Project Update
June 18, 2012
Roadway Projects
• An Environmental Assessment (EA) will be required
• Engineer reviewing existing pipelines and proposed Cowart’s Creek bridges
• Scheduling Design Concept Conference meeting
Pearland Parkway
• Schematic drawings started in early April • Design phase work in full progress
• Completed 60% plan submittal to TxDOT May 18th • 60% project manual submitted May 29th
• Completed 90% plans May 30th and conducted in house plan review the same day
• Submitted 90% plans Tuesday, June 5th • Conducted plan and project manual review week of June
4th Performing power pole survey and measurement to submit attachment permit application to attach fiber optic backbone from east City limits to west City limits
• 100% Submittal – Due June 18th
ITS Project
• Max Road & Fite Road – Awaiting comments on the Request for Qualifications
(RFQ) from TxDOT – RFQ will be advertised as soon as TxDOT approves
TIP Projects Update
• 2013-2016 TIP Funding Years • Eligible Projects
– In the 2035 RTP – Air Quality Conformity Year must be 2019 or earlier – Be able to meet the ‘readiness’ schedule for the funding
year • Project sponsors required to ‘Self Evaluate’
projects • Staff evaluated all Pearland projects that are in the
2035 RTP for AQ Conformity and Readiness
2012 TIP Call for Projects
• Projects Ranked on: – Readiness
• Preliminary Design • ROW • Environmental • Utility Adjustments • Local Commitment of Funds (Council Resolution)
– Planning Factors • Congestion Relief • Regional Impact • Mobility & Air Quality • Safety & Security • Access Management
– Benefit/Cost Analysis
2012 TIP Call for Projects
• Schedule: – 5/30 HGAC TIP Workshop – 6/5 Meeting with HGAC Staff – 7/23 Council Resolution supporting the projects – 8/1 Project Submittal due to HGAC – 12/21 TPC Approval of 2013-2016 TIP Projects
• Available Funding:
2012 TIP Call for Projects
Source 2013 2014 2015 2016 Total
5-CMAQ $12.999 $31.702 $68.190 $69.150 $182.041 7-STP-MM $12.353 $9.528 $78.910 $81.310 $182.101 9-STP-ENH $12.500 $12.500 $25.000 JARC/NF $4.611 $5.186 $5.186 $5.186 $20.168 TOTAL $29.962 $46.416 $164.786 $168.146 $409.309
2012 TIP Call for Projects Project Name
Limits Funding Year
Total Project Cost
City Contribution
TxDOT Contribution
Smith Ranch Rd/CR94
Hughes Ranch to Broadway
2015 $4,984,489 $996,898 $3,987,591
Bailey Rd Veterans Dr to FM 1128 2015 $23,658,081 $4,731,616 $18,926,465
Mykawa Rd BW8 to FM 518 2016 $26,128,536 $4,445,000 $21,683,536
McHard Rd Ext
Cullen to Mykawa 2016 $41,155,664 $8,231,133 $32,924,531
CR 403 CR94 to Cullen 2014 $21,928,000 $4,385,600 $17,542,400
CR 48/ Kingsley
BW8 to Clear Creek 2016 $9,961,000 $1,992,200 $7,968,800
Max Rd Ext Future McHard Road to Hughes Ranch
2016 $7,995,530 $1,599,106 $6,396,424
Shadowcreek Ranch Trail
East of Kingsley to Kirby Dr
2016 $1,624,755 $324,951 $1,299,804
Green Tee Terrace Trail
FM 518 along Clear Creek to Barry Rose Rd
2016 $3,320,316 $664,063 $2,656,253
• Miller Ranch Road – end of summer • O’Day Road - September • Old Alvin Road – end of summer
TxDOT Off-System Bridge Replacements
TxDOT Off-System Bridge Replacements – Miller Ranch Rd
TxDOT Off-System Bridge Replacements
TxDOT Off-System Bridge Replacements
• Contractor is scheduled to re-construct the Hawk
intersection in June. • Paving underway • Possible traffic switch by the end of July • Bridge deck has been completed
Cullen Parkway – Phase II
Phase I Streetlights– Blackhawk to Mary’s Creek Bypass
• Accepted bids on project, low bid below $50,000 • Anchor bolt shortage with CenterPoint will delay
start of construction
Dixie Farm Road
Phase II – Mary’s Creek Bypass to SH35 • Stream gauge installed • Reviewed area for progress on punch list
Dixie Farm Road
• Project will be closed out when new Traffic Signal installed
• New signal construction at Walnut & SH 35 has begun but delays expected waiting for concrete
Walnut Reconstruction
• Working through punch list items and issues
Orange Street
• Continue acquisition process to obtain last
parcels • Potential redesign to avoid significant
acquisition costs near Veterans • Continue utility relocations
Bailey Road (Veterans to FM1128)
• 100% plan review underway • Hold final TRC review for construction plans
in preparation for advertising per the developer agreement
• TxDOT is reviewing plans and environmental permit
Business Center Drive
• Paving for center and median lanes underway • FM518 intersection work continues • Concrete material shortage aggravated by material
trucking shortage may create delays • Signal construction at Walnut underway - conduits
and foundations
SH35 – BW8 to FM518
• Held additional meeting with TxDOT to discuss • Work will be done under a permit • No additional environmental clearance needed • Will need to extend railroad panels • Coordinating with BNSF to address roughness of
the crossing
Quiet Zone Railroad Crossing
Drainage Projects
Diversion Ditch • DD4 continued excavation of diversion ditch west of CR
143 Pump Station • Bids awarded to Reddico on June 11th • Pre-construction conference held June 18th Re-grading of Roadside Ditches • Consultant continued working to resolve utility conflicts
on Wayne Dr. and depth of cover issues on Holland
Cowart Creek Diversion
Facility Projects
• Completed a site assessment – FM518 & Woodcreek – FM518 & Yost
Fire Station #3
Parks
• Waiting on final equipment for mid block crossing to arrive so project can be closed out
Trail Connectivity
• City staff approved Developer plans and combined into City’s plan set
• BDD#4 approved variance and plan • Hickory Slough project advertised June 13th
Sports Complex at Max Road
• Architect submitted 60% plans for review • Staff reviewing plans
Dolores Fenwick Nature Center Phase II
Utility Projects
30” Waterline Interconnect
• Final walk through complete
City of Houston Interconnect
City of Houston Interconnect
Alice Street Water Plant • Initial plant start up complete • Completing punch list • Three flow meters are being replaced • Turbine facility startup will occur once the rest of the
plant punch list is completed
• Received submittals for shop drawings • Site mobilization has begun and installation
of laydown yard fencing and silt fencing
Longwood WWTP Rehabilitation
• 2nd progress meeting held May 30th • Contractor on schedule with equipment
submittals and major equipment buy out
Barry Rose WWTP Rehabilitation
• Staff reviewing 60% PS&E package • Initiated coordination with utilities • Revised alignment on Hatfield to avoid multiple
conflicts
Hatfield Basin Trunk Sewer
• Contract awarded by Council on May 21st • Pre-con held & NTP issued June 12th
Twin Creek Regional Lift Station
Far Northwest Wastewater Treatment Plant Improvements
• Engineer completed the draft PER • Manufacturer reviewing work plan for repairs to
decanters • Initiating final design for UV system and decanter
valve replacement
Old Alvin 20” Waterline
• Reviewed and returned 60% plans to the engineer • 90% plans due in June
BellaVita Waterline Interconnect
• Public Works completed construction around HCFC detention pond
• Staff completed review of 60% plans • Pipelines responding to coordination notifications
SH35 South Water Line
• Contract awarded to Reddico on May 21st • Pre-Con and NTP issued on June 6th
• Held monthly progress meeting • Survey work ongoing • Design underway for segments where survey is
complete
McHard Road 16” Water Line & Roadway PER
Project Update