16 August 2006

22
16 August 2006 16 August 2006 Water Services Water Services Targets Targets Portfolio Committee

description

Portfolio Committee. 16 August 2006. Water Services Targets. The national sector targets are very ambitious- but it helps to focus and prioritise - PowerPoint PPT Presentation

Transcript of 16 August 2006

Page 1: 16 August 2006

16 August 200616 August 2006

Water Services Water Services

TargetsTargets

Portfolio Committee

Page 2: 16 August 2006

Sector Targets

• The national sector targets are very ambitious- but it helps to focus and prioritise

• They far exceed the MDG goals, which is to halve the proportion of people that were without sustainable access to safe drinking water and sanitation in 1990, by 2015.

• As will be shown, SA has already met the MDG target for water supply and is well underway to meet the sanitation MDG as well.

Page 3: 16 August 2006

Sector TargetsTARGET RESPONSIBILITY

Access to services

1 All have access to a functioning basic water supply facility by 2008.

WSAs supported by DWAF.

2 All have access to a functioning basic sanitation facility by 2010.

WSAs supported by DWAF and national sanitation task team.

3 All schools have adequate and safe water supply and sanitation services by 2005.

Provincial Education Departments supported by National DoE & DPW.

4 All clinics have adequate and safe water supply and sanitation services by 2007.

Provincial depts of health supported by National DoH and DPW.

5 All bucket toilets are eradicated by Dec 07. WSAs supported by DWAF.

6 Investment in WS infrastructure in the sector totals at least 0.75% of GDP.

National Treasury.

Page 4: 16 August 2006

Sector Progress – basic water

National Performance: water supply

1994 Population

2001 Population

2006 Population

Year

(million) (million) (million)

Population 38.9 44.8 48.6

People below RDP 15.9 13.1 8.2

% People below RDP 41% 29% 17%

People equal or above RDP 23 31.7 40.4

% People equal or above RDP 59% 71% 83%

% Improvement since 1994 - 30% 59%

Backlog more than halved

Page 5: 16 August 2006

Sector Progress – Basic Sanitation

 

19941994 20012001 20062006

Access toAccess to 48%48% 57%57% 69%69%

BacklogBacklog 52%52% 43%43% 31%31%

40% Improvement40% Improvement

Page 6: 16 August 2006

Sector Progress• Schools - Water backlog reduced from 4785 in

Sept 04 to 2688 (additional 10% of schools) by March 06. In total 2478 schools were served. San. backlog has been reduced from 4300 in Sept 04 to 1822 by March 06.

• ± 2 100 clinics lack acceptable basic water supply (48% of all clinics).

Planned clinics to be served

Total Current backlog

2005/ 06 2006/ 07 2007/ 08 TOTAL 281 59 114 108

Page 7: 16 August 2006

Sector Progress

Money in the sector

•Bucket eradication: Buckets in formal settlements as surveyed in June 2006 was 165 912 and we are on track to wipe this out by December 2007. This will be done through replacing of 74 000 buckets this year and 91 912 next year.

• It is estimated that SA currently invests at least 0.55% of GDP in the water and sanitation sector.

Page 8: 16 August 2006

Sector TargetsTARGET RESPONSIBILITY

Education and health

7 Hygiene education and the wise use of water are taught in all schools by 2005.

National DoE.

8 70% of households with access to at least a basic sanitation facility knowhow to practise safe sanitation by 2005 (and 100% by 2010).

WSAs supported by DWAF.

Free basic services

9 Free basic water policy implemented in all water services authorities by 2005.

WSAs.

10 Free basic sanitation policy implemented in all water services authorities by 2010.

WSAs.

Page 9: 16 August 2006

Sector Progress• One mechanisms to measure % of households with safe

sanitation practices, is to measure decline in water borne illnesses-there was a decline. Or surveys.

• Free Basic Water – 74 % of the total population have access to FBW. Target to reach 78% of population by March 2007.

• Free Basic Sanitation – Implemented in some metros and cities, but practical problems delay implementation in all areas.

Page 10: 16 August 2006

Sector Targets

TARGET RESPONSIBILITY

Institutional development and performance

11 A national institutional reform strategy developed by June 2004. DWAF (together with SALGA and SAAWU1).

12 The institutional reform of regional WSPs is completed by 2013. DWAF (together with SALGA and SAAWU).

13 All assets of WS schemes are transferred from DWAF to WSAs by 2008.

DWAF.

14 By-laws are promulgated in every WSA area by 2005. WSAs.

19 DWAF reports on sector development and progress annually DWAF.

Page 11: 16 August 2006

Sector Progress

•The national institutional reform strategy has been developed and is being discussed with sector partners.

•The institutional reform process has started in 3 priority areas.•With 58% of schemes transferred to date, optimistic of meeting target of 2008.•DWAF produced model bylaws for municipal use, but is not yet able to monitor this. Will be done once regulator fully operational.•DWAF annual reporting consistently done but more specific reports were drafted.

Page 12: 16 August 2006

Sector Targets

TARGET RESPONSIBILITY

Institutional development and performance

15 All water services authorities report annually on progress against their water services development plans by 2005.

WSAs.

16 All external water services providers are rendering services in terms of a contract with the applicable water services authority by 2005.

WSAs.

17 All water services providers are rendering services in terms of a business plan by 2005.

WSAs.

18 All water services authorities have adopted a set of key performance indicators that include those set out in Annexure 2 by 2005 and report on these annually.

WSAs.

Page 13: 16 August 2006

Sector Progress

• 86% of WSAs have completed WSDPs; ongoing DWAF support to complete as well as to improve.

• DWAF produced a model WSA-WSP contract for municipal use. Last survey showed 67% of municipalities started negotiating. Closer monitoring will be done once regulator fully operational.

• DWAF, as part of its regulatory process, has started in 2005 with SALGA a benchmarking process that will enable WSA’s to adopt and report on a set of Key Performance Indicators, e.g. DWQ standards.

Page 14: 16 August 2006

Sector Challenges • WSA lack of capacity, especially tech &

financial• Financial constraints

– financial non-viability of some municipalities– cost of supplying dispersed consumers and – cost of waterborne san in dense urban areas.– Poor cost recovery caused by inadequate

financial administration– Bulk infrastructure funding gap

• Sustainability – targets set as infrastructure delivery, thus municipalities neglect O&M and Infrastructure Asset Management

• Informal settlements

Page 15: 16 August 2006

Sector Challenges • Urbanisation & growth in hhold numbers due to

reduction in hhold size

• FBW specific challenges– Communication – lack of awareness of FBW by officials,

councillors and community– Targeting and prioritising of the Poor for FBW

• Sanitation specific challenges– Changing WSA sanitation planning to reflect 2010

target– Prioritisation of sanitation – Capacity constraints: creating sufficient support

capacity in the regions to support municipalities effectively. Municipalities lack implementation capacity.

– Insufficient funding of sanitation to meet targets and slow MIG expenditure.

Page 16: 16 August 2006

Sector Actions • Operation Gijima – Sanitation acceleration

• Appointment of 21 engineers at municipalities to help with san

• Bucket program acceleration– Special fund of R 1,2 bn allocated over 3 financial years.– Total bucket backlog 165 912 (june 06)– 63 602 buckets will be eradicated by Dec 06 and 102 310

by Dec 07– Currently 85 450 buckets are assigned funding, the

remaining 80 462 buckets will be registered by end August 2006

– 35 contracts in place (to eradicate 29 055 buckets by Dec 06)

– Contracts for remaining 34 547 buckets, will be in place by Aug 06

– If R600 mill is re-allocated to 06/07, contracts can commence immediately to eradicate 102 310 buckets earmarked for Dec 07

Page 17: 16 August 2006

Basic Water Supply and Sanitation Conclusions

If we observe the current rate of population and household growth and compare it with the current implementation rate, we can make the following conclusions:

• South Africa is making very good progress, however

• Indications are that at the current implementation rate, and should this current rate not improve, that the sector may not address all basic water and sanitation backlog challenges in all municipalities, as per the targets.

Page 18: 16 August 2006

Sector Conclusions • Budget for basic services inadequate to meet all

targets.• Bucket target only applies to those in established

(formal) areas, thus in reality there will still be buckets in informal settlements after Dec 07 to be addressed by other subsequent programs.

• Bulk infrastructure needed and this to be integrated with water resource development.

• Essential to facilitate the use of other sources of funding for higher levels of service (such as house connections and water borne sanitation).

Page 19: 16 August 2006

Sector Conclusions

• Basic services in informal settlements can only be addressed in partnership with housing programs;

• Urbanisation and migration play a major role in the growing demand for services (and often formal human settlements in urban areas need over and above just basic services.)

Page 20: 16 August 2006

Way Forward

• Reach agreement on differentiated service levels e.g. interim / rudimentary in deep rural areas

• Water and especially sanitation delivery must be accelerated.

• Likewise the municipal capacity building initiatives and support programmes are essential.

• Cost recovery, dependent on good financial administration, must receive attention as it is an important source of funding.

Page 21: 16 August 2006

• DWAF to monitor not only taps and toilets installed but functionality, so as to ensure sustainability.—DWAF’s regulatory function

• Comprehensive reports on municipal performance as well as total sector performance to be published as a transparent annual measure of performance against all targets.

Way Forward

THANKS

Page 22: 16 August 2006

Sector Progress– Bucket EradicationSum of Bucket

Backlog 2005 Bucket

eradication Sum of Bucket Backlog

(Mar2006) Province

(March 2005) 2005/2006 Total Historic

EASTERN CAPE 70 439 6 512 63 927 37 264

FREE STATE 131 562 11 050 120 512 104 422

GAUTENG 7 184 7 184 0 0 KWAZULU-NATAL 750 750 0 0 LIMPOPO 80 80 0 0 MPUMALANGA 19 628 11 737 7 891 6 491

NORTH WEST 36 178 12 492 23 686 23 686

NORTHERN CAPE 22 455 8 220 14 235 7 242

WESTERN CAPE 3 612 550 3 062 3 062

291 888 58 575 233 313 182 167