2013-08 Barangaroo Headland Park Ea Presentation Rev00

download 2013-08 Barangaroo Headland Park Ea Presentation Rev00

of 117

Transcript of 2013-08 Barangaroo Headland Park Ea Presentation Rev00

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    1/117

     

    BARANGAROOHEADLAND PARKENGINEERS AUSTALIA SYDENY DIVISION,CIVIL AND STRUCTURAL PANEL

    Ken O’Neill BSc(Eng) CPEng NPER MIEAust, Aurecon Andy O’Driscoll BSc (Hons), Lend Lease

    27 August 2013

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    2/117

    SpeakersKen O'Neill - Bridges Leader NSW, AureconContact: [email protected] Ken O'Neill is a Chartered Engineer and Aurecon's NSW Bridges Leader. He is also the 2013chair of the Engineers Australia Sydney Division Civil and Structural Panel. Ken has worked onsome of Sydney's most recognised bridges including the Sydney Harbour Bridge and ANZACBridge. Ken was the Design Manager for Civil and Marine works on the Barangaroo HeadlandPark project. 

     Andy O'Driscoll  - Senior Project Engineer, Engineering, Lend LeaseContact: [email protected]  Andy O'Driscoll is Lend Lease's Senior Project Engineer for the Building and Civil Zone on theBarangaroo Headland Park and has been involved in the project for over a year primarily in

    delivering the building structure. Andy has over 10 years' experience in the industry covering amultitude of sectors from multiple Bridges, Rail, Buildings, Roads and Earthworks. Andy hasspent the last 5 years since emigrating to Australia in Sydney working for Leighton's on theKingsgrove to Revesby Quadruplication (K2RQ) within the Bridges and Building zones.

    Presentation Overview

    mailto:[email protected]:[email protected]:[email protected]:[email protected]

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    3/117

    Part 1 – Project overview

    Part 2 – Civil and Marine

    Part 3 – Cultural Space & Construction

    Questions

    Presentation Overview

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    4/117

    Part 1 – Project overview

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    5/117

    Project Overview

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    6/117

    Project Overview

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    7/117

    Project Overview

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    8/117

    Project Overview

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    9/117

     

    Project Overview

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    10/117

    Project Overview

    Link to animation

    http://www.youtube.com/watch?v=hvx-RvLaoYY&feature=relmfu 

    http://www.youtube.com/watch?v=hvx-RvLaoYY&feature=relmfuhttp://www.youtube.com/watch?v=hvx-RvLaoYY&feature=relmfuhttp://www.youtube.com/watch?v=hvx-RvLaoYY&feature=relmfuhttp://www.youtube.com/watch?v=hvx-RvLaoYY&feature=relmfuhttp://www.youtube.com/watch?v=hvx-RvLaoYY&feature=relmfuhttp://www.youtube.com/watch?v=hvx-RvLaoYY&feature=relmfu

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    11/117

    Project Overview

     – Client – Barangaroo Delivery Authority – Superintendent - Evans & Peck

     – Contactor – Baulderstone (Now Lend Lease) – D&C

     – Value - $163m with a further $35 m optional

     – Current scope covers Separable Parts 1&2 – Headland and NorthCove

     – Separable Parts 3, 4, 5 & 6 covers the integration works, Centralforeshore, Central interim use, Cultural Space future use andHarbour Control Tower design development.

     – Contract Award 23 May 2012 – Contract Program 35 Months (includes for wet weather and some

    contingency)

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    12/117

    Project Overview

    Project Award 23 May 2012

    Planning/Design Phase June 2012 - Jan 2013

    CFEMP approval (Environmental) August 2012

    Main Compound Construction Late August 2012

    Construction started November 2012

    Northern Cove September 2013

    Building Commencement September 2013

    Project completed May 2015

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    13/117

    Project Overview

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    14/117

    Project Overview

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    15/117

    Project Overview

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    16/117

    Discipline Service Consultant

    Civil and Marine Civil and earthworks Aurecon

    Civil Hydraulics Warren Smith and Partners

    Electrical WEBB

    Geotechnical AureconLandscape Architect Johnson Pilton Walker

    Marine Hyder

    Building  Architect WMK Architecture

    Electrical WEBBHydraulics Warren Smith and Partners

    Mechanical Waterman

    Structural Aurecon

    Design: Process

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    17/117

    • Design program driven by construction

    • Safety in Design undertaken for allpackages

    • Maintenance and sustainabilityconsiderations

    Design: Process

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    18/117

    Part 2 – Civil and Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    19/117

    Civil and Marine

    • Retaining walls

    • Sewer Pump Station relocation

    • Stormwater/Seepage water retention• Earthworks

    • Harbour Foreshore

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    20/117

     

    Cultural Space

    Counterfort RW

    Northern RampRW

    Terraced RW

    Foreshore area

    Pump houseSPS14

    Southern RW

    Design: Site layout

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    21/117

    Rock excavation to create

    car park for Culture Space

    Counterfort

    Wall Existing

    ground Surface 

    Foreshore

    area involvingcaisson

    demolition 

    Fill up for

    Headland Park 

    Culture Space 

    Roof for Culture

    Space Future park level Terrace wall 

    Ground anchor

    at each

    buttress 

    Design: Site layout

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    22/117

    Design: Retaining walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    23/117

    Design: Retaining Walls

    • Retaining walls around Cultural Space

     – Counterfort wall

     – Southern retaining wall

     – Northern ramp wall

    • Terraced retaining walls

    • Northern Cove retaining walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    24/117

    Design: Retaining Walls

    Retaining Walls around Cultural Space

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    25/117

    Design: Retaining Walls

    C lt l S R t i i W ll

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    26/117

    Counterfort Retaining Wall

    • Extends approximately 160 m in length withoutmovement joints

    • Separates the park from the Cultural Space with amaximum retained height of 19 m

    • Supports the roof of the Cultural Space

    • Provides restraint to the roof against earthquakeloading in the N-S direction and western direction

    • Supports two future floors at RL8.5 and RL13.0

    • Located on the western ledge of the sandstoneextraction pit

    Cultural Space Retaining Walls

    C lt l S R t i i W ll

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    27/117

    Counterfort Retaining Wall

    Cultural Space Retaining Walls

    C lt l S R t i i W ll

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    28/117

    Counterfort Retaining Wall

    • Vertical Buttresses 4 m deep at 6 m spacing with permanent groundanchors

    • Buttresses are 550 mm thick with a widened back flange of 1000 mm by600 mm

    • Base slab of 5.5 m width with 1 m toe

    • Shear key at heel provides additional sliding resistance and structuralstiffness to the base slab

    • Very efficient wall thickness – 6m Lower section: 750 thick – 6m Middle section: 600 thick – Remaining top section: 400 thick

    • Sill beam at top of wall provides vertical support to the roof and lateralstiffness to the upper 400 mm thick wall

    Cultural Space Retaining Walls

    C lt l S R t i i W ll

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    29/117

    Geotechnical constraints

    • Made ground (demolition rubble, ripped sandstone) to an approximatedepth of 1.2 m (RL1.75)

    • Shallow sandstone bedrock below Made ground

     – Class III at approx. RL1.75 m below ground

     – Class II at approx. RL -1.0 to RL-1.5

     – Class I at approx. RL -4.0

    • Persistent clay seam throughout the site of varying depths

    • Design parameters for founding level at RL 1.0 adopted for SandstoneClass IV

    Cultural Space Retaining Walls

    C lt l S R t i i W ll

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    30/117

    Shale Band  Sandstone  Footing Base  Shear Key 

    Cultural Space Retaining Walls

    Counterfort Retaining wall

    C lt l S R t i i W ll

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    31/117

    Design loading

    • Lateral Earth Pressure φ=28o, c’=3-5kPa, γ=18kN/m3

    • Overburden soil = 500-800mm

    • In Service Live Load: 7.5 kPa

    • Construction surcharge : 10 kPa

    • Earthquake loading

    • Loading from two future floor within Cultural Space

    Cultural Space Retaining Walls

    C lt l S R t i i W ll

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    32/117

    Durability Requirements

    • Design Life: 100 years to AS5100.5-2004 Bridge Code

    • Concrete exposure classification: B1 for front face and B2

    for back face in contact with soil• Drainage detailing and crack width control critical to the

    design

    Cultural Space Retaining Walls

    C lt l S R t i i W ll

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    33/117

    Constructability Requirements

    • Wall constructed with a backward lean of 1:120

    • No movement joints

    • Designed for 9 m of fill without anchors to advance the filloperations

    • Additional reinforcement placed at connection to base slabfor crack control

    Cultural Space Retaining Walls

    C lt l S R t i i W ll

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    34/117

     Key Geotechnical Design Parameters

    Variable  Value Varianceapplied 

    angle of fr iction retained material ( ) 28  10% 

    density of retained material (kN/m3)  18  7% 

    angle of friction for sandstonebedding or foot ing base (

     

    ) 33  15% 

    angle of friction for sandstone

    bedding or shale bands ( ) 24  15% 

     Anchor capacity (kN) 5000  30% 

    Surcharge (kPa)  28  15% 

    Water pressure behind the wall (kPa)  1/3 the height 50% 

    Cultural Space Retaining Walls

    C lt l S R t i i W ll

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    35/117

    • Anchors are installed and stressed at 9 m of fill (35 mm movement intop of wall)

    • Narrow base slab allows an “Active” soil stress to be achieved

    • 3D Plaxis model was used to:• Investigate soil-structure interaction and confirm Ka stress state in soil

    • Determine size and required stress in the anchors

    • Determine in-service deflection of the wall

    • Determine in-service bearing pressure demand on foundation material

     – Front wall slab was designed to Ko to allow geotechnical design toalways govern

    Cultural Space Retaining Walls

    C lt l S R t i i W ll

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    36/117

    Fill Fill Fill

    Mode 1:

    Sliding Along

    Base or Shale

    Band 

    Mode 2:

    Overturning

    About Toe 

    Mode 3:

    Overturning

    About Anchor

    Head 

    Fill

    Sandstone

    Excavation

    Shale band

    Mode 4:

    Bearing

    Capacity

    Failure 

    Cultural Space Retaining Walls

    Counterfort Retaining wall

    C lt ral Space Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    37/117

    Plaxis 3D Model

    Assessed Vertical Soil Stress  Assessed Lateral Soil Stress 

    Cultural Space Retaining Walls

    Cultural Space Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    38/117

     

    Buttresses

    Sill beam

    Top of baseslab

    Cultural Space Retaining Walls

    Behaviour of front wall

    Cultural Space Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    39/117

    Cultural Space Retaining Walls

    Cultural Space Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    40/117

    Cultural Space Retaining Walls

    Cultural Space Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    41/117

    Cultural Space Retaining Walls

    Southern Retaining Wall

    Cultural Space Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    42/117

    Cultural Space Retaining Walls

    Northern Access Road Retaining Wall

    Cultural Space Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    43/117

    Cultural Space Retaining Walls

    Northern Access Road Retaining Wall• Designed as a propped beam• Utilises rock mass on other side for

    stability

    • Varies in height and thickness overlength• Ground anchors stabilise the base• Waterproofing behind wall• Designed for K0 soil pressure due to

    rigid prop at top of wall• Semi-integral connection to roof to

    allow precast girders to remain simplysupported

    Cultural Space Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    44/117

    Cultural Space Retaining Walls

    Northern Access Road Retaining Wall

    Terraced Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    45/117

     

    Terraced RW

    Foreshore area

    Terraced Retaining Walls

    Terraced Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    46/117

    Terraced Retaining Walls

    Conforming Design

    Tender Design

    Terraced Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    47/117

    Terraced Retaining Walls

    Key considerations

     – Robustness of walls to dealwith tree roots

     – Aperture of geogrid throughthe landscape zone

     – Size of units for lifting intoplace

     – Colour and finishes

    On site trial

    Terraced Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    48/117

     

    Terraced Retaining Walls

    Magnumstone RSW

    Terraced Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    49/117

     

    Terraced Retaining Walls

    Terraced Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    50/117

    Terraced Retaining Walls

    Terraced Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    51/117

    Terraced Retaining Walls

    Terraced Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    52/117

    Terraced Retaining Walls

    Terraced Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    53/117

    Terraced Retaining Walls

    Global Stability in Slope-W

    Northern Cove Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    54/117

    Northern Cove Retaining Walls

    Precast L-shaped retaining walls

    Northern Cove Retaining Walls

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    55/117

    Northern Cove Retaining Walls

    Precast L-shaped retaining walls

    SPS 14 Relocation

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    56/117

    SPS 14 Relocation

    SPS 14 Relocation

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    57/117

     

    SPS 14 Relocation

    SPS 14 Relocation

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    58/117

    SPS 14 Relocation

    SPS 14 Relocation

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    59/117

    SPS 14 Relocation

    Key considerations

     – Condition of the wet well

     – Fragile brickwork structure given its age

     – Minimising deflections to control cracking – Condition of brickwork for lifting

     – Constructability

    SPS 14 Relocation

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    60/117

    SPS 14 Relocation

    SPS 14 Relocation

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    61/117

    SPS 14 Relocation

    Simplified analysis

    SPS 14 Relocation

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    62/117

    SPS 14 Relocation

    Steelwork modelled separately to size members

    SPS 14 Relocation

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    63/117

    SPS 14 Relocation

    Contact analysis

    Water retention tanks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    64/117

    Water retention tanks

    Key considerations

     – Safety issues below water table

     – Interface with other construction works

     – Separation of seepage water and stormwater – Buoyancy

    Stormwater retention tank = 1250 m3 

    Seepage water tank = 220 m3 

    Pump room = 50 m2

    Water retention tanks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    65/117

    Water retention tanks

    Detailed design

    Water retention tanks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    66/117

    Changing site conditions dictated the sandstoneexcavation pit needed to go deeper.

    This led to an innovative design alternative being

    pursued.

     All tanks including a seawater heat exchange

    chamber previously located in the foreshore wererelocated into the Cultural Space.

    Water retention tanks

    Water retention tanks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    67/117

    Water retention tanks

    Final design

    Water retention tanks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    68/117

    Water retention tanks

    Water retention tanks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    69/117

    Water retention tanks

    Water retention tanks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    70/117

     

    Water retention tanks

    Water retention tanks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    71/117

    ate ete t o ta s

    Revised key considerations

     – Flooding within Cultural Space Carpark

     – Durability of pipes under 18 m of fill

     – Separation of seepage water and stormwater – Buoyancy

     – Integration with Cultural Space columns

     – Interface with sandstone extraction program

     – Interface with the counterfort retaining wall

    Water retention tanks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    72/117

    Risk mitigation

     – Penstock at foreshore with overflow to Harbour

     – Early weather warning system to empty tanks in advance of

    storm – Sealed tank with pressure lids

    Earthworks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    73/117

    Key considerations

     – Maximise general fill won on site

     – Collect seepage water

     – Build up the park to underside of landscaping level

    Earthworks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    74/117

    Earthworks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    75/117

    Earthworks

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    76/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    77/117

    Key considerations

     – Meet landscape architects design intent

     – Interpretation of the original shoreline

     – Replicates natural jointing in sandstone

     – Logistics of sandstone extraction, processing andplacement

     – Make it constructible

     – Suitability of sandstone in marine environment

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    78/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    79/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    80/117

    Innovations for sandstone placement

     – 12D Earthworks model

     – 3D Revit Model

     – Attributes assigned to each block

     – Individual barcode for each block – Tracked from birth to grave

     – GPS utilised for excavation and sandstone placement

     – Scaled down models

     – 1:1 site trials

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    81/117

    3D Revit model

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    82/117

    Scale down model

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    83/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    84/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    85/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    86/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    87/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    88/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    89/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    90/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    91/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    92/117

    3D Revit model

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    93/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    94/117

    Marine

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    95/117

    Cutting existing caissons

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    96/117

    Part 3 – Cultural Space &

    Construction

    Cultural Space

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    97/117

    Key considerations

     – Maximise use of precast concrete for safety

     – Long span roof beams to meet project brief

     – Construction program

     – Sandstone extraction pit – Future flexibility for a multiple use space

    Cultural Space

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    98/117

    Building consists of the following:- B3 Irrigation retention tanks- Basement car parks B2 & B1

    - Cultural Space @ Ground floorcomprising of a single internalspace 120m Long, 50m wide and15m high.

    - Café & Forecourt- Green Roof

    Cultural Space

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    99/117

    Building Sequence• The building is unique in the manner

    the external walls are all finished tofull height prior to any internalconstruction.

    • It has an existing rock-face cuttingwhich forms the Eastern face andnew counterfort retaining walls on

    Western and Southern elevations.

    • Access for construction is extremely

    restrictive due to the Existing Parksand residential to the East and theEarthworks and Park construction tothe West.

    • The construction of the building hasto been sequenced utilising only the

    space within its own footprint.

    Cultural Space – B3

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    100/117

    • B3 tanks made up of the rainwater tank,

    seepage tank & Pump room.• The tank structure is integral to the

    columns and foundations for the building.• The pump room has its own stair access

    from B2.

    • The tanks aredesigned to dealwith the upliftcaused by thewater pressureat depth

    • All walls andslabs are heavilyreinforced and300mm thick.

    Cultural Space – B2

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    101/117

    • B2 150mm Slabon Ground

    • Slab to have a300mm drainagelayer beneath

    • Column padfootings to befounded on

    sandstone.

    Northern Ramps• Access for Cultural Space car parks

    and loading dock is from Towns Placein the North

    • Internal Ramps include an Entry B1ramp on the east flowing through aone way system down to B2 and thenan Exiting on the B2 ramp on the west

    Cultural Space – B1 Level

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    102/117

    • Post tensioned banded beamsuspended slabs are to beutilised for both B1 andGround floor Slabs.

    • 2 Stair cores are utilised onein the north and one in thesouth and a lift core in the

    south servicing all levelsincluding the café and rooftaken you to the heart of thepark.

    Cultural Space – Ground Floor

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    103/117

    • Similar system to B1 except15kPa design live load.

    • Plantrooms at RL8.5 atnorthern end.

    Cultural SpaceC fé d li k M R

    - Café @ RL13 to be located at thesouthern end of the roof in a insitusection of the main roof

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    104/117

    Café and link to Munn Reserve section of the main roof.- The L-shaped structure forms the

    café which has an externalforecourt opening out into the park.

    - The eastern structure forms aLandbridge into the existing MunnReserve.

    Cultural Space

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    105/117

    Building Footprint

    - The building structure starts on the

    southern side of site and wrapsround the existing rockface all theway to Towns place on the northernedge.

    - The Extraction pit is required to betaken down to a minimum of RL (–)4for the B2 level Basement Car parkand RL (–)7 for the B3 tanks.

    - The main extraction pit has an areaof approx 6000 square metersoverall.

    - The height difference between thetop of the building and deepestextracted level is approx 30m.

    Cultural Space

    Tower Crane

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    106/117

    Crane• JASO J380 Luffing Tower Crane to be

    installed within the Building footprint

    • Tower to feed all construction workswithin main space from Footings tounderside of Headstocks.

    • Scope to include all insitu works prior topre-cast roof stage.

    Tower Crane

    Cultural SpaceP C t R f St t

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    107/117

    Pre-Cast Roof StructurePre-cast Elements- 20 No. Headstocks 10.8m Long & 50T

    - 57 No. Super T’s 30m long 1m Deep- Over 300 + Pre-cast Planks and Slabs

    Cultural SpaceMobile Crane – Pre-cast Install

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    108/117

    Mobile Crane Pre cast Install

    • 450T Mobile Crane to lift pre-cast

    elements from off Ground floorsuspended slab.• Grillage beams to be utilised to transfer

    point loads through building columns• Stage 1 – Install Pre-cast Headstocks

    and stress to columns.

    • Stage 2 – Install Super T’s & Planksfrom Gridline 5 to 15.• Stage 3 - Install 200mm Topping Slab.

    Cultural SpaceFuture Fitout and Expansion

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    109/117

    Future Fitout and Expansion

    - The building has been designed in such a way that the option of a future fit-

    out introducing 2 more floors at RL 8.5 and RL 13 within the main space ispossible.- The 2 levels would add a further 10,000 m2 of usable space to the end

    user.- Provisions have been made in the design for the floors and also a northern

    lift, this ability would not compromise the PT slabs and walls with the future

    required penetrations.

    Cultural Space

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    110/117

    Progress to date

     – Sandstone Extraction Pit

     – Counterfort Wall 95% complete

     – Northern ramp wall commenced – Rock pocketing for prop beams

     – Footings for columns on Northern Ramp commenced

    Cultural Space Northern Approach Structure

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    111/117

    - Northern Approach Rockpocketing underway usingpineapple on Excavator

    - FRP of Struts to tiedirectly into the existingrockface for lateral loadsfrom new structure

    Safety

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    112/117

    The key high risk construction work activities across the

    project include:-• Use of powered mobile plant (people / plant separation)• Remediation of asbestos contaminated fill;• Exposure to respirable crystalline silica dust from sandstone extraction and

    processing;

    • Work along the foreshore that involves both a risk of drowning and divingworks;• Demolition of existing foreshore cellular structure caissons that are load

    bearing;• Excavation works greater than 1.5m (sewer diversion, stormwater and

    hydraulics)

    • Work at heights with risk of significant falls (counterfort wall and buildingstructures);• Work in a confined space (sewer diversion and service investigation); and• Work adjacent to roadways that is in use by traffic.

    Sustainability

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    113/117

     

    • Use of recycled products including recovered glass sand

    and recycled aggregate in drainage•  Average 47% of cement substituted for flyash across all

    concrete mixes

    • FSC certified timber for counterfort wall formwork

    • Sandstone blocks extracted on site

    • Use of site won fill material

    • Redesign of counterfort wall to reduce concrete

    • Biodegradable hydraulic oil• 70,000 plants including trees,

    shrubs, groundcovers• Use of native and endemic

    plant species•  Aquatic and terrestrial habitat

    creation through design

    Environmental

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    114/117

    Remedial Action Plan• material compliance• reuse of on-site materials

    Environmental Management

    Framework• Air Quality• Soil & Water• Noise & Vibration• Waste• Asbestos

    Environmental

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    115/117

    Monitoring

    • Dust - real time alerts & review• Odour• Respirable Dust• Asbestos• Water Quality

    real time alerts & review for Turbidity

    Mitigation Measures• Collection & treatment of site water• Silt curtains• Dust suppression

    • Stockpile management

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    116/117

    Thank you

  • 8/16/2019 2013-08 Barangaroo Headland Park Ea Presentation Rev00

    117/117

    Questions