17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

download 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

of 27

Transcript of 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    1/27

    8/28/2010

    1

    Competitive Bidding: Guidelines

    and Recent Experience

    Department of Industrial and Management Engineering

    Indian Institute of Technology Kanpur

    3rd

    Capacity Building Programme forOfficers of Electricity Regulatory Commissions

    23 28 August, 2010

    Forum of Regulators

    Rajat Mishra, VP

    SBI Capital Markets Limited

    Indian Electricity Act 1910

    - basic framework for development

    - growth through public & private licensee

    Electricity (supply) Act 1948- intervention of state and creation of SEBs

    Electricity Regulatory Commission Act 1998

    Electricity Act 2003

    INDIAN POWER SECTOR REGULATORY FRAMEWORKIndian Power Sector - Evolution

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    2/27

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    3/27

    8/28/2010

    3

    Current State

    GDP growth rate of 8% to 9% will require similar

    growth in power capacity

    Installed generating capacity of 160 GW (March

    2010)

    Required over 200GW / 300GW by yrs 2012/2017

    Electricity Act 2003 focuses on reforms, competition

    Policies framed under Act reinforce the spirit

    Generation:

    All procurement through bidding makes processtransparent

    Slowly beginning to attract foreign players also esp Case II

    Foreign Lenders also making a comeback

    Mundra UMPP attracted Multilaterals and ECAs

    No cost-plus projects through MoU??????

    Issues of gold plating etc FULL CIRCLE

    Deviations decrease confidence of external players

    Opportunities

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    4/27

    8/28/2010

    4

    Generation:

    Paradigm Shift in financing

    Move from Payment Security based lending to

    Competitive Tariff based lending

    Open access very important

    Retrograde steps on open access and cross subsidy hurts investor

    and lender sentiments

    Avoid mistakes of the past

    Opportunities

    Transmission:

    Interregional transfer capacity to increase to 32.7 GW by 2012, to 57 GW by 2015

    & 75 GW by 2017

    Planned XIIth Plan investment is Rs 2,400 bn - Rs 1,400 bn in central sector

    (interstate system) & Rs 1,000 bn in the state sector (intra-state system)

    Empowered Committee 14 Projects identified

    First 3 projects awarded

    Tenders for the next 3 projects launched

    State level projects

    First PPP project awarded by HVPN to Kalpataru

    Rajasthan project awarded by RVPN to GMR

    UP has also invited tenders for state level projects

    Private sector to be involved in development of evacuation systems for UMPP

    Opportunities

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    5/27

    8/28/2010

    5

    Competitive Bidding Guidelines

    Sec 63 of the Electricity Act states that:

    Background

    Notwithstanding anything contained in section 62, the

    Appropriate Commission shall adopt the tariff if such tariff

    has been determined through transparent process of bidding

    in accordance with the guidelines issued by the Central

    Government.

    The guidelines have been framed under the above provisions of

    the Act.

    Issued by the Ministry of Power on 19th January 2005

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    6/27

    8/28/2010

    6

    Objectives

    Promote competitiveprocurement of electricity

    Facilitate transparency and fairness in procurement processes: Transparency ensured by Guidelines & Standard Bid Documents for

    tariffbased bidding

    Enhance standardization and reduce ambiguity and time for materialization

    of projects

    Standardization of Bid documents, Bid submission and evaluation

    process, timelinefor biddingprocess, tariff structure

    Provide flexibil ity to suppliers on internal operations while ensuring

    certainty on availability of power and tariffs for buyers

    Tariff to be quoted upfront for life of plant and Regulator to adopt tariff

    arrived through transparent biddingprocess as specified by Guidelines

    Developer has flexibilityto choose optimum unit configuration Provides incentive to Developer to adopt innovative financial modeling

    and tax planning to ensure competitive tariff & return on investment.

    Period of Procurement

    Long Term Medium Term

    For 7 or more years From 1 upto 7 years

    Procurement Applicable For

    Seasonal Power Peak Load: ???

    Ideally suited for

    hydro

    Base Load

    Scope

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    7/27

    8/28/2010

    7

    Bidding Mechanisms

    Case 1 Case 2

    Scope

    Location/ technology/

    fuel not specified

    Bidder responsible for

    clearances/ approvals etc

    More relevant for Stateswith limitedfuel sources

    Higher risk for developer

    Lower risk for state

    Land/ Fuel provided by

    Procurer

    More applicable for

    States where fuel

    sources are available or

    having coastalareas

    Higher risk for State

    Lower risk for developer

    Tariff under case 2 expected to be lower than that under case 1

    Procurement by more than

    one distribution licensee

    through a combined bid

    process permitted through

    authorized representative.

    In case distribution licensees

    are located in more than one

    State, CERC shall be the

    AppropriateCommission

    Tariff Structure

    Non Escalable

    (Firm Price)

    Medium Term

    Long Term

    One Part Tariff

    Two Part Tariff

    Energy Charge

    Escalable

    (Base Price withIndex)

    Base Price

    (with Index)

    NQHR

    Index notified by CERC

    Optional

    Capacity Charge

    Tariff in INR only except FERV

    on imported coal in case II

    Min/Max Capacity Charge >

    0.7

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    8/27

    8/28/2010

    8

    Current CERC Rates

    Parameter Rate

    Discounting Rate for bid evaluation 9.35%

    Escalation Rate Domestic coal 6.01%

    Escalation Rates Imported Coal

    Coal sub-component 16.4%

    Transportation sub-component 16.23%

    Inland handling sub-component 5.11%

    Bidding Process

    Two stage process for Long term procurement: Request for Qualification (RFQ)

    Request for Proposal (RFP)

    For Medium term the procurer has an option to adopt asingle stage tender process combining the RFP & RFQ

    process.

    The bidding shall be necessarily by way of InternationalCompetitive Bidding (ICB).

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    9/27

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    10/27

    8/28/2010

    10

    Project Capacity (MW) Winner Bid Price

    UMPPs

    Sasan UMPP 4000 Reliance power 1.196

    Krishnapattam

    UMPP4000 Reliance power 2.336

    Mundra UMPP 4000 Tata Power 2.265

    TilaiyaUMPP 4000 Reliance Power 1.77

    Others

    Karachana, UP 1320 Jaiprakash Assoc. 2.97

    Bara, UP 1980 Jaiprakash Assoc. 3.02

    Rajpura, Punjab 1320 L&T 2.89

    TalwandiSabo 2000 Sterlite 2.863

    Bhaiyathan 1320 India Bulls 0.81

    Case 2 Bids

    Project Winner Tx. Charge (Rs. Mn)

    WRSS Project B Reliance Power 1084.899

    WRSS Project C Reliance Power 564.743

    East-North Interconnection Sterlite Energy 1187.95

    North Karanpura Reliance Power 2580.0051

    Talcher-II Reliance Power 1440.0215

    Rajasthan PPP GMR 356.50

    Transmission Bids

    HVPNL has awarded the 1st transmission project based on VGF to consortium of

    KalpataruPowerTransmission and Techno- Electric and Engineering Company Ltd

    Quoted one time grant of Rs.93.90 Crs and unitary charge of Rs.4.5 crs/month

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    11/27

    8/28/2010

    11

    Project DeveloperInvestment

    (Rs bn.)

    Parbati-Koldam PKTCL [RPTL (74%) and Powergrid (26%)] 10.00

    WRSSS-II RPTL 13.85

    Sugen TPGL [Torrent Power (74%) and Powergrid (26%)] 3.20

    Karcham-Wangtoo JPL [(Jaypee (74%) and Powergrid (26%)] 10.00

    Mahan Essar Power Transmission Company 8.57

    Teesta Urja TPTL [(Teesta Urja (74%) and Powergrid (26%)] 7.00

    Mundra (Adani) Adani Power 15.00

    Tiroda

    MEGPTCL [Adani Power (74%) and Mahatransco

    (26%)] 43.79

    Jaigad

    Jaigad Power Transco (JSW Energy -74% and

    MSETCL 26%) 4.46

    East-North Interconnection Sterlite Technologies 18.00

    Talcher-II RPTL 9.00

    North Karanpura RPTL 41.00

    HVPNL (evacuation for Jhajjar

    and power from Adani Power)

    Kalpataru Power Transmission and Techno-

    Electric and Engineering Company Limited 3.82

    Transmission - Private Sector Projects

    20.18

    23.37

    30.6

    0

    5

    10

    15

    20

    25

    30

    35

    2007 2008 2009

    Volume(BnUnits)

    Volume Transacted Through Traders & Power

    Exchanges

    40%

    41%

    9%10%

    Break-up of Short Term Transactions (2009)

    UI Bilateral (Through Traders)

    Bilateral (Between DISCOMS) Through Power Exchanges

    30% increase in volume of power

    transacted through traders & exchanges

    from2008 to 2009

    In 2009, short-term power market

    (including UI) was 8 per cent of the total

    generation

    2009 was 1st year for procurement of

    power by industrial sector consumers

    through power exchanges (IEX only)

    The volume transacted through power

    exchanges could have been 17% higher

    but was restricted due to transmission

    congestion

    Short Term Transactions - Volumes

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    12/27

    8/28/2010

    12

    Price of Short-Term Transactions of Electricity (Rs/Kwh)

    Bilateral Through Traders Power Exchange UI (Grid)

    Period RTC Peak Off-Peak Total IEX PXIL New SR

    Jan-09 7.43 8.55 6.78 7.23 6.16 6.86 4.99 7.61

    Feb-09 6.89 8.16 6.19 6.58 6.85 7.42 4.89 7.68

    Mar-09 7.35 8.08 7.53 7.43 8.33 8.54 4.85 8.2

    Apr-09 6.83 9.05 8.47 7.21 10.1 10.18 5.36 6.04

    May-09 6.60 8.18 8.03 6.82 6.84 8.74 4.17 3.99

    Jun-09 5.04 6.44 5.07 5.05 7.39 9.60 4.94 5.1

    Jul-09 4.72 5.92 4.98 4.75 4.81 4.85 4.12 4.67

    Aug-09 4.46 6.32 5.77 4.64 7.40 6.15 6.29 5.85

    Sep-09 4.6 6.02 5.48 4.73 4.00 4.32 5.02 4.20

    Oct-09 4.86 6.48 5.8 5.07 4.73 5.18 4.24 5.83

    Nov-09 5.05 5.76 5.91 5.33 3.16 3.39 2.72 3.79

    Dec-09 4.96 5.12 5.06 4.99 3.22 3.07 3.26 3.92

    Prices of short-term transactions were higher during Apr-Aug period

    The price of electricity transacted during peak, RTC and Off-peak periods shows a

    declining trend and converged by December 2009

    Short Term Transactions - Prices

    Developers Perspective

    Case Studies

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    13/27

    8/28/2010

    13

    All assumptions to be questioned

    Determine the Hurdle Rate for IRR

    Criteria shifts to IRR from RoE

    Hurdle Rate usually determined by Cost of

    Equity and risk profile

    Typical IRR for cost-plus is 11-12%

    RISK TO BE ASSUMED

    Bidding Considerations

    Extremely important to have pre-bid tie-ups in

    place

    Commitment on major costs

    Time period for which commitments would

    hold

    Interest rates risk?

    Escalation & Currency provisions on EPC? Fuel Price Risk?

    Bidding Considerations

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    14/27

    8/28/2010

    14

    EPC:

    Costs: Are the Chinese really cheap?

    Performance guarantee on heat rate, aux

    Sensitivity on domestic and imported coal

    Degradations

    Construction schedule

    Currency, payment terms

    Availability of ECA financing

    Bidding Considerations

    Domestic coal as fuel:

    Mine development expense

    Calorific value estimates

    Cost of ash disposal

    Cost of transportation MGR etc

    Operations cost

    Mix of Indexed and non-indexed costs

    Bidding Considerations

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    15/27

    8/28/2010

    15

    Imported Coal as Fuel:

    Bidding Strategy and appetite for risk aremore important

    Mix of Indexed and non-indexed costs muchmore important

    More sensitive to variation in quality

    HUGE RISK PERCIEVED BY LENDERS

    FC may get delayed Sponsor Support

    Bidding Considerations

    Criteria Domestic Imported

    Calorific Value

    (kcal/kg)

    3500 6000

    Cost (Rs/MT) 1000 2700

    Variable Cost

    (Rs/kWh)

    0.80 1.4

    Imported Vs Domestic

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    16/27

    8/28/2010

    16

    International Coal Prices

    3224 27

    5545

    5061

    120

    70

    95

    0

    20

    40

    60

    80

    100

    120

    140

    2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 (till

    June)

    $/tonne

    Prices indicative of upward trend since 2001

    Prices increased in 2007 owing to huge demand from Asia, mainly China

    Supply constraints, like port congestion (Australia), floods in Indonesia & strike at exportterminals (South Africa) also led to increase in prices in 2008

    During 2009, prices fell as a result of global financial crisis

    Current coal prices hovering around USD 95 per tonne - indicating close to 35% increase

    over the previous year

    Some Issues with Coal Supply

    Of the 219 coal blocks allotted to private players, 40 were declared no-go byMoEF

    India will have to import approx. 80 million tonnes of coal by 2011-12

    Indonesian government change in Law

    cap coal exports to 150 million tonnes annually from

    2010 onwards

    Indonesian coal Index for sale of coal

    Will Sponsors continue to cross subsidise in rising coal pricescenario?

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    17/27

    8/28/2010

    17

    Financial Assumptions

    Financing Mix and sources to be decided

    Large projects like UMPP have to source mix of RTL

    and external financing

    Limited availability of ECB for sector and such tenures

    ECA are a viable option

    Time consuming Equator Principles to be followed for ECB/ECA funding

    Bidding Considerations

    Bidding Scenarios

    Scenario Effect on Tariff

    D/E 80:20 8 paise

    Loan repayment 15 years 7 paise

    Interest Rate increase by 1% p.a. 3 paise

    Open worksheet

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    18/27

    8/28/2010

    18

    Case Studies

    Some Bids

    Reflects different strategies and risk appetite of

    Bidders

    For GUVNL bid that was all-inclusive, Adani had bid

    based on imported coal

    Tariff for each year fixed and no escalations

    Risk of international coal price, transportation cost, forex

    variation borne by bidder

    Possible only with ownership / long term contracts for coal& transport

    GUVNL Bid

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    19/27

    8/28/2010

    19

    For UMPP Bids for Mundra, Tata Power and Reliance haddifferent bid strategies

    TPL bid numbers were broken into escalable and non-escalable

    components

    Reflects clear direction of owning mine and ships (or

    equivalent long term contracts) while retaining limited risk

    Reliance had bid all numbers as escalable

    Reflects strategy of procurement on spot basis for coal and

    transport

    No upsides possible unless captive mines / long term

    contract on different terms

    Was it conservative or aggressive?

    UMPP Mundra

    CERC Levelised Tariff: Rs 1.77

    Base Operating Parameters:

    Base CaseUMPP Sasan: Base Case

    Auxiliary consumption 7.5%

    O and M Values: Rs. 1 Mn/ MW

    Coal price escalation 6.77%

    Senior debt repayment period: 11 years

    Plant load factor 80%

    Levelised Tariff Quoted by Reliance Power : Rs 1.196 / Kwh

    Project Cost / MW

    (Rs Mn)

    Project IRR

    (%)

    Equity IRR

    (%)

    Base Case 40.48 7% 0%

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    20/27

    8/28/2010

    20

    Senstivity Analysis - Cumulative

    7%

    7.43% 7.81%

    9.23%

    9.30%

    4.63%

    0%

    3.00%

    8.77%

    12.77%

    0%

    2%

    4%

    6%

    8%

    10%

    12%

    14%

    1 2 3 4 5

    Scenarios

    ProjectIRR

    0%

    2%

    4%

    6%

    8%

    10%

    12%

    14%

    EquityIRR

    UMPP Sasan: Sensitivity Analysis

    Scenario 1 2 3 4 5

    Rate of interest 11.0% 8.5% 8.5% 8.5% 8.5%

    Auxilary 7.50% 7.50% 6.50% 6.50% 6.50%

    PLF 80.00% 80.00% 80.00% 90.00% 90.00%

    Repayment period 11 11 11 11 18

    Rate of interest 11.0% 8.5% 8.5% 8.5% 8.5%

    INFERENCE ( SASAN)

    Impact of Rate of Interest and debt repayment period is the

    highest

    In this case the repayment period is 18 years/Other cases 10-12

    years

    Most of the loans planned with Re-Financing

    Some Major loans from IFC/ADB planned as long tenor loan

    Rate of interest greatly brought down by huge ECB borrowing

    Tariff of Rs. 1.196 p.u. extremely aggressive

    Reliance can make project viable only by squeezing every variable ROI,

    Auxiliary consumption, Tenor of loan, PLF and other non-traditional

    venues

    UMPP Sasan: Inference

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    21/27

    8/28/2010

    21

    Use of bi-products flyash, Steam

    Fly ash used in production of Cement

    Reliance plans Cement factory near Sasan to utilize flyash

    Low pressure steam to be used in production of fertilizer

    Alternate use of coal

    Additonal Coal from Captive Mine to be used in setting up other

    power plants

    Certified Emission Reduction(CER)

    CERs could be traded in the Market for $15-$20

    Vertical Integration

    Entering into logistics Sector to reduce cost of transportation

    UMPP Sasan: Alternate Revenue Sources

    KPCL Case 2 Bid Gulbarga

    Capacity 1320 MW

    Location Gulbarga, Karnataka

    Coal Domestic/International - ?

    Procurers 5 DISCOMS of Karnataka

    Key Details Coal to be arranged by the bidders either Domestic or Imported

    Land and other approvals arranged by state

    Plant location around 1000 kms by rail from nearby ports

    Comfort letter required at bid stage from Domestic coal supplier

    regarding supply for entire PPA tenure

    FSA to be signed within 12 months from LoI

    Bid requirements practically rule out any participation based on domestic coal linkages

    allotted are project specific, developers with captive blocks prefer merchant plant

    Imported coal also a practical no-go due to plant location nowhere near a port.Imported coal based tariffs would be very high

    Is this really a well thought out Bid -?

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    22/27

    8/28/2010

    22

    Payment Security offered differs widely

    amongst states

    Best recourse is 3rd party sale in case of default

    Domestic mines offer a significant upside

    potential

    Imported coal bidding strategy differs on risk

    appetite

    Opportunities

    Health of distribution companies

    Too much capacity addition expected from Private Sector

    Shortage in equipment supply

    Slow Execution pace

    Absence of Data on performance of Chinese equipment esp in

    Indian Conditions

    Funds crunch in Indian Financial market Sector/Firm/ group

    Exposure Land Acquisition, R&R and approvals

    Constraints

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    23/27

    8/28/2010

    23

    Conclusion

    Indian Power Sector has come a long way in terms of liberalization

    Electricity Act 2003 combined with NEP, NTP have promoted competition/

    better tariff for end customer

    However developers should be aware of certain pitfalls

    Competition from Captive Power Plants

    Merchant Power tariff assumptions too high

    Efficiency assumptions may not be entirely achievable in India

    Government should play more proactive role

    Sector exposure/Financial closure issues eased out

    Development of Power trading model to be handled carefully

    Path Ahead Really bright

    Thank You

    Questions?

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    24/27

    8/28/2010

    24

    Appendices

    Transmission Projects: Private sector

    Source: India Infrastructure Research

    Project DeveloperInvestment

    (Rs bn.)

    Parbati-Koldam PKTCL [RPTL (74%) and Powergrid (26%)] 10.00

    WRSSS-II RPTL 13.85

    Sugen TPGL [Torrent Power (74%) and Powergrid (26%)] 3.20

    Karcham-Wangtoo JPL [(Jaypee (74%) and Powergrid (26%)] 10.00

    Mahan Essar Power Transmission Company 8.57

    Teesta Urja TPTL [(Teesta Urja (74%) and Powergrid (26%)] 7.00

    Mundra (Adani) Adani Power 15.00

    Tiroda

    MEGPTCL [Adani Power (74%) and Mahatransco

    (26%)] 43.79

    Jaigad

    Jaigad Power Transco (JSW Energy -74% and

    MSETCL 26%) 4.46

    East-North Interconnection Sterlite Technologies 18.00

    Talcher-II RPTL 9.00

    North Karanpura RPTL 41.00

    HVPNL (evacuation for Jhajjar

    and power from Adani Power)

    Kalpataru Power Transmission and Techno-

    Electric and Engineering Company Limited 3.82

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    25/27

    8/28/2010

    25

    Case 1 Bids

    RELIANCE INFRASTRUCTURE (1500MW), May 2010

    Bidder

    Quantity

    (MW) Location

    Levelized

    Tariff

    (Rs/Unit)

    Levelized

    Transmission Charge

    (Rs/Unit)

    Levelized Tariff Net of

    Transmission Charges

    (Rs/Unit)

    PPA Signing

    Date

    Wardha Power 320 Maharashtra 3.42 0.33 3.09 Not Signed

    RKM Powergen 300 Chattisgarh 3.72 0.33 3.39

    Reliance Power 150 Maharashtra 3.99 0.33 3.66

    Reliance Power 1241 M.P. 3.69 0.33 3.36

    Corporate Power 380 Jharkhand 4.57 0.73 3.84

    BIHAR (1500MW), Oct 2009

    Bidder

    Quantity

    (MW)Location

    Levelized

    Tariff

    (Rs/Unit)

    Levelized Transmission

    Charge (Rs/Unit)

    Levelized Tariff Net

    of Transmission

    Charges (Rs/Unit)

    PPA Signing

    Date

    ESSAR (Tori) 450 Jharkhand 2.64 0.35 2.29 July 2010

    Monnet Ispat

    (PTC)200 Orissa 3.62 0.35 3.27

    KVK Nilanchal

    (PTC)250 Orissa 3.97 0.35 3.63

    Ind-Bharath

    (PTC)250 Orissa 3.99 0.35 3.65

    GMR 191 Orissa 4.05 0.35 3.70

    JAS Infra 500 Bihar 4.22 0.35 3.87

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    26/27

    8/28/2010

    26

    GUJARAT (3000MW), Jan 2010

    RAJASTHAN (1200MW), Nov 2009

    Bidder

    Quantity

    (MW) Location

    Levelized

    Tariff

    (Rs/Unit)

    Levelized Transmission

    Charge (Rs/Unit)

    Levelized Tariff Net

    of Transmission

    Charges Rs/Unit)

    PPA Signing

    Date

    Adani Power

    Rajasthan Ltd1200 Rajasthan 3.24 0.284 2.95 Jan 2010

    GMR Kamalanga 100 Orissa 3.81 0.677 3.13 -

    Ind Bharath Energy

    (Utkal) Ltd 200 Orissa 3.95 0.677 3.28 -

    RKM Powergen 300 Chattisgarh 4.30 0.596 3.71 -

    Jindal India Thermal

    Power450 Orissa 4.38 0.677 3.70 -

    Bidder

    Quantity

    (MW) Location

    Levelized

    Tariff

    (Rs/Unit)

    Levelized

    Transmission

    Charge (Rs/Unit)

    Levelized Tariff Net

    of Transmission

    Charges (Rs/Unit)

    PPA Signing

    Date

    KSK Energy Ventures 1010 Chattisgarh 2.34 0.265 2.075 June 2010

    Shapoorji Pallonji 800 Gujarat 2.80 0.265 2.535 May 2010

    Essar Power Ltd. 1000 Gujarat 2.80* 0.265 2.535 May 2010

    KARNATAKA (2000MW), Jan 2010

    Bidder

    Quantity

    (MW) Location

    Levelized

    Tariff

    (Rs/Unit)

    Levelized

    Transmission

    Charge (Rs/Unit)

    Levelized Tariff Net of

    Transmission Charges

    Rs/Unit)

    PPA Signing

    Date

    Monet Power (PTC) 150 Orissa 3.76 0.83 2.93 Not Signed

    Thermal Power Tech

    (PTC)430

    Andhra

    Pradesh3.77 0.458 3.31

    Meenakshi Energy

    (PTC)200

    Andhra

    Pradesh3.80 0.458 3.34

    JSW 600 Maharashtra 3.81 0.756 3.06

    East Coast Energy

    (PTC)400

    Andhra

    Pradesh3.89 0.458 3.43

    NCC Power Projects

    (PTC)400

    Andhra

    Pradesh3.89 0.458 3.43

    MSEDCL (2000MW), May 2010

    Bidder

    Quantity

    (MW) Location

    Levelized

    Tariff

    (Rs/Unit)

    Levelized

    Transmission

    Charge (Rs/Unit)

    Levelized Tariff Net

    of Transmission

    Charges (Rs/Unit)

    PPA Signing

    Date

    GMR EMCO 200 Maharashtra 2.88 0.287 2.593 March 2010

    India Bulls1200 Maharashtra 3.27 0.287 2.983

    Apr & Jun

    2010

    Adani Power

    Maharashtra1200 Maharashtra 3.28 0.287 2.993

    March 2010

  • 8/8/2019 17 - Rajat Mishra - Competitve Building Guidelines and Recent Experiences

    27/27

    8/28/2010

    Other Case I Bids

    Bid Details L1 L2 L3PPA Signing

    Date

    Haryana2113MW

    Nov 2007

    GMR

    Kamalanga2.86 Rs

    300 MW

    Adani Power

    Mundra2.74 Rs

    1424 MW

    - August 2008

    Madhya

    Pradesh2000MW

    Nov 2007

    Lanco Infratech2.34 Rs

    600 MW

    Reliance Power2.70 Rs

    1241 MW

    Essar Power

    (Mahan)2.95 Rs

    300 MW

    Not signed

    Case II Bids

    BIDDER PROJECT BID PRICE (Rs/Kwh) OUTCOME

    Jaiprakash Assoc.

    Nov 20081320 MW, Karachana, UP 2.97

    L 1

    Jaiprakash Assoc.

    Feb 20091980 MW, Bara, UP 3.02

    L 1

    L&T

    Dec 20091320 MW, Rajpura, Punjab 2.89 L 1

    Reliance power

    July 2007

    Sasan UMPP

    4000 MW1.297 L1

    Reliance power

    Nov 2007

    Krishnapattam UMPP

    4000 MW2.33

    L1

    Tata Power

    Dec 2006

    Mundra UMPP

    4000 MW2.265 L1

    Reliance Power

    Aug 2009

    Tilaiya UMPP

    4000 MW1.77 L1

    India Bulls

    Apr 2008

    Bhaiyathan

    1320 MW0.81 L1

    Sterlite

    Jul 2008

    Talwandi

    2000 MW2.863 L1