ABE 482 Lecture 9

download ABE 482 Lecture 9

of 23

Transcript of ABE 482 Lecture 9

  • 7/28/2019 ABE 482 Lecture 9

    1/23

    ABE 482Environmental

    Engineering in Biosystems

    September 22

    Lecture 8

  • 7/28/2019 ABE 482 Lecture 9

    2/23

    Today

    Anaerobic digester parameters

    Biogas production

    Digester heat balance

  • 7/28/2019 ABE 482 Lecture 9

    3/23

    Anaerobic Digestion Parameters

    Consider the Continuous Stirred TankReactor (CSTR)

    Hydraulic retention time

    Specific loading rate

    Specific biogas production

    Specific methane production

  • 7/28/2019 ABE 482 Lecture 9

    4/23

    Hydraulic Retention Time (HRT)

    Not same as length of time biomass is in the digester

    unless there is perfect plug flow Optimum retention time = 10-25 days for material

    with DM% = 4-12 For higher DM%, retention time is not the rate

    limiting parameter!

    /day)(mratefeedDaily)(mdigesterofVolume(days)HRT

    3

    3

    =

    (kg/day)rateremovalSolids

    (kg)TankinSolidsofMassSRT =

  • 7/28/2019 ABE 482 Lecture 9

    5/23

    Specific Loading Rate (SLR)

    Well-designed anaerobic digester willmaximize SLR

    Varies according to feedstock and

    digester type Optimum about 3-6 kg ODM/m3-day

    )(mDigesterofVolumeODM/day)(kgfedOMofMass)

    day-mODMkg(SLR 33 =

  • 7/28/2019 ABE 482 Lecture 9

    6/23

    Biogas Production

    Biogas: CH4, CO2, H2O vapour, H2S, H2 andN2

    Density of CH4 = 0.71 kg/m3

    @ stp Density of CO2 = 1.96 kg/m

    3 @ stp

    Density of biogas?

    Volume of biogas?

    Will actual biogas production be higher orlower than theoretical value?

    Theoretically: Biogas (kg/day) = ODMR (kg/day)

  • 7/28/2019 ABE 482 Lecture 9

    7/23

    Specific Biogas Production (SBP)

    Indicator of digester efficiency Should be higher than 1.5 (target

    2.5)

    )(mVolumeDigester/day)(mProductionBiogas)(daySBP

    3

    3

    1-=

  • 7/28/2019 ABE 482 Lecture 9

    8/23

    Biogas production

    15 - 3055 600.31 0.35MSW

    20640.37 0.61Sheep manure

    10 1558 610.49 0.76Pig manure

    9 3058 600.31 0.56Poultrymanure

    n/an/a0.20 0.33Cattle manure

    RetentionTime(days)

    MethaneContent(%)

    GasProduction(m3/kg dry solids)

    Material

    Table 1: Biogas production rates for a variety of feedstock materials.

  • 7/28/2019 ABE 482 Lecture 9

    9/23

    Specific Methane Production (SMP)

    Relates energy production to the potentialenergy in feedstock

    Between 0.3 0.4 for some energy crops

    Based on table data, 0.8 for some manure

    ODM/day)(kgRateLoadingOM

    /day)m(CHofVolumeODM)/kgCH(mSMP

    3

    44

    3=

  • 7/28/2019 ABE 482 Lecture 9

    10/23

    Example 2aCalculation of biogas production

    Feedstock:

    Mass = 50 t/day ODM = 13.5 t/day OMR = 9 t/day

    Biogas is 60% CH4 Volume of digester is 3,000 m3

    Calculate: Volume of biogas produced Specific loading rate

    Hydraulic retention time Specific biogas production Specific methane production

  • 7/28/2019 ABE 482 Lecture 9

    11/23

    Example 2bCalculation of biogas production

    A bench-scale digestion plant of mixed

    wastes produced the following results Reactor volume = 2 L

    Feedstock CODinf= 97,000 mg/L

    CODeff= 4,000 mg/L Biogas = 1.13 m3/m3-day

    CH4 = 59%

    Daily feed rate = 55 mL

    Determine the volume of CH4 produced perkg of waste digested (SMP)

  • 7/28/2019 ABE 482 Lecture 9

    12/23

    Energy Calculations

    Energy balance of an anaerobicdigester involves

    Fuel value of biogas

    Conversion of biogas to useful energy

    Digester heat input

  • 7/28/2019 ABE 482 Lecture 9

    13/23

    Fuel Value of Biogas

    Lower Calorific Value of CH4

    = 35.7MJ/m3

    How much energy is produced when 1

    m3

    of biogas is combusted (60%CH4)?

  • 7/28/2019 ABE 482 Lecture 9

    14/23

    Example 3Fuel value of biogas

    Calculate the fuel value (kW) of thebiogas produced from Example 2a

    7500 m3/day @ 60% CH4

    Calorific value of CH4

    = 35.7 MJ/m3

  • 7/28/2019 ABE 482 Lecture 9

    15/23

    Conversion of Biogas to UsefulEnergy

    Convert fuel energy to useful energy

    Hot water in a boiler Electricity and hot water

    Methane converted to hot water withefficiency = 85%

    Methane converted to electricity withefficiency = 32%

    Heat also recovered Engine jacket water (80C) efficiency = 35%

    Engine exhaust (500C) efficiency = 18%

  • 7/28/2019 ABE 482 Lecture 9

    16/23

    Conversion of Biogas to UsefulEnergy

    Convert to hot water only (boiler)

    7,500 m3 biogas per day produces 136,400 MJper day of hot water or 1580 kW of continuoushot water

    Convert to electricity and hot water (CHP

    unit) 7,500 m3 biogas produces 595 kW of electricity 7,500 m3 biogas produces 650 kW of hot water

    (engine jacket) 7,500 m3 biogas produces 335 kW of hot water

    (exhaust) Total: 1580 kW of electricity and hot water

  • 7/28/2019 ABE 482 Lecture 9

    17/23

  • 7/28/2019 ABE 482 Lecture 9

    18/23

    Example 4Calculating heat loss and input

    The 3,000 m3 digester was designed with a

    0.33 surface area to volume ratio. Theinsulation thickness is 0.1 m and has aconductivity of 0.035 W/m-C. The digesteris running at a temperature of 37C.

    Calculate the heat loss through the surfaceif the ambient air temperature is 5C.

    The feedstock enters the digester at a

    temperature of 10C and a rate of 50t/day. Calculate the heat input required toraise the temperature to 37C.

    Specific heat capacity of water = 4.19 kJ/kg-C

  • 7/28/2019 ABE 482 Lecture 9

    19/23

    Digester Heat Balance

    Balance between energy produced

    from biogas and energy required tomaintain mesophilic temperatures

    Other energy requirements of

    anaerobic digester? Stirring, pumping, etc.

    Energy produced depends on OMR, so

    for feedstocks with lower ODM,energy produced will be lower

  • 7/28/2019 ABE 482 Lecture 9

    20/23

    Example 5Digester heat balance

    If the 7,500 m3 per day of biogas is used to

    produce hot water only, what percentage ofthis hot water energy is required fordigester heating?

    What percentage of the hot water energyfrom a CHP unit is required for digesterheating?

    What percentage of energy produced (hotwater only) is required for digester heatingduring a Saskatchewan winter?

  • 7/28/2019 ABE 482 Lecture 9

    21/23

    12 weeks3 weeks digestion, plus

    5 weeks composting

    Process time required to produce

    mature compost

    Nil100 150 m3

    /MgBiogas production

    Energy demandEnergy surplusEnergy balance

    100%20%Odours

    100%50%Space requirement (footprint)

    CompostingAnaerobic Digestion

    Comparison Table From: Introduction to Anaerobic Digestion,Wolfgang Muller and Axel Huttner, ORA -Organic Resource Agency Ltd., Malvern Hills Science Park, Geraldine Road, Malvern, Worcestershire WR143SZ, and IGW Ingenieurgemeinschaft Witzenhausen Fricke & Turk, and GmbH, Bischhuser Aue 12, D-37213 Witzenhausen, Germany. Presented at the Biowaste: Digesting the Alternatives Seminar, April 2005,UK.

    A Comparison of Anaerobic Digestion and Composting

  • 7/28/2019 ABE 482 Lecture 9

    22/23

    References

    Wikipedia, 2007. Anaerobic Digestion. Online:

    http://en.wikipedia.org/wiki/Anaerobic_digestionAccessed: October 25, 2007.

    Class notes for ChEng 882. 2006. University ofSaskatchewan.

    Kiely, G. 1997. Environmental Engineering. McGrawHill:USA.

    Chesshire, M. 2005. Process Calculations for Full-Scale Digesters. Biogas from Energy Crops andAgrowastes. 15th Jyvskyl Summer School:Cropgen.

  • 7/28/2019 ABE 482 Lecture 9

    23/23

    Question for next class

    Calculate the $ value of the electricity produced if all theMSW waste and manure waste produced in Canada each

    year was anaerobically digested. 25 million wet tonnes of MSW/year 132 million wet tonnes of manure/year

    30% dairy cow 30% beef cow

    20% pig 20% other

    Assume digester runs 365 days a year, 24 hours a day Assume you can sell electrical energy for 14 cents/kW-hr Assume you can convert methane to electricity with an

    efficiency of 32%

    How many Canadians will this serve?

    Use: Table 1 from lecture, ASABE standards for manurecomposition, internet for electricity consumption of Canadians.