optimisatio

    Same as 17.9, just in more detail for Maintenance Improvement Opportunities

    Same as 17.6, just in more detail for Maintenance Improvement

    Opportunities

    Engineer

    14.1

    Receive approvedMaint Improvement

    ECPs

    Engineer

    14.2InvestigateProposals

    RCFA FMEA

    Estimate CostBenefit

    Spare Parts Reliability

    Availability Efficiency Safety Production

    Environment Process Etc.

    Engineer

    14.4Prioritise Proposals

    for Design

    Engineer

    14.5Design Solution

    FDT Process

    Stock Levels

    Procedure Documentation Etc.

    17.5ECM

    Yes

    No

    Eng Coordinator

    14.7Approve

    designedsolution?

    Planner

    14.6Determine final

    Costs and benefitof designed

    solution

    Yes

    No

    Eng Coordinator

    14.3Go Ahead?

    17.7ECM

    En

    I

    Use sameprocess asSERP

    I

  • 8/3/2019 ALUR WPC

    61/61

    17.10ECM

    ineer

    14.8Prioritise

    plementations

    ImplementationSchedule