A176 Nether Mayne Improvements - School Shut...

1
A176 Nether Mayne Improvements Hospital Roundabout The Knares Cherrydown West Woodland School Entrance Ashdon Way A176 Nether Mayne Improvements Working areas and traffic management Weeks commencing: 3 rd and 10 th November Working areas The Knares to bus stop .Remove and relay kerbs. Northbound traffic in old central reserve area w/c 3/11 Footway and maintenance bay works with lane 1 closure w/c 3/11. Lane 1 and 2 closures for duct crossings w/c 10/11 Key Cherrydown West to Ashdon Way/Nethermayne bus stop. Verge works with footpath closure w/c 3/11 and 10/11 Cherrydown West to Ashdon Way/Nethermayne bus stop. Verge works with footpath closure w/c 3/11 and 10/11 W/c 10/11 Ashdon Way closed to all traffic for 5 weeks. Footway and kerb works with lane 1 closure w/c 3/11. Lane 1 and 2 closures for duct crossings w/c 10/11 with lane closures on roundabout A176 junction with Ashdon Way. One lane northbound and one lane southbound w/c 3/11 and 10/11. Single lane traffic under lights proposed for Wednesday 12 th November 09.30 to 15.30 for lining works. Woodlands School crossing to the Knares. Remove and relay kerbs. Northbound traffic in old central reserve area w/c 3/11 and 10/11.

Transcript of A176 Nether Mayne Improvements - School Shut...

Page 1: A176 Nether Mayne Improvements - School Shut ...woodlandsschool.org/wp/wp-content/uploads/2014/08/TM-w_c...A176 Nether Mayne Improvements Working areas and traffic management Weeks

A176 Nether Mayne Improvements

Hospital Roundabout

The Knares

Cherrydown West

Woodland

School Entrance

Ashdon Way

A176 Nether Mayne

Improvements

Working areas and traffic

management

Weeks commencing:

3rd and 10th November

Working areas

The Knares to bus stop .Remove and

relay kerbs.

Northbound traffic in old central

reserve area w/c 3/11

Footway and maintenance bay

works with lane 1 closure w/c 3/11.

Lane 1 and 2 closures for duct

crossings w/c 10/11

Key

Cherrydown West to Ashdon

Way/Nethermayne bus stop.

Verge works with footpath

closure w/c 3/11 and 10/11

Cherrydown West to Ashdon

Way/Nethermayne bus stop.

Verge works with footpath

closure w/c 3/11 and 10/11

W/c 10/11 Ashdon Way closed

to all traffic for 5 weeks.

Footway and kerb works with lane

1 closure w/c 3/11.

Lane 1 and 2 closures for duct

crossings w/c 10/11 with lane

closures on roundabout

A176 junction with Ashdon Way. One lane

northbound and one lane southbound

w/c 3/11 and 10/11. Single lane traffic

under lights proposed for Wednesday 12th

November 09.30 to 15.30 for lining works.

Woodlands School crossing to the

Knares. Remove and relay kerbs.

Northbound traffic in old central

reserve area w/c 3/11 and 10/11.